A project plan is a document created at the beginning of the
project lifecycle that gives stakeholders and everyone else
involved in a project a clear idea of what a project will entail in
terms of effort, time, cost, and anticipated results.
One of the things that must be identified before the project plan
can be created is the methodology, or approach, the project
manager plans to use to manage the project. Choosing a
methodology is important because a methodology provides the
framework—that is, an overall process and suggested documents
and deliverables—that will guide project development from
beginning to end. Some project methodologies are more
appropriate for some types of projects than for others.
For this assignment, you will:
1. - Choose a project methodology for two different projects
based on project requirements and explain why you chose each
methodology for each project.
2. - Brainstorm your own project and create a draft simplified
project plan for that project. You must indicate in your
simplified project plan whether you intend to apply the Agile or
waterfall methodology. You may create your simplified project
plan using Microsoft® Excel® or, if you choose, another
software application such as Microsoft® Project®.
IT related projects preferred
To complete this assignment:
Read Agile Project Management and the PMBOK® Guide.
Answer the Methodology Selection and Rationale questions.
Brainstorm a project you would like to explore in this course.
You may choose a project from your work experience, from a
description of a project in your textbook or in an online reading,
or a project that is brand new but that you think would improve
a business process at work, at home, or at school.
Read the two linked examples of project plans implemented as
Microsoft® Excel® spreadsheets, Example Plan A and Example
Plan B. You will be using these as guides in creating your own
draft project plan. Notice especially the differences between
these two examples in terms of length (overall and task length),
structure of the work breakdown (iterative vs. non-iterative),
and methodology.
Research additional project plan examples online.
Create a simplified project plan for your own brainstormed
project that resembles the two linked examples.
Save your simplified project plan as a
Microsoft® Excel® spreadsheet document.
Submit both your completed Methodology Selection and
Rationale questions and your project plan draft
(Microsoft® Excel® document).
Project Methodology Selection and Rationale
CMGT/410 v19
Page 2 of 3Project Methodology Selection and
RationaleQuestions
1. Which methodology, Agile or waterfall, do you think is most
appropriate for a project characterized by innovation, loosely
defined requirements, and high risk? Why? Be sure to cite at
least two sources to support your rationale.
2. Which methodology, Agile or waterfall, do you think is most
appropriate for a project characterized by comprehensively
defined requirements and low risk? Why? Be sure to cite at least
two sources to support your rationale.
3. For the project you chose as a good fit for Agile, describe the
following roles: project manager, project sponsor, business
analyst, and scrum master.
4. For the project you chose as a good fit for waterfall, describe
the following roles: project manager, project sponsor, business
analyst, and program manager.
5. Define project, project life cycle, and software development
life cycle. How does a project’s software development life cycle
differ from the project life cycle?
IT related projects preferred
Copyright© 2018 by University of Phoenix. All rights reserved.
