Project Cost Management
Unit 7
Project cost management
• Project cost management includes the processes involved in estimating,
budgeting, and controlling costs so that the project can be completed within
the approved budget
• It is primarily concerned with the cost of the resources needed to complete
schedule activities
• Should consider the information needs of the project stakeholders
• With proper planning, you can:
• Adjust the project plan to conform to the budget
• Track and manage cost once the project execution begins
• Compare actual cost to the original planned cost and analyze any variances between
the two
2
Knowledge Areas Initiating Planning Executing Monitoring & Controlling Closing
Develop project charter
Develop project
management plan
Direct and manage
project execution
Monitor and control project
work
Close
project or
phase
perform Integrated change
control
Collect requirements Varify Scope
define scope Control Scope
Create WBS
Define activities Control schedule
sequence Activity
Estimate acitivity
resources
Estimate activity
durations
Develop schedule
Estimate
costs Control costs
Determine
budget
Project Quality Management Plan quality
Perform quality
assurance Perform quality control
Develop human
resource plan Acquire project team
Develop project team
Manage project team
Identify stakeholders
Plan
communications Distribute information Report performance
Manage stakeholder
expectations Stakeholders
Plan risk
management Monitor and control risks
Identify risks
Perform qualitative
risk analysis
Perform
Quantitative risk
analysis
Project Management Process Groups
Project Integration Mangement
Project Scope Management
Project Time Management
Project Cost Management
Project Human Resource Management
Project Communications Management
Project Risk Management
Cost Management Plan
• The planning effort of the processes of the Cost
Management Plan is a part of the develop project
management plan
( Cost management plan can establish the following )
• Precision level - The prescribed precision for rounding data related to schedule
activity cost estimates
• Units of measure - Define units of measurement for each of the resources
• Organizational procedure links - The WBS component used for the project cost
accounting is called a control account (CA); each CA is assigned a code or account
number
• Control thresholds - Variance thresholds for cost at designated time points in the
project to indicate the agreed to amount allowable variance
4
• The planning effort of the processes of the Cost
Management Plan is a part of the develop project
management plan
( Cost management plan can establish the following )
• Reporting formats - The format for various cost reports
• Process descriptions - Descriptions of each of the three cost management processes
5
Cost Management Plan
6
7.1 Estimate Costs
The process of developing an approximation (estimate) of the cost of the
resources needed to complete each schedule activity
• Estimator must consider the possible causes of variation of cost
estimates, including risks
• Includes identifying and considering various costing alternatives
• Costs for schedule activities are estimated for all resources that will
be charged to the project
7
Scope Baseline
Project Schedule
The type and quantity of resources and the amount of time which those
resources are applied to complete the work of the project are major
factors in determining the project cost.
Human Resource Plan
Project staffing attributes, personnel rates, and related
rewards/recognition
7.1 Estimate Costs
(Inputs)
8
Risk Register
The risk register should be reviewed to consider risk mitigation costs.
Enterprise Environmental Factors
• Market conditions.
• Published commercial information.
Organizational Process Assets
• Cost estimating policies,
• Cost estimating templates,
• Historical information, and
• Lessons learned.
7.1 Estimate Costs
(Inputs)
9
• Expert judgment
• Analogous Estimating
• Parametric Estimating
• Bottom-Up Estimating
• Three-Point Estimates
• Reserve Analysis
• Cost of Quality (COQ)
• Project Management Estimating software
• Vendor Bid Analysis
7.1 Estimate Costs
(Tools & Techniques)
10
• Activity Cost Estimates
• Basis of Estimates
• Project Document Updates
7.1 Estimate Costs
(Outputs)
11
Inputs
• Enterprise
Environmental Factors
• Organizational Process
Assets
• Scope baseline
• Project schedule
• Human resource plan
• Risk register.
Tools & Techniques
• Analogous estimating
• Expert judgment
• Bottom-up estimating
• Parametric estimating
• Project Management
Software
• Vendor Bid Analysis
• Reserve Analysis
• Cost of Quality
• Three-point estimate
Outputs
• Activity Cost
estimates
• Basis of estimates
• Project document
updates
7.1 Estimate Costs
12
7.1 Estimate Costs
13
• Determine Budget is the process of aggregating the estimated costs
of individual activities or work packages to establish an authorized
cost baseline.
• This baseline includes all authorized budgets, but excludes
management reserves.
• Project budgets constitute the funds authorized to execute the
project.
• Project cost performance will be measured against the authorized
budget.
7.2 Determine Budget
14
Activity Cost Estimates (Inputs)
Basis of Estimates (Inputs)
Scope Baseline (Inputs)
Project schedule (Inputs)
Resource Calendars (Inputs)
Contracts (Inputs)
Organizational Process Assets (Inputs)
• Existing formal and informal cost budgeting-related policies,
procedures
• Cost budgeting tools,
7.2 Determine Budget
15
Cost Aggregation (Tool)
• Schedule activity cost estimates are aggregated by work packages
in accordance with the WBS
• Work package cost estimates are then aggregated for the higher
component levels of the WBS, such as the control account, and
ultimately for the entire project
Funding Limit Reconciliation (Tool)
• The expenditure of funds should be reconciled with any funding
limits on the commitment of funds for the project.
