International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
A SYSTEMATIC REVIEW OF UNCERTAINTIES IN 
SOFTWARE PROJECT MANAGEMENT 
Marcelo Marinho1, 2 , Suzana Sampaio2, Telma Lima3 and Hermano de Moura1 
1Informatics Center (CIn), Federal University of Pernambuco (UFPE), Recife, PE, Brazil 
2Statistics and Informatics Department (DEINFO), Federal Rural University of 
Pernambuco (UFRPE), Recife, PE, Brazil 
3Administration Department (DADM), Federal Rural University of Pernambuco 
(UFRPE), Recife, PE, Brazil 
ABSTRACT 
It is no secret that many projects fail, regardless of the business sector, software projects are notoriously 
disaster victims, not necessarily because of technological failure, but more often due to their uncertainties. 
The threats identified by uncertainty in day-to-day of a project are real and immediate and the stakes in a 
project are often high. This paper presents a systematic review about software project management 
uncertainties. It helps to identify the difficulties and the actions that can minimize the uncertainties effects 
in the projects and how managers and teams can prepare themselves for the challenges of their projects 
scenario, with the aim of contributing to the improvement of project management in organizations as well 
as contributing to project success. 
KEYWORDS 
Software Project Management; Systematic literature review; Uncertainties in Projects Management; 
Uncertainty in Software Projects 
1. INTRODUCTION 
Project management has been discussed by executives and academics as one of the possibilities 
for organizations for integrating complex efforts and bureaucracy reduction. Managing projects 
effectively is introduced as a solution and as well as a major challenge for the business world. 
That is why both projects and project management have a highly important role in society and 
have been used as scientific research objects. 
Such subject is being applied in new industries, countries and spheres. Project management has 
become a core business process for a large number of companies both at strategic and operational 
level. We may call a project any activity that is considered significant and necessary and each 
major project can include a series of sub-projects. 
Once software development involves a certain level of complexity and challenges, the techniques 
use, practices and project management tools have become common in software engineering. 
Nowadays it is very common for companies to deal with software development or service as a 
temporary project which needs to be planned, organized, conducted, monitored and controlled. 
DOI : 10.5121/ijsea.2014.5601 1
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
The Standish Group [1] reported that on average only 39% of projects are delivered on time, 
within budget and with the agreed requirements (therefore those projects perceived as successful). 
43% are delivered late, and/or over budget and/or under certain conditions and finally, 18% are 
cancelled on delivery and never used. More than a decade later, very little seems to have changed. 
Projects are seen as a strategic factors in organizations, even though, many projects still fail. One 
of the main reasons for such outcome is that project managers do not know how to deal with 
uncertainties [2]. Moreover, in project risk management literature, there is no common 
understanding as to what uncertainty is [3]. 
The term uncertainty may be understood broadly as “lack of certainty”, which means information 
absence. Therefore, it covers not only probabilistic or indefinite results, but also an ambiguity and 
clarity lack concerning a large number of factors. Uncertainty is simply an ambiguity expression 
and project indeterminacy [4]. 
A systematic review discovers, evaluates and interprets all available research relating to the 
particular question. A systematic review aims to better understand and explore the topic, which is 
a planned and ideally repeatable way of synthesizing results from the existing body of scientific 
literature which has been prepared. 
The authors developed a systematic review of related studies in the period from 1994 to 2013 
guided by the research questions. The research aims to investigate: The relation of the uncertainty 
level associated with innovation projects; what the best practices to manage the uncertainties in 
software projects are; what are the sources of uncertainty perceived by studies; and what practices 
(techniques or strategies) are used for the problem nature recognition and uncertainties 
containment in projects. 
Following the introductory section, this paper is structured as follows: Section 2 is about 
Evidence-based-Software Engineering; Section 3presents the research method adopted for this 
study; Section 4 describes a data analysis extracted from the selected studies; in Section 5 the 
results for each research question are presented and summarized and finally Section 6 contains 
the conclusion. 
2. EVIDENCE-BASED SOFTWARE ENGINEERING 
Evidence-based software engineering aims to provide means by which the best evidence from 
research can be integrated with practical experience and human values in the decision-making 
process considering the development and software maintenance [7]. The essence of evidence-based 
paradigm is systematically collect and analyze all available data about a phenomenon for a 
2 
more comprehensive and broader perspective than one can capture through a single study. 
The paradigm based on evidence gained forces initially Medicine (Evidence-based 
Medicine/EBM), which aims to integrate the best research evidence with clinical experience and 
assessment of patients. Work kitchenham et al. [5] was the first to establish a parallel between 
Medicine and Engineering Software regarding to evidence-based approach. Kitchenham et al. [5] 
believe that software engineering can provide evidence-based mechanisms needed to help the 
professional to adopt appropriate technologies and avoid unsuitable ones, aiming the best 
practices and procedures. Some studies suggest that software engineering professionals 
(researchers) must consider the use of evidence-based software engineering support to improve 
their decisions about which technologies to adopt [5],[6],[7],[8],[40],[41].
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
Software engineering based on evidence gathers and evaluates existing evidence in a technology 
through a five-step methodology. The steps 1, 2, 3 and 4 their evaluation (step 5) is done through 
a systematic review [40]: 
• Transforming the problem or need for information on a research question; 
• Search the literature for the better available evidence to answer questions; 
• Critically evaluate the evidence about its validity, impact and applicability; 
• Integrate the evaluated evidence with practical experiences, values and clients 
3 
circumstances to make decisions; 
• Evaluate the steps of 1 to 4 performance and search for ways to improve them. 
