SlideShare a Scribd company logo
Project Time Management
Unit 6
Project Time Management
Includes the processes required to manage
Timely completion of the project.
2
Planning
6.1 Define Activities
6.2 Sequence Activities
6.3 Estimate Activity Resources
6.4 Estimate Activity Durations
6.5 Develop Schedule
Monitoring and controlling
6.6 Control Schedule
3
Dependency Relationships in the Precedence
Diagramming Method (PDM)
Dependency Determination
Three types of dependencies are used to define the
sequence among the activities
• Mandatory dependencies
– Those that are contractually required or inherent in the nature of the
work.
– Are also sometimes referred to as hard logic
• Discretionary dependencies ( optional )
– Discretionary dependencies are sometimes referred to as preferred,
or soft logic.
– Should be fully documented since they can create arbitrary total float
values and can Limit later scheduling options.
• External dependencies
– Involve a relationship between project activities and non-project
activities.
4
.
Applying Leads and Lags
A Lead
Allows an acceleration of the successor activity.
A Lag
Directs a delay in the successor activity
5
Precedence Diagramming Method
A
Start
D
F
H
K
L
End
I
C
B
E
G
J
SS +10
FS +15
FF
SS
Start
Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
Network Diagramming Analysis
A network diagrams is a schematic display of project’s
activities and dependencies
7
Network Diagramming
Activities
Code
Activity
Description
Resources
Needed
Original
Duration
Predecessor
Logic
Start 0 -------------
A 2 Start
B 12 A
C 5 B & D
D 6 Start
E 7 D
F 3 E
Finish 0 C & F 8
Network Diagram Analysis
9
Start
A
D
2 Days
6 Days
The Forward Pass …
0 0
Early Start ES
Box
Early Finish EF
Box
0 2
0 6
10
Start Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
The Forward Pass …
0
0
0
0 2 2 14 14 19
6 6 13 13 16
19 19
Highest of predecessor’s
Early Finish Times
Early Start =
Network Diagram Analysis
11
Finish
C
F
5 Days
3 Days
The Backward Pass …
19 19
Late Start
Box
Late Finish
Box
13 16
14 19
14 19
16 19
19 19
Network Diagram Analysis
12
Start
Finish
A B C
D E F
2 Days 12 Days 5 Days
6 Days 7 Days 3 Days
0
0
0
0 2 2 14 14 19
6 6 13 13 16
19 19
Lowest of successor’s
Late Start Times
Late Finish =
2 14
19
16
14 19
19
19
0 0
0 2
3 9 9 16
The Backward Pass …
Network Diagram Analysis
13
• Calculates the theoretical early start and finished dates.
• And late start and finish date for all schedule activities.
• The Critical Path is the longest time the project can last
• Total Float (Slack) The amount of time an activity can delay without
delaying the project completion date
A
START END
E
D
B
Network Diagram Analysis
14
Precedence Diagramming Method
Exercise
15
Precedence Diagramming Method
Exercise
Exercise
30 minutes
.
16
You are the project manager for project
with the following network diagram
A. Draw the network diagram ?
B. Calculate all of the paths in
this network diagram?
C. What is the duration of the
critical path of this network
diagram?
D. What is the float of task 3?
E. What is the float of task 5?
F. What is the float of task 1?
G. What is the slack of task 7?
Estimate
in months
Preceding
Activity
task
0
Start
2
Start
1
3
Start
2
7
1
3
9
1,2
4
3
2
5
2
3
6
8
4
7
0
5,6,7
End
17
.
B. 1 - 3 - 6 : 2 + 7 + 2 = 11 months
1 - 4 - 7 : 2 + 9 + 8 = 19months
2 - 4 - 7 : 3 + 9 + 8 = 20months
2 - 5 : 3 + 3 = 6 months
C. 20 months
D. Using float = LS – ES = 9 months
E. 14 months
F. 1 month
G. Since Task VII is in the critical path by
definition the slack is 0.
18
Start
I
III VI
End
II
IV VII
2
7
3
8
9
V
2
3
6.1 Define Activities
• Identifying the specific actions to be performed to produce the
project deliverables
• Project work packages are typically decomposed into smaller
component called activities that represent the work necessary to
complete the work package.
• Activities provide a basis for estimating, scheduling, executing,
and monitoring and controlling the project work
19
6.1 Define Activities
(Inputs)
20
Scope Baseline
Enterprise Environmental Factors
• Project management information system (PMIS).
Organizational Process Assets
• Existing formal and informal activity planning-related policies,
procedures, and guidelines,
• Lessons-learned knowledge base
6.1 Define Activities
(Tools & Techniques)
21
Decomposition
• Involves subdividing the project work packages into smaller ,more
manageable components called activities.
• Activities represent the effort needed to complete a work package.
• Defines the final outputs as activities rather than deliverables.
• The activity list, WBS, WBS dictionary can be developed either
sequentially or concurrently as the basis for development of the final
activity list.
Rolling Wave Planning
Is a form of progressive elaboration planning where the work to be
accomplished in the near term is planned in detail and future work is
planned at a higher level of the WBS
6.1 Define Activities
(Tools & Techniques)
22
Templates
A standard activity list or a portion of an activity list from a
previous project is often usable as a template for a new
project.
Expert Judgment
Project team members or other experts, who are experienced
and skilled in developing detailed project scope statements,
the WBS, and project schedules, can provide expertise in
defining activities.
6.1 Define Activities
(Outputs)
23
Activity List
The activity list includes the activity identifier and the scope
of work description for each activity in sufficient detail to
ensure that the project team members understand what work
is required to be completed.
Activity Attributes
Activity attributes extend the description of the activity by
identifying the multiple components associated with each
activity.
Milestone List
A milestone list identifies all milestones and indicates
whether the milestone is mandatory, or optional.
6.1 Define Activities
24
6.1 Define Activities
25
6.2 Sequence Activities
• Sequence activities is the process of identifying
and documenting relationships among the
project activities.
• It may be necessary to use lead or lag time
between activities to support a realistic and
achievable project schedule.