Task_TableNameDurationPredecessorsResourcesNotesMobile
app plan34 days3/17/16Project set-up7 days2/1/162/9/16Define
project processes2 days2/1/162/2/16project manager, product
ownerSet up working environment4 days2/3/162/8/163technical
administratorDetermine initial sprint velocity1
day2/9/162/9/164lead developerProject setup complete0
days2/9/162/9/165Sprint 1 UI6 days2/10/162/17/162Sprint 1
plan0.5 days2/10/162/10/16Select sprint 1 user stories0.25
days2/10/162/10/16product ownerAssign user stories0.25
days2/10/162/10/169product owner, lead developerSprint 1 plan
complete0 days2/10/162/10/1610User Interface5
days2/10/162/16/16Design User Interface2
days2/10/162/11/16UX developerBuild User Interface2
days2/12/162/15/1613UX developerTest User Interface1
day2/16/162/16/1614test engineerUAT of UI1
day2/17/162/17/1612test engineer, product ownerCorrect Issues
From UAT UI1 day2/26/162/26/1625UX developerSprint 2
reports15 daysSprint 2 plan0.5 days2/18/162/18/16Select sprint
2 user stories0.25 days2/18/162/18/16lead developerAssign user
stories0.25 days2/18/162/18/1619lead developerSprint 1.1 plan
complete0 days2/18/162/18/1620Client Specified Reports7
days2/18/162/26/16Design Reports2
days2/18/162/19/16reporting developerBuild Reports2
days2/22/162/23/1623reporting developerTest Reports2
days2/24/162/25/1624test engineerUAT of Reports1
day2/29/162/29/1622test engineer, product ownerCorrect Issues
From UAT of Reports1 day3/8/163/8/16reporting
developerSprint 3 Platform7 days3/1/163/9/1617Sprint 3
plan0.5 days3/1/163/1/16Select sprint 3 user stories0.25
days3/1/163/1/16lead developerAssign user stories0.25
days3/1/163/1/1630lead developerSprint 3 plan complete0
days3/1/163/1/1631Cross Platform Support6
days3/1/163/8/16Design Cross Platform Support2
days3/1/163/2/16technical administratorBuild Cross Platform
Support2 days3/3/163/4/1634technical administratorTest Cross
Platform Support1 day3/7/163/7/1635technical
administratorUAT of CPS1 day3/9/163/9/1633technical
administrator, test engineerProject End2
days3/16/163/17/1644Obtain Final Client Signoff1
day3/16/163/16/16project manager, product ownerProvide
Project Report Out0.5 days3/17/163/17/1648project manager,
product ownerProject End Celebration0.5
days3/17/163/17/1649project manager, product owner
Task_TableIDNameDurationStartFinishPredecessorsResourcesN
otesProject Server 2016 upgrade - waterfall1Plan for upgrade to
Project Server 20165 days1/25/16 8:001/29/16
17:00http://go.microsoft.com/fwlink/p/?LinkId=2573572Review
system requirements for upgrade1 day1/25/16 8:001/25/16
17:00Server Administrator, Technical Analyst3Plan for clients1
day1/26/16 8:001/26/16 17:002Technical Analyst, Server
Administrator4Gather information about your Project Server
2010 environment1 day1/27/16 8:001/27/16 17:003Server
Engineer, Server Administrator5Plan to upgrade
customizations1 day1/28/16 8:001/28/16 17:0046Create an
upgrade communications plan1 day1/29/16 8:001/29/16
17:005Project Manager7Prepare your environment for upgrade4
days2/1/16 8:002/4/16 17:001Server
Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257359
8Deploy your Project Server 2016 destination environment1
day2/1/16 8:002/1/16 17:00Server Engineer9Prepare your
Windows PowerShell environment1 day2/2/16 8:002/2/16
17:008Server Engineer10Disable backward compatibility mode
in your Project Server 2010 environment1 day2/3/16 8:002/3/16
17:009Server Administrator11Check your Project Server 2010
data for issues that can cause the upgrade to fail1 day2/4/16
8:002/4/16 17:0010Server Administrator12Create backup copies
of your Project Server 2010 farm databases1 day2/5/16
8:002/5/16 17:007Server
Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257360
13Restore your Project Server 2010 farm databases for upgrade1
day2/8/16 8:002/8/16 17:0012Server
Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257361
14Upgrade your databases and Project Web App site
collections14 days2/9/16 8:002/26/16 17:0013Server
Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257363
15SharePoint upgrade6 days2/9/16 8:002/16/16 17:0016Check
the SharePoint content database for errors that can cause
upgrade to fail1 day2/9/16 8:002/9/16 17:0017Attach and
upgrade the SharePoint content database1 day2/10/16
8:002/10/16 17:0016Server Administrator18Add your account as
a secondary owner of the Project Web App site collection that
you want to upgrade1 day2/11/16 8:002/11/16 17:0017Server
