Sound Transit
    Capitol Hill Station
Construction Update Meeting
          April 14, 2010
       6:30 p.m. – 8:30 p.m.
              SCCC
Agenda
6:30 p.m. – Open House
7:00 p.m. – Presentation
    Project Update– Rhonda Dixon, CH Station Outreach Coordinator
    Construction Activities – Jeff Munnoch, U-Link Community
     Outreach
    Construction Wall Art Program
          Barbara Luecke, STart Manager
          D.K. Pan, Lead Artist Capitol Hill construction wall
      Q&A
8:00 p.m. – Return to Open House
Central Link
• Westlake to SeaTac Airport
• 16 miles
• 13 stations
University Link
        • 3.15-mile light rail extension
           – Capitol Hill Station
           – UW Station
        • Schedule
           – Construction: 6.5 years
           – Open for Service: 2016
        • Adds 70,000 daily riders,
          114,000 system wide (2030)
Capitol Hill Station

• Underground station with 3
  entrances
• Staging area - station and
  tunnel excavation at site
• Ridership: 14,000 daily
  boardings
• Travel time:
   – 3 minutes to downtown
     Seattle (University St.)
   – 3 minutes to UW Station
Capitol Hill Construction Contracts
1. Demolition (complete)                    2. I-5 undercrossing (on-going)




3. Excavation / tunneling (2010 – 2013)   4. Station Construction (2013 – 2015)
I-5 Undercrossing Work
         2009 - 2010

                  • Preparing the ground
                    beneath I-5 for the
                    TBM’s
                  • Pike/Pine HOV off-
                    ramp will open in April
                  • Olive Way off-ramp
                    will open in May as
                    originally planned
Haul Route Pedestrian Improvements
           Completed March, 2010
Restaurant, Retailing and
 Social Media Seminars

 • Restaurant Management
 • Retail Management
 • Social Media Applications
 (Facebook, Twitter, and other on-
 line tools)
Construction Update
Current Work
                               Apr-Jun 2010

               Soldier   • Construction wall
               piles

                         • Utility relocation
                         • Solider Piles
Utility relocation
Soldier Piles

         • Steel beams support
           wood planks that keep
           the sides of the
           excavation stable
         • 120 total piles
         • 100 feet deep
Sidewalk closed               Current Work
                               Apr-Jun 2010
   Jet
grouting




                Soldier   • Utility relocation
                piles

                          • Construction wall
                          • Solider Piles
                          • Jet grouting (north
 Utility relocation
                            end of site)
                          • Sidewalk closed
                             on John St.
Temporary sidewalk
              • Steel containers
                incorporated into
                the wall
              • No sidewalk detour
                necessary
              • Potential viewing
                portals
Excavation
         May 2010

• Increased truck activity
  (approx. 8 truck / hour)
• Daytime work
• Night work does not start
  until tunneling begins
Excavation sequence

As dirt is removed, wooden
planks are inserted into the
I-beams to support the
sides of the excavation
Pine Street Jet Grouting

• Stabilize ground
  where TBM will exit
• Sidewalk closure,
  south side (4 weeks)

                               Sidewalk
                                closed
Construction Wall
• Surround the site on
  all sides
• 8 to 24 feet high,
  plywood construction
• Help contain noise,
  dust, and debris



  KEY
        8’ wall
        12’ wall
        16’ wall
        24’ wall
STart Program
Construction Wall Art
            Keep the sidewalk active

             Mitigate impact with art

            Continued Commitment to
                   placemaking
           – STart On Broadway
           – Oscillating Field
D.K. Pan, Lead Artist
Master Plan to integrate:
                             CALL TO ARTISTS
   •Art
                             Applications Due
   •Project information
                              Monday April 19
   •Neighborhood promotion
Next Steps
•   Artist applications due – April 19
•   Decision on noise variance published – April 22
•   Finish site preparations, begin excavation – May
•   North Link kick-off meeting - May
•   Pine Street site preparation – Summer
•   TBM assembly begins – early 2011
Questions?
Staying Informed
Quarterly Open Houses
Monthly electronic newsletters:
  www.soundtransit.org/subscribe
Sound Transit Website: www.soundtransit.org/u-link
Printed and electronic construction alerts
Full time outreach staff
24 hour construction hotline: 1-888-298-2395