26
• Activity List
• Activity Attributes
• Milestone List
• Project Scope Statement
• Organizational Process Assets
27
6.2 Sequence Activities
(Inputs)
• Precedence Diagramming method (PDM)
• Dependency Determination
• Applying Leads and Lags
28
6.2 Sequence Activities
(Tools & Techniques)
• Project schedule network diagram
– Are schematic displays of the project’s schedule
activities and the logical relationships among them.
– Can be produced manually or by using project
management software.
• Project document updates
Project documents that may be updated include:
• Activity lists,
• Activity attributes,
• Risk register
29
6.2 Sequence Activities
(Output)
6.2 Sequence Activities
30
6.2 Sequence Activities
31
6.3 Estimate Activity Resources
Estimate activity resources is the process of
estimating the type and quantities of material,
people, equipment, or supplies required to
perform each activity.
32
33
Activity List
Activity Attributes
Resource Calendars
• Specify when and how long identified project resources will be
available during the project.
Enterprise Environmental Factors
• Resource availability and skills.
Organizational Process Assets
• Policies and procedures regarding staffing,
• Policies and procedures relating to rental and purchase of
supplies and equipment, and
• Historical information regarding types of resources used for
similar work on previous projects.
6.3 Estimate Activity Resources
(Inputs)
6.3 Estimate Activity Resources
(Tools & Techniques)
34
Expert Judgment
Any group or person with specialized knowledge in resource planning
and estimating can provide such expertise.
Alternatives Analysis
Include using various levels of resources capability or skills, different
size or type of machines, different tools, and make-or-buy decisions
regarding the resources.
Published Estimating Data
Several companies routinely publish updated production rates and
unit costs of resources, and equipment for different countries, and
geographical locations within countries.
35
Bottom-Up Estimating
When an activity cannot be estimated with a reasonable degree of
confidence, the work within the activity is decomposed into more
detail. The resource needs are estimated. These estimates are then
aggregated into a total quantity for each of the activity’s resources.
Project Management Software
Project management software has the capability to help plan,
organize, and manage resources pools and develop resources
estimates
6.3 Estimate Activity Resources
(Tools & Techniques)
36
Activity Resource Requirements
Identifies the types and quantities of resources required for each
activity in a work package
Resource Breakdown Structure
The resource breakdown structure is a hierarchical structure of the
identified resources by resource category and resource type.
Project Document Updates
• Activity list,
• Activity attributes, and
• Resource calendars
6.3 Estimate Activity Resources
(Outputs)
37
6.3 Estimate Activity Resources
38
6.3 Estimate Activity Resources
6.4 Estimate Activity Durations
• Is the process of approximating the number of work periods
needed to complete individual activities with estimated resources.
• The input for the estimates of activity duration originate from the
person or group on the project team who is most familiar with the
nature of the work in the specific activity.
• Most project management software for scheduling will handle this
situation by using project calendar and alternative work-period
resource calendars that are usually identified by the resource that
require specific work periods.
39
6.4 Estimate Activity Durations
(Inputs)
40
Activity List
Activity Attributes
Activity Resource Requirements
Resource Calendars
Project Scope Statement
Constraints and assumptions .
6.4 Estimate Activity Durations
(Inputs)
41
Enterprise Environmental Factors
• Duration estimating databases and other reference data,
• Productivity metrics, and
• Published commercial information.
Organizational Process Assets
• Historical duration information,
• Scheduling methodology, and
• Lessons learned.
6.4 Estimate Activity Durations
(Tools & Techniques)
42
Expert Judgment
Expert judgment can provide duration estimate information or recommend
maximum activity duration from prior similar projects.
Analogous Estimating
• This technique relies on the actual duration of previous similar projects as
the basis for estimating the duration of the current project.
• Generally less costly and time consuming than other techniques, but it is
also generally less accurate.
Reserve Analysis
Duration estimates may include contingency reserve, (time reserve or buffers)
into the overall project schedule to account for schedule uncertainty.
43
Parametric Estimating
Parametric estimating uses a statistical relationship between historical data
and other variables to calculate an estimate for activity parameters, such as
cost, budget, and duration.
Three-point estimates
PERT uses three estimates to define an approximate range for an activity’s
duration
• Most likely:
the activity duration is based on analysis of the average
productivity of the resource.
• Optimistic:
the activity duration is based on analysis of the best-case scenario
for the activity.
• Pessimistic:
the activity duration is based on analysis of the worst-case scenario
for the activity
T = O+4M+P
6
6.4 Estimate Activity Durations
(Tools & Techniques)
44
• Activity Duration Estimates
• Project Document Updates
 Activity Attributes
6.4 Estimate Activity Durations
(Outputs)
6.4 Estimate Activity Durations
45
6.4 Estimate Activity Durations
46
• Develop schedule is the process of analyzing
activity sequences, durations, resource
requirements, and schedule constraints to create
the project schedule.
• Developing an acceptable project schedule is
often an iterative process.
47
6.5 Develop Schedule
6.5 Develop Schedule
(Inputs)
48
• Activity List
• Activity Attributes
• Project Schedule network Diagrams
• Activity Resource Requirements
• Resource Calendars
• Activity Duration Estimates
• Project Scope Statement
• Enterprise Environmental Factors
• Organizational Process Assets
6.5 Develop Schedule
(Tools & Techniques)
49
Schedule network analysis
• Is the technique that generate the project schedule
• It employs various analytical techniques, such as Critical Path
Method, Critical Chain Method, what-if analysis, and resource
leveling to calculate the early and late start and finish dates for the
uncompleted portions of project activities
Critical Chain Method
• A schedule network analysis technique that modifies the project
schedule to account for limited resources.
• Applied after critical path is identified, resource availability is
entered and the resource-limited schedule result is determined, the
resulting schedule often has an altered critical path.
50
Resource Leveling
Schedule network analysis technique in which scheduling decisions
are driven by resource constraints and applied to a schedule model
that has already been analyzed by the critical path method.
Applying Leads and Lags
Leads and lags are refinements applied during network analysis to
develop a viable schedule.
