Project Update
                                               IOCS
(Integrated Operation Control System)

                            To Steering Committee:
                 JKTOP,JKTOS,JKTML, JKTQX
                                        04 August 2008




                        Ref: JKTDO/SKEP/50001/08 – 26 Mei-2008
                      Project duration : 8 Month (until Feb 2009)



           04 August 2008
Agenda


        Project Background
        Project Update: Time frame & Issue
        ‘Workflow’ - Workshop Preparation
        Summary




4 August 2008
                                             2
Background




4 August 2008
                   3
OCC Concept

                                                             Short Time to take decisions
                Flights Control
                 Department




                                                    STRESS
                                                             No Tools, everything is done manually


                                                             Current KPI’s:
                                                             Delays / # Operations
Maintenance
                                                             Cancelations / # de Operations

                                           O.C.C. takes
                              O.C.C.       information from each
                                           department , evaluates
                                           the situation and
                                           makes a decision.
      Crew
   Department
                         Tail Assignment                          Passenger
                              (MCC)                          Traffic department
                                                                   Passenger re-route
                                                                   solutions after the
                                                                   decision was made.
Background (2)




                                                  
light Schedule-Related activities, and the application of the relevant NetLine Decision Support Suite component for the activity.



  4 August 2008
                                                                                                                                    5
Garuda Operation Control: As-Is / Existing
      High Level Flow Process - end of May 2008
        System:                              Publish time table
     netline/sched                      to ARGA (reservations system)

  JKTCNS
                             Time       LSYI
                             table



                                                               System:
        Download         A/C Rotation                                                                 Monthly
                                                            Crew mgt. Sys
        data from          Seasonal                                                                   Planning
                                                                (CMS)
      netline/sched                                                                                   Aircraft
     and create new                                         JKTOGM                                   Maintenance
        document
                                                CROPA                    Crew
      JKTOGR                                   (M. excel)               Roaster
                                                                                                       Weekly
                                                                                                       Aircraft
                                                                                                       Rotation
                                             Create crew
                        Monthly               operating              publish roaster
                        schedule              pattern in            by SMS &web Do                     Weekly
                                            Microsoft Excel                                           Workload
                                                                                                        Plan
                                         JKTOGM                   JKTOGM
          AC rotation                    Crew Management                                             Aircraft Daily
            Daily
                                                                                                         Status

                                         AC monitoring                            AC monitoring
                                                                                                     Maintenance
                                        by telex, phone &                      by telex , phone &      Control
                                              Web ?                                 Web-AMS          Daily Report

                                        OCC                                  MCC                    GA Technics
4 August 2008                           GA JKTOGM                            GMF                    /GMF
                                                                                                                      6
Garuda Operation Control: As-Is / Existing
      High Level Flow Process - end of May 2008
        System:                             Publish time table
     netline/sched                     to ARGA (reservations system)

  JKTCNS
                           Time        LSYI
                           table


                        A/C Rotation
                          Seasonal
        Download                                                                               Monthly
        data from                                                                              Planning
      netline/sched                                                                            Aircraft
     and create new                                                                           Maintenance
        document

      JKTOGR                                                                                    Weekly
                                                          Monthly
                                                      Flight schedule                           Aircraft
                                                                                                Rotation


                                                                                                Weekly
                                                                                               Workload
                                                                                                 Plan

          AC rotation
                                                                                              Aircraft Daily
            Daily
                                                                                                  Status

                                        AC monitoring                    AC monitoring
                                                                                              Maintenance
                                       by telex, phone &                by telex , phone &      Control
                                             Web ?                          Web-AMS           Daily Report

                                       OCC                              MCC                  GA Technics
4 August 2008                          GA JKTOGM                        GMF                  /GMF
                                                                                                               7
Project Time Frame
                                                           -Blade server - 4 July 08
                                                           -Storage – 19 July 08                      Netline/Ops ready
                                                           -DB installation – from 4Aug




