Business Case
CMS IT Governance Training
CMS’ Target Life Cycle (TLC)
• CMS is now operating under the Target Life Cycle (TLC) IT Governance
Framework
• The TLC brings together Subject Matter Experts (SMEs) and decision-
makers from across CMS to strategically manage our IT Portfolio.
• In order for these SMEs to evaluate new IT projects properly, we may
require you to complete a Business Case outlining your proposal.
IT Business Case
• When do I need one?
New IT development or major changes to existing systems usually
require a Business Case – confirmed by CMS IT Governance upon
receiving your intake form in the “Initiate” phase of the TLC.
• How is it used?
The Business Case allows the Governance Review Team (GRT) and
Governance Review Board (GRB) to evaluate, advise, and ultimately
approve or deny your project.
TLC "Initiate" Phase Process Flow
IT Business Case – What Does it Cover?
• Business Need
• Description of the business need/issue/problem and why you are proposing a new IT
solution to meet this business need rather than meeting the need within existing
resources.
• Benefits to CMS
• How this effort benefits CMS, including any information on how it supports CMS'
mission and strategic goals, creates efficiencies and/or cost savings, or reduces risk.
• Alignment with Organizational Priorities
• Does this effort support any Administrator priorities or new legislative or regulatory
mandates?
• Performance Measurement
• How will you determine whether or not this effort is successful? Here’s a good rule of
thumb: State the exact data or metrics to use in support of this Performance Goal:
WHO is going to do exactly WHAT, by exactly HOW MUCH, by exactly WHEN?
Proposed Alternatives to Meet Business Need
• This is where you identify options and alternatives to meet your
business need. Your team must exercise due diligence in determining
the most viable and cost effective solution.
• This includes a summary of the approaches, how you will acquire the
solution, and describe the pros, cons, total life cycle costs and
potential cost savings/avoidance for each alternative considered.
• Include at least three viable alternatives: keeping things “as-is” or
reuse existing people, equipment, or processes; and at least two
additional alternatives. Identify your preferred solution.
Proposed Alternatives cont’d
• Some examples of alternatives to consider may include:
• Buy vs. build vs. lease vs. reuse of existing system
• Commercial off the shelf (COTS) vs. Government off the shelf (GOTS)
• Mainframe vs. server-based vs. clustering vs. Cloud
• In your alternatives, include details such as differences between
system capabilities, user friendliness, technical and security
considerations, ease and timing of integration with CMS' IT
infrastructure, etc.
Estimated Life Cycle Cost
• Estimate the total life cycle cost
• How much to develop/initialize the product or service?
• AND how long to operate after development is complete – how long until
we have to replace? (a 5 year total life cycle is typical)
• Note: these estimates will likely evolve as you refine your Business Case
throughout the intake process – no worries.
• Your Life Cycle Cost projections are one of the most important factors that
the Board considers when making a determination on your project.
• The IT Investment Management team can assist with your cost estimates if
needed
Highlights
• Within CMS’ IT Governance Framework, SMEs use your Business Case to
evaluate your proposal and ultimately approve or deny your project.
• Please fill out the entire Business Case to the best of your ability and with as
much precision as possible to facilitate this process. Help is available:
• EnterpriseArchitecture@cms.hhs.gov
• CMS_TRB@cms.hhs.gov
• IT_Investments@cms.hhs.gov
• Our IT Governance homepage is a one-stop shop for all TLC-related
information, including the IT Intake form, and the IT Business Case Template
For questions about IT Governance or more information
email:
IT_Governance@cms.hhs.gov
or visit:
IT Governance (https://www.cms.gov/TLC)
Contact Us

More Related Content

PDF
Practical tips for implementing corporate performance management system
PDF
WEEK2-Analyzing the Business Case.pdf
PDF
Who Does What, When, and How for a Divestiture?
PDF
SQL Saturday STL 2016 Presentation
PDF
Kapten Case Study April 2019 for HR presentation
PDF
The moving force behind IT decisions are variable as to what context.pdf
PPTX
Leveraging Your CMMS - From Selection to Daily Use
PPTX
Financial Crime Projects
Practical tips for implementing corporate performance management system
WEEK2-Analyzing the Business Case.pdf
Who Does What, When, and How for a Divestiture?
SQL Saturday STL 2016 Presentation
Kapten Case Study April 2019 for HR presentation
The moving force behind IT decisions are variable as to what context.pdf
Leveraging Your CMMS - From Selection to Daily Use
Financial Crime Projects