2.1. Systematic Literature Review 
Systematic literature reviews evaluate evidence in a systematic and transparent way. In a 
traditional literature review, the research strategy and results evaluation criteria are usually hidden 
from the reader, which means that the revision may perfectly be done in an unstructured way, ad 
hoc and evidence that do not support the researcher's preferred hypothesis might be ignored. 
However, in a systematic literature review the research strategy and the evaluation criteria are 
explicit and all relevant evidence are included in the evaluation [5],[6],[7]. 
A systematic literature review “is a way of evaluating and interpreting all available research 
relating to a particular research question, topic area, or phenomenon of interest” [42]. Travassos 
[43] believes systematic reviews “provide the means to perform comprehensive literature review 
and not biased, giving their results have scientific value”. Kitchenham [5] adds that systematic 
reviews aim to present a fair assessment of a research topic using a reliable, accurate and 
auditable methodology. 
Kitchenham [5] e Travassos [43] present some of the reasons for conducting a systematic review: 
• Summarize existing evidence about a phenomenon; 
• Identify gaps in current research; 
• Provide a framework to position new research; and 
• Support the generation of new hypotheses. 
According to Kitchenham [5], his early studies were based on the guidelines used in the medical 
field, however it is important to recognize that software engineering research have large 
differences from medical research, so an approach that incorporates guidelines of social science 
researchers was added in their studies and more current recommendations. Kitchenham [5] 
summarizes the steps of a systematic review in three main phases: Planning the review, 
Conducting the revision and Presenting the revision. These steps are described below. 
2.2. Planning a Systematic Review 
As in any scientific endeavor, a systematic review of the literature needs a detailed protocol 
describing the process and the methods to be applied. The most important activity during the 
planning phase is the formulation of research questions to be answered as all the other aspects of 
the review process depend on them [40]. To Kitchenham cite{kitchenham2004procedures}, 
before undertaking a systematic review researchers must ensure that it is necessary and the 
protocol should be able to answer some questions: 
• What are the objectives of this review? 
• What sources were searched to identify primary studies? Were there any restrictions? 
• What were the criteria for inclusion / exclusion and how they are applied?
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
4 
• What criteria were used to evaluate the quality of the primary studies? 
• How were the quality criteria applied? 
• How was the data extracted from primary studies? 
• How was the data synthesized? 
• What were the differences between studies investigated? 
• Because the data were combined? 
Through these and other questions, the researcher plans and documents all necessary information 
to carry out the systematic review. 
2.3. Planning a Systematic Review 
Once the protocol has been defined and validated the review can begin. The primary studies 
selection, or else, the execution of the selection process defined in the protocol for the pursuit of 
studies and subsequently data extraction and evaluation are part of the implementation phase of 
the systematic review execution. For the studies selection, inclusion and exclusion criteria are 
used. The information extraction and evaluation are conducted through forms and may be 
supported by a software tool. The steps, according to Travassos [43], summarized for the review 
implementation are: 
• Searches in the defined sources: the process should be transparent, repeatable and 
documented, as well as the changes that occur in the process; 
• Primary studies selection with the inclusion and exclusion criteria defined; 
• Data extraction from general information studies to answers to the research questions. 
Forms are a good way to record all the necessary data and the use of a computational tool 
can support the data extraction and recording and subsequent analysis; 
• Assessing the studies quality is important to balance the importance of different studies, 
reduce bias (tendency to produce ``biased results'' that systematically separates from true 
results), maximize internal and external validity and guide recommendations for future 
research; 
• Data synthesis is performed according to the research questions, through tables to 
highlight the similarities and differences between studies. If quantitative data are 
available, making a meta-analysis can be considered. 
2.4. Presenting the results 
The last step of a systematic review consists on writing a review report and its evaluation, 
according to the synthesis, and data analysis. Lately, the results are consistently presented with 
tabulated information and the research question, highlighting similarities and differences between 
the results, or else, highlighting the possible data combination and analyzes. 
3. RESEARCH METHOD 
This section describes the research method according to Kitchenham methodological guideline 
for systematic reviews [8]. A systematic review protocol was written to describe the plan for the 
review. Details on the course of these steps are described in the following sub-sections. 
3.2. Research questions 
These are research questions which guided the systematic review: 
• RQ 1: What is the relation between uncertainty and innovative projects? 
• RQ 2: What are the sources of uncertainty perceived? 
• RQ 3: How is it possible to reduce the uncertainty level in software projects?
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
• RQ 4: What practices (techniques or strategies) can help reduce the uncertainties in 
5 
project management software? 
3.2. Search environment 
A directory in the cloud was created before starting the research. A free web store service was 
used by the researchers to store all artifacts used. This enabled a total standardization and control, 
so all of them could access the material as if they were in the same environment, thought being 
remote. 
Furthermore, some datasheets were developed to be used in all phases. Those datasheets 
facilitated the data organization in many aspects; for example, a standard to enumerate searched 
publications, filters to extract objective information among others. 
3.3. Generation of Search Strategy 
Aiming to identify and recover the smallest possible publications super group which meet the 
systematic review eligibility criteria, it incorporates a search strategy for a research. The 
eligibility criteria are conditions to determine if primary studies are about the systematic review 
research questions. The search results are transformed into in a sequential publication list of the 
chosen engines. Each resource has a different community, interests, language, examining issues 
and search syntaxes as well. Therefore, different resources might require different search strings. 
