Mission Support PC Refresh 2012 Closeout
Greg Podoba
10/11/2012
Project Results
OPS PC Deployment Project
– A four-year computer refresh cycle is needed in order for users to be productive and
efficient with new operating systems and productivity software (MS-Office)
– As of completion of this project:
• 20% of OPS computers are 4 years of age or older
• 36% of OPS computers are still on Windows XP.
 Project desired outcome and factors for success
253, 20%
246, 20%
392, 32%
347, 28%
OPS Computers as of April 28, 2012
Less than 2 years
Between 2 and 3 years
Between 3 and 4 years
Greater than 4 years
650, 52%
246, 20%
182, 15%
160, 13%
OPS Computers as of October 1, 2012
Less than 2 years
Between 2 and 3 years
Between 3 and 4 years
Greater than 4 years
Project Deliverables
– Created Project Plan showing weekly milestones
– Created Process, Checklists and Tools to be used during the deployment process
– Created communication plan to be used when replacing computers
– Reviewed list of computers being replaced and conducted software inventory using
SCCM
– Reviewed Argonne Tools (SCCM/ OSD/ USMT) and made needed adjustments as
necessary.
– Completed at least six hours of hardware stress testing on each computer before
passing.
– Provided bi-weekly 1-hour Windows 7 and Office 2010 transitional overview for
affected users
– Provided Satisfaction Survey for all affected users
Project Schedule and Milestones
 Project Dates (explain variance > 20%)
Planned Finish: 08/24/12 Actual Finish: 09/21/12
 Milestone Dates (explain variance > 20%)
Milestone 1 – 10% complete (40 machines)
Planned Finish: 04/06/12 Actual Finish: 04/06/12
Milestone 2 – 15% complete (60 machines)
Planned Finish: 04/13/12 Actual Finish: 04/13/12
Milestone 3 – 30% complete (120 machines)
Planned Finish: 05/11/12 Actual Finish: 05/21/12
Project Schedule and Milestones
 Milestone Dates (explain variance > 20%)
Milestone 4 – 45% complete (180 machines)
Planned Finish: 06/08/12 Actual Finish: 06/19/12
Milestone 5 – 60% complete (240 machines)
Planned Finish: 07/06/12 Actual Finish: 07/23/12
Milestone 5 – 75% complete (300 machines)
Planned Finish: 07/27/12 Actual Finish: 08/20/12
Milestone 7 – 90% complete (360 machines)
Planned Finish: 08/17/12 Actual Finish: 09/04/12
Milestone 8 – 100% complete (400 machines)
Planned Finish: 08/24/12 Actual Finish: 09/21/12
Actual vs. Forecasted Machines Completed
0
50
100
150
200
250
300
350
400
450
Actual # of Machines Completed
Forecasted # of Machines Completed
Project Resources
 Project team members and total hours effort (explain variance > 20%)
– Staff of 4 Kemtah Contractors
• Phil Panopio - Project Leader
• Imran Khawaja - Technician
• Chad Karkos - Technician
• Milissa Keene - Technician
– Greg Podoba – Project Manager
– Chris Waterman – Desktop Support Technician
– Matt Knor – ITSA/Tools Support
– Other CIS members to assist with specialized software installations when
needed
• S2 Support with a few applications
Budgeted Hours: 560 Actual Hours: 325
 Non CIS participants division and name (explain variance > 20%)
None
 Project materials and services cost (explain variance > 20%)
Budgeted Cost: $500,000 Actual Cost: $500,000 Computers/Contractors
Planned but Currently Unfinished Project Tasks
Typical Project Startup Planning Considerations _
Project and system risks Cyber Policies
Data security Architecture compliance
Backup processes Disaster recovery
Software libraries updated Release to production checklist
Training Communications to the division
Retiring hardware and software Records mgmt. for project docs
Location of project and system docs Customer acceptance
State of the Above Planned but Unfinished Project Considerations _
• Two Refreshes still remaining – WFO Application being replaced with InfoEd.
• Donna Cardia
• Rosemary Gonzalez
Project Results Summary
43
9
1
13
7
10
13
9
31
23
58
29
152
CIS TDC LEG HR HEW OPS/OTD PMA IAD CEP NWM ESQ OCF FMS
List of Computers Deployed by Division
Hardware Burn-In Results
7, 50%
5, 36%
1, 7%
1, 7%
3.5% Failure Detected by Burn-In
Bad Motherboard
Bad DVD Drives
Bad Memory
Bad Power Supply
Overall Migration Experience
36.6%, 11 users
26.7%, 8 users
13.3%, 4 users
16.7%, 5 users
6.7%, 2 users
66.7%, 68 users
18.6%, 19 users
6.9%, 7 users
3.9%, 4 users 3.9, 4 users
0.0
10.0
20.0
30.0
40.0
50.0
60.0
70.0
80.0
Very Satisfied Somewhat Satisfied Neutral Somewhat Dissatisfied Very Dissatisfied
2011 Survey
2012 Survey
• Total Number of Survey Responses
• 2011 – 30 Users
• 2012 – 102 Users
• Total Number of Very Satisfied and Somewhat Satisfied
• 2011 – 63.3%
• 2012 - 85.3%
• Increase of 22% in User Satisfaction with their Overall Migration Experience
• 56 Total Attendees to one-hour Windows 7 and Office 2010 Overview session
Lessons Learned and Noteworthy Accomplishments
 Lessons Learned
– Pre-migration/strategy meeting should be held with division contacts and SME prior
to start of deployments. This assists with mitigation of any risks associated with
culture, legacy software, hardware, and peripherals.
– A centralized location for media and installation instructions would help streamline
the installation of legacy software
– Communication invite sent to user needs to be rearranged to have “You must be
present for the delivery and installation of your new computer” in the 1st paragraph
– Cultural issue with users taking the time to learn
 Noteworthy Accomplishments
– Slimmed down on unnecessary software installed on the 400 newly deployed
machines
– 90% of delivery/installation/verification completed within an hour
– Windows 7 and Office 2010 Overview received good reviews from the 56 total
attendees
– Addition of 15 minute interview with user prior to migration aided with identifying
any possible pain points to watch out for
– Mandatory 24 to 48 hour follow up after the refresh was done for every user