                                                                Week 10
                                                                          Week 11
                                                                          Week 12
                                                                          Week 13
                                                                          Week 14
                                                                                    Week 15
                                                                                    Week 16


                                                                                              Week 18
                                                                                              Week 19
                                                                                              Week 20
                                                                                              Week 21
                                                                                                        Week 22
                                                                                                        Week 23
                                                                                                        Week 24
                                                                                                                  Week 25
                                                                                                                  Week 26
                                                                                                                  Week 27
                                                                                                                  Week 28
                                                                                                                            Week 29
                                                                                                                            Week 30
                                                           08




                                                                                    Week17
                                              Week 0
                                              Week 1
                                              Week 2
                                              Week 3
                                                       Week 4
                                                       Week 5
                                                       Week 6
                                                       Week 7
                                                                 Week 8
                                                                 Week 9
                                                           -Still In Progress


 1 Select Hardware
 2 Hardware,Standard SW, Lines ordered
 3 Project start
 4 Instalation                                                                                             GA crew rules is
                                                                                                          already submitted
 5 Netline/Base                                                                                                to LSY
 6 Netline/Sched
 7 Netline/Ops
 8 Netline/Ops MaintenanceControl

 9 Netline/Crew Legalities
10 Netline/Crew Pairing
11 Netline/Crew Assignment
12 Netline/Crew Tracking
13 netline/Crew CrewLink

14 Netline/Crew Pairing Optimizer                            List of interface is already finished.
15 Netline/Crew Fair Optimizer                               Detail program specification still in
                                                             progress.
16 Built Netline/Ops Interface with GA sys                   Interface platform still evaluated
17 Built Netline/Crew Interface with GA sys
18 Change Management
                                                                                        Project time line template from LS
4 August 2008
                                                                                                                               8
Issue
         1. Team member consolidations
         2. Interface with other application in Garuda (jeppesen, SAP-MRO,
            SAP-HR, fuel management, GMF-AMS, Catering system etc)
                •Existing, mostly by FTP & synchronous – hard to maintain
                •Consider Enterprise Service Bus (ESB) approach.


                                                  xml           xml

                                                  Service Bus
                                                   xml          xml




                    Existing                 With ESB




         3. Network connections to netline/Sched at Ratu Plaza, LSYI (
            2 MB/s lease line) should be established.
4 August 2008
                                                                             9
Issue (2)
         4. IOCS can be integrate to Aircraft Maintenance Planning systems.



                  Netine/ops       1
                  What is                     2


                  Netine/ops                       3    SAP R/3 Aircraft
                  Original              database
                                                        maintenance
                                  5                4    planning

                                                       Notification/HIL monitoring
                                                       Maintenance event builder
                                                       Work package creation

                Case Study: Lufthansa -CityLine


        • When &how the aircraft maintenance planning project will be started ?
        • Clear task/responsibilities between GMF/GA technique ?

4 August 2008
                                                                                     10
Garuda & GMF Operation Control System

                                                                   Garuda                                                                                                         GMF
                                                        Aircraft scheduling
                                                           & time table                                                                             SAP MRO stabilization
                                                          (netline/sched)                                                                           & improvement                              Data integrity for
                                                                                                                                                    •SN -leading zero
                                                                                                                                                                                                 aircraft site
                                                                                                                                                    •Engine configuration control
                                                                                                                                                    •Reliability report
                                                                                                                                                    •FFF Class                                 Data integrity for
                                                                                                                                                                                               line maintenance



                                                                                                                            t c ej or P O R M PAS
                                                                                                                                                    A/C maintenance planning
                                                        Aircraft operation                                                                          & document management.:
                                                           (netline/ops)                                                                                                                      Line maintenance
                                                                                                                                                    •Maint. program definitions
                                                                                                                                                    •A/C technical doc..                      planning & control
                                                                                                                                                    •Integrated job card sys.
                                                        Crew management                                                                                                                     Finance & controlling
                                                          (netline/crew)                                                                                                                           project
                                                                               . sy Sr et ne C l ort no C ec na net n a M