Next, we conducted initial studies for all phases of the major study, called “pilot studies”. These 
were performed to align a phase-to-phase understanding among researchers, all search engines 
mechanisms test and the adjust of some search terms. The study only proceed when the two 
researchers agreed with the pilot results. 
The resources used to searches are: IEEEXplore Digital Library (httt://ieeexplore.ieee.org/); 
ACM Digital Library (http://portal.acm.org); Elsevier ScienceDirect (www.sciencedirect.com); 
Springer Link (http://link.springer.com). 
Other sources were initially considered as potential for searches:Google, Google Scholar, Wiley 
InterScience, InspecDirect, Scopus and Scirus. However, these were later excluded from the final 
list of sources for some of the following reasons: 
• Some because they were not present in significant or systematic reviews or not having 
been recommended by experts; 
• Some for not allowing the viewing or downloading of the works without payment or 
license that the institution responsible for the work did not have; 
• Some because they were already indexed by some of the sources already listed in the 
search. 
To search all results from sources, the researchers grouped to search publications. The sources 
(engines) were divided among them. Each researcher was responsible to find results in their 
engine and, finally the papers were catalogued. Then, when the search was performed, there were 
identified 3,044 publications. The searches results were extracted in Bibtex files to merge in a 
datasheet developed to consolidate the results of all engines. After excluding duplicated results 
from the datasheet, we found 2,933 articles to start the first phase.
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
6 
3.4. Paper Selection 
The idealized selection process was done in two parts: an initial document selection of the 
research results that could reasonably satisfy the selection criteria based on a title and the articles 
abstract reading, followed by a final selection of the initially selected papers list that meet the pre-established 
criteria, based on the introduction and conclusion reading of the papers. To reduce 
potential bias, the process was conducted in pairs, in which both researchers worked individually 
on the inclusion or exclusion of the paper and then a comparison of spreadsheets was done. The 
possible divergence was discussed and finally a consensus was reached. If there was not a 
consensus, a third researcher should be consulted. In case doubts still remained, the work would 
be inserted in the list. 
In the pilot study performed before the first phase beginning, the first ten results from all engines 
were catalogued and the group read the titles and the abstracts and discussed about them to 
calibrate comprehension. Other pilot study was performed having more five publications done, 
because the researches were not ready to continue after the first pilot. After a reliability 
agreement, the first phase initiated. Each researcher read the publications` titles and abstracts to 
select or exclude them. They discussed about the results to gather them together according to a 
new datasheet agreement. Out of the initial selection of 2,933 papers, 111 articles were selected to 
the second phase. 
After the first and before second phase, a new pilot study was done. Then, we selected a single 
article to be read by researchers aiming a consensus for both. In this phase, the introduction and 
the conclusion should be read. Similarly to the first phase, each researcher read the articles 
individually and later discussed its results. After the phase two selection, the researches 
eliminated 88 and selected 23 papers out of 111 to be read for data extraction phase. 
3.5. Study Quality Assessment 
In the data extraction phase, each publication methodological quality of was assessed. Three 
factors were assessed as follows, and each were marked yes or no: Does the publication mention 
the possibility of selection, publication, or experimenter bias?; Does the publication mention 
possible threats to internal validity? and Does the publication mention possible threats to external 
validity? 
The quality assessment was made only on the basis of whether the publication explicitly 
mentioned those issues. We did not make judgement about whether the publication had a “good” 
treatment of the issues. The results of the study quality assessment were not used to limit the 
selection of publications. 
3.6. Data Extraction 
Beforehand, a new pilot was done to calibrate the stage. We selected two relevant articles and 
compared the extraction data performed so far with ours. Thus, a pitot was carried out with an 
article found with one of the 23 selected works. In the data extraction phase, researchers had to 
read the papers selected for extracting information according to the datasheet model. 
We had selected 23 works, but during the extraction phase we identified 2 articles that showed no 
relevant citations or possible reasons to be extracted, thus, there were 21 articles. For each 
publication there was extracted information.
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
From each study, a list of shares was extracted, where each share described answered a research 
question. Or else, each simple sentence that answered one or more research question was 
considered a quota. We had a total of 165 quotas extracted from 21 studies. Finally, these shares 
were recorded on a datasheet. 
7 
3.7. Data Synthesis 
The two researchers worked on the synthesis work to generate combinations of quotas with 
answers of the research questions. 
There was a good level of inter-rater agreement, differences in opinion were discussed in a 
meeting, and it was easily solved without the need of involving a third arbitrating researcher, as 
planned. 
4. SYSTEMATIC REVIEW RESULTS 
This section describes the analysis of the data extracted from our selected studies. 
Figure 1. Results obtained on each stage at systematic review process.
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
8 
4.1. Data Search 
In the Data Search phase the searches were conducted in four sources. The Figure 1 shows the 
results obtained on each stage at systematic review process. 
4.2. Data Selection 
The Data Selection was divided in two phases: Phase 1: Title and Abstract analyses; and, Phase 2: 
Introduction and the Conclusion analyses. 
In Phase 1, after checking the titles and abstracts, 111 articles were selected for the next phase. A 
total of 2,822 articles were eliminated. Among the criteria used, we may highlight: “0 - Not 
applicable” (this is a research non related with management or uncertainties), with 52%; “Outside 
the uncertainties in project management area”, with 38% and “2 -It is about this risks in projects” 
with 10%. 