More Related Content

PDF
AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...
PPTX
eazyLY Mix, Match & Mash Up Project Data
PPT
Resource1 nou
PDF
Sap Application Assurance Service Offerings
PPTX
#speakgeek - Testing Recipe: The iconnect360 Way
PPTX
出口目標市場潛力指標資料庫簡介
PPTX
Городская жизнь
PPTX
AGILE PORTUGAL 2018: Changing global Quality operations: how Kanban did the t...
eazyLY Mix, Match & Mash Up Project Data
Resource1 nou
Sap Application Assurance Service Offerings
#speakgeek - Testing Recipe: The iconnect360 Way
出口目標市場潛力指標資料庫簡介
Городская жизнь

Viewers also liked (19)

DOCX
De thi hsg anh 6
PPTX
What kind of institution might distribute your media?
PDF
El Realismo
PPTX
The power of human augmentation
PDF
Sculptures
TXT
Thirdpartylicensereadme
DOC
TimBrownBankingExecutiveResume1-2
PPTX
Learn at lunch Eportfolios
PPTX
Breaded the other side of colombia
PDF
Graphics portfolio
RTF
Ingles
PDF
Keith - intro astro-Ecliptic Worksheet
PPTX
Metro power
PPTX
Euclid’ s geometry
PDF
The Soa Brand Deck
DOCX
Tugas 3 Matematika
ODP
Pickup Systems LTD.odp
PDF
Early Grade Reading Activity Malawi (1)
PDF
Expression of luxS
De thi hsg anh 6
What kind of institution might distribute your media?
El Realismo
The power of human augmentation
Sculptures
Thirdpartylicensereadme
TimBrownBankingExecutiveResume1-2
Learn at lunch Eportfolios
Breaded the other side of colombia
Graphics portfolio
Ingles
Keith - intro astro-Ecliptic Worksheet
Metro power
Euclid’ s geometry
The Soa Brand Deck
Tugas 3 Matematika
Pickup Systems LTD.odp
Early Grade Reading Activity Malawi (1)
Expression of luxS
Ad

