ASCE
2013 Tri-County Workshop
State of South Florida’s Infrastructure
Miami-Dade County
WASD Infrastructure Update
May 10, 2013
Existing Water Infrastructure
• 3 large regional and 5 small water treatment plants
• 100 water supply wells
• 7,918 miles of pipes
• 38,000 fire hydrants
• 126,000 valves
• 11 treated water storage tanks
• 455,000 water meters
Existing Wastewater Infrastructure
• 3 wastewater treatment
plants
• 2 ocean outfalls
• 21 deep injection wells
• 6,277 miles of pipes
• 1,042 sewer pumps
stations
Infrastructure Deficiencies
• In February 2012, the Board of County
Commissioners directed the Mayor to provide report
addressing WASD’s aging and deteriorating
infrastructure
• In July 2012, report transmitted to the Board
• Report identified:
– Critical water and sewer projects
– $1.1 Billion estimated cost to implement
 $364.2 Million Water
 $736.1 Million Wastewater
– Funding needs
Regulatory Requirements
• Federal Clean Water Act
(EPA Consent Decree)
• State 2008 Ocean
Outfall Legislation
• 20-Yr Water Use Permit
EPA Consent Decree
• Implementation of capital projects in 15 years, at a
cost of about $1.6 billion
• Development of Capacity, Management, Operation,
and Maintenance (CMOM) Procedures to ensure
compliance with Clean Water Act
• Implementation of a Supplemental Environmental
Project for $2.047 million
State Ocean Outfall Legislation
• Bill passed in the 2008 Session requires:
 July 1, 2013, submit implementation plan to FDEP
 Reduce nutrients out to the ocean
 December 31, 2025, stop using outfall and implement 60%
reuse
• On April 24, 2013, the Governor signed an amendment
to the bill that saves WASD approximately $1 Billion
by:
 Allowing wet weather flows to continue going out the outfall (up
to 5% of the flow)
 Giving credit for reuse at other facilities (WASD/FPL 90 MGD
reuse project)
MYCIP FY 13-19 Combined (000)
Total Proposed FY13-19 Plan is $12.6Billion:
– $4.08 Billion Water
– $8.56 Billion Wastewater
$0
$1,000,000
$2,000,000
$3,000,000
$4,000,000
$5,000,000
$6,000,000
$7,000,000
$8,000,000
Prior FY13-14 FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 Future
$722,134
$312,415
$551,681 $582,923
$930,315
$1,102,733
$924,694
$7,508,328
MYCIP FY13-19 Drivers
Aging
Infrastructure
Projects,
$4,321,631 , 34%
Regulatory
Compliance
Projects,
$4,668,179 , 37%
Plant
Rehabilitation,
$891,627 , 7%
Consent Decree,
$1,603,677 , 13%
All Other,
$1,150,109 ,
9%
Funding Sources
Funding Sources
FUNDING SOURCES Amount (000)'s
Future WASD Revenue Bonds $8,861,800
Renewal and Replacement Fund $2,675,727
2013 Revenue Bond Sold $300,000
WASD revenue Bond Sold $237,748
General Obligation Fund $204,809
Plant Expansion Fund $200,086
HLD - Construction Fund $74,146
Special Construction Funds $46,364
Fire Hydrant Fund $34,542
Total $12,635,222
Significant Water Projects
Project Description
Multi-Year
Impact
% Multi-
Year
Impact
WATER TREATMENT PLANT
ALEXANDER ORR JR. EXPANSION
$428,442 11%
WATER DISTRIBUTION SYSTEM
EXTENSION ENHANCEMENTS
$1,756,804 43%
SAFE DRINKING WATER ACT
MODIFICATIONS-SWT RULE & D-DBP
$631,424 15%
SOUTH MIAMI HEIGHTS WATER
TREATMENT PLANT & WELLFIELDS
$189,085 5%
WATER SYSTEM MAINTENANCE AND
UPGRADES
$336,772 8%
ALL OTHER PROJECTS $732,655 18%
TOTAL $4,075,182
Significant Wastewater Projects
Project Description
Multi-Year
Impact
% Multi-
Year
Impact
SOUTH DISTRICT WASTEWATER
TREATMENT PLANT EXPANSION
$237,010 2%
CONSENT DECREE WASTEWATER
TREATMENT PLANTS
$1,026,767 11%
PEAK FLOW MANAGEMENT $867,392 9%
SANITARY SEWER SYSTEM
EXTENSION
$434,625 5%
CONSENT DECREE WASTEWATER
COLLECTION AND TRANSMISSION
LINES
$470,142 5%
CONSENT DECREE SEWER PUMP
STATION SYSTEMS
$106,768 1%
OUTFALL LEGISLATION $2,987,930 42%
ALL OTHER PROJECTS $2,429,407 25%
TOTAL $8,560,041
Questions?