In Phase 2, after reading the introduction and conclusion, just 23 papers were selected for the 
extraction phase. A total of 88 articles were eliminated. Among the criteria used we highlight: “1- 
Outside the uncertainties in project management area” with 59% , “2 - It is about this risks in 
projects'' with 34%, followed by “0 - Not applicable”, with 7%. 
Table 1. List of engines and its absolute contributions. 
Engine Automatic Selection 1 Selection 2 Extraction 
ACM 548 10 2 2 
IEEE 722 63 15 13 
ScienceDirect 569 11 4 4 
Springerlink 1094 27 2 2 
Total 2933 111 23 21 
4.3. Data Extraction and Quality Assessment 
In the Data Extraction and Quality Assessment each research read a full paper for the quotes 
extraction, at the same time they did the paper quality assessment. At the quality assessment 
phase three factors were assessed as follows, and were each researcher marked YES or NO: i) 
Does the publication discuss the possibility of selection, experimenter, or publication bias?; ii) 
Does the publication discuss threats to internal validity?; and, iii) Does the publication discuss 
threats to external validity? The quality assessment was made only on the basis of whether the 
publication itself mentions with these issues – we did not assess whether the publications had a 
treatment of these issues. 
Out of 23 works selected in the previous stage, the researchers worked with 21 articles. Two were 
eliminated for not answering the research questions. Additional studies were identified by search 
technique snowball, or else, covering the studies references already found. This technique 
allowed us to identify high-quality works that were not found by the automatic search. 6 works 
that contributed to the discussion were added to be held in Section 5. 6 works out of 4 are books 
and 2 are journals that are not indexed by engines the selected research. 
It is worth pointing out that some of the non-selected studies for extraction phase were considered 
so, because they confused risk with uncertainty. Note that although the risk and uncertainty are
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
related, they are not the same thing. The uncertainty is the unknown, whereas risk is what can go 
wrong. Clearly, much of the risk of the project depends on the uncertainty, but there are other 
factors that contribute to the risk of the project, including deadlines, lack of resources and 
inadequate skills. Several of the articles report “uncertainties in the estimates” when in fact they 
are trying to estimate risks in the project process. 
9 
4.4. Data Synthesis 
Considering the studies evaluated in the extraction and adding the works found by snowball in the 
Synthesis phase 165 quotas were analyzed, in which 18 answer the first research question; 44 the 
second; 30 the third and 73 the last. 
Figure 2 represents the distribution of works by continent. The geographical distribution of the 
uncertainties related to studies in project management was as follows: The United States was 
ahead with 13 articles; England, with 3; Brazil, China and Singapore with 2; and Australia, 
Scotland, Philadelphia, Israel and Pakistan, with 1. 
We note that in the last 10 years it has been published 20 out of 27 of the papers included in the 
study. It demonstrates and confirms that research on uncertainties in project management have 
been growing since the last decade. Figure 3 illustrates the distribution of studies identified by 
selection process throughout the years. 
Figure 2. Distribution by continent. Figure 3. Distribution by years.
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
10 
Figure 4. Distribution by engines. Figure 5. Distribution by type of publication. 
Figure 4 shows the distribution of documents found by search engines and Figure 5 shows the 
distribution of jobs by type of publication, showing that most of the studies, 44%, were published 
in journals, following a 41% of the annals of events (Conferences, Workshops and symposia) and 
15% in books. Figure 6 shows the papers`methodologies adopted. Table 2 displays a list with the 
number of studies returned by event. It can be noticed that most of the studies were published in 
some editions of the PICMET annals Portland International Conference on Management of 
Engineering and Technology, followed by the IJPM periodicals International journal of project 
management and the third, JPIM Journal of Product Innovation Management. 
Figure 6. Distribution by methodologies. 
5. FINDINGS 
All evidence is properly referenced by 27 studies [9], [10], [11], [12], [13], [14], [15], [16], 
[17],[18], [19], [20], [21], [22], [2], [23], [3], [24], [25], [26], [27],[28], [29], [30], [31], [32], 
[33]. In this section, the results for each research question are presented. In Section 5.1 the 
evidence that the uncertainties become larger and larger as the project is more innovative are 
presented. In Section 5.2 sources of uncertainties are perceived in the studies. In Section 5.3 the 
evidences are presented about the possibility of reducing the uncertainties in software projects. In 
Section 5.4 evidences on how the techniques or strategies that favor uncertainties reduction in 
project management are presented.
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
11 
Table 2. List with the number of studies returned by event. 
Published in Amount 
Portland International Conference on Management of Engineering & 
5 
Technology 
International journal of project management 4 
Books 4 
Journal of Product Innovation Management 3 
Engineering Management Conference 2 
International Conference onSoftware Engineering -Workshop on 
Cooperative and Human Aspects on Software Engineering 
1 
IEEE International Conference on Systems, Man, and Cybernetics 
(SMC) 
1 
IEEE Software 1 
IEEE Transactions on Engineering Management 1 
IEEE Transactions on Systems, Man and Cybernetics 1 
International Conference on System Sciences 1 
MIT Sloan Management Review 1 
Small Business Economics 1 
SIGPLAN conference companion on object oriented programming 
1 
systems languages and applications 
5.1. What is the relation between uncertainty and innovative projects? 
This question sought to investigate the relationship of the uncertainties with innovative projects 
and aspects of how we manage these projects. One of the findings is that the evidence report that 
innovative projects are more likely the occurrence of uncertainties. The following evidence of the 
studies is reported. 