Similar to 2012 PC Refresh Closeout (20)

PPTX
It department meeting presentation slides
PPTX
Colaborative Cloud Poster EDUCAUSE12
PDF
KSU IT Capstone Report 2012-2017.pdf
PPT
Projects and Achievements at GosNIIAS - Victor Berenshteyn
PDF
KSU IT4983 Capstone Projects Report 2017 Update
PPT
01. Developing Business _ IT Solutions 2011.ppt
PDF
chapter12-120827115424-phpapp01.pdf
PDF
AFITC 2018 - Using Process Maturity and Agile to Strengthen Cyber Security
PPTX
Chapter 12 Managing Systems Support and Security .pptx
PDF
Project charter and plan document for millennium upgrade
PDF
Agile sem meet_upba_nov2011_v03
PDF
Oracle R12 Upgrade Lessons Learned
PPTX
Senior Capstone Project
PDF
Business Intelligence for Government - Clark County Family Services Departmen...
DOCX
project summary
DOC
Resume
PPTX
GXC Advisory Board Business Windows 7 Accelerated Migration September2012
PDF
Keith odom sample microsoft project template data center move
PPTX
Task tracking system
PPTX
Lean and kanban from the trenches experience report
It department meeting presentation slides
Colaborative Cloud Poster EDUCAUSE12
KSU IT Capstone Report 2012-2017.pdf
Projects and Achievements at GosNIIAS - Victor Berenshteyn
KSU IT4983 Capstone Projects Report 2017 Update
01. Developing Business _ IT Solutions 2011.ppt
chapter12-120827115424-phpapp01.pdf
AFITC 2018 - Using Process Maturity and Agile to Strengthen Cyber Security
Chapter 12 Managing Systems Support and Security .pptx
Project charter and plan document for millennium upgrade
Agile sem meet_upba_nov2011_v03
Oracle R12 Upgrade Lessons Learned
Senior Capstone Project
Business Intelligence for Government - Clark County Family Services Departmen...
project summary
Resume
GXC Advisory Board Business Windows 7 Accelerated Migration September2012
Keith odom sample microsoft project template data center move
Task tracking system
Lean and kanban from the trenches experience report
Ad