7.2 Determine Budget
16
1. Activity estimates
2. Work package estimates
3. Control Account estimates
4. Project estimates
5. Contingency reserves
6. Cost baseline
7. Management reserves
8. Cost budget
7.2 Determine Budget
17
Reserve Analysis (Tools)
Expert judgment (Tools)
Historical Relationships (Tools)
7.2 Determine Budget
18
Cost Performance Baseline (Output)
• The cost performance baseline is an authorized time-phased budget at
completion (BAC) used to measure, monitor, and control overall cost
performance on the project.
• It is developed as a summation of the approved budgets by time period
and is typically displayed in the form of an S-curve
Project Funding Requirements (Output)
• Total funding requirements and periodic funding requirements (e.g.,
quarterly, annually) are derived from the cost baseline.
• The cost baseline will include projected expenditures plus anticipated
liabilities.
• Funding often occurs in incremental amounts that are not continuous,
which appear as steps
7.2 Determine Budget
19
7.2 Determine Budget
20
Inputs
• Activity cost
estimates
• Basis of estimates
• Scope baseline
• Project schedule
• Resource calendars
• Contracts
• Organizational
process assets
Tools & Techniques
• Cost Aggregation
• Reserve Analysis
• Historical relationships
• Expert judgment
• Funding Limit
Reconciliation
Outputs
• Cost performance
baseline
• Project Funding
Requirements
• Project document updates
7.2 Determine Budget
21
7.2 Determine Budget
22
7.3 Control Costs
Control Costs is the process of monitoring the status of the
project to update the project budget and managing changes to
the cost baseline.
Project cost control includes:
• Influencing the factors that create changes to the authorized cost baseline,
• Ensuring that all change requests are acted on in a timely manner,
• Managing the actual changes when and as they occur,
• Ensuring that cost expenditures do not exceed the authorized funding, by
period and in total for the project,
• Monitoring work performance against funds expended,
23
Project Management Plan (Input)
The project management plan contains the following information that is used
to control cost:
• Cost Performance Baseline.
• Cost Management Plan.
Organizational Process Assets (Input)
• Existing formal and informal cost control-related policies, procedures,
• Cost control tools; and
• Monitoring and reporting methods to be used
Project Funding Requirements (Input)
Work Performance Information (Input)
7.3 Control Costs
24
• Earned Value Management (Tools)
• Forecasting (Tools)
• To-Complete Performance Index (TCPI) (Tools)
• Performance Reviews (Tools)
• Variance Analysis (Tools)
7.3 Control Costs
25
Inputs
• Project management
plan
• Project Funding
Requirements
• Work Performance
Information
• Organizational
process assets
Tools & Techniques
• Earned value management
• Performance measurement
Analysis
• Forecasting
• To-complete performance
index (TCPI)
• Performance Reviews
• Project Management
Software
• Variance analysis
Outputs
• Work Performance
Measurements
• Budget forecasts
• Change requests
• Recommended Corrective
action
• Organizational Process
Assets (Updates)
• Project management plan
(Updates)
• Project document (Updates)
7.3 Control Costs
26
7.3 Control Costs
27
Earned Value Management Analysis
Earned value technique (EVT)
Compares the cumulative value of the budgeted cost of work Earned to both
1. The budgeted cost of work scheduled (planned)
2. The actual cost or work performed (actual)
An important part of Cost Control is to determine the cause of a variance, the
magnitude of the variance, and to decide if the variance requires corrective
action
EVT uses the Cost Baseline contained in the project management plan to
assess project progress and the magnitude of any variations that occur
28
• Earned Value. (EV)
Value of work performed expressed in terms of the approved budget
• Planned Value. (PV)
Authorized budget assigned to the work to be accomplished for an activity or
work breakdown structure component.
• Actual Cost. (AC)
Total cost actually incurred and recorded in accomplishing work performed
for an activity or work breakdown structure component.
• Schedule Variance (SV)
is a measure of schedule performance on a project.
SV = ( EV – PV )
• Cost Variance (CV)
is a measure of cost performance on a project.
CV = ( EV – AC )
Earned Value Management Analysis
29
• Schedule performance index (SPI)
Is a measure of progress achieved compared to progress planned on a the
project.
SPI = ( EV / PV )
• Cost performance index (CPI)
Is a measure of the value of work completed compared to the actual cost on
the project.
CPI = ( EV / AC )
Earned Value Management Analysis
30
Example
We are about to produce 20 tables in 20 days cost is $20 for each.
How much BAC = ???