                                                                                                                                                    A/C phase In/ phase out
                                                                                                                    i
           t c ej or P. s y S l ort no C no t are p O




                                                                                                                                                                                              Business intelligent
                                                        Business intelligent                                                                        AGDL (Hermes / Aircom)                         project
                                                             project
                                           i




                                                                                                                                                                              Ref.“IT Planning for GMF
                                                                                                                                                                              AeroAsia rev0.5-19Dec Document”



      Source : Rencana kerja periode 2008 –JKTQX- 22 Jan 2008
4 August 2008
                                                                                                                                                                                                                     11
Case Study from Lufthansa CityLine
      CLH - Reengineering with SAP : MRO Business Process
                                   Maintenance
                                     Task List
                  Maintenance
                                       Job
                  Schedule
                                    Instruction
                                       Card
                                                                                          Rework-
                                                              Maintenance
                                    Deferred                                                Order
                                                                 Event
                                    Management                                          Administration
                                                                 Builder
                                                                                            (incl.
                                                             (Materialreserv.)
                                                                                       Contract, Billing)
                                     Modifications
                                                                                             Component
                                                                                              Subcon-
                                                                                              tracting
                                      Long
                  Flight
                                      Term
                 Schedule
                                     Planning

                                                              Legend:            Supported
                                                                                                   Legacy
                                                                                    by
                                                                                                   System
                                                                                  SAP R/3


                Source : International IS AD Forum , Düsseldorf, 06. 03. 2002 by Mark Nowak
4 August 2008
                                                                                                            12
‘IOCS workflow’ - Workshop Preparation


                    B                          B

                O       S                 O        S




        When & Where?

4 August 2008
                                                       13
Summary
         1. Pelaksanaan instalasi aplikasi perlu di monitor dengan ketat.
         2. Agggota tim IOCS agar mulai konsentrasi pada kegiatan
            implementasi, kegiatan IOCS disupport penuh oleh seluruh
            anggota steering committee .
         3. Adanya anggota tim yang PPS dan juga usulan penambahan
            anggota tim , untuk itu akan dilakukan pembuatan SK baru.
         4. Workshop workflow IOCS akan dilaksanakan dalam jangka 1
            bulan dari sekarang.
         5. Rapat anggota timsetiap hari Selasa pagi dan Kamis pagi.
            Update informasi perkembangan proyek melalui email. Rapat
            steering committee minimal 1 bulan sekali dan disarankan lebih
            sering.
         6. Proyek aircraft maintenance planning agar segera dimulai.




4 August 2008
                                                                             14
4 August 2008
                15

More Related Content

PPT
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
PDF
Robert.bayt
PDF
Operations reports may 2014
PPTX
ITChamps - Application Management Services
PPT
Project Management KPIs
PPT
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
PDF
Paul Saunders - Rusada Client Forum
PDF
Nek e am_overview_2010_1f.ppt [compatibility m
IGARSS 2011 - RCM, The Making of (AC) (Short).ppt
Robert.bayt
Operations reports may 2014
ITChamps - Application Management Services
Project Management KPIs
USCG R&D Center’s Analysis of Standard Boat Asset Project Office (APO’s) Met...
Paul Saunders - Rusada Client Forum
Nek e am_overview_2010_1f.ppt [compatibility m

Similar to 20080804 iocs steering commitee edited janto (20)