Administrator19Migrate users who are using Windows Classic
authentication mode to claims based authentication (optional)1
day2/12/16 8:002/12/16 17:0018Server Administrator20Check
your Project Web App site collection for issues that can cause
upgrade of the site to fail1 day2/15/16 8:002/15/16
17:0019Server Administrator21Upgrade the Project Web App
site from SharePoint 2010 mode1 day2/16/16 8:002/16/16
17:0020Server Administrator22Project Server upgrade8
days2/17/16 8:002/26/16 17:001523Consolidate your Project
Server 2010 databases to a Project Services database1
day2/17/16 8:002/17/16 17:0024Attach the Project Services
database to the web application1 day2/18/16 8:002/18/16
17:0023Server Administrator25Check your Project Services
database for errors that can cause upgrade to fail1 day2/19/16
8:002/19/16 17:0024Server Administrator26Upgrade the Project
Services database1 day2/22/16 8:002/22/16 17:0025Server
Administrator27Mount the Project Web App instance1
day2/23/16 8:002/23/16 17:0026Server Administrator28Check
the Project Web App instance for issues that can cause upgrade
to fail1 day2/24/16 8:002/24/16 17:0027Server
Administrator29Upgrade the Project Web App instance1
day2/25/16 8:002/25/16 17:0028Server Administrator30Enable
Project Web App features1 day2/26/16 8:002/26/16
17:0029Server Administrator31Testing2 days2/29/16 8:003/1/16
17:002232Test Sharepoint Server1 day2/29/16 8:002/29/16
17:00Server Administrator, Server Engineer33Test Project
Server1 day3/1/16 8:003/1/16 17:0032Server Administrator,
Server Engineer
Resource_TableIDNameInitialsTypeMaterial LabelGroupEmail
AddressUser Logon AccountMax UnitsStandard RateCost Per
UseNotes1Technical AnalystTWork100%$50.00/h02Server
AdministratorSWork100%$65.00/h03Server
EngineerSWork100%$60.00/h0
Assignment_TableTask NameResource Name% Work
CompleteWorkUnitsReview system requirements for
upgradeServer Administrator08h100%Review system
requirements for upgradeTechnical Analyst08h100%Plan for
clientsTechnical Analyst08h100%Gather information about your
Project Server 2010 environmentServer
Administrator08h100%Gather information about your Project
Server 2010 environmentServer Engineer08h100%Plan to
upgrade customizationsServer Administrator08h100%Deploy
your Project Server 2016 destination environmentServer
Engineer08h100%Prepare your Windows PowerShell
environmentServer Engineer08h100%Disable backward
compatibility mode in your Project Server 2010
environmentServer Administrator08h100%Check your Project
Server 2010 data for issues that can cause the upgrade to
failServer Administrator08h100%Create backup copies of your
Project Server 2010 farm databasesServer
Administrator08h100%Restore your Project Server 2010 farm
databases for upgradeServer Administrator08h100%Check the
SharePoint content database for errors that can cause upgrade to
failServer Administrator08h100%Attach and upgrade the
SharePoint content databaseServer Administrator08h100%Add
your account as a secondary owner of the Project Web App site
collection that you want to upgradeServer
Administrator08h100%Migrate users who are using Windows
Classic authentication mode to claims based authentication
(optional)Server Administrator08h100%Check your Project Web
App site collection for issues that can cause upgrade of the site
to failServer Administrator08h100%Upgrade the Project Web
App site from SharePoint 2010 modeServer
Administrator08h100%Consolidate your Project Server 2010
databases to a Project Services databaseServer
Administrator08h100%Attach the Project Services database to
the web applicationServer Administrator08h100%Check your
Project Services database for errors that can cause upgrade to
failServer Administrator08h100%Upgrade the Project Services
databaseServer Administrator08h100%Mount the Project Web
App instanceServer Administrator08h100%Check the Project
Web App instance for issues that can cause upgrade to
failServer Administrator08h100%Upgrade the Project Web App
instanceServer Administrator08h100%Enable Project Web App
featuresServer Administrator08h100%Test Sharepoint
ServerServer Administrator08h100%Test Sharepoint
ServerServer Engineer08h100%Test Project ServerServer
Administrator08h100%Test Project ServerServer
Engineer08h100%

More Related Content

DOCX
Introduction to Public Relations TheoryPitch LetterAfter liste.docx
DOCX
CMGT410 v19Project Methodology Selection and RationaleCMGT41.docx
PPTX
Step Wise Project Planning Method,Step Wise Project Planning Metho,Step Wise ...