BAC = $20 * 20 tables = $400
Today is day 4 How much is the PV ?
PV = $20 x 4 tables = $80
At day 4 i earned only 3 tables, how much is the EV ?
EV = $20 x 3 tables = $60
AC = $90
SV = EV – PV = 60 – 80 = -$20
CV =EV – AC = 60 – 90 = -$30
SPI = EV / PV = 60 / 80 = 0.75
CPI = EV / AC = 60 / 90 = 0.666
Earned Value Management Analysis
31
Forecasting
Estimate At Completion (EAC) actual costs incurred for work completed, plus an
estimate to complete (ETC) the remaining work.
EAC = ( AC + ETC )
EAC forecast for ETC work performed at the budgeted rate
EAC = AC + ( BAC – EV )
= 90 + ( 400 – 60 ) = $430
EAC forecast for work performed at the percent CPI
EAC = BAC / CPI
= 400 / .66 = $606.6
EAC forecast for ETC work considering both SPI and CPI factors
EAC = AC + [ ( BAC – EV ) / ( CPI * SPI ) ]
= 90 + [ (400 – 60 ) / ( 0.75 * 0.66 ) ]
= $868.68
32
To-Complete Performance Index (TCPI)
The calculated projection of cost performance that must be
achieved on the remaining work to meet a specified management
goal, such as the BAC or the EAC.
Work Remaining / Funds Remaining
Work Remaining = ( BAC – EV )
Funds Remaining = ( BAC – AC ) Or ( EAC – AC )
TCPI = ( 400 – 60 ) / ( 400 – 90 )
= 1.096
OR
TCPI = (400 – 60 ) / ( 606 – 90 )
= 0.658
33
Project Performance Management
Time
Cost
BAC
EAC
Data date
PV
AC
EV
SV= EV - PV
CV= EV - AC
Exercise
.
34
35
Example - Wall Construction
Wall Construction
Time = 1 week per wall
Cost = $ 1,000 per wall, materials and labor
Total Schedule = 4 weeks
Total Cost = $ 4,000
Working days 5 day per week starting on
Sunday and finish on Thursday by 5 PM
Assume production is liner
36
Wall 1 100% = $ 1,000
Wall 2 80% = $ 800
Wall 3 0% = 0
Wall 4 0% = 0
PV = $ 1,800
How much work should
have been completed -
PV?
5 pm Wednesday, Week 2
PLANNED
37
Wall 1 100% = $ 1,000
Wall 2 50% = $ 500
Wall 3 10% = $100
Wall 4 0% = 0
Total = $1,600
5 pm Wednesday, Week 2
What is the budgeted
value of actual work -
EV?
10 %
50 %
EARNED
38
5 pm Wednesday, Week 2
Total Cost to date –
AC = $ 2,250
39
5 pm Wednesday, Week 2
Earned Value
PV $1,800
EV $1,600
AC $2,250
Schedule Variance = EV - PV
= $1,600 - $1,800
= ($200)
Cost Variance = EV - AC
= $1,600 - $2,250
= ($650)
40
5 pm Wednesday, Week 2
Performance Indices
PV $1,800
EV $1,600
AC $2,250
SPI = EV / PV
= $1,600 / $1,800
= .9
CPI = EV / AC
= $1,600 / $2,250
= .7
Questions
41
1- Half way through the executing processes of your
project, a team member alerts you to a potential cost
overrun for a specific deliverable. What do you do first?
A ) Determine the projected actual cost.
B ) Implement a change control process to track the
change
C ) Inform the customer.
D ) Determine the cause of the overage
42
1- Half way through the executing processes of your
project, a team member alerts you to a potential cost
overrun for a specific deliverable. What do you do first?
A ) Determine the projected actual cost.
B ) Implement a change control process to track the
change
C ) Inform the customer.
D ) Determine the cause of the overage
43
2 - Which type of costs is team training?
A ) Direct
B ) E V
C ) Indirect
D ) fixed
44
2 - Which type of costs is team training?
A ) Direct
B ) E V
C ) Indirect
D ) fixed
45
3- A project manager has completed a detailed
WBS and cost estimates for each work package.
To create a cost baseline from this data, the
project manager would :
A ) Use the highest level of the WBS to estimate
analogously
B ) Sum up the work package and risk contingency
reserve estimates.
C ) Roll up work package estimates into a project total
and add managements reserves.
D ) Gain expert opinions of the project costs.
46
3- A project manager has completed a detailed
WBS and cost estimates for each work package.
To create a cost baseline from this data, the
project manager would :
A ) Use the highest level of the WBS to estimate
analogously
B ) Sum up the work package and risk contingency
reserve estimates.
C ) Roll up work package estimates into a project total
and add managements reserves.
D ) Gain expert opinions of the project costs.
47
4- You are having difficulty estimating the cost of your
project. Which of the following BEST describes the
most probable cause of your difficulty?