More Related Content

PDF
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
PDF
The Paterson Greenway Project
PPTX
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
PPTX
Buey Oil Well Permit
PPTX
Tantallon tweaks slideshow2 a
PPTX
Bistonte Oil Well Permit
PPTX
Grant Wilkinson, Senior Engineer, Ruamoko Solutions
PPTX
Grantham’s car park
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
The Paterson Greenway Project
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
Buey Oil Well Permit
Tantallon tweaks slideshow2 a
Bistonte Oil Well Permit
Grant Wilkinson, Senior Engineer, Ruamoko Solutions
Grantham’s car park

What's hot (7)

PPTX
City Hall Site Selection
PDF
Cass Park Analysis & Development Recommendations
PPTX
Building Profits on Brownfield Sites
PPTX
Virginia's Historic Bridges
PPTX
University Town Center Rezoning
PPTX
Oak Harbor City Council Workshop: Design Update
City Hall Site Selection
Cass Park Analysis & Development Recommendations
Building Profits on Brownfield Sites
Virginia's Historic Bridges
University Town Center Rezoning
Oak Harbor City Council Workshop: Design Update
Ad

Viewers also liked (9)

PDF
Streetcar Recommendation for City Council Transportation Cmte
PDF
First hillstreetcarartpresentation6.16.10
PDF
4 6 09 Forecast Mtg Council
PDF
Budget20100614 3
PPT
Capitol Hill Light Rail TOD Forum 2/23/10
PDF
Mayor Stakeholders 3172010
KEY
James Natchwey
PPTX
James Nachtwey
PDF
Heroin Bust
Streetcar Recommendation for City Council Transportation Cmte
First hillstreetcarartpresentation6.16.10
4 6 09 Forecast Mtg Council
Budget20100614 3
Capitol Hill Light Rail TOD Forum 2/23/10
Mayor Stakeholders 3172010
James Natchwey
James Nachtwey
Heroin Bust
Ad

Similar to 2010 4-14 open house (20)

PPTX
Forest Hill Station Open House - June 2017
PPTX
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
PPTX
Fairbank & Oakwood Stations Open House - April 2017
PPTX
Cn tower.. a detailed study
PPTX
Cn tower.. a detailed study
PPTX
Caledonia Station, West Portal and Elevated Guideway Open House
PDF
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
PPTX
Construction of the highline
PPTX
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
PPTX
Community Information Meeting of parkette design plan at Fairbank Station
PPTX
Leaside Station Open House - March 2017
PDF
Big Challenge, Big Success
PPTX
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
PPTX
The Highline
PPTX
Cedarvale station open house for website final2
PPTX
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
PPTX
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
PDF
West Open House - Progress Update Sept 2014
PPTX
Eglinton Station Open House - March 2017
PDF
Brentcliffe - Victoria Park Construction Liaison Committee Meeting
Forest Hill Station Open House - June 2017
West Open House (Mount Dennis Station to Keelesdale Station) - March 2018
Fairbank & Oakwood Stations Open House - April 2017
Cn tower.. a detailed study
Cn tower.. a detailed study
Caledonia Station, West Portal and Elevated Guideway Open House
Brentcliffe-Victoria Park Construction Liaison Committee (CLC) Meeting - May ...
Construction of the highline
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Community Information Meeting of parkette design plan at Fairbank Station
Leaside Station Open House - March 2017
Big Challenge, Big Success
Fairbank & Oakwood Stations Construction Liaison Committee Meeting - Aug 2017
The Highline
Cedarvale station open house for website final2
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
West Open House - Progress Update Sept 2014
Eglinton Station Open House - March 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting

More from jseattle (11)

PDF
Broadway Tod Report 2 Charrette
PDF
Broadway Tod Report 1 Precedents
PDF
Broadway Tod Report 3 Recommendations
PDF
2010 2 11 Noise Public Meeting
PDF
Capitol Hill Cc 12110
PDF
DRAFT: Development Guidelines and Urban Design Recommendations Report
PDF
Capitol Hill Transit Oriented Development Open House
PPT
Sound Transit 6/17/09 Noise And Construction Meeting
PDF
Ch Station Constructionschedule
PDF
Ch Open House0905
PDF
Seattle City Council Budget Briefing
Broadway Tod Report 2 Charrette
Broadway Tod Report 1 Precedents
Broadway Tod Report 3 Recommendations
2010 2 11 Noise Public Meeting
Capitol Hill Cc 12110
DRAFT: Development Guidelines and Urban Design Recommendations Report
Capitol Hill Transit Oriented Development Open House
Sound Transit 6/17/09 Noise And Construction Meeting
Ch Station Constructionschedule
Ch Open House0905
Seattle City Council Budget Briefing