Innovation and projects aimed at the innovation development, being them a new product, process 
or service, should be on the executive diary, along with the understanding of the business 
environment changes and the action plan needed to respond to these changes or influence them 
[31]. 
Various perspectives emerge from the literature to explain why companies have difficulty in 
managing the various sources of uncertainty associated with converting innovations in innovative 
companies. Understanding the innovative project characteristics and the uncertainty nature that 
permeates them is critical for developing appropriate management practices [32]. 
Each project has different characteristics, so the uncertainty level is varied. High-risk projects, 
typically innovation projects, which normally pursue ambitious goals and high failure probability, 
will have a high uncertainty capacity [4]. Low uncertainty projects typically create limited 
opportunities, whereas a project of high uncertainty will be evaluated primarily on their 
commercial effect and long-term, rather than measures of time and budget [34]. 
The largest uncertainty occurs in projects in which the company has no previous experience or 
existing project on which to build. On the contrary, the projects in which only a small amount 
from the existing project is changed, the uncertainty to the development teams is reduced [14].
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
Where uncertainty about future events is high, tolerance of uncertainty may be particularly 
necessary [19]. Management practices that are effective in established companies are often 
ineffective and even destructive when applied to innovative projects because of high levels of 
uncertainty inherent in these projects [32]. 
Flexibility is required on projects where goals are unclear or open to negotiation, the strategy is 
emerging and the project is highly subject to external influences. Keeping options open, and 
adopt a flexible and robust management approach can be much more effective than prematurely 
freeze projects plans relying on conventional control mechanisms to measure performance [19]. 
Strategies, techniques, best practices are important to manage or contain the uncertainties in 
innovative projects. The recognition of the uncertainty sources in projects can be a determining 
factor in the success of the project. You need to clarify what can be done, decide what should be 
done, and to ensure that management is carried out based on the uncertainty level observed in the 
project. 
12 
5.2. What are the sources of uncertainty perceived? 
This question sought to investigate what the sources of perceived uncertainty in software projects 
are. From the 27 studies analyzed, 44 quotes was found. In the studies surveyed there is not a 
single label to the sources, it is common in some articles to speak from a particular source that is 
a single uncertainty, but classified differently, for example: market source [21], [17], [25], [22], 
[31], [32], external source [33] and novel source [11],[2] represent a single source of uncertainty. 
For doing so, we try to group the uncertainty and create a unique classification for these sources. 
Among those quotas found (they could cite more than one source, if they are in the same 
sentence), we find: 16 references to market uncertainty; 15 references to technological 
uncertainty; 14 for environment uncertainty and 9 for socio-human uncertainty. The following 
describes the sources of uncertainties grouped by research: 
5.2.1. Market 
Market uncertainty indicates how news products are to the market, to consumers and to potential 
users. It represents the extent to which buyers and users are familiar with this type of product, its 
benefits and how they can use it. The level of market uncertainty indicates the external 
uncertainty, and also reflects the uncertainty of the project goal. It also indicates the easiness of 
knowing what to do or what to build and how to introduce consumers to the product. The market 
uncertainty comprehends client, suppliers, partners and current market situation [11],[13], [21], 
[17], [25], [22], [2], [29], [31], [32], [33]. 
5.2.2. Technological 
Technological uncertainty depends on the extent to which the project uses new technology or 
mature technology. The level of project technological uncertainty is not universal, but subjective, 
and depends not only on what technology exists, but also what is accessible to the organization. It 
is therefore a measure of the amount of existing new technology compared to mature technology 
available for use in the project. The technological uncertainty causes, among other things, an 
impact in the project, in the communication, in the freezing time of the plan and the number of 
planning cycles. It can also affect the technical expertise that the project manager and their team 
members need to have [10], [11], [13], [16], [17], [21], [22],[25], [31], [32].
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
13 
5.2.3. Environment 
This source indicates the degree of uncertainty of the external and internal organizational 
environment. Organizational theories emphasize that organizations must adapt to their 
environment if they are to remain viable. Environmental uncertainty can arise from the actions of 
different organizations (suppliers, competitors, consumers, government, shareholders, etc.) and 
this may affect the project. Doubts about the probability or nature of changes in the environment 
(socio-cultural trends, demographic changes) can lead to a number of environmental uncertainties 
[11], [16], [21], [29], [31], [32]. 
5.2.4. Socio-Human 
Although modern organizations have technological tools that can meet most needs and structural 
deficiencies, it alone is not enough to ensure the acquisition of individual and group knowledge. 
This is due to cognitive factors intrinsically related to how people perceive, learn, remember and 
think about information. Projects can be a unique way of helping organizational processes to 
change, innovate and adapt to competitive market reality. 
Human relations are often viewed as fuzzy in the management process. When misunderstood, 
they can lead to conflicts that can threaten project development, especially in technological 
innovation projects that present a high degree of complexity and uncertainty. This kind of 
challenge requires creativity and flexibility in project teams [31]. 
The socio-human source considers the relationships between people within an organization. It is 
necessary to consider religious issues, politics, different values, personal experiences and cultural 
training. Any of the mentioned factors can affect project performance and results. Project 
managers need to deal with social differences and avail themselves of each team member's 
particularity and their potential in order to assist in the project success everyone [26], [28], [30], 
[31]. 