PDF
A Google Maps-based approach to Real-Time Traffic and Travel Information (RTT...
PDF
David.graham
PDF
Portofolio Control Version SN
PPT
Extractioncockpit
PPT
SWIMing in a Standards Soup
PDF
IRJET- Front View Identification of Vehicles by using Machine Learning Te...
PDF
Linda Jackman - Oracle
PPTX
Ruszkowski.james
PDF
An Architecture for Collaboration Patterns in Agile Event-Driven Environments
PPTX
Enabling the next generation airport at DXB
PDF
CG-LIMS for Kimball II team
PPTX
Peak’s Synchrophasor Technology Implementation Progress and Roadmap
PPTX
PDF
Mechatronics engineer
PPT
B Kindilien-Does Manufacturing Have a Future?
ODP
Internship Project (Lasindu) WSO2
PDF
Low cost Real Time Centralized Speed Control of DC Motor Using Lab View -NI U...
DOCX
Megalingam_Thiruvarangam_Resume
PDF
2011 07-27 ecoop innovation network
PDF
IRJET- Research Paper on Energy-Aware Virtual Machine Migration for Cloud Com...
A Google Maps-based approach to Real-Time Traffic and Travel Information (RTT...
David.graham
Portofolio Control Version SN
Extractioncockpit
SWIMing in a Standards Soup
IRJET- Front View Identification of Vehicles by using Machine Learning Te...
Linda Jackman - Oracle
Ruszkowski.james
An Architecture for Collaboration Patterns in Agile Event-Driven Environments
Enabling the next generation airport at DXB
CG-LIMS for Kimball II team
Peak’s Synchrophasor Technology Implementation Progress and Roadmap
Mechatronics engineer
B Kindilien-Does Manufacturing Have a Future?
Internship Project (Lasindu) WSO2
Low cost Real Time Centralized Speed Control of DC Motor Using Lab View -NI U...
Megalingam_Thiruvarangam_Resume
2011 07-27 ecoop innovation network
IRJET- Research Paper on Energy-Aware Virtual Machine Migration for Cloud Com...
Ad

