Formwork removal time crucial for bridge strength and durability

View profile for Rahul kumar thakur

Structural/Bridge engineer

𝑭𝒐𝒓𝒎𝒘𝒐𝒓𝒌 𝑹𝒆𝒎𝒐𝒗𝒂𝒍 𝑻𝒊𝒎𝒆:- In bridge construction, formwork is temporary but its removal time decides the permanent strength and durability of the structure. 𝑰𝒇 𝒓𝒆𝒎𝒐𝒗𝒆𝒅 𝒕𝒐𝒐 𝒆𝒂𝒓𝒍𝒚 → cracks, deflection, even failure. 𝑰𝒇 𝒓𝒆𝒎𝒐𝒗𝒆𝒅 𝒄𝒐𝒓𝒓𝒆𝒄𝒕𝒍𝒚 → safe, strong, long-lasting bridges. As per 𝑰𝑺 456:2000 & 𝑴𝒐𝑹𝑻𝑯 𝑺𝒆𝒄𝒕𝒊𝒐𝒏 1500, here are the standard stripping times (normal conditions): Columns/Walls → 16–24 hrs Slabs → 7–14 days Beams/Arches → 14–21 days Cube test results are more reliable than just counting days. Always ensure that the concrete has gained enough strength before striking formwork. #BridgeEngineering #MoRTH1500 #IS456 #Formwork #ConstructionQuality #CivilEngineering #BridgeDesign