Is the Floating LNG moment?
OCTOBER, 2021
2
Index
1. LNG Trade.
1.1 LNG Imports.
1.2 LNG and Gas Pricing.
1.3 Floating Liquefaction Capacity
Worldwide.
2. Floating Liquefied Natural Gas (FLNG).
2.1 In Operation Global FLNG.
3. Business Opportunity.
4. FLNG Project.
4.1 Justification.
4.2 Scope of project.
4.3 Study cases.
4.4 FLNG CAPEX (referential)
4.5 Risk of Project.
4.6 Advantages.
3
Figure: 2020 LNG Imports and Market Share by Market.
Source: GIIGNL.
Despite COVID-19 impacts on
demand and supply, global LNG
trade continued its upward trend
in 2020 for another consecutive
year of growth, reaching 356.1
MT.
China, India, Chinese Taipei, the
United States (Puerto Rico), and
Brazil increased net imports
through expansion of import
capacity.
1. LNG Trade
1.1 LNG Imports
4
Lowest point for Brent
US$ 69.96/bbl
on 6 Jan 2020
Lowest point JKM
US$ 1.83/MMBtu
on 28 Apr 2020
Lowest point for HH
US$ 1.47/MMBtu
on 26 Jun 2020
Highest point for HH
US$ 3.29/MMBtu
on 30 Oct 2020
35
30
25
20
15
10
5
0
Dec 2019 Jan 2020 Feb 2020 Mar 2020 Apr 2020 May 2020 Jun 2020 Jul 2020 Aug 2020 Sep 2020 Oct 2020 Nov 2020 Dec 2020 Jan 2021 Feb 2021 Mar 2021
90
80
70
60
50
40
30
20
10
0
Dated Brent (US$/bbl)
JKM LNG (US$/MMBtu)
WIM LNG (US$/MMBtu)
NEW LNG (US$/MMBtu)
GCM LNG (US$/MMBtu)
Dutch TTF (US$/MMBtu)
Henry Hub (US$/MMBtu)
Lowest point for Brent
US$ 13.24/bbl
on 21 Apr 2020
Lowest point for TTF
US$ 1.13/MMBtu
on 28 May 2020
Highest point for TTF
US$ 6.90/MMBtu
on 31 Dec 2020
Feb JKM Price at record
US$ 32.50/MMBtu
on 13 Jan 2021
Source: IGU World LNG report - 2021 Edition.
1. LNG Trade
1.2 LNG and Gas Pricing
5
1. LNG Trade
1.3 Floating Liquefaction Capacity Worldwide
Australia, 3.6 MTPA Mozambique, 3.4 MTPA Malaysia, 2.7 MTPA
Mauritania, 2.5 MTPA Cameroon, 2.4 MTPA
Figure: Global sanctioned and operational FLNG liquefaction capacity as a february 2021.
Source: Rystad Energy
Figure: Global proposed FLNG liquefaction capacity.
Source: Rystad Energy.
United States, 54 MTPA Canada, 32 MTPA Djibouti, 10 MTPA
Mauritania, 7.5 MTPA Australia, 6 MTPA Israel, 3 MTPA
Cameroon, 1.4 MTPA Russia, 1.3 MTPA Congo, 1.2 MTPA
6
2. Floating Liquefied Natural Gas (FLNG)
A floating LNG (FLNG) is an LNG plant constructed on a ship or a barge which has
LNG storage and offloading facilities.
The FLNG accomplishes the gas treatment and liquefaction (production of LNG)
from the natural gases produced in gas fields, and the storage/offloading of
product LNG to LNG carriers for ocean transportation.
In operation liquefaction technology:
 Black & Veatch PRICO (Cameroon FLNG, Tango FLNG)
 Shell DMR (Prelude LNG)
7
Source: Rystad Energy.