20080804 iocs steering commitee edited janto

  • 1. Project Update IOCS (Integrated Operation Control System) To Steering Committee: JKTOP,JKTOS,JKTML, JKTQX 04 August 2008 Ref: JKTDO/SKEP/50001/08 – 26 Mei-2008 Project duration : 8 Month (until Feb 2009) 04 August 2008
  • 2. Agenda Project Background Project Update: Time frame & Issue ‘Workflow’ - Workshop Preparation Summary 4 August 2008 2
  • 4. OCC Concept Short Time to take decisions Flights Control Department STRESS No Tools, everything is done manually Current KPI’s: Delays / # Operations Maintenance Cancelations / # de Operations O.C.C. takes O.C.C. information from each department , evaluates the situation and makes a decision. Crew Department Tail Assignment Passenger (MCC) Traffic department Passenger re-route solutions after the decision was made.
  • 5. Background (2)                                                    light Schedule-Related activities, and the application of the relevant NetLine Decision Support Suite component for the activity. 4 August 2008 5
  • 6. Garuda Operation Control: As-Is / Existing High Level Flow Process - end of May 2008 System: Publish time table netline/sched to ARGA (reservations system) JKTCNS Time LSYI table System: Download A/C Rotation Monthly Crew mgt. Sys data from Seasonal Planning (CMS) netline/sched Aircraft and create new JKTOGM Maintenance document CROPA Crew JKTOGR (M. excel) Roaster Weekly Aircraft Rotation Create crew Monthly operating publish roaster schedule pattern in by SMS &web Do Weekly Microsoft Excel Workload Plan JKTOGM JKTOGM AC rotation Crew Management Aircraft Daily Daily Status AC monitoring AC monitoring Maintenance by telex, phone & by telex , phone & Control Web ? Web-AMS Daily Report OCC MCC GA Technics 4 August 2008 GA JKTOGM GMF /GMF 6
  • 7. Garuda Operation Control: As-Is / Existing High Level Flow Process - end of May 2008 System: Publish time table netline/sched to ARGA (reservations system) JKTCNS Time LSYI table A/C Rotation Seasonal Download Monthly data from Planning netline/sched Aircraft and create new Maintenance document JKTOGR Weekly Monthly Flight schedule Aircraft Rotation Weekly Workload Plan AC rotation Aircraft Daily Daily Status AC monitoring AC monitoring Maintenance by telex, phone & by telex , phone & Control Web ? Web-AMS Daily Report OCC MCC GA Technics 4 August 2008 GA JKTOGM GMF /GMF 7
  • 8. Project Time Frame -Blade server - 4 July 08 -Storage – 19 July 08 Netline/Ops ready -DB installation – from 4Aug Week 10 Week 11 Week 12 Week 13 Week 14 Week 15 Week 16 Week 18 Week 19 Week 20 Week 21 Week 22 Week 23 Week 24 Week 25 Week 26 Week 27 Week 28 Week 29 Week 30 08 Week17 Week 0 Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8 Week 9 -Still In Progress 1 Select Hardware 2 Hardware,Standard SW, Lines ordered 3 Project start 4 Instalation GA crew rules is already submitted 5 Netline/Base to LSY 6 Netline/Sched 7 Netline/Ops 8 Netline/Ops MaintenanceControl 9 Netline/Crew Legalities 10 Netline/Crew Pairing 11 Netline/Crew Assignment 12 Netline/Crew Tracking 13 netline/Crew CrewLink 14 Netline/Crew Pairing Optimizer List of interface is already finished. 15 Netline/Crew Fair Optimizer Detail program specification still in progress. 16 Built Netline/Ops Interface with GA sys Interface platform still evaluated 17 Built Netline/Crew Interface with GA sys 18 Change Management Project time line template from LS 4 August 2008 8