PPTX
Project charter sample
PDF
8 Project Plan
DOCX
project and risk management level 1 2 3 and ms project
PPT
PPT
L02 pm & it context
Introduction to Public Relations TheoryPitch LetterAfter liste.docx
CMGT410 v19Project Methodology Selection and RationaleCMGT41.docx
Step Wise Project Planning Method,Step Wise Project Planning Metho,Step Wise ...
Project charter sample
8 Project Plan
project and risk management level 1 2 3 and ms project
L02 pm & it context

Similar to A project plan is a document created at the beginning of the proje.docx (20)

PDF
Building Sustainable Software: An Introduction to Software Engineering
PPTX
Sessionnnnnnnnnnnnndewfcecsdddnnnnn 1.pptx
DOCX
CIS 348 Entire Course NEW
PDF
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
PDF
Lect-2: Overview and Traditional SPM, Classic mistakes
PPTX
2. PAE AcFn621 Ch-2 Principle ppt.pptx
PDF
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
PDF
SOFTWARE PROJECT MANAGEMENT PLAN PDF.pdf
PPTX
Unit 1 spm
PPTX
Unit 1 spm
PPT
IIIT Guest Talk 0512
PPTX
Software Engineering and Project Management - Introduction to Project Management
PPTX
Selecting a Digital Collections Management System: Getting Large Projects Don...
PPTX
PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY CONTEXT
PDF
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
PDF
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
PDF
Project Management for It Related Projects Roger Ireland
PPTX
MIS Project management
PPTX
HI600 U02_inst_slides
PPT
Pmbok framework helping material
Building Sustainable Software: An Introduction to Software Engineering
Sessionnnnnnnnnnnnndewfcecsdddnnnnn 1.pptx
CIS 348 Entire Course NEW
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
Lect-2: Overview and Traditional SPM, Classic mistakes
2. PAE AcFn621 Ch-2 Principle ppt.pptx
Lect-1: Software Project Management - Project Dimensions, Players, SDLC and P...
SOFTWARE PROJECT MANAGEMENT PLAN PDF.pdf
Unit 1 spm
Unit 1 spm
IIIT Guest Talk 0512
Software Engineering and Project Management - Introduction to Project Management
Selecting a Digital Collections Management System: Getting Large Projects Don...
PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY CONTEXT
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
Project Management for It Related Projects Roger Ireland
MIS Project management
HI600 U02_inst_slides
Pmbok framework helping material

More from blondellchancy (20)

DOCX
1. Report contentThe report should demonstrate your understa.docx
DOCX
1. Research the assessment process for ELL students in your state. W.docx
DOCX
1. Reply:2.Reply:.docx
DOCX
1. Review the three articles about Inflation that are of any choice..docx
DOCX
1. Read the RiskReport to see what requirements are.2. Read the .docx
DOCX
1. Quantitative According to the scoring criteria for the BAI, .docx
DOCX
1. Prof. Lennart Van der Zeil’s theorem says that any programmin.docx
DOCX
1. Review the results of your assessment using the explanation.docx
DOCX
1. Search the internet and learn about the cases of nurses Julie.docx
DOCX
1. Qualitative or quantitative paperresearch required(Use stati.docx
DOCX
1. Prepare a one page paper on associative analysis. You may researc.docx
DOCX
1. Prepare a comparative table in which you contrast the charact.docx
DOCX
1. Portfolio part II a) APRN protocol also known as collab.docx
DOCX
1. Post the link to one news article, preferably a piece of rece.docx
DOCX
1. Please explain fixed and flexible budgeting. Provide an examp.docx
DOCX
1. Open and print the Week 6 Assignment.2. The assignment .docx
DOCX
1. Plato’s Republic takes as its point of departure the question of .docx