Scheduling Tool
Automated scheduling tools expedite the scheduling process by
generating start and finish dates based on the inputs of activities,
network diagrams, resources and activity durations.
6.5 Develop Schedule
(Tools & Techniques)
51
Schedule Compression
Shortens the project schedule without changing the project scope, to
meet schedule constraints, imposed dates, or other schedule 0bjectives.
Crashing:
Approving overtime, bringing in additional resources, or paying to
expedite delivery to activities on the critical path.
Fast tracking:
Doing activities in parallel that would normally be done in sequence.
Fast tracking often results in rework and usually increases risk
6.5 Develop Schedule
(Tools & Techniques)
52
Project Schedule
 As a minimum, the project schedule includes a planned start date
and planned finish date for each activity.
 the project schedule may be presented in summary form, sometimes
referred to as the master schedule, or presented in detail.
• Milestone Charts
these charts are similar to bar charts, but only identify the
scheduled start or completion of major deliverables and key
external interfaces.
• Bar Charts
These charts, with bars representing activities, show activity
start and end dates as well as expected durations.
• Project Schedule Network Diagrams
These diagrams, with activity date information, usually show
both the project network logic and the project’s critical path
schedule activities.
6.5 Develop Schedule
(Outputs)
53
6.5 Develop Schedule
(Outputs)
54
Schedule Baseline
Is the accepted and approved version of the project schedule.
Schedule Data
The schedule data for the project schedule includes at least the
schedule milestones, schedule activities, activity attributes, and
documentation of all identified assumptions and constraints.
Project Document Updates
• Activity resource requirements
• Activity attributes
• Calendar
• Risk register
6.5 Develop Schedule
(Outputs)
55
6.5 Develop Schedule
56
6.5 Develop Schedule
• Determining the current status of the project
schedule
• Influencing the factors that create schedule
changes
• Determining that the schedule has changed
• Managing the actual changes when and as they
occur
57
6.6 Control Schedule
6.6 Control Schedule
(Inputs)
58
• Project Management Plan
• Project Schedule
• Work Performance information
• Organizational Process Assets
6.6 Control Schedule
(Tools & Techniques)
59
Performance Reviews
Measure, compare, and analyze schedule performance such as actual
start and finish dates, percent complete, and remaining duration for
work in progress.
Variance analysis
• Schedule performance measurements (SV, SPI) are used to assess
the magnitude of variation to the original schedule baseline.
• The total float variance is an essential planning component to
evaluate project time performance.
6.6 Control Schedule
(Tools & Techniques)
60
• Project management Software
• Resource Leveling
• What-if Scenario Analysis
• Adjusting Leads and Lags
• Schedule Compression
• Scheduling Tool
6.6 Control Schedule
(Outputs)
61
• Work Performance measurements
• Organizational Process Assets Updates
• Change Requests
• Project management Plan Updates
 Schedule baseline
 Cost baseline
• Project Document Updates
 Project Schedule
62
6.6 Control Schedule
63
6.6 Control Schedule
Questions
64
1- Which of the following is the BEST to do to try to
complete your project two months earlier?
A ) Tell senior management that the project’s critical path does
not allow the project to be finished earlier.
B ) Tell your boss.
C ) Meet with the team and look for options for crashing or fast
tracking the critical path.
D ) Work hard and see what the project status is next month.
65
1- Which of the following is the BEST to do to try to
complete your project two months earlier?
A ) Tell senior management that the project’s critical path does
not allow the project to be finished earlier.
B ) Tell your boss.
C ) Meet with the team and look for options for crashing or fast
tracking the critical path.
D ) Work hard and see what the project status is next month.
66
2- A problem occurs on an activity with free float and the
project manager has extended its duration. What is MOST likely
to be affected?
A) Project duration
B) Resource schedules
C) Project scope management plan
D) The latest start for the successor activity
67
2- A problem occurs on an activity with free float and the
project manager has extended its duration. What is MOST likely
to be affected?
A) Project duration
B) Resource schedules
C) Project scope management plan
D) The latest start for the successor activity
68
3- An activity has an early start (ES) of day 3, a late
start (LS) of day 13, an early finish (EF) of day 9 and a
late finish (LF) of day 19. what is the activity float?
A) 10
B) 6
C) 3
D) 19
69
3- An activity has an early start (ES) of day 3, a late
start (LS) of day 13, an early finish (EF) of day 9 and a
late finish (LF) of day 19. what is the activity float?
A) 10
B) 6
C) 3
D) 19
70
4- An activity has an early start (ES) of day 3, a late start
(LS) of day 13, an early finish (EF) of day 9 and a late finish
(LF) of day 19. what is the duration of this activity?
A) 3
B) 6
C) 7
D) 10
71
4- An activity has an early start (ES) of day 3, a late start
(LS) of day 13, an early finish (EF) of day 9 and a late finish
(LF) of day 19. what is the duration of this activity?
A) 3
B) 6
C) 7
D) 10
72
5- Based on the chart, a resource on your project from the
consumer affairs department comes to you to tell you that
they are taking a two-week leave due to a family emergency.
They are assigned to activity F, which is currently in progress.
This is a problem because activity F has:
a) One week of float
b) Two months of float
c) One month of float
d) No float
Estimate
(months)
Preceding
activity
Activity
Start
3
Start
A
7
Start
B
2
A
C
4
A
D
5
C, D
E
9
B
F
3
E, F
G
G
end 73
a) One week of float
b) Two months of float
c) One month of float
d) No float
Estimate
(months)
Preceding
activity
Activity
Start
3
Start
A
7
Start
B
2
A
C
4
A
D
5
C, D
E
9
B
F
3
E, F
G
G
end 74
5- Based on the chart, a resource on your project from the
consumer affairs department comes to you to tell you that
they are taking a two-week leave due to a family emergency.
They are assigned to activity F, which is currently in progress.
This is a problem because activity F has:
a) Zero days
b) Two days
c) Four days
d) One day 75
6- Management wants the project completed in 40 days. The cost
performance index (CPI) is 1.1, the project critical path duration is
38 days with a standard deviation of two days. What is the
maximum project float?