5.3. How can you reduce the uncertainty level in software projects? 
This question aimed to investigate the possibility of reducing the uncertainty level in software 
projects. From 27 studies analyzed, 30 quotes were found and classified. There are 5 ways to 
manage uncertainties in projects identified by the research. They are: 9 approach adopting 
techniques and strategies to facilitate the uncertainties reduction; 8 address adapting management 
style to the projects type; 6 approach dealing with uncertainty when they happen; 5 approach 
understanding the uncertainty sources to better manage each type of project; 2 address identifying 
uncertainties in order to turn them into risks. 
5.3.1. Adopting techniques and strategies to facilitate the uncertainty reduction 
It is tempting to wish to eliminate all uncertainty, but the high levels of necessary resources even 
to get close to project goal are, in the most exceptional cases, unjustified. In fact, great efforts in 
the uncertainty sources eradication often divert attention from the real goals. Eradication is rarely 
the answer, it is more feasible to manage uncertainty within acceptable levels. This leads to 
another guiding principle for the uncertainty management: The objective is the uncertainty 
containment, not its elimination [13],[18], [22], [2], [23], [3], [29], [33]. 
Although there are no easy answers or fast solutions, we may say that uncertainty can be 
``tamed'', part of the answer lies in recognizing the nature of the problem and select the right
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
technique (or strategy) to work. Like any good craftsman, the project manager must have of a set 
of comprehensive tools for managing uncertainty and - equally important - a good knowledge of 
the capabilities and limitations of those tools [29]. For different types of problems, the manager 
and the team should have strategies, mindset and different paradigms [18]. 
14 
5.3.2. Adapting management style to the type of projects 
Many projects with all the ingredients for success still fail. The reason for this is that executives, 
project managers and the project teams are not used to assessing and analyzing uncertainties, so 
they fail to adapt their management style to the situation. Shenhar et al [34] affirms that “the same 
size does not fit all”, meaning that every project is unique, and that one must understand how they 
differ and take the proper actions according to the particular needs of the organization and the 
project. 
The authors described the importance of evaluating and analyzing a project’s uncertainties and 
complexities and so, adapting their management style to situation [31]. It is also addressed in 
some studies that projects fail because managers applied the wrong management style to the 
project [18]. It is important to point out that project managers cannot predict the future, but can 
perceive the uncertainty degree in their projects and choose an appropriate management style to 
use [10],[13]. 
5.3.3. Dealing with uncertainty when they happen 
Some uncertainty types cannot simply be solved through an analytical approach. Such as: a 
number of events, random combinations, may contribute to an unexpected result. Pharmaceutical 
companies have struggled with this problem. Despite extensive testing programme, there is 
always the risk of an unlikely combination of external factors (other drugs usually administered 
by the patient) to react causing harmful side effects [21], [22], [2], [3]. 
Project managers can try to contain uncertainty at its font but they can hardly ever have a hundred 
percent of success. Therefore, a project needs strength and should be able to rapidly detect and 
respond to unexpected events. A project manager must decide how best to cope with unexpected 
results [29],[31]. 
5.3.4. Understand the sources of uncertainty to better manage each type of project 
Uncertainty can arise from deficiencies in various sources, such as contextual information about 
the project, our understanding of underlying processes, past events explanations and speed (or 
time) change. We may ask where these factors happen within a project and what aspects of a 
project plan are particularly vulnerable to each uncertainty type. To answer those questions, first 
it is interesting to see the elements that make a typical project. Then, we need to examine what 
happens when the scale and complexity of the model increases. Thus, it is possible to choose 
styles and strategies to manage the project properly [11], [13], [22], [15], [2], [23], [31]. 
5.3.5. Identify uncertainties in order to turn it into risk 
Strategies can be used to contain the uncertainties. These strategies can help you learn more about 
the nature of uncertainty, for example, through the formulation of the problem that it represents or 
the modeling of future scenarios to prepare for them. Once an uncertainty is revealed, analytical 
techniques, such as risk management can be used in project management [11], [23].
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
5.4. What practices (techniques or strategies) can help reduce the uncertainties in 
project management software? 
This question sought to identify practices to support the software projects management that help 
reduce the uncertainties in innovative projects. Out of 73 quotas extracted for that matter, 18 
practices for managing projects focusing on reducing uncertainties were found. These practices 
are described below together with their references of studies that support each of them. We 
presented an evidence before the explanation. 
15 
5.4.1. Identifying the project type to adopt appropriate management 
“It is necessary to understand in what way projects are different from each other in order to suit 
the right situation to the particular project.”[31] 
To reduce the failure probability of a project it is important to characterize it properly, so 
knowing in advance if there is a related uncertainty to their goals and solutions adopting a 
management model that fits the project type. [9], [10],[18], [19], [2], [23], [3], [29], [27], [28], 
[31], [33]. 
5.4.2. Managing the stakeholders’ expectations so that they flexibly accept changes 
“With uncontrolled uncertainty, a lot of time and effort must go into managing relationships with 
stakeholders and getting them to accept and respond to unplanned changes.” [18] 
“A lot of time and effort must go into managing relationships with stakeholders and getting them 
to accept unplanned changes.”[13] 
Innovative projects can create high expectations for clients. You need to manage them, keeping 
clients informed and aware of the project uncertainties, as well as creating a bond of trust between 
project members and clients [13], [18], [19], [21], [23], [3], [24], [27], [33]. 