Tango FLNG
Cameroon FLNG
Petronas Prelude FLNG
2. Floating Liquefied Natural Gas (FLNG)
2.1 In Operation Global Floating LNG
7.2 MTPA
Operational Floating Liquefaction Capacity Worldwide as of Jan 2021
The Tango FLNG vessel is
currently available for other
projects.
0.5 MTPA
16,500 m3
Start up: 2019
2.4 MTPA
125,000 m3
Start up: 2018
3.6 MTPA
437,500 m3
Start up: 2019
Liquefaction Technology:
Black & Veatch PRICO
Liquefaction Technology:
Shell DMR
Liquefaction Technology:
Black & Veatch PRICO
As global liquefied natural gas trade continues to expand rapidly, the challenge of
liquefaction process selection becomes increasingly important. Selecting more
versatile and cost-effective liquefaction technologies that meet stringent
emissions standards will be a key focus for new projects as governments and
companies commit to decarbonisation efforts.
Cost estimates for most new projects suggest that they will be able to profitably
deliver to stronger import markets, such as China and Southeast Asia, which are
expected to see larger increases in LNG imports during this period.
8
3. Business Opportunity
4. FLNG Project
4.1 Justification
9
The development of a FLNG project is
supported by:
 Current decarbonization trend.
 The difficulties that a natural gas
liquefaction plant on land may
present.
4. FLNG Project
4.2 Scope of Project
10
To install a Floating Liquefaction Natural Gas in order to provide the facilities
required to:
Facilities for the liquefaction of natural gas.
LNG storage and utilities required.
4. FLNG Project
4.3 Proposed Cases (estimated)
11
Component Maximun concentration
CO2 50 ppmv
H2O 0.1 ppmv
Mercury 0.01 µg/Sm3
H2S 4 ppmv
Mercaptan Sulfur 8 ppmw
Nitrogen 1.0 mol%
Pentanes & heavier 0.075 mol%
Limits for feed gas impurities to
liquefaction process (referential)
Case 1: 90 MMPCED of feed gas in
order to reach 0.5 MTPA of
liquefaction capacity (small scale).
Case 2: 380 MMPCED of feed gas in
order to reach 2.4 MTPA of
liquefaction capacity (medium scale).
Case 3: 550 MMPCED of feed gas in
order to reach 3.5 MTPA of
liquefaction capacity (large scale).
4. FLNG Project
4.4 FLNG CAPEX $/tpa (referential, 2019)
12
Figure: FLNG Cost. Source: Brian Songhurst, Research Associate, OIES. “Floating LNG Update, 2019.”
0 500 1000 1500 2000 2500
Prelude
Satu (Petronas PFLNG 1)
Dua (Petronas PFLNG 2)
Tortue (Golar Gimi)
Cameroon Episeyo (Golar Hilli)
Tango (was Caribbean FLNG)
$/tpa
13
4. FLNG Project
4.5 Risk of Project
Risk Factors Impact on LNG Project Development
Projects Economics Long-term sales contracts that allow for a sufficient return typically underpin the financing of LNG projects. High
project costs or changing market prices can have a large impact.
Politics & Geopolitics Permitting may be time consuming.
Regulatory Approvals Regulatory approval may be costly and extends to the approval of upstream development and pipeline
construction.
Partner Priorities Not all partners are equally committed to a project and face different constraints depending on their respective
portfolios. Ensuring alignment in advance of an FID may be difficult.
Ability to Execute Partners must have the technical, operational, financial, and logistical capabilities to fully execute a project.
Certain complex projects may present additional technical hurdles that could impact project feasibility.
Business Cycle Larger economic trends.
Feedstock Availability The overall availability of gas to supply an LNG project may be limited by technical characteristics of the associated
fields.
Marketing/Contracting Project developers generally need to secure long-term LNG buyers for a large portion of project capacity before
sanctioning a project.
Source: IGU World LNG report - 2019 Edition.
14
4. FLNG Project
4.6 Advantages
 Fast track solution that can fill sudden need of gas.