6- Management wants the project completed in 40 days. The cost
performance index (CPI) is 1.1, the project critical path duration is
38 days with a standard deviation of two days. What is the
maximum project float?
a) Zero days
b) Two days
c) Four days
d) One day 76
7- Total float is the amount of time an activity
can be delayed without delaying the :
A ) project.
B ) completion date required by the customer.
C ) early start of its successor.
D ) project completion date.
77
7- Total float is the amount of time an activity
can be delayed without delaying the :
A ) project.
B ) completion date required by the customer.
C ) early start of its successor.
D ) project completion date.
78
8- Your boss tells you that one of your resources is
needed on another project. All the activities in the
chart are occurring at the same time. Assuming
that all the resources working on which activity
would you pick to move to the other project?
A ) Activity D
B ) Activity C
C ) Activity H
D ) Activity B
Float
(month)
activity
Start
2
B
1
C
0
D
1
F
0
G
4
H
0
I
3
E
End 79
A ) Activity D
B ) Activity C
C ) Activity H
D ) Activity B
Float
(month)
activity
Start
2
B
1
C
0
D
1
F
0
G
4
H
0
I
3
E
End 80
8- Your boss tells you that one of your resources is
needed on another project. All the activities in the
chart are occurring at the same time. Assuming
that all the resources working on which activity
would you pick to move to the other project?
9- Lag means:
A ) The amount of time an activity can be delayed
without delaying the project finish date.
B ) The amount of time an activity can be delayed
without delaying the early start date of its successor.
C ) Waiting time
D ) The product of a forward and backward pass
81
9- Lag means:
A ) The amount of time an activity can be delayed
without delaying the project finish date.
B ) The amount of time an activity can be delayed
without delaying the early start date of its successor.
C ) Waiting time
D ) The product of a forward and backward pass
82
10- Management has decided to “crash” a project to avoid
penalty payments for late deliveries. Additional costs are
expected. To crash the project, either overtime or additional
resources should be assigned to:
A ) all activities
B ) only those activities with the longest time durations
C ) those activities on the critical path beginning with
the lowest additional cost activities
D ) those activities with the greatest degree of risk 83
10- Management has decided to “crash” a project to avoid
penalty payments for late deliveries. Additional costs are
expected. To crash the project, either overtime or additional
resources should be assigned to:
A ) all activities
B ) only those activities with the longest time durations
C ) those activities on the critical path beginning with
the lowest additional cost activities
D ) those activities with the greatest degree of risk 84
11- Using the chart, the resource for activity A is assigned to an
additional, more important project. As a result the resource will not
be able to devote as much time to your project. Activity A will now
take 10 weeks. How does this affect the project?
A) There are three critical
paths
B) The project will be delayed
C) The project is riskier
D) Activity D will be delayed
Estimates
(weeks)
Preceding
activity
Activity
0
Start
3
Start
C
6
C
D
8
C
A
4
D
E
5
A,E
B
3
E
F
0
B,F
end 85
11- Using the chart, the resource for activity A is assigned to an
additional, more important project. As a result the resource will not
be able to devote as much time to your project. Activity A will now
take 10 weeks. How does this affect the project?
A) There are three critical
paths
B) The project will be delayed
C) The project is riskier
D) Activity D will be delayed
Estimates
(weeks)
Preceding
activity
Activity
0
Start
3
Start
C
6
C
D
8
C
A
4
D
E
5
A,E
B
3
E
F
0
B,F
end 86
12- All of the following processes are included in
project time management except:
A ) define activities
B ) estimate activity durations
C ) control schedule
D ) plan resources
87
12- All of the following processes are included in
project time management except:
A ) define activities
B ) estimate activity durations
C ) control schedule
D ) plan resources
88
13- Any form of network analysis in which
scheduling decisions, such as start and finish dates,
are driven by resource management concern is
called resource------------
A ) allocation
B ) leveling
C ) partitioning
D ) quantification 89
13- Any form of network analysis in which
scheduling decisions, such as start and finish dates,
are driven by resource management concern is
called resource------------
A ) allocation
B ) leveling
C ) partitioning
D ) quantification 90
91
A B F G H J K
C D E
I
6 7
10 1 4
3
6
4
8
9
11
14 ) What is the duration of the near critical path ?
A. 33
B. 44
C. 47
D. 43
92
A B F G H J K
C D E
I
6 7
10 1 4
3
6
4
8
9
11
14 ) What is the duration of the near critical path ?
A. 33
B. 44
C. 47
D. 43
Thank you
.
93

More Related Content

PDF
MG6088 SOFTWARE PROJECT MANAGEMENT
PPTX
Project management and control
PPTX
Software Project Management
PDF
Primavera p6 manual edited
PPTX
Project time management
PPTX
Project Scheduling
PPT
041006-Program Management PMI NB - PMI Logo
PPTX
What are the Basic Principles of Project Management | AIMS, UK
MG6088 SOFTWARE PROJECT MANAGEMENT
Project management and control
Software Project Management
Primavera p6 manual edited
Project time management
Project Scheduling
041006-Program Management PMI NB - PMI Logo
What are the Basic Principles of Project Management | AIMS, UK

What's hot (20)

PPTX
Project Estimation
PPT
Pressman ch-22-process-and-project-metrics
PDF
The New PMP Exam: Changes and Implications (With Annotation)
PPT
Project audit & closure
PPT
PROJECT QUALITY MANAGEMENT for Project.ppt
PPTX
Project Schedule Management - PMBOK6
PDF
Basics of Project Planning
PDF
ASMS Project Plan
PPTX
Progress control
PDF
Ms Project Workshop
PDF
MS Project
PPTX
SPM Activity Planning Introduction
PPT
project planning-estimation
PPTX
Project Stakeholder Management - PMBOK6
PDF
PERT AND CPM PROJECT MANAGEMENT
PPT
06. Project Management Process Groups
PPT
Software estimation
PPTX
Risk Management
PPT
1. introduction
ZIP
Project Monitoring and Control
Project Estimation
Pressman ch-22-process-and-project-metrics
The New PMP Exam: Changes and Implications (With Annotation)
Project audit & closure
PROJECT QUALITY MANAGEMENT for Project.ppt
Project Schedule Management - PMBOK6
Basics of Project Planning
ASMS Project Plan
Progress control
Ms Project Workshop
MS Project
SPM Activity Planning Introduction
project planning-estimation
Project Stakeholder Management - PMBOK6
PERT AND CPM PROJECT MANAGEMENT
06. Project Management Process Groups
Software estimation
Risk Management
1. introduction
Project Monitoring and Control
Ad

Similar to 3- Project Time Management.ppt (20)

PPTX
Day 3 Schedule -walaa (3).pptx
PPTX
Session 8 4th edition PMP
PPTX
TIME MANAGEMENT chapter(6), PMBOK5
PPT
Episode 23 : PROJECT TIME MANAGEMENT
PPTX
DOC-20230811-WA0054..pptx busnises plangood
PDF
Topic 11 - Project Schedule Management.pdf
PPTX
6.3 Sequence Activities
PPT
lecture8-190719030939.ppthjtyuiytiytiyti
PPT
Software Engineering (Project Scheduling)
PPTX
Project time management involves the processes required to ensure timely comp...
