A Guide to Create a
Quality Project
Schedule
Successful projects start with a good quality
project schedule. Creating a schedule is one of
the first tasks you should do when given a project
to manage. There is often a temptation to get on
with the work and worry about the schedule later,
but this is a mistake. You will be left exposed and
if challenged, will have no evidence of whether
your project is on time or running late.
This article looks at a simple, practical approach
to creating project schedules. After reading this
article, you will have a sound approach to creating
schedules that you can use for future projects.
1. Plan with the Team
Team planning is more effective than planning on your
own, and ensures everyone has a stake in the schedule
and ownership of the outcome. The project team must
account for all the phases, milestones and tasks so the
project can reach a successful conclusion.
I like to create a basic high-level schedule to kick things
off. Even if it's wrong, it helps the session start moving.
It’s better than sitting in a meeting with your team staring
at a blank sheet of paper.
2. Cover the Project Scope
Use the scope statement from your Charter to make sure
you include everything the customer expects you to
deliver. List all the activities needed to deliver the scope.
Look at the order of activities; often it is best to start with
the most difficult tasks. The type of project may dictate the
order, clearly, you can't build a house until the foundations
have been laid. Think about the work you can do in
parallel and what is dependent on other activities being
finished first. Make sure you include the dependencies in
your schedule.
3. Group the Tasks into Phases
Projects typically go through phases, starting with an idea all the way to
launch and rollout. You should arrange your project schedule in these
phases. This is an example I’ve used for software development
projects:
1. Ideas (the first concept, creating the team and everything needed to
get the project started).
2. Feasibility (often development of a prototype, model or proof of
concept).
3. Build (doing the work to create the product or service).
4. Launch (preparing to go-live with the product or service, often as a
pilot first).
5. Rollout (delivering the product or service to the wider audience
following updates from the pilot).
6. Closure (finishing the project, disbanding the project team and tying up
any loose ends).
4. Create Milestones
Adding milestones to your schedule helps the
project team stay focussed and motivated.
Milestones are the end of certain phases, the
point where work needs completing, or sign-off
obtained for work carried out. These milestones
are how the team sees and measures their
progress. Poring over hundreds of tasks each
week is daunting. The milestones help put the
entire project into perspective and keep everyone
on track to a successful finish.
5. Make Time for Time
When adding time estimates (hours or days) against tasks
and activities it’s best to use people's experience. Better
still if you can use a database of production rates to give
more accurate estimates.
Estimating as a team is effective, because it gives the
opportunity for team members to challenge estimates. If
an estimate is given by one team member, another may
challenge it because he or she has direct experience of
similar work.
Make sure everyone agrees with the estimates and signs
off during the session. This way there are no arguments
later.
6. Plan Your People
Now you have your schedule, it's time to add your people, either
existing or new team members. Try to match your people's skill-set
to the work. Have they done similar work in the past? Do they have a
skill that would be useful on a particular aspect of the project? Have
they shown an interest in working on a certain area?
A common mistake when new to project scheduling is to use people
for 100% of their time. It’s best to assume people will only be
productive on the project for 80% of their time. Administration, filling
out time sheets, team meetings, support and other unrelated tasks
take up the remaining 20%.
Once you have assigned people to the tasks in your schedule,
review it for conflicts. Have you got areas where people are working
on two work streams simultaneously? Is the work allocated evenly
across the team? Be careful not to overload your key people, while
under-utilising others.
Finally…
Check your schedule thoroughly to make sure there are no
errors. Here are a few common problems found in
schedules:
•
•
•
•
•
•
•
•
•

Not including public holidays in the schedule.
Not including team member's holidays in the schedule.
Missing links to dependencies.
Creating one continuous block of work with no milestone
deliverables along the way.
Using poor task estimates or guesses instead of people's
experience or production rates.
Starting with an end date and making the schedule fit it.
Assigning people for 100% of their time.
Dividing tasks between more than one person.
Not building in contingency time in the event things go
wrong.
Remember to regularly update the schedule with
your team to check progress and make
adjustments where necessary. A daily 15 minute
‘Scrum’ style meeting or phone call is useful,
where each team member says what he or she
did yesterday; what they intend to do today and
highlights any blockers holding them back. It is
your responsibility as project manager to help
remove any blockers and smooth the path
ahead.
In Summary…
1. Define the tasks and activities using your scope
statement.
2. Sequence the activities identifying any
dependencies.
3. Group the tasks and activities into phases.
4. Create milestones.
5. Create time estimates for the tasks and
activities.
6. Assign people to the tasks and activities.
7. Review your schedule for errors and correct.
8. Hold daily progress meetings with your team
and adjust the schedule.
A quality project schedule is the basis of project
success, so spend time with your team creating a
schedule that is both meaningful and realistic.
Source
http://certifications-review.blogspot.in/2013/11/aguide-to-creating-quality-project.html
Looking for more details or Planning to get PMP
certified, mail your details on
courses@wiziq.com or call +91-0172 5032409
to get PMP Certification training and gain 35 contact
hours..!!
A guide to create a quality project schedule