Similar to Business Case Training - Slides.pptx (20)

PDF
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
PPTX
Gaining and Maintaining IT & Business Alignment.pptx
PPTX
Analyzing the Business Case for System Analysis and Design
PDF
THE CIO PLAYBOOK NINE STEPS CIOS MUST TAKE FOR SUCCESSFUL DIVESTITURE
PDF
Enterprise Governance - The Key to Success
PPTX
ITM business barriers.pptx
PPTX
BPM (Business Process Management) Introduction
PPTX
Market Volatility Considerations for Scale-up Stage Tech Companies in 2023 - ...
PPTX
Standardize the Service Desk
PPTX
ISBB_Chapter8.pptx
PPTX
ISBB_Chapter8.pptx
PPTX
How to increase utilisation and realisation levels
PDF
Three steps-to-selecting-a-plm-system-white-paper
PPTX
Business Change and Transformation Services V4
PPTX
Operating model - Restructuring - Case study
PDF
The New Way CPAs are Delivering Value: Aligning Automation with Client Success
DOCX
University of the CumberlandsITS 831 Information Technology Impo.docx
PDF
Kaizen Egypt | Introduction to Business Process Management & Process Developm...
PPTX
Strategic Value Assessment
PPSX
Supporting material for my Webinar to the ACS - June2017
How Nationwide Insurance Transformed and Accelerated its Small_1.3.1
Gaining and Maintaining IT & Business Alignment.pptx
Analyzing the Business Case for System Analysis and Design
THE CIO PLAYBOOK NINE STEPS CIOS MUST TAKE FOR SUCCESSFUL DIVESTITURE
Enterprise Governance - The Key to Success
ITM business barriers.pptx
BPM (Business Process Management) Introduction
Market Volatility Considerations for Scale-up Stage Tech Companies in 2023 - ...
Standardize the Service Desk
ISBB_Chapter8.pptx
ISBB_Chapter8.pptx
How to increase utilisation and realisation levels
Three steps-to-selecting-a-plm-system-white-paper
Business Change and Transformation Services V4
Operating model - Restructuring - Case study
The New Way CPAs are Delivering Value: Aligning Automation with Client Success
University of the CumberlandsITS 831 Information Technology Impo.docx
Kaizen Egypt | Introduction to Business Process Management & Process Developm...
Strategic Value Assessment
Supporting material for my Webinar to the ACS - June2017
Ad

More from ReemaAsker1 (8)

PDF
05_nlp_Vectorization_ML_model_in_text_analysis.pdf
PPTX
frontendwebdevelopment-190510024804 (1).pptx
PPT
IntroductionToCSharp.ppt
PPT
IntroductionToCSharp.ppt
PPTX
Programming Lesson by Slidesgo - Copy.pptx
PPTX
Stuttgarter Weindorf by Slidesgo.pptx
PPTX
Formal Presentation Template.pptx
PPTX
note2_DesignPatterns (1).pptx
05_nlp_Vectorization_ML_model_in_text_analysis.pdf
frontendwebdevelopment-190510024804 (1).pptx
IntroductionToCSharp.ppt
IntroductionToCSharp.ppt
Programming Lesson by Slidesgo - Copy.pptx
Stuttgarter Weindorf by Slidesgo.pptx
Formal Presentation Template.pptx
note2_DesignPatterns (1).pptx
Ad

Recently uploaded (20)

PDF
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
PDF
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
PPTX
TNA_Presentation-1-Final(SAVE)) (1).pptx
PDF
LDMMIA Reiki Yoga Finals Review Spring Summer
PDF
Complications of Minimal Access-Surgery.pdf
PDF
International_Financial_Reporting_Standa.pdf
PPTX
Computer Architecture Input Output Memory.pptx
PDF
Weekly quiz Compilation Jan -July 25.pdf
PDF
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
PDF
Trump Administration's workforce development strategy
PDF
Paper A Mock Exam 9_ Attempt review.pdf.
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PDF
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
PPTX
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
PDF
advance database management system book.pdf
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PDF
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
PDF
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
PDF
IGGE1 Understanding the Self1234567891011
PPTX
Share_Module_2_Power_conflict_and_negotiation.pptx
medical_surgical_nursing_10th_edition_ignatavicius_TEST_BANK_pdf.pdf
BP 704 T. NOVEL DRUG DELIVERY SYSTEMS (UNIT 1)
TNA_Presentation-1-Final(SAVE)) (1).pptx
LDMMIA Reiki Yoga Finals Review Spring Summer
Complications of Minimal Access-Surgery.pdf
International_Financial_Reporting_Standa.pdf
Computer Architecture Input Output Memory.pptx
Weekly quiz Compilation Jan -July 25.pdf
Vision Prelims GS PYQ Analysis 2011-2022 www.upscpdf.com.pdf
Trump Administration's workforce development strategy
Paper A Mock Exam 9_ Attempt review.pdf.
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
ChatGPT for Dummies - Pam Baker Ccesa007.pdf
ELIAS-SEZIURE AND EPilepsy semmioan session.pptx
advance database management system book.pdf
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
MBA _Common_ 2nd year Syllabus _2021-22_.pdf
1.3 FINAL REVISED K-10 PE and Health CG 2023 Grades 4-10 (1).pdf
IGGE1 Understanding the Self1234567891011
Share_Module_2_Power_conflict_and_negotiation.pptx