A ) Inadequate scope definition
B ) Unavailability of desired resources
C ) Lack of historical records from previous
projects
D ) Lack of company processes
48
4- You are having difficulty estimating the cost of your
project. Whish of the following BEST describes the most
probable cause of your difficulty?
A ) Inadequate scope definition
B ) Unavailability of desired resources
C ) Lack of historical records from previous
projects
D ) Lack of company processes
49
5- Which of the following represents the value
of work we have actually completed?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
50
5- Which of the following represents the value
of work we have actually completed?
A ) Earned value
B ) Planned value
C ) Actual cost
D ) Estimate to complete
51
6- While completing your project, you realized that you
need to decrease the project costs. After researching
your options, you came up with the following choices.
Which choice would DECREASE project costs?
A ) Change to component A from component B. component A
costs more to purchase, but has a lower life cycle cost than B.
B ) Change activity A to be completed by resource B instead of
resource c. resource B is more experienced worker.
C ) Move activities B and H to occur concurrently, and accept a
30 percent increase in the risk that five more resources will be
needed later.
D ) Remove a test from the project management plan.
52
6- While completing your project, you realized that you
need to decrease the project costs. After researching
your options, you came up with the following choices.
Which choice would DECREASE project costs?
A ) Change to component A from component B. component A
costs more to purchase, but has a lower life cycle cost than B.
B ) Change activity A to be completed by resource B instead of
resource c. resource B is more experienced worker.
C ) Move activities B and H to occur concurrently, and accept a
30 percent increase in the risk that five more resources will be
needed later.
D ) Remove a test from the project management plan.
53
7- If earned value (EV) is U.S.$300000, actual
cost (AC) is U.S.$350000, and planned value (PV)
is U.S. $375000, what does the schedule
performance index (SPI) indicate?
A ) You are progressing at 86% of the rate originally
planned.
B ) You are progressing at 125% of the rate originally
planned.
C ) You are progressing at 116% of the rate originally
planned.
D ) You are progressing at 80% of the rate originally
planned. 54
7- If earned value (EV) is U.S.$300000, actual
cost (AC) is U.S.$350000, and planned value (PV)
is U.S. $375000, what does the schedule
performance index (SPI) indicate?
A ) You are progressing at 86% of the rate originally
planned.
B ) You are progressing at 125% of the rate originally
planned.
C ) You are progressing at 116% of the rate originally
planned.
D ) You are progressing at 80% of the rate originally
planned. 55
8- The formula, EAC = BAC/CPI, assumes that:
A ) All subsequent work will be completed at the
planned expenditures.
B ) All subsequent work will be completed at the
planned expenditures, excluding the work packages
currently under way
C ) All subsequent work will be completed based upon
the cost performance to-date
D ) The cost performance cannot change during the
project
56
8- The formula, EAC = BAC/CPI, assumes that:
A ) All subsequent work will be completed at the
planned expenditures.
B ) All subsequent work will be completed at the
planned expenditures, excluding the work packages
currently under way
C ) All subsequent work will be completed based upon
the cost performance to-date
D ) The cost performance cannot change during the
project
57
9- Feasibility study answers the question “can
we do it?” cost benefit analysis answer the
question---------
A ) Should we do it?
B ) Are the safety risks acceptable?
C ) Is it beneficial to have a high level sponsor?
D ) Does the technology exist?
58
9- Feasibility study answers the question “can
we do it?” cost benefit analysis answer the
question---------
A ) Should we do it?
B ) Are the safety risks acceptable?
C ) Is it beneficial to have a high level sponsor?
D ) Does the technology exist?
59
10- What tool must project managers rely upon
to accurately identify the costs associated with
the project?
A ) A bill of materials
B ) A Gantt chart
C ) A precedence diagram network
D ) A work breakdown structure
60
10- What tool must project managers rely upon
to accurately identify the costs associated with
the project?
A ) A bill of materials
B ) A Gantt chart
C ) A precedence diagram network
D ) A work breakdown structure
61
Thank you
.
62

More Related Content

PPT
PMP Module 4 - Cost
PPTX
PMP-Cost Management area
PPTX
Project Cost Management - PMBOK6
PDF
Project Cost Management for IEM talk on 13 January 2018.
PPTX
7.2 Estimate Cost
PPTX
Presintation on Project constraint
PDF
Topic 12 - Project Cost Management.pdf
PPTX
PMP Module 4 - Cost
PMP-Cost Management area
Project Cost Management - PMBOK6
Project Cost Management for IEM talk on 13 January 2018.
7.2 Estimate Cost
Presintation on Project constraint
Topic 12 - Project Cost Management.pdf

Similar to 4- Project Cost Management.ppt (20)

PDF
PDF
A brief on project cost management
PPTX
Projectcontrol
PPTX
Lecture 8 (software Metrics) Unit 3.pptx
PPTX
cost Management V4
PPTX
Session 21 4th edition PMP
PPTX
7.4 Control Costs
PPTX
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
PPSX
Projectmanagement 130721095616-phpapp01
PPTX
ITPM ch7 project cost management notes>?