  • 9. Issue 1. Team member consolidations 2. Interface with other application in Garuda (jeppesen, SAP-MRO, SAP-HR, fuel management, GMF-AMS, Catering system etc) •Existing, mostly by FTP & synchronous – hard to maintain •Consider Enterprise Service Bus (ESB) approach. xml xml Service Bus xml xml Existing With ESB 3. Network connections to netline/Sched at Ratu Plaza, LSYI ( 2 MB/s lease line) should be established. 4 August 2008 9
  • 10. Issue (2) 4. IOCS can be integrate to Aircraft Maintenance Planning systems. Netine/ops 1 What is 2 Netine/ops 3 SAP R/3 Aircraft Original database maintenance 5 4 planning Notification/HIL monitoring Maintenance event builder Work package creation Case Study: Lufthansa -CityLine • When &how the aircraft maintenance planning project will be started ? • Clear task/responsibilities between GMF/GA technique ? 4 August 2008 10
  • 11. Garuda & GMF Operation Control System Garuda GMF Aircraft scheduling & time table SAP MRO stabilization (netline/sched) & improvement Data integrity for •SN -leading zero aircraft site •Engine configuration control •Reliability report •FFF Class Data integrity for line maintenance t c ej or P O R M PAS A/C maintenance planning Aircraft operation & document management.: (netline/ops) Line maintenance •Maint. program definitions •A/C technical doc.. planning & control •Integrated job card sys. Crew management Finance & controlling (netline/crew) project . sy Sr et ne C l ort no C ec na net n a M A/C phase In/ phase out i t c ej or P. s y S l ort no C no t are p O Business intelligent Business intelligent AGDL (Hermes / Aircom) project project i Ref.“IT Planning for GMF AeroAsia rev0.5-19Dec Document” Source : Rencana kerja periode 2008 –JKTQX- 22 Jan 2008 4 August 2008 11
  • 12. Case Study from Lufthansa CityLine CLH - Reengineering with SAP : MRO Business Process Maintenance Task List Maintenance Job Schedule Instruction Card Rework- Maintenance Deferred Order Event Management Administration Builder (incl. (Materialreserv.) Contract, Billing) Modifications Component Subcon- tracting Long Flight Term Schedule Planning Legend: Supported Legacy by System SAP R/3 Source : International IS AD Forum , Düsseldorf, 06. 03. 2002 by Mark Nowak 4 August 2008 12
  • 13. ‘IOCS workflow’ - Workshop Preparation B B O S O S When & Where? 4 August 2008 13
  • 14. Summary 1. Pelaksanaan instalasi aplikasi perlu di monitor dengan ketat. 2. Agggota tim IOCS agar mulai konsentrasi pada kegiatan implementasi, kegiatan IOCS disupport penuh oleh seluruh anggota steering committee . 3. Adanya anggota tim yang PPS dan juga usulan penambahan anggota tim , untuk itu akan dilakukan pembuatan SK baru. 4. Workshop workflow IOCS akan dilaksanakan dalam jangka 1 bulan dari sekarang. 5. Rapat anggota timsetiap hari Selasa pagi dan Kamis pagi. Update informasi perkembangan proyek melalui email. Rapat steering committee minimal 1 bulan sekali dan disarankan lebih sering. 6. Proyek aircraft maintenance planning agar segera dimulai. 4 August 2008 14

