The document is a project report analyzing power system upgrades needed after retirement of the SANDERS69 power plant in Metropolis. It summarizes the initial base case with losses of 13.54 MW and notes all bus voltages and line flows are within limits. It then outlines steps taken to analyze available new transmission line rights-of-way and identify the most economical system upgrades to ensure secure and compliant operation after plant retirement.