DOCX
1. Objective Learn why and how to develop a plan that encompasses a.docx
DOCX
1. Open the attached Excel Assignment.xlsx” file and name it LastN.docx
DOCX
1. must be a research article from either pubmed or google scholar..docx
1. Report contentThe report should demonstrate your understa.docx
1. Research the assessment process for ELL students in your state. W.docx
1. Reply:2.Reply:.docx
1. Review the three articles about Inflation that are of any choice..docx
1. Read the RiskReport to see what requirements are.2. Read the .docx
1. Quantitative According to the scoring criteria for the BAI, .docx
1. Prof. Lennart Van der Zeil’s theorem says that any programmin.docx
1. Review the results of your assessment using the explanation.docx
1. Search the internet and learn about the cases of nurses Julie.docx
1. Qualitative or quantitative paperresearch required(Use stati.docx
1. Prepare a one page paper on associative analysis. You may researc.docx
1. Prepare a comparative table in which you contrast the charact.docx
1. Portfolio part II a) APRN protocol also known as collab.docx
1. Post the link to one news article, preferably a piece of rece.docx
1. Please explain fixed and flexible budgeting. Provide an examp.docx
1. Open and print the Week 6 Assignment.2. The assignment .docx
1. Plato’s Republic takes as its point of departure the question of .docx
1. Objective Learn why and how to develop a plan that encompasses a.docx
1. Open the attached Excel Assignment.xlsx” file and name it LastN.docx
1. must be a research article from either pubmed or google scholar..docx

Recently uploaded (20)

PDF
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
PDF
Classroom Observation Tools for Teachers
PDF
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
PPTX
UNIT III MENTAL HEALTH NURSING ASSESSMENT
PDF
Trump Administration's workforce development strategy
PDF
Supply Chain Operations Speaking Notes -ICLT Program
PPTX
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
PDF
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
PDF
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
PPTX
202450812 BayCHI UCSC-SV 20250812 v17.pptx
PPTX
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
PDF
Indian roads congress 037 - 2012 Flexible pavement
PPTX
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
PDF
A systematic review of self-coping strategies used by university students to ...
PPTX
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
PPTX
Orientation - ARALprogram of Deped to the Parents.pptx
PDF
Practical Manual AGRO-233 Principles and Practices of Natural Farming
PPTX
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
PDF
Weekly quiz Compilation Jan -July 25.pdf
PPTX
Introduction to Building Materials
Black Hat USA 2025 - Micro ICS Summit - ICS/OT Threat Landscape
Classroom Observation Tools for Teachers
احياء السادس العلمي - الفصل الثالث (التكاثر) منهج متميزين/كلية بغداد/موهوبين
UNIT III MENTAL HEALTH NURSING ASSESSMENT
Trump Administration's workforce development strategy
Supply Chain Operations Speaking Notes -ICLT Program
Introduction-to-Literarature-and-Literary-Studies-week-Prelim-coverage.pptx
SOIL: Factor, Horizon, Process, Classification, Degradation, Conservation
OBE - B.A.(HON'S) IN INTERIOR ARCHITECTURE -Ar.MOHIUDDIN.pdf
202450812 BayCHI UCSC-SV 20250812 v17.pptx
Tissue processing ( HISTOPATHOLOGICAL TECHNIQUE
Indian roads congress 037 - 2012 Flexible pavement
Onco Emergencies - Spinal cord compression Superior vena cava syndrome Febr...
A systematic review of self-coping strategies used by university students to ...
