💰 𝗖𝗖𝗣 𝗤𝗨𝗘𝗦𝗧𝗜𝗢𝗡 #12 📉 During cost analysis, the project is trending over budget due to material price escalation. What is the BEST action for the cost engineer? ➤ A. Update the cost baseline immediately ➤ B. Perform a detailed variance analysis and recommend corrective actions ➤ C. Apply a management reserve to cover the increase ➤ D. Escalate the issue to senior management without analysis ✔ 𝗔𝗻𝘀𝘄𝗲𝗿 𝘁𝗼 𝗖𝗖𝗣 𝗤𝘂𝗲𝘀𝘁𝗶𝗼𝗻 #11: 𝗖 – Apply value engineering to reduce costs without affecting quality 𝗘𝘅𝗽𝗹𝗮𝗻𝗮𝘁𝗶𝗼𝗻: Value engineering helps optimize cost without sacrificing functionality or quality. Get more challenges from here: https://lnkd.in/dPFFCJGu #𝗖𝗖𝗣 #𝗔𝗔𝗖𝗘 #𝗖𝗼𝘀𝘁𝗠𝗮𝗻𝗮𝗴𝗲𝗺𝗲𝗻𝘁 #𝗣𝗿𝗼𝗷𝗲𝗰𝘁𝗖𝗼𝗻𝘁𝗿𝗼𝗹𝘀 #𝗘𝗮𝗿𝗻𝗲𝗱𝗩𝗮𝗹𝘂𝗲
The answer is B. We need to first analyze why costs are increasing and then propose corrective measures.
[B] Analyze the variance, justify the reason or root cause, and the study all impacts of escalation, then suggest the corrective actions, not to recommend unless review the contract conditions, and other areas of damages
B
B
sure we have to analyze first before taking actions 👌 (B)
B
B
Asst. Planning Manager at L&T ll Project Management & Controls II PMP in progress
2wB