More Related Content

PPTX
Sustainable Groundwater Management Act (SGMA) | Enrique Lopezcalva, RMC Water...
PPTX
Texas Water Development Board Presentation October 4, 2011
PPTX
How OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWD
DOC
Attachment A Memo 2015
PDF
WPC Report - FINAL with signatures
PDF
WHCRWA APWA Presentation on CIP
PPTX
Urban Water Management Plan Update
PPTX
Water-Wastewater Impact Fees
Sustainable Groundwater Management Act (SGMA) | Enrique Lopezcalva, RMC Water...
Texas Water Development Board Presentation October 4, 2011
How OCWD Plans to Comply with SGMA, Or Are We Already There? | Roy Herndon, OCWD
Attachment A Memo 2015
WPC Report - FINAL with signatures
WHCRWA APWA Presentation on CIP
Urban Water Management Plan Update
Water-Wastewater Impact Fees

What's hot (20)

PDF
What’s in the Region H Plan? How much conservation do we need and how are we ...
PPTX
Ikhrata Climate Change
PDF
Water Conservation by the Yard: Estimating Savings from Outdoor Watering Rest...
PPTX
Texas Water Development Board Update
PDF
City of Huntsville: Deferring Capitol Costs through Outdoor Irrigation Restri...
PPTX
Well-to-Wheels overview from CHBC meeting
PPTX
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
PPTX
TWCA Speech – Rep. James Frank
PPTX
Update on ERCOT Activities
PPT
World Bank Water project for Andhra Pradesh
PPTX
Latur water supply project
PDF
Wp final climate action plan oct 24 2013
PPTX
How Does Texas Measure Up? Comparing Laws & Regulations Enacted in the 50 States
PPTX
CAP and the Navajo Generating Station
PPTX
State Legislative Changes Affecting Water Conservation
PDF
Climate Action Plan Update Sept 12 2013 Special Board Mtg
PDF
WHCRWA Town Hall Meeting 11-10-2014
PPTX
Groundwater management strategy by Dr S K Jain, CGWB
PDF
Master Plan EIR CAP Presentation - March 27, 2014
PPT
2011 Winter Meeting Lake Comp Plan update
What’s in the Region H Plan? How much conservation do we need and how are we ...
Ikhrata Climate Change
Water Conservation by the Yard: Estimating Savings from Outdoor Watering Rest...
Texas Water Development Board Update
City of Huntsville: Deferring Capitol Costs through Outdoor Irrigation Restri...
Well-to-Wheels overview from CHBC meeting
Brian Bradley, PA DEP, “Pennsylvania AML/AMD Program and Funding Overview”
TWCA Speech – Rep. James Frank
Update on ERCOT Activities
World Bank Water project for Andhra Pradesh
Latur water supply project
Wp final climate action plan oct 24 2013
How Does Texas Measure Up? Comparing Laws & Regulations Enacted in the 50 States
CAP and the Navajo Generating Station
State Legislative Changes Affecting Water Conservation
Climate Action Plan Update Sept 12 2013 Special Board Mtg
WHCRWA Town Hall Meeting 11-10-2014
Groundwater management strategy by Dr S K Jain, CGWB
Master Plan EIR CAP Presentation - March 27, 2014
2011 Winter Meeting Lake Comp Plan update
Ad

Viewers also liked (7)

PPT
Presentation3
PDF
ASSESSMENT OF WASTE WATER TREATMENT IN CANAANLAND, OTA, OGUN STATE, NIGERIA.O...
PPTX
Presentation1
PPTX
Presentation2
PPTX
New York activities
PDF
Dan Slee 'Social Media is local' DCCStudio Know How Session
PDF
Integrated Solid Waste Management as Panacea for a sustainable Clean City in ...
Presentation3
ASSESSMENT OF WASTE WATER TREATMENT IN CANAANLAND, OTA, OGUN STATE, NIGERIA.O...
Presentation1
Presentation2
New York activities
Dan Slee 'Social Media is local' DCCStudio Know How Session
Integrated Solid Waste Management as Panacea for a sustainable Clean City in ...
Ad