PDF
Project Management Essentials Materials_0.pdf
DOC
Network diagrams
PPTX
PMNM101 Lesson 2 2022.pptx
PPT
Gantt Charts.ppt
PPT
Project Time Management
PPTX
Chapter 4.pptx
PPTX
PMP Training - Project Time Management Part 2
PPTX
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
PPTX
Critical Path Method (CPM) & Network Analysis
PDF
3210cpmslideshare-1610302073773770419.pdf
Day 3 Schedule -walaa (3).pptx
Session 8 4th edition PMP
TIME MANAGEMENT chapter(6), PMBOK5
Episode 23 : PROJECT TIME MANAGEMENT
DOC-20230811-WA0054..pptx busnises plangood
Topic 11 - Project Schedule Management.pdf
6.3 Sequence Activities
lecture8-190719030939.ppthjtyuiytiytiyti
Software Engineering (Project Scheduling)
Project time management involves the processes required to ensure timely comp...
Project Management Essentials Materials_0.pdf
Network diagrams
PMNM101 Lesson 2 2022.pptx
Gantt Charts.ppt
Project Time Management
Chapter 4.pptx
PMP Training - Project Time Management Part 2
CPM and pert(IT)-SOWFTWARE PROJECT MANAGEMENT
Critical Path Method (CPM) & Network Analysis
3210cpmslideshare-1610302073773770419.pdf
Ad

Recently uploaded (20)

PDF
R24 SURVEYING LAB MANUAL for civil enggi
PPTX
Geodesy 1.pptx...............................................
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
Well-logging-methods_new................
PPTX
Sustainable Sites - Green Building Construction
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
composite construction of structures.pdf
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
web development for engineering and engineering
PPTX
Welding lecture in detail for understanding
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
R24 SURVEYING LAB MANUAL for civil enggi
Geodesy 1.pptx...............................................
Automation-in-Manufacturing-Chapter-Introduction.pdf
KTU 2019 -S7-MCN 401 MODULE 2-VINAY.pptx
OOP with Java - Java Introduction (Basics)
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Model Code of Practice - Construction Work - 21102022 .pdf
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Well-logging-methods_new................
Sustainable Sites - Green Building Construction
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
composite construction of structures.pdf
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Foundation to blockchain - A guide to Blockchain Tech
web development for engineering and engineering
Welding lecture in detail for understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT

3- Project Time Management.ppt

  • 2. Project Time Management Includes the processes required to manage Timely completion of the project. 2 Planning 6.1 Define Activities 6.2 Sequence Activities 6.3 Estimate Activity Resources 6.4 Estimate Activity Durations 6.5 Develop Schedule Monitoring and controlling 6.6 Control Schedule
  • 3. 3 Dependency Relationships in the Precedence Diagramming Method (PDM)
  • 4. Dependency Determination Three types of dependencies are used to define the sequence among the activities • Mandatory dependencies – Those that are contractually required or inherent in the nature of the work. – Are also sometimes referred to as hard logic • Discretionary dependencies ( optional ) – Discretionary dependencies are sometimes referred to as preferred, or soft logic. – Should be fully documented since they can create arbitrary total float values and can Limit later scheduling options. • External dependencies – Involve a relationship between project activities and non-project activities. 4
  • 5. . Applying Leads and Lags A Lead Allows an acceleration of the successor activity. A Lag Directs a delay in the successor activity 5
  • 7. Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days Network Diagramming Analysis A network diagrams is a schematic display of project’s activities and dependencies 7
  • 8. Network Diagramming Activities Code Activity Description Resources Needed Original Duration Predecessor Logic Start 0 ------------- A 2 Start B 12 A C 5 B & D D 6 Start E 7 D F 3 E Finish 0 C & F 8
  • 9. Network Diagram Analysis 9 Start A D 2 Days 6 Days The Forward Pass … 0 0 Early Start ES Box Early Finish EF Box 0 2 0 6
  • 10. 10 Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days The Forward Pass … 0 0 0 0 2 2 14 14 19 6 6 13 13 16 19 19 Highest of predecessor’s Early Finish Times Early Start = Network Diagram Analysis
  • 11. 11 Finish C F 5 Days 3 Days The Backward Pass … 19 19 Late Start Box Late Finish Box 13 16 14 19 14 19 16 19 19 19 Network Diagram Analysis
  • 12. 12 Start Finish A B C D E F 2 Days 12 Days 5 Days 6 Days 7 Days 3 Days 0 0 0 0 2 2 14 14 19 6 6 13 13 16 19 19 Lowest of successor’s Late Start Times Late Finish = 2 14 19 16 14 19 19 19 0 0 0 2 3 9 9 16 The Backward Pass … Network Diagram Analysis
  • 13. 13 • Calculates the theoretical early start and finished dates. • And late start and finish date for all schedule activities. • The Critical Path is the longest time the project can last • Total Float (Slack) The amount of time an activity can delay without delaying the project completion date A START END E D B Network Diagram Analysis
  • 17. You are the project manager for project with the following network diagram A. Draw the network diagram ? B. Calculate all of the paths in this network diagram? C. What is the duration of the critical path of this network diagram? D. What is the float of task 3? E. What is the float of task 5? F. What is the float of task 1? G. What is the slack of task 7? Estimate in months Preceding Activity task 0 Start 2 Start 1 3 Start 2 7 1 3 9 1,2 4 3 2 5 2 3 6 8 4 7 0 5,6,7 End 17
  • 18. . B. 1 - 3 - 6 : 2 + 7 + 2 = 11 months 1 - 4 - 7 : 2 + 9 + 8 = 19months 2 - 4 - 7 : 3 + 9 + 8 = 20months 2 - 5 : 3 + 3 = 6 months C. 20 months D. Using float = LS – ES = 9 months E. 14 months F. 1 month G. Since Task VII is in the critical path by definition the slack is 0. 18 Start I III VI End II IV VII 2 7 3 8 9 V 2 3