PDF
07 project cost management
PPTX
Chapter 3 Project Cost Control and Monitoring.pptx
PPT
7 cost managmenet
PPTX
7.3 Determine Budget
PPT
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
PPTX
Lecture 2.pptx
PPSX
Projectmanagement 130721095616-phpapp01
PPSX
Projectmanagement 130721095616-phpapp01
PPTX
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
PPTX
Cost Management PMBOK
A brief on project cost management
Projectcontrol
Lecture 8 (software Metrics) Unit 3.pptx
cost Management V4
Session 21 4th edition PMP
7.4 Control Costs
Online PMP Training Material for PMP Exam - Time Management Knowledge Area
Projectmanagement 130721095616-phpapp01
ITPM ch7 project cost management notes>?
07 project cost management
Chapter 3 Project Cost Control and Monitoring.pptx
7 cost managmenet
7.3 Determine Budget
FINAL PROJECT COST MANAGEMENT STUDENT COPY.ppt
Lecture 2.pptx
Projectmanagement 130721095616-phpapp01
Projectmanagement 130721095616-phpapp01
Online PMP Training Material for PMP Exam - Cost Management Knowledge Area
Cost Management PMBOK
Ad

Recently uploaded (20)

PPTX
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
PPT
Project quality management in manufacturing
PDF
composite construction of structures.pdf
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
Structs to JSON How Go Powers REST APIs.pdf
PPTX
web development for engineering and engineering
PPTX
additive manufacturing of ss316l using mig welding
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
MCN 401 KTU-2019-PPE KITS-MODULE 2.pptx
OOP with Java - Java Introduction (Basics)
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
Project quality management in manufacturing
composite construction of structures.pdf
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Structs to JSON How Go Powers REST APIs.pdf
web development for engineering and engineering
additive manufacturing of ss316l using mig welding
Operating System & Kernel Study Guide-1 - converted.pdf
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
Arduino robotics embedded978-1-4302-3184-4.pdf
bas. eng. economics group 4 presentation 1.pptx
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Internet of Things (IOT) - A guide to understanding
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Lesson 3_Tessellation.pptx finite Mathematics
Ad

4- Project Cost Management.ppt

  • 2. Project cost management • Project cost management includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget • It is primarily concerned with the cost of the resources needed to complete schedule activities • Should consider the information needs of the project stakeholders • With proper planning, you can: • Adjust the project plan to conform to the budget • Track and manage cost once the project execution begins • Compare actual cost to the original planned cost and analyze any variances between the two 2
  • 3. Knowledge Areas Initiating Planning Executing Monitoring & Controlling Closing Develop project charter Develop project management plan Direct and manage project execution Monitor and control project work Close project or phase perform Integrated change control Collect requirements Varify Scope define scope Control Scope Create WBS Define activities Control schedule sequence Activity Estimate acitivity resources Estimate activity durations Develop schedule Estimate costs Control costs Determine budget Project Quality Management Plan quality Perform quality assurance Perform quality control Develop human resource plan Acquire project team Develop project team Manage project team Identify stakeholders Plan communications Distribute information Report performance Manage stakeholder expectations Stakeholders Plan risk management Monitor and control risks Identify risks Perform qualitative risk analysis Perform Quantitative risk analysis Project Management Process Groups Project Integration Mangement Project Scope Management Project Time Management Project Cost Management Project Human Resource Management Project Communications Management Project Risk Management
  • 4. Cost Management Plan • The planning effort of the processes of the Cost Management Plan is a part of the develop project management plan ( Cost management plan can establish the following ) • Precision level - The prescribed precision for rounding data related to schedule activity cost estimates • Units of measure - Define units of measurement for each of the resources • Organizational procedure links - The WBS component used for the project cost accounting is called a control account (CA); each CA is assigned a code or account number • Control thresholds - Variance thresholds for cost at designated time points in the project to indicate the agreed to amount allowable variance 4
  • 5. • The planning effort of the processes of the Cost Management Plan is a part of the develop project management plan ( Cost management plan can establish the following ) • Reporting formats - The format for various cost reports • Process descriptions - Descriptions of each of the three cost management processes 5 Cost Management Plan
  • 6. 6 7.1 Estimate Costs The process of developing an approximation (estimate) of the cost of the resources needed to complete each schedule activity • Estimator must consider the possible causes of variation of cost estimates, including risks • Includes identifying and considering various costing alternatives • Costs for schedule activities are estimated for all resources that will be charged to the project
