Purpose & Description
The purpose of this exercise is to introduce ETAP’s 3D database operation. The configuration and data
manager s should be used to create and modify the data. The configurations can also be directly edited
from the one-line diagram.
Setup
Open project “WrkShopEx_1” (system from “Creating One-Line Diagram” exercise).
Procedure
1. Create Configurations: The configurations can be created from the configuration manager.
Name Parameters Parameters*
Normal All PDs are closed.
Tie-Open Open Tie CB CB9 open
Co Gen Off Open Generator terminal CB CB3 open
Network 1 Down Disconnect Network 1 from sources CB4 and 6 open
*Note that the protective device names may not match, but the equivalent elements (as displayed above) should be selected.
Exercises for 3 Dimensional Data Base
ETAP Workshop Notes ©1996-2012 ETAP/Operation Technology, Inc. Page 2 of 2
2. Create, Merge Revisions: The revisions can be created from the data manager.
Revision Different from Base Revision
Revision1 T1: Z=5.5; Cable 2: Length = 500ft, Size = 350 Group 1
Revision2 T3: Z=5.5; Cable 1: Length = 550ft, Size = 350 Group 1
Revision3 Lump 3: 6.5 MVA; T1: Z=6.5; T3: Z=6.5;
a. Revision Merge - I
 Create Revision4
 Merge Revision 1 and Revision 2 to Revision 4.
 Check the difference between Revision 1 and 4.
b. Revision Merge - II
 Merge Revision 1 to Revision 3.
 Check T1 and T3 impedance. Are they same and why?
c. Change in Base Revision Data
 In Base Revision, change Cable1 and Cable 2: Length = 1000, Size = 750.
 Run load flow calculation
 Check cable data in Revision 1 – 4. Are they same as Base and why?
 Check report

More Related Content

PPTX
Fyp poster
DOCX
Analysis of Bracket for stress performance
PDF
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
PDF
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
DOCX
Reversible data hiding with optimal value transfer
PDF
Practica_Configuracion_Basica_SW_Cisco
PDF
DigSILENT PF - 06 irena additional exercises
Fyp poster
Analysis of Bracket for stress performance
Non linear analysis of Robot Gun Support Structure using Equivalent Dynamic A...
Static Analysis of Go-Kart Chassis by Analytical and Solid Works Simulation
Reversible data hiding with optimal value transfer
Practica_Configuracion_Basica_SW_Cisco
DigSILENT PF - 06 irena additional exercises

Similar to 3 d db-exercise-workshop (20)

PPTX
Iwsm2014 performance measurement for cloud computing applications using iso...
PDF
Scaling Networks Lab Manual 1st Edition Cisco Solutions Manual
PDF
JavaOne2013: Implement a High Level Parallel API - Richard Ning
PPTX
Comtrade file manipulationver1
PDF
Advanced FEM and Meshfree Class Workshop.pdf
PPT
Per domain power analysis
PDF
Data center-server-cooling-power-management-paper
PDF
ETAP - Power system modeling
PDF
Physical design
PPTX
How to Cost-Optimize Cloud Data Pipelines_.pptx
PDF
1 z0 052
DOCX
empirical analysis modeling of power dissipation control in internet data ce...
PDF
IRJET- Implementation and Simulation of Failsafe Network Architecture
DOCX
References1. HCS 2010 online manuals.2. Data Data provi.docx
PDF
Odd numbered home work problem solutions
PPT
11 req specs
PDF
Improve datacenter energy efficiency with Intel Node Manager
DOC
Ecet 380 Success Begins / snaptutorial.com
PPTX
Performance Tuning Oracle's BI Applications
PDF
ASIC Synthesis Optimizations And Settings Part 3
Iwsm2014 performance measurement for cloud computing applications using iso...
Scaling Networks Lab Manual 1st Edition Cisco Solutions Manual
JavaOne2013: Implement a High Level Parallel API - Richard Ning
Comtrade file manipulationver1
Advanced FEM and Meshfree Class Workshop.pdf
Per domain power analysis
Data center-server-cooling-power-management-paper
ETAP - Power system modeling
Physical design
How to Cost-Optimize Cloud Data Pipelines_.pptx
1 z0 052
empirical analysis modeling of power dissipation control in internet data ce...
IRJET- Implementation and Simulation of Failsafe Network Architecture
References1. HCS 2010 online manuals.2. Data Data provi.docx
Odd numbered home work problem solutions
11 req specs
Improve datacenter energy efficiency with Intel Node Manager
Ecet 380 Success Begins / snaptutorial.com
Performance Tuning Oracle's BI Applications
ASIC Synthesis Optimizations And Settings Part 3
Ad

Recently uploaded (20)

PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPT
Project quality management in manufacturing
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Sustainable Sites - Green Building Construction
PPTX
Geodesy 1.pptx...............................................
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
UNIT 4 Total Quality Management .pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
web development for engineering and engineering
PPTX
Artificial Intelligence
PPTX
additive manufacturing of ss316l using mig welding
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PDF
Well-logging-methods_new................
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
bas. eng. economics group 4 presentation 1.pptx
Project quality management in manufacturing
Fundamentals of safety and accident prevention -final (1).pptx
Model Code of Practice - Construction Work - 21102022 .pdf
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Sustainable Sites - Green Building Construction
Geodesy 1.pptx...............................................
Safety Seminar civil to be ensured for safe working.
UNIT 4 Total Quality Management .pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
web development for engineering and engineering
Artificial Intelligence
additive manufacturing of ss316l using mig welding
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Well-logging-methods_new................
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Foundation to blockchain - A guide to Blockchain Tech
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Operating System & Kernel Study Guide-1 - converted.pdf
Ad

3 d db-exercise-workshop

  • 1. Exercises for 3 Dimensional Data Base ETAP Workshop Notes ©1996-2012 ETAP/Operation Technology, Inc. Page 1 of 2 Purpose & Description The purpose of this exercise is to introduce ETAP’s 3D database operation. The configuration and data manager s should be used to create and modify the data. The configurations can also be directly edited from the one-line diagram. Setup Open project “WrkShopEx_1” (system from “Creating One-Line Diagram” exercise). Procedure 1. Create Configurations: The configurations can be created from the configuration manager. Name Parameters Parameters* Normal All PDs are closed. Tie-Open Open Tie CB CB9 open Co Gen Off Open Generator terminal CB CB3 open Network 1 Down Disconnect Network 1 from sources CB4 and 6 open *Note that the protective device names may not match, but the equivalent elements (as displayed above) should be selected.
  • 2. Exercises for 3 Dimensional Data Base ETAP Workshop Notes ©1996-2012 ETAP/Operation Technology, Inc. Page 2 of 2 2. Create, Merge Revisions: The revisions can be created from the data manager. Revision Different from Base Revision Revision1 T1: Z=5.5; Cable 2: Length = 500ft, Size = 350 Group 1 Revision2 T3: Z=5.5; Cable 1: Length = 550ft, Size = 350 Group 1 Revision3 Lump 3: 6.5 MVA; T1: Z=6.5; T3: Z=6.5; a. Revision Merge - I  Create Revision4  Merge Revision 1 and Revision 2 to Revision 4.  Check the difference between Revision 1 and 4. b. Revision Merge - II  Merge Revision 1 to Revision 3.  Check T1 and T3 impedance. Are they same and why? c. Change in Base Revision Data  In Base Revision, change Cable1 and Cable 2: Length = 1000, Size = 750.  Run load flow calculation  Check cable data in Revision 1 – 4. Are they same as Base and why?  Check report