Similar to 1.1 mdwasd update (20)

PPTX
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
PDF
2024 milon-Capital-Budget-Presentation.pdf
PDF
2024-Capital-Budget-Presentation.pdf milon
PPTX
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
PDF
Winter Springs 2023 Water and Wastewater Rate Study
PDF
2023 Winter Springs Water and Wastewater Rate Study Presentation
PDF
SV Ranganath's Lecture on Water Governance in Bangalore
PDF
Bay-Delta Update - Carlsbad City Council, Sept. 17, 2013
PPTX
What’s in the Region C Plan: How much conservation do we need and how are we ...
PPTX
LSL replacement
PPTX
Civil Works Multi-purpose Reservoir Infrastructure Strategy & Future Opportun...
PPT
Steve Stewart CCW
PPT
Georgia Water Conservation by Alice Miller Keyes, GA EPD
PPTX
College Station Water Supply
PDF
Carlsbad Seawater Desalination Project Update
PDF
Paul Helliker - BDCP
PPT
State of the City 2012
PPTX
Wastewater Master Plan Update
PPTX
Chesapeake Bay Watershed Implementation Planning Process
PDF
2015-2016 Bay-Delta Workplan - February 26, 2015
USCID conference in San Diego May 17-20, 2016_GrD Salton Sea update presentat...
2024 milon-Capital-Budget-Presentation.pdf
2024-Capital-Budget-Presentation.pdf milon
Mr. Anju Gaur IEWP @ Workshop on River Basin Management Planning and Governan...
Winter Springs 2023 Water and Wastewater Rate Study
2023 Winter Springs Water and Wastewater Rate Study Presentation
SV Ranganath's Lecture on Water Governance in Bangalore
Bay-Delta Update - Carlsbad City Council, Sept. 17, 2013
What’s in the Region C Plan: How much conservation do we need and how are we ...
LSL replacement
Civil Works Multi-purpose Reservoir Infrastructure Strategy & Future Opportun...
Steve Stewart CCW
Georgia Water Conservation by Alice Miller Keyes, GA EPD
College Station Water Supply
Carlsbad Seawater Desalination Project Update
Paul Helliker - BDCP
State of the City 2012
Wastewater Master Plan Update
Chesapeake Bay Watershed Implementation Planning Process
2015-2016 Bay-Delta Workplan - February 26, 2015

More from ascemiami-dade (20)

PDF
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
PDF
3.1 defining level of service based on dynamic environmental, economic, and s...
PDF
2.3 i 595 improvements
PPT
K.1 turkey point units 6 & 7 project
PDF
2.4 fll airport improvements
PPT
K.2 vogtle units 3 and 4 nuclear development early site construction progression
PDF
3.1 defining level of service based on dynamic environmental, economic, and s...
PDF
2.3 i 595 improvements
PDF
4 public policy panel
PDF
3.4 northern everglades payment for environmental services a public private p...
PDF
PDF
3.2 wpb transit village
PDF
3.3 everglades restoration plans
PDF
3 climate change
PDF
2.2 tri rail coastal link
PDF
2.2 tri rail coastal link
PDF
2.1 port of miami tunnel cei
PDF
1.4 l 8 feb and c51 reservoir
PDF
2 transportation
PDF
1.4 l 8 feb and c51 reservoir
Joint fsawwa region vii asce-ewri pipeline rehabilitation presentation ro 11-...
3.1 defining level of service based on dynamic environmental, economic, and s...
2.3 i 595 improvements
K.1 turkey point units 6 & 7 project
2.4 fll airport improvements
K.2 vogtle units 3 and 4 nuclear development early site construction progression
3.1 defining level of service based on dynamic environmental, economic, and s...
2.3 i 595 improvements
4 public policy panel
3.4 northern everglades payment for environmental services a public private p...
3.2 wpb transit village
3.3 everglades restoration plans
3 climate change
2.2 tri rail coastal link
2.2 tri rail coastal link
2.1 port of miami tunnel cei
1.4 l 8 feb and c51 reservoir
2 transportation
1.4 l 8 feb and c51 reservoir