Editor's Notes

  • #2: Sambutan Selamat pagi kepada bapak-bapak komite pengarah Selamat pagi kepada bapak dan ibu anggota tim IOCS. Pengantar dari anggota steering committee.
  • #3: Pada hari yang berbahagia ini kami akan menyampaikan: Project background yang berisi motivasi untuk membangun sistem IOCS, terutama kepada anggota steering committee yang baru dalam proyek ini (JKTML). Project update; mengenai time frame dari proyek dan issue yang perlu diperhatikan atau diselesaikan agar proyek dapat diselesaikan dengan tepat waktu. Workflow workshop (preparation); perlunya workshop dengan calon user untuk mapping proses bisnis , organisasi dan sistem. Summary; konfirmasi item-item yang perlu segera ditindaklanjuti.
  • #4: Motivasi untuk mempunyai sistem operation control yang terintegrasi adalah kompleksitas dari kontrol operasional suatu airline seperti terlihat pada slide ini. Dibutuhkan beberapa departemen untuk menunjang airline dan juga keharusan airline untuk melakukan antisipasi bila terjadi irregularities seperti cuaca, airport tutup, banjir dan lain-lain. Airline yang memiliki sistem operation control yang terintegrasi akan memiliki keunggulan operasional (operational excellence) dibandingkan airline lainnya.
  • #6: Planning dapat dibagi menjadi long range, medium, short. Untuk selanjutnya planning tersebut harus dapat diimplementasikan dan dikontrol dengan baik. Menggunakan aplikasi netline (solusi dari lufthansa system) maka proses dari perencanaan, implementasi dan kontrol dapat dilakukan menggunakan aplikasi yang terintegrasi dengan baik . Selanjutnya akan di sampaikan aliran pekerjaan di Garuda yang rencananya akan di support oleh ‘Netline/Ops’.
  • #7: Operation control yang di Garuda. Data diperoleh melalui wawancara sampai akhir bulan May 2008. Peserta rapat tanggal 4 Agustus 2008 ini menambahkan bahwa nama unit berubah dari OP menjadi OG, weekly schedule berubah menjadi monthly schedule, namun aliran pekerjaan tidak berubah. Kotak berwarna biru adalah sistem netline/sched, sistem reservasi Arga dan Crew management system (CMS) dan sistem untuk mengirimkan SMS. Kotak lainnya merupakan proses manual atau data excel atau database access yang tidak dapat diakses oleh unit lainnya atau stand alone. Netline/sched akan menghasilkan schedule pesawat (belum ada tail number) didistribusikan dalam bentuk file elektronik ke sistem Arga reservasi dan DCS. Selain itu formatnya juga disesuaikan lagi untuk menjadi time table Garuda (seasonal). Data dari netline sched didownload oleh unit JKTOGR, untuk dijadikan sumber data untuk penerbitan jadwal pesawat menjadi bentuk dokumen (hard copy) ‘aircraft rotation seasonal’ (selanjutnya diberikan kepada GMF) , dalam bentuk dokumen ‘monthly schedule’ file elektronik dan hardcopy . Serta dokumen AC rotation daily yang sudah ada tail numbernya, diprint setiap hari dan ditandai berdasarkan pergerakan pesawat yang terjadi. Perhatikan bahwa OCC dan MCC mempunyai sistem yang berbeda untuk memonitor pergerakan pesawat. Sistem OCC (dinamakan AC flight monitoring) masih belum dinyatakan sebagai sistem yang resmi.
  • #8: Operation control yang di Garuda. Data diperoleh melalui wawancara sampai akhir bulan May 2008. Peserta rapat tanggal 4 Agustus 2008 ini menambahkan bahwa nama unit berubah dari OP menjadi OG, weekly schedule berubah menjadi monthly schedule, namun aliran pekerjaan tidak berubah. Kotak berwarna biru adalah sistem netline/sched, sistem reservasi Arga dan Crew management system (CMS) dan sistem untuk mengirimkan SMS. Kotak lainnya merupakan proses manual atau data excel atau database access yang tidak dapat diakses oleh unit lainnya atau stand alone. Netline/sched akan menghasilkan schedule pesawat (belum ada tail number) didistribusikan dalam bentuk file elektronik ke sistem Arga reservasi dan DCS. Selain itu formatnya juga disesuaikan lagi untuk menjadi time table Garuda (seasonal). Data dari netline sched didownload oleh unit JKTOGR, untuk dijadikan sumber data untuk penerbitan jadwal pesawat menjadi bentuk dokumen (hard copy) ‘aircraft rotation seasonal’ (selanjutnya diberikan kepada GMF) , dalam bentuk dokumen ‘monthly schedule’ file elektronik dan hardcopy . Serta dokumen AC rotation daily yang sudah ada tail numbernya, diprint setiap hari dan ditandai berdasarkan pergerakan pesawat yang terjadi. Perhatikan bahwa OCC dan MCC mempunyai sistem yang berbeda untuk memonitor pergerakan pesawat. Sistem OCC (dinamakan AC flight monitoring) masih belum dinyatakan sebagai sistem yang resmi.