  • 19. 6.1 Define Activities • Identifying the specific actions to be performed to produce the project deliverables • Project work packages are typically decomposed into smaller component called activities that represent the work necessary to complete the work package. • Activities provide a basis for estimating, scheduling, executing, and monitoring and controlling the project work 19
  • 20. 6.1 Define Activities (Inputs) 20 Scope Baseline Enterprise Environmental Factors • Project management information system (PMIS). Organizational Process Assets • Existing formal and informal activity planning-related policies, procedures, and guidelines, • Lessons-learned knowledge base
  • 21. 6.1 Define Activities (Tools & Techniques) 21 Decomposition • Involves subdividing the project work packages into smaller ,more manageable components called activities. • Activities represent the effort needed to complete a work package. • Defines the final outputs as activities rather than deliverables. • The activity list, WBS, WBS dictionary can be developed either sequentially or concurrently as the basis for development of the final activity list. Rolling Wave Planning Is a form of progressive elaboration planning where the work to be accomplished in the near term is planned in detail and future work is planned at a higher level of the WBS
  • 22. 6.1 Define Activities (Tools & Techniques) 22 Templates A standard activity list or a portion of an activity list from a previous project is often usable as a template for a new project. Expert Judgment Project team members or other experts, who are experienced and skilled in developing detailed project scope statements, the WBS, and project schedules, can provide expertise in defining activities.
  • 23. 6.1 Define Activities (Outputs) 23 Activity List The activity list includes the activity identifier and the scope of work description for each activity in sufficient detail to ensure that the project team members understand what work is required to be completed. Activity Attributes Activity attributes extend the description of the activity by identifying the multiple components associated with each activity. Milestone List A milestone list identifies all milestones and indicates whether the milestone is mandatory, or optional.
  • 26. 6.2 Sequence Activities • Sequence activities is the process of identifying and documenting relationships among the project activities. • It may be necessary to use lead or lag time between activities to support a realistic and achievable project schedule. 26
  • 27. • Activity List • Activity Attributes • Milestone List • Project Scope Statement • Organizational Process Assets 27 6.2 Sequence Activities (Inputs)
  • 28. • Precedence Diagramming method (PDM) • Dependency Determination • Applying Leads and Lags 28 6.2 Sequence Activities (Tools & Techniques)
  • 29. • Project schedule network diagram – Are schematic displays of the project’s schedule activities and the logical relationships among them. – Can be produced manually or by using project management software. • Project document updates Project documents that may be updated include: • Activity lists, • Activity attributes, • Risk register 29 6.2 Sequence Activities (Output)
  • 32. 6.3 Estimate Activity Resources Estimate activity resources is the process of estimating the type and quantities of material, people, equipment, or supplies required to perform each activity. 32
  • 33. 33 Activity List Activity Attributes Resource Calendars • Specify when and how long identified project resources will be available during the project. Enterprise Environmental Factors • Resource availability and skills. Organizational Process Assets • Policies and procedures regarding staffing, • Policies and procedures relating to rental and purchase of supplies and equipment, and • Historical information regarding types of resources used for similar work on previous projects. 6.3 Estimate Activity Resources (Inputs)
  • 34. 6.3 Estimate Activity Resources (Tools & Techniques) 34 Expert Judgment Any group or person with specialized knowledge in resource planning and estimating can provide such expertise. Alternatives Analysis Include using various levels of resources capability or skills, different size or type of machines, different tools, and make-or-buy decisions regarding the resources. Published Estimating Data Several companies routinely publish updated production rates and unit costs of resources, and equipment for different countries, and geographical locations within countries.
  • 35. 35 Bottom-Up Estimating When an activity cannot be estimated with a reasonable degree of confidence, the work within the activity is decomposed into more detail. The resource needs are estimated. These estimates are then aggregated into a total quantity for each of the activity’s resources. Project Management Software Project management software has the capability to help plan, organize, and manage resources pools and develop resources estimates 6.3 Estimate Activity Resources (Tools & Techniques)
  • 36. 36 Activity Resource Requirements Identifies the types and quantities of resources required for each activity in a work package Resource Breakdown Structure The resource breakdown structure is a hierarchical structure of the identified resources by resource category and resource type. Project Document Updates • Activity list, • Activity attributes, and • Resource calendars 6.3 Estimate Activity Resources (Outputs)
  • 39. 6.4 Estimate Activity Durations • Is the process of approximating the number of work periods needed to complete individual activities with estimated resources. • The input for the estimates of activity duration originate from the person or group on the project team who is most familiar with the nature of the work in the specific activity. • Most project management software for scheduling will handle this situation by using project calendar and alternative work-period resource calendars that are usually identified by the resource that require specific work periods. 39
  • 40. 6.4 Estimate Activity Durations (Inputs) 40 Activity List Activity Attributes Activity Resource Requirements Resource Calendars Project Scope Statement Constraints and assumptions .