CHAPTER IV. MAN AND BIOSPHERE AND ITS TOTALITY.pptx
Orientation - ARALprogram of Deped to the Parents.pptx
Practical Manual AGRO-233 Principles and Practices of Natural Farming
Chinmaya Tiranga Azadi Quiz (Class 7-8 )
Weekly quiz Compilation Jan -July 25.pdf
Introduction to Building Materials

A project plan is a document created at the beginning of the proje.docx

  • 1. A project plan is a document created at the beginning of the project lifecycle that gives stakeholders and everyone else involved in a project a clear idea of what a project will entail in terms of effort, time, cost, and anticipated results. One of the things that must be identified before the project plan can be created is the methodology, or approach, the project manager plans to use to manage the project. Choosing a methodology is important because a methodology provides the framework—that is, an overall process and suggested documents and deliverables—that will guide project development from beginning to end. Some project methodologies are more appropriate for some types of projects than for others. For this assignment, you will: 1. - Choose a project methodology for two different projects based on project requirements and explain why you chose each methodology for each project. 2. - Brainstorm your own project and create a draft simplified project plan for that project. You must indicate in your simplified project plan whether you intend to apply the Agile or waterfall methodology. You may create your simplified project plan using Microsoft® Excel® or, if you choose, another software application such as Microsoft® Project®. IT related projects preferred To complete this assignment: Read Agile Project Management and the PMBOK® Guide. Answer the Methodology Selection and Rationale questions. Brainstorm a project you would like to explore in this course. You may choose a project from your work experience, from a description of a project in your textbook or in an online reading, or a project that is brand new but that you think would improve a business process at work, at home, or at school. Read the two linked examples of project plans implemented as Microsoft® Excel® spreadsheets, Example Plan A and Example Plan B. You will be using these as guides in creating your own
  • 2. draft project plan. Notice especially the differences between these two examples in terms of length (overall and task length), structure of the work breakdown (iterative vs. non-iterative), and methodology. Research additional project plan examples online. Create a simplified project plan for your own brainstormed project that resembles the two linked examples. Save your simplified project plan as a Microsoft® Excel® spreadsheet document. Submit both your completed Methodology Selection and Rationale questions and your project plan draft (Microsoft® Excel® document). Project Methodology Selection and Rationale CMGT/410 v19 Page 2 of 3Project Methodology Selection and RationaleQuestions 1. Which methodology, Agile or waterfall, do you think is most appropriate for a project characterized by innovation, loosely defined requirements, and high risk? Why? Be sure to cite at least two sources to support your rationale. 2. Which methodology, Agile or waterfall, do you think is most appropriate for a project characterized by comprehensively defined requirements and low risk? Why? Be sure to cite at least two sources to support your rationale. 3. For the project you chose as a good fit for Agile, describe the following roles: project manager, project sponsor, business analyst, and scrum master. 4. For the project you chose as a good fit for waterfall, describe the following roles: project manager, project sponsor, business analyst, and program manager. 5. Define project, project life cycle, and software development life cycle. How does a project’s software development life cycle differ from the project life cycle?
