⚡ 𝗖𝗖𝗣 𝗤𝘂𝗲𝘀𝘁𝗶𝗼𝗻 #2️⃣ Which estimating technique is most appropriate during the early stages of a project when detailed information is not available? A. Bottom-Up Estimating B. Analogous Estimating C. Parametric Estimating D. Three-Point Estimating 💬 𝗖𝗼𝗺𝗺𝗲𝗻𝘁 𝘆𝗼𝘂𝗿 𝗮𝗻𝘀𝘄𝗲𝗿 𝗯𝗲𝗹𝗼𝘄 & 𝗙𝗼𝗹𝗹𝗼𝘄 𝗺𝗲 for daily CCP and Cost Engineering insights! ✅ 𝗔𝗻𝘀𝘄𝗲𝗿 𝘁𝗼 𝗖𝗖𝗣 𝗤𝘂𝗲𝘀𝘁𝗶𝗼𝗻 #1️⃣: 𝗕 – Scope Baseline Explanation: The Scope Baseline defines the project scope, which is essential for accurate cost estimation. #𝗖𝗖𝗣 #𝗖𝗼𝘀𝘁𝗖𝗼𝗻𝘁𝗿𝗼𝗹 #𝗔𝗔𝗖𝗘 #𝗣𝗹𝗮𝗻𝗻𝗶𝗻𝗴𝗘𝗻𝗴𝗶𝗻𝗲𝗲𝗿 #𝗣𝗿𝗼𝗷𝗲𝗰𝘁𝗠𝗮𝗻𝗮𝗴𝗲𝗺𝗲𝗻𝘁
B
B
A
B
B
Analogous Estimation technique is used for Estimation at early stages of project when very less information of deliverables are available
B: Analogous estimating