  • 41. 6.4 Estimate Activity Durations (Inputs) 41 Enterprise Environmental Factors • Duration estimating databases and other reference data, • Productivity metrics, and • Published commercial information. Organizational Process Assets • Historical duration information, • Scheduling methodology, and • Lessons learned.
  • 42. 6.4 Estimate Activity Durations (Tools & Techniques) 42 Expert Judgment Expert judgment can provide duration estimate information or recommend maximum activity duration from prior similar projects. Analogous Estimating • This technique relies on the actual duration of previous similar projects as the basis for estimating the duration of the current project. • Generally less costly and time consuming than other techniques, but it is also generally less accurate. Reserve Analysis Duration estimates may include contingency reserve, (time reserve or buffers) into the overall project schedule to account for schedule uncertainty.
  • 43. 43 Parametric Estimating Parametric estimating uses a statistical relationship between historical data and other variables to calculate an estimate for activity parameters, such as cost, budget, and duration. Three-point estimates PERT uses three estimates to define an approximate range for an activity’s duration • Most likely: the activity duration is based on analysis of the average productivity of the resource. • Optimistic: the activity duration is based on analysis of the best-case scenario for the activity. • Pessimistic: the activity duration is based on analysis of the worst-case scenario for the activity T = O+4M+P 6 6.4 Estimate Activity Durations (Tools & Techniques)
  • 44. 44 • Activity Duration Estimates • Project Document Updates  Activity Attributes 6.4 Estimate Activity Durations (Outputs)
  • 45. 6.4 Estimate Activity Durations 45
  • 46. 6.4 Estimate Activity Durations 46
  • 47. • Develop schedule is the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. • Developing an acceptable project schedule is often an iterative process. 47 6.5 Develop Schedule
  • 48. 6.5 Develop Schedule (Inputs) 48 • Activity List • Activity Attributes • Project Schedule network Diagrams • Activity Resource Requirements • Resource Calendars • Activity Duration Estimates • Project Scope Statement • Enterprise Environmental Factors • Organizational Process Assets
  • 49. 6.5 Develop Schedule (Tools & Techniques) 49 Schedule network analysis • Is the technique that generate the project schedule • It employs various analytical techniques, such as Critical Path Method, Critical Chain Method, what-if analysis, and resource leveling to calculate the early and late start and finish dates for the uncompleted portions of project activities Critical Chain Method • A schedule network analysis technique that modifies the project schedule to account for limited resources. • Applied after critical path is identified, resource availability is entered and the resource-limited schedule result is determined, the resulting schedule often has an altered critical path.
  • 50. 50 Resource Leveling Schedule network analysis technique in which scheduling decisions are driven by resource constraints and applied to a schedule model that has already been analyzed by the critical path method. Applying Leads and Lags Leads and lags are refinements applied during network analysis to develop a viable schedule. Scheduling Tool Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the inputs of activities, network diagrams, resources and activity durations. 6.5 Develop Schedule (Tools & Techniques)
  • 51. 51 Schedule Compression Shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule 0bjectives. Crashing: Approving overtime, bringing in additional resources, or paying to expedite delivery to activities on the critical path. Fast tracking: Doing activities in parallel that would normally be done in sequence. Fast tracking often results in rework and usually increases risk 6.5 Develop Schedule (Tools & Techniques)
  • 52. 52 Project Schedule  As a minimum, the project schedule includes a planned start date and planned finish date for each activity.  the project schedule may be presented in summary form, sometimes referred to as the master schedule, or presented in detail. • Milestone Charts these charts are similar to bar charts, but only identify the scheduled start or completion of major deliverables and key external interfaces. • Bar Charts These charts, with bars representing activities, show activity start and end dates as well as expected durations. • Project Schedule Network Diagrams These diagrams, with activity date information, usually show both the project network logic and the project’s critical path schedule activities. 6.5 Develop Schedule (Outputs)
  • 54. 54 Schedule Baseline Is the accepted and approved version of the project schedule. Schedule Data The schedule data for the project schedule includes at least the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints. Project Document Updates • Activity resource requirements • Activity attributes • Calendar • Risk register 6.5 Develop Schedule (Outputs)
  • 57. • Determining the current status of the project schedule • Influencing the factors that create schedule changes • Determining that the schedule has changed • Managing the actual changes when and as they occur 57 6.6 Control Schedule
  • 58. 6.6 Control Schedule (Inputs) 58 • Project Management Plan • Project Schedule • Work Performance information • Organizational Process Assets
  • 59. 6.6 Control Schedule (Tools & Techniques) 59 Performance Reviews Measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress. Variance analysis • Schedule performance measurements (SV, SPI) are used to assess the magnitude of variation to the original schedule baseline. • The total float variance is an essential planning component to evaluate project time performance.