  • #9: Pada slide project time frame (template dari LSY) , perhatikan bahwa application installation merupakan predesesor dari aktivitas lain. Bila hardware yang terakhir datang (yaitu storage atau hardisk besar yang bisa diakses oleh blade server) pada tanggal 19 July 2008 dianggap sebagai awal installation maka seharusnya tanggal 4 Agustus installation sudah selesai (pada time frame, targetnya adalah 2 ,minggu). Namun saat ini kondisinya masih DB installation, untuk itu mohon perhatian kepada QX (atau perwakilannya ) untuk mempercepat pelaksanaanya.
  • #10: Team member consolidation: anggota tim ada yang ikut shift atau terbang (sebagai awak cabin dan kokpit), mohon arahan dan perhatian steering committee agar anggota tim tetap dapat datang pada rapat-rapat proyek, meskipun mereka juga sibuk oleh penugasan lain. Konsentrasi dari anggota tim merupakan syarat kesuksesan implementasi. Pada proyek IOCS ini akan dicoba pendekatan baru dalam membangun interface ke dan dari aplikasi lain, yaitu penggunaan Enterprise Sevice Bus (ESB). Lihat gambaran interface –existing, interface dibangun dengan berbagai platform dan beberapa programmer, sering terjadi programmer tidak ada pada saat sistem mengalami gangguan, atau interface dibangun di komputer yang juga digunakan untuk kegiatan sehari-hari. Cara ini tentunya tidak dapat menjamin ketersediaan sistem (high availability) yang seharusnya ada pada sistem penunjang operasional Garuda. Pada IOCS akan disiapkan blade server yang khusus berfungsi sebagai pusat interface dan diletakan di ruang server. Network connection antara ratuplaza dan garuda data center perlu ditingkatkan kehandalannya.
  • #11: Bila Garuda sudah mempunyai sistem netline/ops maka sistem untuk menunjang maintenance juga perlu dibangun. Seperti yang tergambar pada slide sebelumnya, sistem penunjang kegiatan maintenance masih manual ataupun bila sudah ada sistem IT-nya, masih belum terintegrasi. Sebagai contoh bila Garuda teknik/GMF menetapkan adanya AC yang harus menjalani perawatan maka komunikasi dilakukan via telex ataupun telpon, dimana masing masing unit (MCC atau OCC) tidak saling mengetahui kondisi yang realtime. Usulan perawatan pesawat (maintenanace plan) disampaikan melalui dokumen hardcopy kepada JKTOGR ataupun JKTCNS. Berikut adalah gambaran sistem di CityLine-anak perusahaan lufthansa. CityLine mempunyai 67 pesawat. Sistem netline/ops saling bertukar data dengan SAP R/3. MCC dan OCC-nya mempunyai screen yang sama untuk memonitor kegiatan operasional. Pada screen netline/ops, pada pesawat yang operasional (dapat diterbangkan), unit OCC dapat melihat HIL yang harus dikerjakan oleh unit perawatan. Demikian pula dengan MCC dapat melihat pesawat sedang diterbangkan kemana sehingga dapat momonitor harus dikerjakan dimana bila diperlukan kegiatan perawatan pesawat. Garuda direkomendasikan untuk segera memulai proyek untuk membangun sistem Aircraft maintenance planning, yang sebaiknya juga lengkap dengan fitur hil monitoring , maintenance even builder dan work package creation.
  • #12: Usulan untuk membangun sistem aircraft maintenance planning di SAP sudah masuk dalam pembahasan ‘rencana kerja IT 2008’ antara Garuda dan GMF, sebagaimana tergambar pada slide ini. Sebelum memulai proyek ini tentunya stabilisasi SAP untuk modul yang sudah diimplementasikan juga harus diselesaikan terlebih dahulu. Saat ini adalah saat yang tepat untuk memulai project preparation untuk AC maintenance planning. Pak Adi Widhananto yang ditugaskan oleh QX untuk aktivitas ini akan menjelaskan lebih lanjut mengenai status dari proyek aircraft maintenance planning.
  • #13: Berikut ini adalah blok sistem yang sudah diterapkan di CityLine. Gambar diambil pada tahun 2003 pada pertemuan SAP aerospace &defence di dusseldorf. Dan pada saat visit di Cityline – Cologne tahun 2008 ini, fitur/blok sistem tsb dapat berjalan dengan sangat baik.
  • #14: BOS: Business, Organization dan System. Lihat gambar sebelah kiri; pemetaaan dari proses bisnis ke organisasi yang ada perlu di detilkan kembali terutama dengan adanya perubahan organisasi. Bila sistem sudah diinstall, maka business process dan oraganisasi yang ada juga perlu dipetakan ke sistem IOCS yang baru. Diskusi ini kan di dokumentasikan kedalam Business blue print document. Tim IOCS kan segera menyelengarakan workshop yang harus diikuti oleh user representative, dalam jangka waktu 1 bulan dari pertemuan ini. Dukungan dari steering committee diperlukan untuk menghadirkan dan memastikan workshop dapat berjalan produktif.
  • #15: Diskusi dan Tanya Jawab
  • #16: Terima kasih kepada seluruh anggota steering committee dan anggoa tim yang telah menyediakan waktu pada pertemuan ini. Kehadiran seluruh anggota steering committee merupakan indikasi dukungan manajemen sehingga pelaksanaan implementasi sistem ini nantinya diharapkan dapat berjalan lancar.