 Competitive costs for temporary, shorter-term operation.
 Overcome onshore site limitations.
 To reduce the infrastructure and environmental impact on onshore since FLNG
does not require the coastal development.
 To be built in fabrication yards where facilities and practices are well-
established for construction of the topsides modules and hull without
constraints of the countries or regions of the gas field or onshore LNG plant,
which secures the efficiency and the safety of construction.

More Related Content

PDF
IGU - 2016 World LNG Report
PDF
DNV report: How LNG takes shape
PDF
New base special 26 august 2014
PDF
LNG18_FSRU Risk and Opportunities
PDF
Platts oilgram news julio 29 2014 articulo pag 7 Colombia oil Orlando Hernandez
PDF
New base special 29 may 2014
PDF
Liquefied Natural Gas (LNG) Life Cycle
PDF
New base special 14 april 2014
IGU - 2016 World LNG Report
DNV report: How LNG takes shape
New base special 26 august 2014
LNG18_FSRU Risk and Opportunities
Platts oilgram news julio 29 2014 articulo pag 7 Colombia oil Orlando Hernandez
New base special 29 may 2014
Liquefied Natural Gas (LNG) Life Cycle
New base special 14 april 2014

What's hot (20)

PDF
Microsoft word new base 672 special 25 august 2015
PDF
Sgcp14bradshaw
PDF
LNG as ship fuel
PDF
LNG fuelled ships recent development 2014 02
PDF
New base energy news issue 951 dated 20 november 2016
PDF
Lng eng
PDF
New base 814 special 23 march 2016
PDF
US (MARAD) LNG Bunkering Study 2014
PDF
LNGT
DOC
Gogakos
PDF
The Future Of Lng As Fuel, Technical And Infrastructure Aspects And Considera...
PDF
Pipeline & Gas Journal_ Dec11_p40
PDF
Economic Model In Exploiting Stranded Natural Gas In Niger Delta Offshore Fields
PDF
LNG as Fuel magazine
PPTX
World LNG fueled fleet as of march 2014
PDF
Outlook on LNG Bunkering Facilities in China Inland Waterways and Ports
PDF
FloatingLNGRevolutionEvolution
PDF
Scandinavia Oil-Gas Magazine May 2011 paper
PPTX
Lng regasification asit
PDF
NewBase March 23-2022 Energy News issue - 1498 by Khaled Al Awadi.pdf
Microsoft word new base 672 special 25 august 2015
Sgcp14bradshaw
LNG as ship fuel
LNG fuelled ships recent development 2014 02
New base energy news issue 951 dated 20 november 2016
Lng eng
New base 814 special 23 march 2016
US (MARAD) LNG Bunkering Study 2014
LNGT
Gogakos
The Future Of Lng As Fuel, Technical And Infrastructure Aspects And Considera...
Pipeline & Gas Journal_ Dec11_p40
Economic Model In Exploiting Stranded Natural Gas In Niger Delta Offshore Fields
LNG as Fuel magazine
World LNG fueled fleet as of march 2014
Outlook on LNG Bunkering Facilities in China Inland Waterways and Ports
FloatingLNGRevolutionEvolution
Scandinavia Oil-Gas Magazine May 2011 paper
Lng regasification asit
NewBase March 23-2022 Energy News issue - 1498 by Khaled Al Awadi.pdf
Ad

Similar to 2021 Is the floating LNG moment? (20)

PDF
2011 LNG AS PROPULSION FUEL
PDF
Gas Arabia Summit: Unconventional Gas Developments in the Gulf
PDF
Lng paper v2_lq
PDF
Rosneft Investor Day_2013
PPTX
LNG Infrastructure of Pakistan and Opportunities
PDF
A STUDY ON COMMERCIAL ASPECTS OF LNG
PDF
Oil in Georgia: Dream or Challenge?