  • 60. 6.6 Control Schedule (Tools & Techniques) 60 • Project management Software • Resource Leveling • What-if Scenario Analysis • Adjusting Leads and Lags • Schedule Compression • Scheduling Tool
  • 61. 6.6 Control Schedule (Outputs) 61 • Work Performance measurements • Organizational Process Assets Updates • Change Requests • Project management Plan Updates  Schedule baseline  Cost baseline • Project Document Updates  Project Schedule
  • 65. 1- Which of the following is the BEST to do to try to complete your project two months earlier? A ) Tell senior management that the project’s critical path does not allow the project to be finished earlier. B ) Tell your boss. C ) Meet with the team and look for options for crashing or fast tracking the critical path. D ) Work hard and see what the project status is next month. 65
  • 66. 1- Which of the following is the BEST to do to try to complete your project two months earlier? A ) Tell senior management that the project’s critical path does not allow the project to be finished earlier. B ) Tell your boss. C ) Meet with the team and look for options for crashing or fast tracking the critical path. D ) Work hard and see what the project status is next month. 66
  • 67. 2- A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected? A) Project duration B) Resource schedules C) Project scope management plan D) The latest start for the successor activity 67
  • 68. 2- A problem occurs on an activity with free float and the project manager has extended its duration. What is MOST likely to be affected? A) Project duration B) Resource schedules C) Project scope management plan D) The latest start for the successor activity 68
  • 69. 3- An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. what is the activity float? A) 10 B) 6 C) 3 D) 19 69
  • 70. 3- An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. what is the activity float? A) 10 B) 6 C) 3 D) 19 70
  • 71. 4- An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. what is the duration of this activity? A) 3 B) 6 C) 7 D) 10 71
  • 72. 4- An activity has an early start (ES) of day 3, a late start (LS) of day 13, an early finish (EF) of day 9 and a late finish (LF) of day 19. what is the duration of this activity? A) 3 B) 6 C) 7 D) 10 72
  • 73. 5- Based on the chart, a resource on your project from the consumer affairs department comes to you to tell you that they are taking a two-week leave due to a family emergency. They are assigned to activity F, which is currently in progress. This is a problem because activity F has: a) One week of float b) Two months of float c) One month of float d) No float Estimate (months) Preceding activity Activity Start 3 Start A 7 Start B 2 A C 4 A D 5 C, D E 9 B F 3 E, F G G end 73
  • 74. a) One week of float b) Two months of float c) One month of float d) No float Estimate (months) Preceding activity Activity Start 3 Start A 7 Start B 2 A C 4 A D 5 C, D E 9 B F 3 E, F G G end 74 5- Based on the chart, a resource on your project from the consumer affairs department comes to you to tell you that they are taking a two-week leave due to a family emergency. They are assigned to activity F, which is currently in progress. This is a problem because activity F has:
  • 75. a) Zero days b) Two days c) Four days d) One day 75 6- Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float?
  • 76. 6- Management wants the project completed in 40 days. The cost performance index (CPI) is 1.1, the project critical path duration is 38 days with a standard deviation of two days. What is the maximum project float? a) Zero days b) Two days c) Four days d) One day 76
  • 77. 7- Total float is the amount of time an activity can be delayed without delaying the : A ) project. B ) completion date required by the customer. C ) early start of its successor. D ) project completion date. 77
  • 78. 7- Total float is the amount of time an activity can be delayed without delaying the : A ) project. B ) completion date required by the customer. C ) early start of its successor. D ) project completion date. 78
  • 79. 8- Your boss tells you that one of your resources is needed on another project. All the activities in the chart are occurring at the same time. Assuming that all the resources working on which activity would you pick to move to the other project? A ) Activity D B ) Activity C C ) Activity H D ) Activity B Float (month) activity Start 2 B 1 C 0 D 1 F 0 G 4 H 0 I 3 E End 79
  • 80. A ) Activity D B ) Activity C C ) Activity H D ) Activity B Float (month) activity Start 2 B 1 C 0 D 1 F 0 G 4 H 0 I 3 E End 80 8- Your boss tells you that one of your resources is needed on another project. All the activities in the chart are occurring at the same time. Assuming that all the resources working on which activity would you pick to move to the other project?
  • 81. 9- Lag means: A ) The amount of time an activity can be delayed without delaying the project finish date. B ) The amount of time an activity can be delayed without delaying the early start date of its successor. C ) Waiting time D ) The product of a forward and backward pass 81
  • 82. 9- Lag means: A ) The amount of time an activity can be delayed without delaying the project finish date. B ) The amount of time an activity can be delayed without delaying the early start date of its successor. C ) Waiting time D ) The product of a forward and backward pass 82
  • 83. 10- Management has decided to “crash” a project to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to: A ) all activities B ) only those activities with the longest time durations C ) those activities on the critical path beginning with the lowest additional cost activities D ) those activities with the greatest degree of risk 83
  • 84. 10- Management has decided to “crash” a project to avoid penalty payments for late deliveries. Additional costs are expected. To crash the project, either overtime or additional resources should be assigned to: A ) all activities B ) only those activities with the longest time durations C ) those activities on the critical path beginning with the lowest additional cost activities D ) those activities with the greatest degree of risk 84
  • 85. 11- Using the chart, the resource for activity A is assigned to an additional, more important project. As a result the resource will not be able to devote as much time to your project. Activity A will now take 10 weeks. How does this affect the project? A) There are three critical paths B) The project will be delayed C) The project is riskier D) Activity D will be delayed Estimates (weeks) Preceding activity Activity 0 Start 3 Start C 6 C D 8 C A 4 D E 5 A,E B 3 E F 0 B,F end 85
  • 86. 11- Using the chart, the resource for activity A is assigned to an additional, more important project. As a result the resource will not be able to devote as much time to your project. Activity A will now take 10 weeks. How does this affect the project? A) There are three critical paths B) The project will be delayed C) The project is riskier D) Activity D will be delayed Estimates (weeks) Preceding activity Activity 0 Start 3 Start C 6 C D 8 C A 4 D E 5 A,E B 3 E F 0 B,F end 86
  • 87. 12- All of the following processes are included in project time management except: A ) define activities B ) estimate activity durations C ) control schedule D ) plan resources 87
  • 88. 12- All of the following processes are included in project time management except: A ) define activities B ) estimate activity durations C ) control schedule D ) plan resources 88
  • 89. 13- Any form of network analysis in which scheduling decisions, such as start and finish dates, are driven by resource management concern is called resource------------ A ) allocation B ) leveling C ) partitioning D ) quantification 89
  • 90. 13- Any form of network analysis in which scheduling decisions, such as start and finish dates, are driven by resource management concern is called resource------------ A ) allocation B ) leveling C ) partitioning D ) quantification 90
  • 91. 91 A B F G H J K C D E I 6 7 10 1 4 3 6 4 8 9 11 14 ) What is the duration of the near critical path ? A. 33 B. 44 C. 47 D. 43
  • 92. 92 A B F G H J K C D E I 6 7 10 1 4 3 6 4 8 9 11 14 ) What is the duration of the near critical path ? A. 33 B. 44 C. 47 D. 43