1.1 mdwasd update

  • 1. ASCE 2013 Tri-County Workshop State of South Florida’s Infrastructure Miami-Dade County WASD Infrastructure Update May 10, 2013
  • 2. Existing Water Infrastructure • 3 large regional and 5 small water treatment plants • 100 water supply wells • 7,918 miles of pipes • 38,000 fire hydrants • 126,000 valves • 11 treated water storage tanks • 455,000 water meters
  • 3. Existing Wastewater Infrastructure • 3 wastewater treatment plants • 2 ocean outfalls • 21 deep injection wells • 6,277 miles of pipes • 1,042 sewer pumps stations
  • 4. Infrastructure Deficiencies • In February 2012, the Board of County Commissioners directed the Mayor to provide report addressing WASD’s aging and deteriorating infrastructure • In July 2012, report transmitted to the Board • Report identified: – Critical water and sewer projects – $1.1 Billion estimated cost to implement  $364.2 Million Water  $736.1 Million Wastewater – Funding needs
  • 5. Regulatory Requirements • Federal Clean Water Act (EPA Consent Decree) • State 2008 Ocean Outfall Legislation • 20-Yr Water Use Permit
  • 6. EPA Consent Decree • Implementation of capital projects in 15 years, at a cost of about $1.6 billion • Development of Capacity, Management, Operation, and Maintenance (CMOM) Procedures to ensure compliance with Clean Water Act • Implementation of a Supplemental Environmental Project for $2.047 million
  • 7. State Ocean Outfall Legislation • Bill passed in the 2008 Session requires:  July 1, 2013, submit implementation plan to FDEP  Reduce nutrients out to the ocean  December 31, 2025, stop using outfall and implement 60% reuse • On April 24, 2013, the Governor signed an amendment to the bill that saves WASD approximately $1 Billion by:  Allowing wet weather flows to continue going out the outfall (up to 5% of the flow)  Giving credit for reuse at other facilities (WASD/FPL 90 MGD reuse project)
  • 8. MYCIP FY 13-19 Combined (000) Total Proposed FY13-19 Plan is $12.6Billion: – $4.08 Billion Water – $8.56 Billion Wastewater $0 $1,000,000 $2,000,000 $3,000,000 $4,000,000 $5,000,000 $6,000,000 $7,000,000 $8,000,000 Prior FY13-14 FY14-15 FY15-16 FY16-17 FY17-18 FY18-19 Future $722,134 $312,415 $551,681 $582,923 $930,315 $1,102,733 $924,694 $7,508,328
  • 9. MYCIP FY13-19 Drivers Aging Infrastructure Projects, $4,321,631 , 34% Regulatory Compliance Projects, $4,668,179 , 37% Plant Rehabilitation, $891,627 , 7% Consent Decree, $1,603,677 , 13% All Other, $1,150,109 , 9%
  • 11. Funding Sources FUNDING SOURCES Amount (000)'s Future WASD Revenue Bonds $8,861,800 Renewal and Replacement Fund $2,675,727 2013 Revenue Bond Sold $300,000 WASD revenue Bond Sold $237,748 General Obligation Fund $204,809 Plant Expansion Fund $200,086 HLD - Construction Fund $74,146 Special Construction Funds $46,364 Fire Hydrant Fund $34,542 Total $12,635,222
  • 12. Significant Water Projects Project Description Multi-Year Impact % Multi- Year Impact WATER TREATMENT PLANT ALEXANDER ORR JR. EXPANSION $428,442 11% WATER DISTRIBUTION SYSTEM EXTENSION ENHANCEMENTS $1,756,804 43% SAFE DRINKING WATER ACT MODIFICATIONS-SWT RULE & D-DBP $631,424 15% SOUTH MIAMI HEIGHTS WATER TREATMENT PLANT & WELLFIELDS $189,085 5% WATER SYSTEM MAINTENANCE AND UPGRADES $336,772 8% ALL OTHER PROJECTS $732,655 18% TOTAL $4,075,182
  • 13. Significant Wastewater Projects Project Description Multi-Year Impact % Multi- Year Impact SOUTH DISTRICT WASTEWATER TREATMENT PLANT EXPANSION $237,010 2% CONSENT DECREE WASTEWATER TREATMENT PLANTS $1,026,767 11% PEAK FLOW MANAGEMENT $867,392 9% SANITARY SEWER SYSTEM EXTENSION $434,625 5% CONSENT DECREE WASTEWATER COLLECTION AND TRANSMISSION LINES $470,142 5% CONSENT DECREE SEWER PUMP STATION SYSTEMS $106,768 1% OUTFALL LEGISLATION $2,987,930 42% ALL OTHER PROJECTS $2,429,407 25% TOTAL $8,560,041