PPTX
global lng fleet market
PDF
August Newsletter - Affinity Small Scale LNG.pdf
PDF
Global LNG Navigating Risks in a Dynamic Market
PDF
Presentation given at CLSA investors' forum in Hong Kong
PPTX
Global lng market assessment
PPTX
LNG Bunkering Market.pptx
PDF
Teekay LNG Partners (NYSE: TGP) Investor Day Presentation, Sep 30, 2014
PDF
Microsoft word new base 11 june energy news issue - 1041 by khaled al awadi
PDF
Platts oilgram news sep 17 2014 pag 5 colombian pipelines attacks
PDF
Comparative Economic Analysis of Using Natural Gas For Liquefied Natural Gas ...
PDF
September 2013 Investor Presentation
PDF
Teekay Corp group presentation September 2013
PDF
NewBase 31 August 2023 Energy News issue - 1652 by Khaled Al Awadi_compresse...
2011 LNG AS PROPULSION FUEL
Gas Arabia Summit: Unconventional Gas Developments in the Gulf
Lng paper v2_lq
Rosneft Investor Day_2013
LNG Infrastructure of Pakistan and Opportunities
A STUDY ON COMMERCIAL ASPECTS OF LNG
Oil in Georgia: Dream or Challenge?
global lng fleet market
August Newsletter - Affinity Small Scale LNG.pdf
Global LNG Navigating Risks in a Dynamic Market
Presentation given at CLSA investors' forum in Hong Kong
Global lng market assessment
LNG Bunkering Market.pptx
Teekay LNG Partners (NYSE: TGP) Investor Day Presentation, Sep 30, 2014
Microsoft word new base 11 june energy news issue - 1041 by khaled al awadi
Platts oilgram news sep 17 2014 pag 5 colombian pipelines attacks
Comparative Economic Analysis of Using Natural Gas For Liquefied Natural Gas ...
September 2013 Investor Presentation
Teekay Corp group presentation September 2013
NewBase 31 August 2023 Energy News issue - 1652 by Khaled Al Awadi_compresse...
Ad

Recently uploaded (20)

PPTX
introduction to high performance computing
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
PPTX
Management Information system : MIS-e-Business Systems.pptx
PDF
August -2025_Top10 Read_Articles_ijait.pdf
PDF
Abrasive, erosive and cavitation wear.pdf
PPTX
communication and presentation skills 01
PPTX
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPTX
Amdahl’s law is explained in the above power point presentations
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPTX
CyberSecurity Mobile and Wireless Devices
PPTX
Current and future trends in Computer Vision.pptx
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
III.4.1.2_The_Space_Environment.p pdffdf
introduction to high performance computing
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Graph Data Structures with Types, Traversals, Connectivity, and Real-Life App...
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
BIO-INSPIRED ARCHITECTURE FOR PARSIMONIOUS CONVERSATIONAL INTELLIGENCE : THE ...
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
UNIT no 1 INTRODUCTION TO DBMS NOTES.pdf
Management Information system : MIS-e-Business Systems.pptx
August -2025_Top10 Read_Articles_ijait.pdf
Abrasive, erosive and cavitation wear.pdf
communication and presentation skills 01
AUTOMOTIVE ENGINE MANAGEMENT (MECHATRONICS).pptx
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Amdahl’s law is explained in the above power point presentations
Categorization of Factors Affecting Classification Algorithms Selection
CyberSecurity Mobile and Wireless Devices
Current and future trends in Computer Vision.pptx
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
III.4.1.2_The_Space_Environment.p pdffdf

2021 Is the floating LNG moment?

  • 1. Is the Floating LNG moment? OCTOBER, 2021
  • 2. 2 Index 1. LNG Trade. 1.1 LNG Imports. 1.2 LNG and Gas Pricing. 1.3 Floating Liquefaction Capacity Worldwide. 2. Floating Liquefied Natural Gas (FLNG). 2.1 In Operation Global FLNG. 3. Business Opportunity. 4. FLNG Project. 4.1 Justification. 4.2 Scope of project. 4.3 Study cases. 4.4 FLNG CAPEX (referential) 4.5 Risk of Project. 4.6 Advantages.