  • 7. 7 Scope Baseline Project Schedule The type and quantity of resources and the amount of time which those resources are applied to complete the work of the project are major factors in determining the project cost. Human Resource Plan Project staffing attributes, personnel rates, and related rewards/recognition 7.1 Estimate Costs (Inputs)
  • 8. 8 Risk Register The risk register should be reviewed to consider risk mitigation costs. Enterprise Environmental Factors • Market conditions. • Published commercial information. Organizational Process Assets • Cost estimating policies, • Cost estimating templates, • Historical information, and • Lessons learned. 7.1 Estimate Costs (Inputs)
  • 9. 9 • Expert judgment • Analogous Estimating • Parametric Estimating • Bottom-Up Estimating • Three-Point Estimates • Reserve Analysis • Cost of Quality (COQ) • Project Management Estimating software • Vendor Bid Analysis 7.1 Estimate Costs (Tools & Techniques)
  • 10. 10 • Activity Cost Estimates • Basis of Estimates • Project Document Updates 7.1 Estimate Costs (Outputs)
  • 11. 11 Inputs • Enterprise Environmental Factors • Organizational Process Assets • Scope baseline • Project schedule • Human resource plan • Risk register. Tools & Techniques • Analogous estimating • Expert judgment • Bottom-up estimating • Parametric estimating • Project Management Software • Vendor Bid Analysis • Reserve Analysis • Cost of Quality • Three-point estimate Outputs • Activity Cost estimates • Basis of estimates • Project document updates 7.1 Estimate Costs
  • 13. 13 • Determine Budget is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline. • This baseline includes all authorized budgets, but excludes management reserves. • Project budgets constitute the funds authorized to execute the project. • Project cost performance will be measured against the authorized budget. 7.2 Determine Budget
  • 14. 14 Activity Cost Estimates (Inputs) Basis of Estimates (Inputs) Scope Baseline (Inputs) Project schedule (Inputs) Resource Calendars (Inputs) Contracts (Inputs) Organizational Process Assets (Inputs) • Existing formal and informal cost budgeting-related policies, procedures • Cost budgeting tools, 7.2 Determine Budget
  • 15. 15 Cost Aggregation (Tool) • Schedule activity cost estimates are aggregated by work packages in accordance with the WBS • Work package cost estimates are then aggregated for the higher component levels of the WBS, such as the control account, and ultimately for the entire project Funding Limit Reconciliation (Tool) • The expenditure of funds should be reconciled with any funding limits on the commitment of funds for the project. 7.2 Determine Budget
  • 16. 16 1. Activity estimates 2. Work package estimates 3. Control Account estimates 4. Project estimates 5. Contingency reserves 6. Cost baseline 7. Management reserves 8. Cost budget 7.2 Determine Budget
  • 17. 17 Reserve Analysis (Tools) Expert judgment (Tools) Historical Relationships (Tools) 7.2 Determine Budget
  • 18. 18 Cost Performance Baseline (Output) • The cost performance baseline is an authorized time-phased budget at completion (BAC) used to measure, monitor, and control overall cost performance on the project. • It is developed as a summation of the approved budgets by time period and is typically displayed in the form of an S-curve Project Funding Requirements (Output) • Total funding requirements and periodic funding requirements (e.g., quarterly, annually) are derived from the cost baseline. • The cost baseline will include projected expenditures plus anticipated liabilities. • Funding often occurs in incremental amounts that are not continuous, which appear as steps 7.2 Determine Budget
  • 20. 20 Inputs • Activity cost estimates • Basis of estimates • Scope baseline • Project schedule • Resource calendars • Contracts • Organizational process assets Tools & Techniques • Cost Aggregation • Reserve Analysis • Historical relationships • Expert judgment • Funding Limit Reconciliation Outputs • Cost performance baseline • Project Funding Requirements • Project document updates 7.2 Determine Budget
  • 22. 22 7.3 Control Costs Control Costs is the process of monitoring the status of the project to update the project budget and managing changes to the cost baseline. Project cost control includes: • Influencing the factors that create changes to the authorized cost baseline, • Ensuring that all change requests are acted on in a timely manner, • Managing the actual changes when and as they occur, • Ensuring that cost expenditures do not exceed the authorized funding, by period and in total for the project, • Monitoring work performance against funds expended,
  • 23. 23 Project Management Plan (Input) The project management plan contains the following information that is used to control cost: • Cost Performance Baseline. • Cost Management Plan. Organizational Process Assets (Input) • Existing formal and informal cost control-related policies, procedures, • Cost control tools; and • Monitoring and reporting methods to be used Project Funding Requirements (Input) Work Performance Information (Input) 7.3 Control Costs
