The document provides details from the final inspection submission for the Bulk Liquid Storage Terminal Facility Phase II project. It includes information on 8 foundation sites that were inspected on April 19, 2015, such as location markings, dimensions, diagonal lengths, top of concrete levels, and anchor bolt top levels. Deviations from design drawings are also noted. Inspections found dimensions to be within 0.02 mm of specifications for all foundations.