5.4.3. Ability to formulate qualitative measures of success 
“Ability to formulate qualitative success measures for projects is another tool that should be 
added to the project management armoury to assist in managing softer projects.”[19] 
Projects with low uncertainty can often be assessed through quantitative success measurement, 
such as time and cost, and tangible performance measurement related to their tangible final 
deliverables. Projects with high levels of uncertainty require different forms of performance 
evaluation that recognize the validity of different perspectives and worldviews [19], [2]. 
5.4.4. Identifying early warning signs to manage the uncertainties 
“to identify unforeseeable uncertainties is through the perception of early signs.”[33] 
The objective is to identify the cause of problems and the solutions for each early signal [22], [3], 
[28], [33]. 
5.4.5. Sensemaking 
“understanding and sensemaking affect strategic decisions, and consequently, performance of the 
firm.”[3] 
Sensemaking is the process by which organizations and individuals work out uncertainties, 
ambiguities, changes and problem situations generating inventions and new situations that end up 
in actions that lead to problem solution and environmental stability. [22], [3], [28], [33].
International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 
16 
5.4.6. Management flexibility and ability to respond to changes 
“Each manager tends to build his or her own's mental model of the project and its challenges, 
albeit based on his or her experience and professional judgement” [12] 
The flexibility and ability to communicate the changes is fundamental. Complex and uncertain 
projects changes require greater flexibility and reflection. The project manager and the team 
performance should change as the profile and the uncertainty evolve. [12], [13], [17], [20], [21], 
[2], [3], [31]. 
5.4.7. Managerial ability to perceive uncertainty and deal with them 
A preliminary observation of the areas of uncertainty can help project managers and teams to 
conduct a successful project.” [31] 
The ability the project manager should have to take reasonable decisions to ensure there is 
necessary support to get everyone involved in the project; they must have personal ability, such as 
intuition and trial to perceive uncertainties [18], [12], [13], [21], [3], [26], [31]. 
5.4.8. Team willing to learn and develop new ideas in order to generate knowledge 
“When enough new information arises, they must be willing to learn and then formulate new 
solutions.” [13] 
Crisis management and continuous observation of threats and/or opportunities must be controlled 
by the team . When new information arises, everyone should be willing to learn and then 
formulate new solutions [12], [13], [18], [3], [24], [31], [33]. 
5.4.9. The creation of flexible contracts 
“The manager’s job is to anticipate and soften resistance by creating flexible contracts and 
keeping stakeholders well informed” [13] 
Creating flexible contracts for innovative projects help mitigating resistance to changes necessary 
for the project. In order to keep project stakeholders well informed, it is obviously important to 
have a flexible contract [13],[33]. 
5.4.10. Building trust between team, management and customer 
“The relationship is characterized by trust.”[13] 
The relationship between clients, managers and teams is characterized by trust. Once it is 
conquered, helps facilitate the strategies change during the project [13],[21],[28]. 
5.4.11. Verify information outside environment of the project 
“Judging the source and relevance of information that comes from the outer project environment 
and, thus, represent contextual uncertainty is an intuitive process rather than a rational one, 
since the rational processes are isolated from the surrounding world.” [3] 
Relevant actions to organizations or groups within the organization (suppliers, competitors, 
consumers, government, shareholders, etc) can affect the product, as well as doubts about the 
likelihood or nature of changes in the environment general condition (socio-cultural trends, 
demographic changes) [3],[13], [2], [28], [31], [32]. 
5.4.12. Understanding the sources of uncertainties
International Journal of Software Engineering  Applications (IJSEA), Vol.5, No.6, November 2014 
“it is necessary to understand the areas of uncertainty in a project to be able to contribute to its 
success.” [31] 
Project management can be conducted focusing on solving the project uncertainties; for doing so, 
it is necessary to understand where the uncertainties of projects can arise, ie, what the possible 
sources of uncertainty are. Understanding the sources we may be able to make the necessary 
changes as the project progresses [14], [2], [31], [32]. 
17 
5.4.13. Project Managers must incorporate the investigation of uncertainties in projects 
“The use of uncertainty management within project management can be a determining factor in 
project success.” [31] 
Ongoing uncertainties investigation is important for projects members act in a proactive way and 
for the organization benefit strategically. The articles show that managerial knowledge aligned 
with research uncertainties may contribute to transformation of uncertainties in risk [20], [2], 
[31], [32], [33]. 
5.4.14. Learning method 
“learning strategies: give the project manager, and the organization as a whole, the ability to 
improve and benefit from experience over time.” [4] 
This is about experimentation and improvisation. The more we experience knowledge of a 
particular subject the more we reduce uncertainty. Improvisation itself can be a differentiator for 
innovative projects to deviate from uncertainties, leading to new goals [4],[18],[28],[33]. 
5.4.15. Creativity techniques 
“Encourage diversity and stimulate the creativity of empowered team members.” [18] 
Some articles suggest techniques to obtain knowledge such as: brainstorming, feasibility study, 
market research [18],[28],[33]. 
5.4.16. Managers should facilitate communication within the organization 
“Managers need to participate in and facilitate freeflowing communication and conversations 
which are absolutely critical to success.” [18] 
Some articles suggest that innovative projects with small teams and located in the same 
environment easily pass on the information received [13], [17], [18], [3]. 