  • 24. 24 • Earned Value Management (Tools) • Forecasting (Tools) • To-Complete Performance Index (TCPI) (Tools) • Performance Reviews (Tools) • Variance Analysis (Tools) 7.3 Control Costs
  • 25. 25 Inputs • Project management plan • Project Funding Requirements • Work Performance Information • Organizational process assets Tools & Techniques • Earned value management • Performance measurement Analysis • Forecasting • To-complete performance index (TCPI) • Performance Reviews • Project Management Software • Variance analysis Outputs • Work Performance Measurements • Budget forecasts • Change requests • Recommended Corrective action • Organizational Process Assets (Updates) • Project management plan (Updates) • Project document (Updates) 7.3 Control Costs
  • 27. 27 Earned Value Management Analysis Earned value technique (EVT) Compares the cumulative value of the budgeted cost of work Earned to both 1. The budgeted cost of work scheduled (planned) 2. The actual cost or work performed (actual) An important part of Cost Control is to determine the cause of a variance, the magnitude of the variance, and to decide if the variance requires corrective action EVT uses the Cost Baseline contained in the project management plan to assess project progress and the magnitude of any variations that occur
  • 28. 28 • Earned Value. (EV) Value of work performed expressed in terms of the approved budget • Planned Value. (PV) Authorized budget assigned to the work to be accomplished for an activity or work breakdown structure component. • Actual Cost. (AC) Total cost actually incurred and recorded in accomplishing work performed for an activity or work breakdown structure component. • Schedule Variance (SV) is a measure of schedule performance on a project. SV = ( EV – PV ) • Cost Variance (CV) is a measure of cost performance on a project. CV = ( EV – AC ) Earned Value Management Analysis
  • 29. 29 • Schedule performance index (SPI) Is a measure of progress achieved compared to progress planned on a the project. SPI = ( EV / PV ) • Cost performance index (CPI) Is a measure of the value of work completed compared to the actual cost on the project. CPI = ( EV / AC ) Earned Value Management Analysis
  • 30. 30 Example We are about to produce 20 tables in 20 days cost is $20 for each. How much BAC = ??? BAC = $20 * 20 tables = $400 Today is day 4 How much is the PV ? PV = $20 x 4 tables = $80 At day 4 i earned only 3 tables, how much is the EV ? EV = $20 x 3 tables = $60 AC = $90 SV = EV – PV = 60 – 80 = -$20 CV =EV – AC = 60 – 90 = -$30 SPI = EV / PV = 60 / 80 = 0.75 CPI = EV / AC = 60 / 90 = 0.666 Earned Value Management Analysis
  • 31. 31 Forecasting Estimate At Completion (EAC) actual costs incurred for work completed, plus an estimate to complete (ETC) the remaining work. EAC = ( AC + ETC ) EAC forecast for ETC work performed at the budgeted rate EAC = AC + ( BAC – EV ) = 90 + ( 400 – 60 ) = $430 EAC forecast for work performed at the percent CPI EAC = BAC / CPI = 400 / .66 = $606.6 EAC forecast for ETC work considering both SPI and CPI factors EAC = AC + [ ( BAC – EV ) / ( CPI * SPI ) ] = 90 + [ (400 – 60 ) / ( 0.75 * 0.66 ) ] = $868.68
  • 32. 32 To-Complete Performance Index (TCPI) The calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC. Work Remaining / Funds Remaining Work Remaining = ( BAC – EV ) Funds Remaining = ( BAC – AC ) Or ( EAC – AC ) TCPI = ( 400 – 60 ) / ( 400 – 90 ) = 1.096 OR TCPI = (400 – 60 ) / ( 606 – 90 ) = 0.658
  • 33. 33 Project Performance Management Time Cost BAC EAC Data date PV AC EV SV= EV - PV CV= EV - AC
  • 35. 35 Example - Wall Construction Wall Construction Time = 1 week per wall Cost = $ 1,000 per wall, materials and labor Total Schedule = 4 weeks Total Cost = $ 4,000 Working days 5 day per week starting on Sunday and finish on Thursday by 5 PM Assume production is liner
  • 36. 36 Wall 1 100% = $ 1,000 Wall 2 80% = $ 800 Wall 3 0% = 0 Wall 4 0% = 0 PV = $ 1,800 How much work should have been completed - PV? 5 pm Wednesday, Week 2 PLANNED
  • 37. 37 Wall 1 100% = $ 1,000 Wall 2 50% = $ 500 Wall 3 10% = $100 Wall 4 0% = 0 Total = $1,600 5 pm Wednesday, Week 2 What is the budgeted value of actual work - EV? 10 % 50 % EARNED
  • 38. 38 5 pm Wednesday, Week 2 Total Cost to date – AC = $ 2,250
  • 39. 39 5 pm Wednesday, Week 2 Earned Value PV $1,800 EV $1,600 AC $2,250 Schedule Variance = EV - PV = $1,600 - $1,800 = ($200) Cost Variance = EV - AC = $1,600 - $2,250 = ($650)
  • 40. 40 5 pm Wednesday, Week 2 Performance Indices PV $1,800 EV $1,600 AC $2,250 SPI = EV / PV = $1,600 / $1,800 = .9 CPI = EV / AC = $1,600 / $2,250 = .7
  • 42. 1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first? A ) Determine the projected actual cost. B ) Implement a change control process to track the change C ) Inform the customer. D ) Determine the cause of the overage 42
  • 43. 1- Half way through the executing processes of your project, a team member alerts you to a potential cost overrun for a specific deliverable. What do you do first? A ) Determine the projected actual cost. B ) Implement a change control process to track the change C ) Inform the customer. D ) Determine the cause of the overage 43
  • 44. 2 - Which type of costs is team training? A ) Direct B ) E V C ) Indirect D ) fixed 44
