Engineering Interfaces: Resolving Complex Dependencies Between EPC Contractors
Challenge Scenario:
In a recent onshore oil and gas processing facility project, there was the interface between two EPC contractors with interdependent scopes:
EPC-A: Responsible for process engineering, equipment selection, and procurement (e.g., compressors and heat exchangers).
EPC-B: Tasked with civil and structural design, including equipment foundations and pipe racks.
The interface relied on EPC-A providing detailed equipment specifications, including critical data such as weights, dynamic loads, anchor bolt arrangements, and vibration analysis. To facilitate this, EPC-B issued formal interface queries to EPC-A, specifying the required data and requesting clarity on any preliminary assumptions. Each interface query carried a contractual response deadline of two weeks. Delays or incomplete responses from EPC-A would directly impact EPC-B's ability to finalize the foundation and structural designs, creating potential knock-on effects on construction schedules and material procurement. This dependency highlighted the need for timely and accurate information exchange to maintain project momentum.
Complication: Delays from EPC-A in delivering finalized equipment data created a cascade of issues:
Design Bottlenecks: EPC-B couldn't finalize foundation and structural designs, leading to construction delays.
Misaligned Assumptions: In an attempt to stay on schedule, EPC-B began working with preliminary assumptions, which later conflicted with the actual equipment specifications.
Cost Overruns and Rework Risk: Adjustments to accommodate revised specifications threatened the project’s budget and timeline.
Accountability Conflicts: Both EPCs blamed each other for the delay, escalating tensions and straining collaboration.
Action Plan:
1. Revised Interface Agreement:
Collaborated with both EPCs to redefine the Interface Management Plan (IMP), including:
-- Clear deadlines for critical equipment data submissions + follow-up via Interface Planning registers and monitoring the IQ response and target dates through Interface tools.
-- Agreed-upon interim assumptions to allow preliminary designs to proceed without risking rework.
Documented mutual responsibilities in interface agreements, ensuring alignment with the project schedule.
2. Data Staggering Milestones:
Broke down the equipment data submission into stages:
-- Stage 1: Preliminary data (weights, approximate dimensions, and estimated load ranges) for EPC-B to start foundation designs. + Separate IQ (Interface Query) exchange for future reference need to be included to IA (Interface Agreement).
-- Stage 2: Detailed specifications (bolt patterns, vibration analysis) at a later stage for final adjustments. + Separate IQ (Interface Query) exchange for future reference need to be included to IA (Interface Agreement).
3. Collaborative Workshops:
Conducted joint workshops every two weeks, involving process engineers from EPC-A and structural engineers from EPC-B. These workshops:
-- Resolved ambiguities in design assumptions.
-- Created a forum to discuss risks and develop immediate action plans for open issues.
In case agreement is not reached, Company (PMT) has to take decision based on collected inputs by EPCs.
4. Risk Mitigation and Adjustments:
Advised EPC-B to integrate flexibility into foundation designs (e.g., oversized bolt slots and additional reinforcement allowances) to reduce rework risks when final data arrived.
Used progress dashboards to track data submission and design progress, ensuring transparency and accountability.
5. Escalation Mechanism:
Established an escalation protocol involving the client’s technical team as a neutral mediator for unresolved disputes.
This avoided prolonged delays by ensuring decisions were made swiftly without compromising quality.
Outcome:
The staggered data release and adaptive design measures allowed civil works to proceed with minimal delays.
Rework was limited to minor adjustments, saving approximately 10% of the foundation budget.
Both contractors acknowledged the benefits of structured collaboration, and the project achieved a milestone completion within one week of the original schedule.
Lessons learned were documented to improve interface management in future multi-EPC projects.
Key Takeaways: This experience reinforced the importance of:
Early and detailed interface planning.
Flexible and adaptive design approaches.
Proactive, transparent communication across engineering teams.
This example provides detailed insights into the technical and management aspects of resolving an engineering interface challenge.