  • 3. 3 Figure: 2020 LNG Imports and Market Share by Market. Source: GIIGNL. Despite COVID-19 impacts on demand and supply, global LNG trade continued its upward trend in 2020 for another consecutive year of growth, reaching 356.1 MT. China, India, Chinese Taipei, the United States (Puerto Rico), and Brazil increased net imports through expansion of import capacity. 1. LNG Trade 1.1 LNG Imports
  • 4. 4 Lowest point for Brent US$ 69.96/bbl on 6 Jan 2020 Lowest point JKM US$ 1.83/MMBtu on 28 Apr 2020 Lowest point for HH US$ 1.47/MMBtu on 26 Jun 2020 Highest point for HH US$ 3.29/MMBtu on 30 Oct 2020 35 30 25 20 15 10 5 0 Dec 2019 Jan 2020 Feb 2020 Mar 2020 Apr 2020 May 2020 Jun 2020 Jul 2020 Aug 2020 Sep 2020 Oct 2020 Nov 2020 Dec 2020 Jan 2021 Feb 2021 Mar 2021 90 80 70 60 50 40 30 20 10 0 Dated Brent (US$/bbl) JKM LNG (US$/MMBtu) WIM LNG (US$/MMBtu) NEW LNG (US$/MMBtu) GCM LNG (US$/MMBtu) Dutch TTF (US$/MMBtu) Henry Hub (US$/MMBtu) Lowest point for Brent US$ 13.24/bbl on 21 Apr 2020 Lowest point for TTF US$ 1.13/MMBtu on 28 May 2020 Highest point for TTF US$ 6.90/MMBtu on 31 Dec 2020 Feb JKM Price at record US$ 32.50/MMBtu on 13 Jan 2021 Source: IGU World LNG report - 2021 Edition. 1. LNG Trade 1.2 LNG and Gas Pricing
  • 5. 5 1. LNG Trade 1.3 Floating Liquefaction Capacity Worldwide Australia, 3.6 MTPA Mozambique, 3.4 MTPA Malaysia, 2.7 MTPA Mauritania, 2.5 MTPA Cameroon, 2.4 MTPA Figure: Global sanctioned and operational FLNG liquefaction capacity as a february 2021. Source: Rystad Energy Figure: Global proposed FLNG liquefaction capacity. Source: Rystad Energy. United States, 54 MTPA Canada, 32 MTPA Djibouti, 10 MTPA Mauritania, 7.5 MTPA Australia, 6 MTPA Israel, 3 MTPA Cameroon, 1.4 MTPA Russia, 1.3 MTPA Congo, 1.2 MTPA
  • 6. 6 2. Floating Liquefied Natural Gas (FLNG) A floating LNG (FLNG) is an LNG plant constructed on a ship or a barge which has LNG storage and offloading facilities. The FLNG accomplishes the gas treatment and liquefaction (production of LNG) from the natural gases produced in gas fields, and the storage/offloading of product LNG to LNG carriers for ocean transportation. In operation liquefaction technology:  Black & Veatch PRICO (Cameroon FLNG, Tango FLNG)  Shell DMR (Prelude LNG)
  • 7. 7 Source: Rystad Energy. Tango FLNG Cameroon FLNG Petronas Prelude FLNG 2. Floating Liquefied Natural Gas (FLNG) 2.1 In Operation Global Floating LNG 7.2 MTPA Operational Floating Liquefaction Capacity Worldwide as of Jan 2021 The Tango FLNG vessel is currently available for other projects. 0.5 MTPA 16,500 m3 Start up: 2019 2.4 MTPA 125,000 m3 Start up: 2018 3.6 MTPA 437,500 m3 Start up: 2019 Liquefaction Technology: Black & Veatch PRICO Liquefaction Technology: Shell DMR Liquefaction Technology: Black & Veatch PRICO
  • 8. As global liquefied natural gas trade continues to expand rapidly, the challenge of liquefaction process selection becomes increasingly important. Selecting more versatile and cost-effective liquefaction technologies that meet stringent emissions standards will be a key focus for new projects as governments and companies commit to decarbonisation efforts. Cost estimates for most new projects suggest that they will be able to profitably deliver to stronger import markets, such as China and Southeast Asia, which are expected to see larger increases in LNG imports during this period. 8 3. Business Opportunity
  • 9. 4. FLNG Project 4.1 Justification 9 The development of a FLNG project is supported by:  Current decarbonization trend.  The difficulties that a natural gas liquefaction plant on land may present.