More Related Content

PPTX
PROJECT SCHEDULE
PPTX
Seven Basic Steps to Build Realistic Schedule in Project 2010
PDF
Meeting Project Schedule Compliance Standards
PPT
09 lecture project scheduling 1
PPTX
Project Scheduling
PDF
construction project planing
PPT
Project Management focused on Scheduling of a Project
PPTX
Project planning and scheduling techniques
PROJECT SCHEDULE
Seven Basic Steps to Build Realistic Schedule in Project 2010
Meeting Project Schedule Compliance Standards
09 lecture project scheduling 1
Project Scheduling
construction project planing
Project Management focused on Scheduling of a Project
Project planning and scheduling techniques

What's hot (20)

PPTX
Building a-project-schedule
PPT
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
PPTX
Project Scheduling
PPT
Fundamentals of scheduling
PPTX
PM scheduling techniques
PPTX
Project scheduling
PDF
PPT
PROJECT SCHEDULING
PPSX
Project Management 4 Schedule Management
PDF
Project planning and scheduling
PPTX
00 Introduction of project scheduling
PPT
Chap 6 Developing A Project Plan
PPTX
Wbs & Bar chart for Civil engg
PPTX
Pert, cpm & gert
DOCX
Project scheduling
PPTX
Project scheduling and tracking
PPT
Pert
PPTX
4 an activity analysis of project scheduling problem a case study 1
PPTX
Project scheduling
PPTX
Software engineering 11 project scheduling
Building a-project-schedule
PLANNING AND SCHEDULING DONE BY A CIVIL ENGINEERS
Project Scheduling
Fundamentals of scheduling
PM scheduling techniques
Project scheduling
PROJECT SCHEDULING
Project Management 4 Schedule Management
Project planning and scheduling
00 Introduction of project scheduling
Chap 6 Developing A Project Plan
Wbs & Bar chart for Civil engg
Pert, cpm & gert
Project scheduling
Project scheduling and tracking
Pert
4 an activity analysis of project scheduling problem a case study 1
Project scheduling
Software engineering 11 project scheduling
Ad

Similar to A guide to create a quality project schedule (20)

PDF
A guide to creating a quality project schedule it-toolkits
PDF
[Guide] How to create a realistic project schedule
PDF
Mastering Project Time Management: The 5-Step Guide and Tips
PDF
Project Management: Your Guide in Acing the Project
PDF
Top 10 Reasons- Why You Need Effective Resource Allocation
PDF
Project Timeline: How To Create One In 8 Simple Steps
PDF
Managing your projects effectively in a shared resource environment
PPTX
The industry experts' top 11 time management tThe Industry Experts' Top 11 Ti...
PDF
Article 2
PDF
Article 2
PPT
Strategies to Manage Tasks & Time During Long-Term Projects
PDF
Project Workflow Management Ultimate Guidee (1).pdf
PDF
Project Workflow Management Ultimate Guide
PDF
Time Estimation: Expert Tips & Proven Project Techniques
PPT
Nine keys to successful delegation in project management
PDF
Advice & Tips To Improve Your Skills
PDF
2Project_management. Ghjjkkutfghuuijkpdf
PPTX
PDF
Top 10 project management tips
PDF
how-to-conduct-a-successful-project-debrief.pdf
A guide to creating a quality project schedule it-toolkits
[Guide] How to create a realistic project schedule
Mastering Project Time Management: The 5-Step Guide and Tips
Project Management: Your Guide in Acing the Project
Top 10 Reasons- Why You Need Effective Resource Allocation
Project Timeline: How To Create One In 8 Simple Steps
Managing your projects effectively in a shared resource environment
The industry experts' top 11 time management tThe Industry Experts' Top 11 Ti...
Article 2
Article 2
Strategies to Manage Tasks & Time During Long-Term Projects
Project Workflow Management Ultimate Guidee (1).pdf
Project Workflow Management Ultimate Guide
Time Estimation: Expert Tips & Proven Project Techniques
Nine keys to successful delegation in project management
Advice & Tips To Improve Your Skills
2Project_management. Ghjjkkutfghuuijkpdf
Top 10 project management tips
how-to-conduct-a-successful-project-debrief.pdf
Ad

More from NirtiSingla (10)

PPT
Boost your bottom line with scalable it methodologies
PPT
Swot analysis in project management
PPT
Leading meetings with multicultural audiences
PPT
Successful projects are led not managed
PPT
Top five communication skills for project managers
PPT
10 more quotes that make you a better project manager
PPT
Creating a work breakdown structure with microsoft project
PPT
Five essential elements for successful software development
PPT
How to become an accidental project manager
PPT
Project management- A Marathon not a Sprint
Boost your bottom line with scalable it methodologies
Swot analysis in project management
Leading meetings with multicultural audiences
Successful projects are led not managed
Top five communication skills for project managers
10 more quotes that make you a better project manager
Creating a work breakdown structure with microsoft project
Five essential elements for successful software development
How to become an accidental project manager
Project management- A Marathon not a Sprint