2012 PC Refresh Closeout

  • 1. Mission Support PC Refresh 2012 Closeout Greg Podoba 10/11/2012
  • 2. Project Results OPS PC Deployment Project – A four-year computer refresh cycle is needed in order for users to be productive and efficient with new operating systems and productivity software (MS-Office) – As of completion of this project: • 20% of OPS computers are 4 years of age or older • 36% of OPS computers are still on Windows XP.  Project desired outcome and factors for success 253, 20% 246, 20% 392, 32% 347, 28% OPS Computers as of April 28, 2012 Less than 2 years Between 2 and 3 years Between 3 and 4 years Greater than 4 years 650, 52% 246, 20% 182, 15% 160, 13% OPS Computers as of October 1, 2012 Less than 2 years Between 2 and 3 years Between 3 and 4 years Greater than 4 years
  • 3. Project Deliverables – Created Project Plan showing weekly milestones – Created Process, Checklists and Tools to be used during the deployment process – Created communication plan to be used when replacing computers – Reviewed list of computers being replaced and conducted software inventory using SCCM – Reviewed Argonne Tools (SCCM/ OSD/ USMT) and made needed adjustments as necessary. – Completed at least six hours of hardware stress testing on each computer before passing. – Provided bi-weekly 1-hour Windows 7 and Office 2010 transitional overview for affected users – Provided Satisfaction Survey for all affected users
  • 4. Project Schedule and Milestones  Project Dates (explain variance > 20%) Planned Finish: 08/24/12 Actual Finish: 09/21/12  Milestone Dates (explain variance > 20%) Milestone 1 – 10% complete (40 machines) Planned Finish: 04/06/12 Actual Finish: 04/06/12 Milestone 2 – 15% complete (60 machines) Planned Finish: 04/13/12 Actual Finish: 04/13/12 Milestone 3 – 30% complete (120 machines) Planned Finish: 05/11/12 Actual Finish: 05/21/12
  • 5. Project Schedule and Milestones  Milestone Dates (explain variance > 20%) Milestone 4 – 45% complete (180 machines) Planned Finish: 06/08/12 Actual Finish: 06/19/12 Milestone 5 – 60% complete (240 machines) Planned Finish: 07/06/12 Actual Finish: 07/23/12 Milestone 5 – 75% complete (300 machines) Planned Finish: 07/27/12 Actual Finish: 08/20/12 Milestone 7 – 90% complete (360 machines) Planned Finish: 08/17/12 Actual Finish: 09/04/12 Milestone 8 – 100% complete (400 machines) Planned Finish: 08/24/12 Actual Finish: 09/21/12
  • 6. Actual vs. Forecasted Machines Completed 0 50 100 150 200 250 300 350 400 450 Actual # of Machines Completed Forecasted # of Machines Completed
  • 7. Project Resources  Project team members and total hours effort (explain variance > 20%) – Staff of 4 Kemtah Contractors • Phil Panopio - Project Leader • Imran Khawaja - Technician • Chad Karkos - Technician • Milissa Keene - Technician – Greg Podoba – Project Manager – Chris Waterman – Desktop Support Technician – Matt Knor – ITSA/Tools Support – Other CIS members to assist with specialized software installations when needed • S2 Support with a few applications Budgeted Hours: 560 Actual Hours: 325  Non CIS participants division and name (explain variance > 20%) None  Project materials and services cost (explain variance > 20%) Budgeted Cost: $500,000 Actual Cost: $500,000 Computers/Contractors
  • 8. Planned but Currently Unfinished Project Tasks Typical Project Startup Planning Considerations _ Project and system risks Cyber Policies Data security Architecture compliance Backup processes Disaster recovery Software libraries updated Release to production checklist Training Communications to the division Retiring hardware and software Records mgmt. for project docs Location of project and system docs Customer acceptance State of the Above Planned but Unfinished Project Considerations _ • Two Refreshes still remaining – WFO Application being replaced with InfoEd. • Donna Cardia • Rosemary Gonzalez
  • 9. Project Results Summary 43 9 1 13 7 10 13 9 31 23 58 29 152 CIS TDC LEG HR HEW OPS/OTD PMA IAD CEP NWM ESQ OCF FMS List of Computers Deployed by Division
  • 10. Hardware Burn-In Results 7, 50% 5, 36% 1, 7% 1, 7% 3.5% Failure Detected by Burn-In Bad Motherboard Bad DVD Drives Bad Memory Bad Power Supply
  • 11. Overall Migration Experience 36.6%, 11 users 26.7%, 8 users 13.3%, 4 users 16.7%, 5 users 6.7%, 2 users 66.7%, 68 users 18.6%, 19 users 6.9%, 7 users 3.9%, 4 users 3.9, 4 users 0.0 10.0 20.0 30.0 40.0 50.0 60.0 70.0 80.0 Very Satisfied Somewhat Satisfied Neutral Somewhat Dissatisfied Very Dissatisfied 2011 Survey 2012 Survey • Total Number of Survey Responses • 2011 – 30 Users • 2012 – 102 Users • Total Number of Very Satisfied and Somewhat Satisfied • 2011 – 63.3% • 2012 - 85.3% • Increase of 22% in User Satisfaction with their Overall Migration Experience • 56 Total Attendees to one-hour Windows 7 and Office 2010 Overview session
  • 12. Lessons Learned and Noteworthy Accomplishments  Lessons Learned – Pre-migration/strategy meeting should be held with division contacts and SME prior to start of deployments. This assists with mitigation of any risks associated with culture, legacy software, hardware, and peripherals. – A centralized location for media and installation instructions would help streamline the installation of legacy software – Communication invite sent to user needs to be rearranged to have “You must be present for the delivery and installation of your new computer” in the 1st paragraph – Cultural issue with users taking the time to learn  Noteworthy Accomplishments – Slimmed down on unnecessary software installed on the 400 newly deployed machines – 90% of delivery/installation/verification completed within an hour – Windows 7 and Office 2010 Overview received good reviews from the 56 total attendees – Addition of 15 minute interview with user prior to migration aided with identifying any possible pain points to watch out for – Mandatory 24 to 48 hour follow up after the refresh was done for every user