  • 3. IT related projects preferred Copyright© 2018 by University of Phoenix. All rights reserved. Task_TableNameDurationPredecessorsResourcesNotesMobile app plan34 days3/17/16Project set-up7 days2/1/162/9/16Define project processes2 days2/1/162/2/16project manager, product ownerSet up working environment4 days2/3/162/8/163technical administratorDetermine initial sprint velocity1 day2/9/162/9/164lead developerProject setup complete0 days2/9/162/9/165Sprint 1 UI6 days2/10/162/17/162Sprint 1 plan0.5 days2/10/162/10/16Select sprint 1 user stories0.25 days2/10/162/10/16product ownerAssign user stories0.25 days2/10/162/10/169product owner, lead developerSprint 1 plan complete0 days2/10/162/10/1610User Interface5 days2/10/162/16/16Design User Interface2 days2/10/162/11/16UX developerBuild User Interface2 days2/12/162/15/1613UX developerTest User Interface1 day2/16/162/16/1614test engineerUAT of UI1 day2/17/162/17/1612test engineer, product ownerCorrect Issues From UAT UI1 day2/26/162/26/1625UX developerSprint 2 reports15 daysSprint 2 plan0.5 days2/18/162/18/16Select sprint 2 user stories0.25 days2/18/162/18/16lead developerAssign user stories0.25 days2/18/162/18/1619lead developerSprint 1.1 plan complete0 days2/18/162/18/1620Client Specified Reports7 days2/18/162/26/16Design Reports2 days2/18/162/19/16reporting developerBuild Reports2 days2/22/162/23/1623reporting developerTest Reports2 days2/24/162/25/1624test engineerUAT of Reports1 day2/29/162/29/1622test engineer, product ownerCorrect Issues From UAT of Reports1 day3/8/163/8/16reporting developerSprint 3 Platform7 days3/1/163/9/1617Sprint 3 plan0.5 days3/1/163/1/16Select sprint 3 user stories0.25 days3/1/163/1/16lead developerAssign user stories0.25 days3/1/163/1/1630lead developerSprint 3 plan complete0 days3/1/163/1/1631Cross Platform Support6 days3/1/163/8/16Design Cross Platform Support2
  • 4. days3/1/163/2/16technical administratorBuild Cross Platform Support2 days3/3/163/4/1634technical administratorTest Cross Platform Support1 day3/7/163/7/1635technical administratorUAT of CPS1 day3/9/163/9/1633technical administrator, test engineerProject End2 days3/16/163/17/1644Obtain Final Client Signoff1 day3/16/163/16/16project manager, product ownerProvide Project Report Out0.5 days3/17/163/17/1648project manager, product ownerProject End Celebration0.5 days3/17/163/17/1649project manager, product owner Task_TableIDNameDurationStartFinishPredecessorsResourcesN otesProject Server 2016 upgrade - waterfall1Plan for upgrade to Project Server 20165 days1/25/16 8:001/29/16 17:00http://go.microsoft.com/fwlink/p/?LinkId=2573572Review system requirements for upgrade1 day1/25/16 8:001/25/16 17:00Server Administrator, Technical Analyst3Plan for clients1 day1/26/16 8:001/26/16 17:002Technical Analyst, Server Administrator4Gather information about your Project Server 2010 environment1 day1/27/16 8:001/27/16 17:003Server Engineer, Server Administrator5Plan to upgrade customizations1 day1/28/16 8:001/28/16 17:0046Create an upgrade communications plan1 day1/29/16 8:001/29/16 17:005Project Manager7Prepare your environment for upgrade4 days2/1/16 8:002/4/16 17:001Server Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257359 8Deploy your Project Server 2016 destination environment1 day2/1/16 8:002/1/16 17:00Server Engineer9Prepare your Windows PowerShell environment1 day2/2/16 8:002/2/16 17:008Server Engineer10Disable backward compatibility mode in your Project Server 2010 environment1 day2/3/16 8:002/3/16 17:009Server Administrator11Check your Project Server 2010 data for issues that can cause the upgrade to fail1 day2/4/16 8:002/4/16 17:0010Server Administrator12Create backup copies of your Project Server 2010 farm databases1 day2/5/16 8:002/5/16 17:007Server
  • 5. Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257360 13Restore your Project Server 2010 farm databases for upgrade1 day2/8/16 8:002/8/16 17:0012Server Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257361 14Upgrade your databases and Project Web App site collections14 days2/9/16 8:002/26/16 17:0013Server Administratorhttp://go.microsoft.com/fwlink/p/?LinkId=257363 15SharePoint upgrade6 days2/9/16 8:002/16/16 17:0016Check the SharePoint content database for errors that can cause upgrade to fail1 day2/9/16 8:002/9/16 17:0017Attach and upgrade the SharePoint content database1 day2/10/16 8:002/10/16 17:0016Server Administrator18Add your account as a secondary owner of the Project Web App site collection that you want to upgrade1 day2/11/16 8:002/11/16 17:0017Server Administrator19Migrate