  • 10. 4. FLNG Project 4.2 Scope of Project 10 To install a Floating Liquefaction Natural Gas in order to provide the facilities required to: Facilities for the liquefaction of natural gas. LNG storage and utilities required.
  • 11. 4. FLNG Project 4.3 Proposed Cases (estimated) 11 Component Maximun concentration CO2 50 ppmv H2O 0.1 ppmv Mercury 0.01 µg/Sm3 H2S 4 ppmv Mercaptan Sulfur 8 ppmw Nitrogen 1.0 mol% Pentanes & heavier 0.075 mol% Limits for feed gas impurities to liquefaction process (referential) Case 1: 90 MMPCED of feed gas in order to reach 0.5 MTPA of liquefaction capacity (small scale). Case 2: 380 MMPCED of feed gas in order to reach 2.4 MTPA of liquefaction capacity (medium scale). Case 3: 550 MMPCED of feed gas in order to reach 3.5 MTPA of liquefaction capacity (large scale).
  • 12. 4. FLNG Project 4.4 FLNG CAPEX $/tpa (referential, 2019) 12 Figure: FLNG Cost. Source: Brian Songhurst, Research Associate, OIES. “Floating LNG Update, 2019.” 0 500 1000 1500 2000 2500 Prelude Satu (Petronas PFLNG 1) Dua (Petronas PFLNG 2) Tortue (Golar Gimi) Cameroon Episeyo (Golar Hilli) Tango (was Caribbean FLNG) $/tpa
  • 13. 13 4. FLNG Project 4.5 Risk of Project Risk Factors Impact on LNG Project Development Projects Economics Long-term sales contracts that allow for a sufficient return typically underpin the financing of LNG projects. High project costs or changing market prices can have a large impact. Politics & Geopolitics Permitting may be time consuming. Regulatory Approvals Regulatory approval may be costly and extends to the approval of upstream development and pipeline construction. Partner Priorities Not all partners are equally committed to a project and face different constraints depending on their respective portfolios. Ensuring alignment in advance of an FID may be difficult. Ability to Execute Partners must have the technical, operational, financial, and logistical capabilities to fully execute a project. Certain complex projects may present additional technical hurdles that could impact project feasibility. Business Cycle Larger economic trends. Feedstock Availability The overall availability of gas to supply an LNG project may be limited by technical characteristics of the associated fields. Marketing/Contracting Project developers generally need to secure long-term LNG buyers for a large portion of project capacity before sanctioning a project. Source: IGU World LNG report - 2019 Edition.
  • 14. 14 4. FLNG Project 4.6 Advantages  Fast track solution that can fill sudden need of gas.  Competitive costs for temporary, shorter-term operation.  Overcome onshore site limitations.  To reduce the infrastructure and environmental impact on onshore since FLNG does not require the coastal development.  To be built in fabrication yards where facilities and practices are well- established for construction of the topsides modules and hull without constraints of the countries or regions of the gas field or onshore LNG plant, which secures the efficiency and the safety of construction.