2010 4-14 open house

  • 1. Sound Transit Capitol Hill Station Construction Update Meeting April 14, 2010 6:30 p.m. – 8:30 p.m. SCCC
  • 2. Agenda 6:30 p.m. – Open House 7:00 p.m. – Presentation  Project Update– Rhonda Dixon, CH Station Outreach Coordinator  Construction Activities – Jeff Munnoch, U-Link Community Outreach  Construction Wall Art Program  Barbara Luecke, STart Manager  D.K. Pan, Lead Artist Capitol Hill construction wall  Q&A 8:00 p.m. – Return to Open House
  • 3. Central Link • Westlake to SeaTac Airport • 16 miles • 13 stations
  • 4. University Link • 3.15-mile light rail extension – Capitol Hill Station – UW Station • Schedule – Construction: 6.5 years – Open for Service: 2016 • Adds 70,000 daily riders, 114,000 system wide (2030)
  • 5. Capitol Hill Station • Underground station with 3 entrances • Staging area - station and tunnel excavation at site • Ridership: 14,000 daily boardings • Travel time: – 3 minutes to downtown Seattle (University St.) – 3 minutes to UW Station
  • 6. Capitol Hill Construction Contracts 1. Demolition (complete) 2. I-5 undercrossing (on-going) 3. Excavation / tunneling (2010 – 2013) 4. Station Construction (2013 – 2015)
  • 7. I-5 Undercrossing Work 2009 - 2010 • Preparing the ground beneath I-5 for the TBM’s • Pike/Pine HOV off- ramp will open in April • Olive Way off-ramp will open in May as originally planned
  • 8. Haul Route Pedestrian Improvements Completed March, 2010
  • 9. Restaurant, Retailing and Social Media Seminars • Restaurant Management • Retail Management • Social Media Applications (Facebook, Twitter, and other on- line tools)
  • 11. Current Work Apr-Jun 2010 Soldier • Construction wall piles • Utility relocation • Solider Piles Utility relocation
  • 12. Soldier Piles • Steel beams support wood planks that keep the sides of the excavation stable • 120 total piles • 100 feet deep
  • 13. Sidewalk closed Current Work Apr-Jun 2010 Jet grouting Soldier • Utility relocation piles • Construction wall • Solider Piles • Jet grouting (north Utility relocation end of site) • Sidewalk closed on John St.
  • 14. Temporary sidewalk • Steel containers incorporated into the wall • No sidewalk detour necessary • Potential viewing portals
  • 15. Excavation May 2010 • Increased truck activity (approx. 8 truck / hour) • Daytime work • Night work does not start until tunneling begins
  • 16. Excavation sequence As dirt is removed, wooden planks are inserted into the I-beams to support the sides of the excavation
  • 17. Pine Street Jet Grouting • Stabilize ground where TBM will exit • Sidewalk closure, south side (4 weeks) Sidewalk closed
  • 18. Construction Wall • Surround the site on all sides • 8 to 24 feet high, plywood construction • Help contain noise, dust, and debris KEY 8’ wall 12’ wall 16’ wall 24’ wall
  • 19. STart Program Construction Wall Art Keep the sidewalk active Mitigate impact with art Continued Commitment to placemaking – STart On Broadway – Oscillating Field
  • 20. D.K. Pan, Lead Artist
  • 21. Master Plan to integrate: CALL TO ARTISTS •Art Applications Due •Project information Monday April 19 •Neighborhood promotion
  • 22. Next Steps • Artist applications due – April 19 • Decision on noise variance published – April 22 • Finish site preparations, begin excavation – May • North Link kick-off meeting - May • Pine Street site preparation – Summer • TBM assembly begins – early 2011
  • 24. Staying Informed Quarterly Open Houses Monthly electronic newsletters: www.soundtransit.org/subscribe Sound Transit Website: www.soundtransit.org/u-link Printed and electronic construction alerts Full time outreach staff 24 hour construction hotline: 1-888-298-2395