users who are using Windows Classic authentication mode to claims based authentication (optional)1 day2/12/16 8:002/12/16 17:0018Server Administrator20Check your Project Web App site collection for issues that can cause upgrade of the site to fail1 day2/15/16 8:002/15/16 17:0019Server Administrator21Upgrade the Project Web App site from SharePoint 2010 mode1 day2/16/16 8:002/16/16 17:0020Server Administrator22Project Server upgrade8 days2/17/16 8:002/26/16 17:001523Consolidate your Project Server 2010 databases to a Project Services database1 day2/17/16 8:002/17/16 17:0024Attach the Project Services database to the web application1 day2/18/16 8:002/18/16 17:0023Server Administrator25Check your Project Services database for errors that can cause upgrade to fail1 day2/19/16 8:002/19/16 17:0024Server Administrator26Upgrade the Project Services database1 day2/22/16 8:002/22/16 17:0025Server Administrator27Mount the Project Web App instance1 day2/23/16 8:002/23/16 17:0026Server Administrator28Check the Project Web App instance for issues that can cause upgrade to fail1 day2/24/16 8:002/24/16 17:0027Server Administrator29Upgrade the Project Web App instance1 day2/25/16 8:002/25/16 17:0028Server Administrator30Enable
  • 6. Project Web App features1 day2/26/16 8:002/26/16 17:0029Server Administrator31Testing2 days2/29/16 8:003/1/16 17:002232Test Sharepoint Server1 day2/29/16 8:002/29/16 17:00Server Administrator, Server Engineer33Test Project Server1 day3/1/16 8:003/1/16 17:0032Server Administrator, Server Engineer Resource_TableIDNameInitialsTypeMaterial LabelGroupEmail AddressUser Logon AccountMax UnitsStandard RateCost Per UseNotes1Technical AnalystTWork100%$50.00/h02Server AdministratorSWork100%$65.00/h03Server EngineerSWork100%$60.00/h0 Assignment_TableTask NameResource Name% Work CompleteWorkUnitsReview system requirements for upgradeServer Administrator08h100%Review system requirements for upgradeTechnical Analyst08h100%Plan for clientsTechnical Analyst08h100%Gather information about your Project Server 2010 environmentServer Administrator08h100%Gather information about your Project Server 2010 environmentServer Engineer08h100%Plan to upgrade customizationsServer Administrator08h100%Deploy your Project Server 2016 destination environmentServer Engineer08h100%Prepare your Windows PowerShell environmentServer Engineer08h100%Disable backward compatibility mode in your Project Server 2010 environmentServer Administrator08h100%Check your Project Server 2010 data for issues that can cause the upgrade to failServer Administrator08h100%Create backup copies of your Project Server 2010 farm databasesServer Administrator08h100%Restore your Project Server 2010 farm databases for upgradeServer Administrator08h100%Check the SharePoint content database for errors that can cause upgrade to failServer Administrator08h100%Attach and upgrade the SharePoint content databaseServer Administrator08h100%Add your account as a secondary owner of the Project Web App site collection that you want to upgradeServer Administrator08h100%Migrate users who are using Windows
  • 7. Classic authentication mode to claims based authentication (optional)Server Administrator08h100%Check your Project Web App site collection for issues that can cause upgrade of the site to failServer Administrator08h100%Upgrade the Project Web App site from SharePoint 2010 modeServer Administrator08h100%Consolidate your Project Server 2010 databases to a Project Services databaseServer Administrator08h100%Attach the Project Services database to the web applicationServer Administrator08h100%Check your Project Services database for errors that can cause upgrade to failServer Administrator08h100%Upgrade the Project Services databaseServer Administrator08h100%Mount the Project Web App instanceServer Administrator08h100%Check the Project Web App instance for issues that can cause upgrade to failServer Administrator08h100%Upgrade the Project Web App instanceServer Administrator08h100%Enable Project Web App featuresServer Administrator08h100%Test Sharepoint ServerServer Administrator08h100%Test Sharepoint ServerServer Engineer08h100%Test Project ServerServer Administrator08h100%Test Project ServerServer Engineer08h100%