  • 45. 2 - Which type of costs is team training? A ) Direct B ) E V C ) Indirect D ) fixed 45
  • 46. 3- A project manager has completed a detailed WBS and cost estimates for each work package. To create a cost baseline from this data, the project manager would : A ) Use the highest level of the WBS to estimate analogously B ) Sum up the work package and risk contingency reserve estimates. C ) Roll up work package estimates into a project total and add managements reserves. D ) Gain expert opinions of the project costs. 46
  • 47. 3- A project manager has completed a detailed WBS and cost estimates for each work package. To create a cost baseline from this data, the project manager would : A ) Use the highest level of the WBS to estimate analogously B ) Sum up the work package and risk contingency reserve estimates. C ) Roll up work package estimates into a project total and add managements reserves. D ) Gain expert opinions of the project costs. 47
  • 48. 4- You are having difficulty estimating the cost of your project. Which of the following BEST describes the most probable cause of your difficulty? A ) Inadequate scope definition B ) Unavailability of desired resources C ) Lack of historical records from previous projects D ) Lack of company processes 48
  • 49. 4- You are having difficulty estimating the cost of your project. Whish of the following BEST describes the most probable cause of your difficulty? A ) Inadequate scope definition B ) Unavailability of desired resources C ) Lack of historical records from previous projects D ) Lack of company processes 49
  • 50. 5- Which of the following represents the value of work we have actually completed? A ) Earned value B ) Planned value C ) Actual cost D ) Estimate to complete 50
  • 51. 5- Which of the following represents the value of work we have actually completed? A ) Earned value B ) Planned value C ) Actual cost D ) Estimate to complete 51
  • 52. 6- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs? A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B. B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker. C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later. D ) Remove a test from the project management plan. 52
  • 53. 6- While completing your project, you realized that you need to decrease the project costs. After researching your options, you came up with the following choices. Which choice would DECREASE project costs? A ) Change to component A from component B. component A costs more to purchase, but has a lower life cycle cost than B. B ) Change activity A to be completed by resource B instead of resource c. resource B is more experienced worker. C ) Move activities B and H to occur concurrently, and accept a 30 percent increase in the risk that five more resources will be needed later. D ) Remove a test from the project management plan. 53
  • 54. 7- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate? A ) You are progressing at 86% of the rate originally planned. B ) You are progressing at 125% of the rate originally planned. C ) You are progressing at 116% of the rate originally planned. D ) You are progressing at 80% of the rate originally planned. 54
  • 55. 7- If earned value (EV) is U.S.$300000, actual cost (AC) is U.S.$350000, and planned value (PV) is U.S. $375000, what does the schedule performance index (SPI) indicate? A ) You are progressing at 86% of the rate originally planned. B ) You are progressing at 125% of the rate originally planned. C ) You are progressing at 116% of the rate originally planned. D ) You are progressing at 80% of the rate originally planned. 55
  • 56. 8- The formula, EAC = BAC/CPI, assumes that: A ) All subsequent work will be completed at the planned expenditures. B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way C ) All subsequent work will be completed based upon the cost performance to-date D ) The cost performance cannot change during the project 56
  • 57. 8- The formula, EAC = BAC/CPI, assumes that: A ) All subsequent work will be completed at the planned expenditures. B ) All subsequent work will be completed at the planned expenditures, excluding the work packages currently under way C ) All subsequent work will be completed based upon the cost performance to-date D ) The cost performance cannot change during the project 57
  • 58. 9- Feasibility study answers the question “can we do it?” cost benefit analysis answer the question--------- A ) Should we do it? B ) Are the safety risks acceptable? C ) Is it beneficial to have a high level sponsor? D ) Does the technology exist? 58
  • 59. 9- Feasibility study answers the question “can we do it?” cost benefit analysis answer the question--------- A ) Should we do it? B ) Are the safety risks acceptable? C ) Is it beneficial to have a high level sponsor? D ) Does the technology exist? 59
  • 60. 10- What tool must project managers rely upon to accurately identify the costs associated with the project? A ) A bill of materials B ) A Gantt chart C ) A precedence diagram network D ) A work breakdown structure 60
  • 61. 10- What tool must project managers rely upon to accurately identify the costs associated with the project? A ) A bill of materials B ) A Gantt chart C ) A precedence diagram network D ) A work breakdown structure 61