Business Case Training - Slides.pptx

  • 1. Business Case CMS IT Governance Training
  • 2. CMS’ Target Life Cycle (TLC) • CMS is now operating under the Target Life Cycle (TLC) IT Governance Framework • The TLC brings together Subject Matter Experts (SMEs) and decision- makers from across CMS to strategically manage our IT Portfolio. • In order for these SMEs to evaluate new IT projects properly, we may require you to complete a Business Case outlining your proposal.
  • 3. IT Business Case • When do I need one? New IT development or major changes to existing systems usually require a Business Case – confirmed by CMS IT Governance upon receiving your intake form in the “Initiate” phase of the TLC. • How is it used? The Business Case allows the Governance Review Team (GRT) and Governance Review Board (GRB) to evaluate, advise, and ultimately approve or deny your project.
  • 4. TLC "Initiate" Phase Process Flow
  • 5. IT Business Case – What Does it Cover? • Business Need • Description of the business need/issue/problem and why you are proposing a new IT solution to meet this business need rather than meeting the need within existing resources. • Benefits to CMS • How this effort benefits CMS, including any information on how it supports CMS' mission and strategic goals, creates efficiencies and/or cost savings, or reduces risk. • Alignment with Organizational Priorities • Does this effort support any Administrator priorities or new legislative or regulatory mandates? • Performance Measurement • How will you determine whether or not this effort is successful? Here’s a good rule of thumb: State the exact data or metrics to use in support of this Performance Goal: WHO is going to do exactly WHAT, by exactly HOW MUCH, by exactly WHEN?
  • 6. Proposed Alternatives to Meet Business Need • This is where you identify options and alternatives to meet your business need. Your team must exercise due diligence in determining the most viable and cost effective solution. • This includes a summary of the approaches, how you will acquire the solution, and describe the pros, cons, total life cycle costs and potential cost savings/avoidance for each alternative considered. • Include at least three viable alternatives: keeping things “as-is” or reuse existing people, equipment, or processes; and at least two additional alternatives. Identify your preferred solution.
  • 7. Proposed Alternatives cont’d • Some examples of alternatives to consider may include: • Buy vs. build vs. lease vs. reuse of existing system • Commercial off the shelf (COTS) vs. Government off the shelf (GOTS) • Mainframe vs. server-based vs. clustering vs. Cloud • In your alternatives, include details such as differences between system capabilities, user friendliness, technical and security considerations, ease and timing of integration with CMS' IT infrastructure, etc.
  • 8. Estimated Life Cycle Cost • Estimate the total life cycle cost • How much to develop/initialize the product or service? • AND how long to operate after development is complete – how long until we have to replace? (a 5 year total life cycle is typical) • Note: these estimates will likely evolve as you refine your Business Case throughout the intake process – no worries. • Your Life Cycle Cost projections are one of the most important factors that the Board considers when making a determination on your project. • The IT Investment Management team can assist with your cost estimates if needed
  • 9. Highlights • Within CMS’ IT Governance Framework, SMEs use your Business Case to evaluate your proposal and ultimately approve or deny your project. • Please fill out the entire Business Case to the best of your ability and with as much precision as possible to facilitate this process. Help is available: • EnterpriseArchitecture@cms.hhs.gov • CMS_TRB@cms.hhs.gov • IT_Investments@cms.hhs.gov • Our IT Governance homepage is a one-stop shop for all TLC-related information, including the IT Intake form, and the IT Business Case Template
  • 10. For questions about IT Governance or more information email: IT_Governance@cms.hhs.gov or visit: IT Governance (https://www.cms.gov/TLC) Contact Us