A guide to create a quality project schedule

  • 1. A Guide to Create a Quality Project Schedule
  • 2. Successful projects start with a good quality project schedule. Creating a schedule is one of the first tasks you should do when given a project to manage. There is often a temptation to get on with the work and worry about the schedule later, but this is a mistake. You will be left exposed and if challenged, will have no evidence of whether your project is on time or running late. This article looks at a simple, practical approach to creating project schedules. After reading this article, you will have a sound approach to creating schedules that you can use for future projects.
  • 3. 1. Plan with the Team Team planning is more effective than planning on your own, and ensures everyone has a stake in the schedule and ownership of the outcome. The project team must account for all the phases, milestones and tasks so the project can reach a successful conclusion. I like to create a basic high-level schedule to kick things off. Even if it's wrong, it helps the session start moving. It’s better than sitting in a meeting with your team staring at a blank sheet of paper.
  • 4. 2. Cover the Project Scope Use the scope statement from your Charter to make sure you include everything the customer expects you to deliver. List all the activities needed to deliver the scope. Look at the order of activities; often it is best to start with the most difficult tasks. The type of project may dictate the order, clearly, you can't build a house until the foundations have been laid. Think about the work you can do in parallel and what is dependent on other activities being finished first. Make sure you include the dependencies in your schedule.
  • 5. 3. Group the Tasks into Phases Projects typically go through phases, starting with an idea all the way to launch and rollout. You should arrange your project schedule in these phases. This is an example I’ve used for software development projects: 1. Ideas (the first concept, creating the team and everything needed to get the project started). 2. Feasibility (often development of a prototype, model or proof of concept). 3. Build (doing the work to create the product or service). 4. Launch (preparing to go-live with the product or service, often as a pilot first). 5. Rollout (delivering the product or service to the wider audience following updates from the pilot). 6. Closure (finishing the project, disbanding the project team and tying up any loose ends).
  • 6. 4. Create Milestones Adding milestones to your schedule helps the project team stay focussed and motivated. Milestones are the end of certain phases, the point where work needs completing, or sign-off obtained for work carried out. These milestones are how the team sees and measures their progress. Poring over hundreds of tasks each week is daunting. The milestones help put the entire project into perspective and keep everyone on track to a successful finish.
  • 7. 5. Make Time for Time When adding time estimates (hours or days) against tasks and activities it’s best to use people's experience. Better still if you can use a database of production rates to give more accurate estimates. Estimating as a team is effective, because it gives the opportunity for team members to challenge estimates. If an estimate is given by one team member, another may challenge it because he or she has direct experience of similar work. Make sure everyone agrees with the estimates and signs off during the session. This way there are no arguments later.
  • 8. 6. Plan Your People Now you have your schedule, it's time to add your people, either existing or new team members. Try to match your people's skill-set to the work. Have they done similar work in the past? Do they have a skill that would be useful on a particular aspect of the project? Have they shown an interest in working on a certain area? A common mistake when new to project scheduling is to use people for 100% of their time. It’s best to assume people will only be productive on the project for 80% of their time. Administration, filling out time sheets, team meetings, support and other unrelated tasks take up the remaining 20%. Once you have assigned people to the tasks in your schedule, review it for conflicts. Have you got areas where people are working on two work streams simultaneously? Is the work allocated evenly across the team? Be careful not to overload your key people, while under-utilising others.
  • 9. Finally… Check your schedule thoroughly to make sure there are no errors. Here are a few common problems found in schedules: • • • • • • • • • Not including public holidays in the schedule. Not including team member's holidays in the schedule. Missing links to dependencies. Creating one continuous block of work with no milestone deliverables along the way. Using poor task estimates or guesses instead of people's experience or production rates. Starting with an end date and making the schedule fit it. Assigning people for 100% of their time. Dividing tasks between more than one person. Not building in contingency time in the event things go wrong.
  • 10. Remember to regularly update the schedule with your team to check progress and make adjustments where necessary. A daily 15 minute ‘Scrum’ style meeting or phone call is useful, where each team member says what he or she did yesterday; what they intend to do today and highlights any blockers holding them back. It is your responsibility as project manager to help remove any blockers and smooth the path ahead.
  • 11. In Summary… 1. Define the tasks and activities using your scope statement. 2. Sequence the activities identifying any dependencies. 3. Group the tasks and activities into phases. 4. Create milestones. 5. Create time estimates for the tasks and activities. 6. Assign people to the tasks and activities. 7. Review your schedule for errors and correct. 8. Hold daily progress meetings with your team and adjust the schedule.
  • 12. A quality project schedule is the basis of project success, so spend time with your team creating a schedule that is both meaningful and realistic.
  • 13. Source http://certifications-review.blogspot.in/2013/11/aguide-to-creating-quality-project.html Looking for more details or Planning to get PMP certified, mail your details on courses@wiziq.com or call +91-0172 5032409 to get PMP Certification training and gain 35 contact hours..!!