5.4.17. Managers should facilitate self-organization and the team adaptability 
“The managers should facilitate evolutionary, double-loop learning, and facilitate self-organization, 
innovation, and adaptability” [18] 
They need to encourage diversity of thought and interaction, breaking organizational and 
hierarchical structures. The team need to adapt to changes and to interact getting feedback with 
market and technology providers constantly. The managerial focus should be on group dynamics 
to keep large project objectives in mind, instead of labor control [18], [28]. 
5.4.18. The Collaborative Work 
“The development team is collocated in a collaborative workspace” [24]
International Journal of Software Engineering  Applications (IJSEA), Vol.5, No.6, November 2014 
The democratic management style is best appropriated; very tight control might lead an 
innovative project clutter and the project vision become an illusion. Collaborative working is 
essential in projects with many uncertainties [18], [2], [24]. 
18 
6. CONCLUSIONS 
This paper presented a systematic review of uncertainties in project management software. 
Various approaches to project management does not consider the impact that uncertainty has on 
project management. The threats posed by uncertainty are real and immediate and the stakes in a 
project are often important. The project manager faces a dilemma: decisions must be made now 
about future situations that are inherently uncertain. The use of uncertainty management in 
project management can be a determining factor in the success of the project. 
This research aimed to contribute with to the uncertainties management in project management 
software, contribute to software engineering based on evidence. The paper presented a detailed 
process for conducting a systematic review of literature that can be followed by other researchers 
for other works. 
Finally, the results of this research contribute to the project management software in two ways. 
Firstly, the results of the systematic review provide to the academic community a better 
understanding of the challenges of dealing with uncertainties in project management and, thus, 
show gaps in the area that may be good opportunities for future research. Secondly, how to deal 
with the uncertainties, the techniques and strategies presented and sources of uncertainties that 
can support practitioners and researchers in identifying relevant challenges and developing 
solutions for projects, making use of the best practices that have been tested by other primary 
studies in experimental and industrial environments. 
ACKNOWLEDGEMENTS 
Authors would like to thank CAPES for supporting the development of this work as well as the 
reviewers. 
REFERENCES 
[1] “Standish group international,” 2013, [Online; accessed 02-Ago-2014].[Online]. Available: 
http://standishgroup.com 
[2] A. Shenhar and D. Dvir, Reinventing project management: the diamond approach to successful 
growth and innovation. Harvard Business Press,2007. 
[3] O. Perminova, M. Gustafsson, and K. Wikstr¨om, “Defining uncertainty in projects–a new 
perspective,” International Journal of Project Management, vol. 26, no. 1, pp. 73–79, 2008. 
[4] D. Cleden, Managing project uncertainty. Gower Publishing Company, 2009. 
[5] B. A. Kitchenham, T. Dyba, and M. Jorgensen, “Evidence-based software engineering,” in Software 
Engineering, 2004. ICSE 2004. Proceedings.26th International Conference on. IEEE, 2004, pp. 273– 
281. 
[6] B. J. Oates and G. Capper, “Using systematic reviews and evidence based software engineering with 
masters students,” in EASE, vol. 9, 2009, pp. 20–21. 
[7] B. Kitchenham, O. Pearl Brereton, D. Budgen, M. Turner, J. Bailey, and S. Linkman, “Systematic 
literature reviews in software engineering–a systematic literature review,” Information and software 
technology, vol. 51, no. 1, pp. 7–15, 2009. 
[8] B. Kitchenham, “Procedures for performing systematic reviews,” Keele,UK, Keele University, vol. 
33, p. 2004, 2004.
International Journal of Software Engineering  Applications (IJSEA), Vol.5, No.6, November 2014 
[9] A. J. Shenhar and D. Dvir, “Managing technology projects: a contingent exploratory approach,” in 
System Sciences, 1995. Proceedings of the Twenty-Eighth Hawaii International Conference on, vol. 
3. IEEE, 1995, pp. 494–503. 
[10] A. J. Shenhar and Z. Bonen, “The new taxonomy of systems: Toward an adaptive systems 
engineering framework,” Systems, Man and Cybernetics, Part A: Systems and Humans, IEEE 
Transactions on, vol. 27, no. 2, pp. 137–145, 1997. 
[11] M. V. Tatikonda and S. R. Rosenthal, “Technology novelty, project complexity, and product 
development project execution success: a deeper look at task uncertainty in product innovation,” 
Engineering Management, IEEE Transactions on, vol. 47, no. 1, pp. 74–87, 2000. 
[12] A. Jaafari, “Management of risks, uncertainties and opportunities on projects: time for a fundamental 
19 
shift,” International journal of project management, vol. 19, no. 2, pp. 89–101, 2001. 
[13] A. De Meyer, C. H. Loch, and M. T. Pich, “From variation to chaos,” MIT Sloan Management 
Review, vol. 43, pp. 60–7, 2002. 
[14] A. MacCormack and R. Verganti, “Managing the sources of uncertainty: Matching process and 
context in software development,” Journal of Product Innovation Management, vol. 20, no. 3, pp. 
217–232, 2003. 
[15] S. Ward and C. Chapman, “Transforming project risk management into project uncertainty 
management,” International Journal of Project Management, vol. 21, no. 2, pp. 97–105, 2003. 
[16] M. S. Freel, “Perceived environmental uncertainty and innovation in small firms,” Small Business 
Economics, vol. 25, no. 1, pp. 49–64, 2005. 
[17] T. Little, “Context-adaptive agility: managing complexity and uncertainty,” Software, IEEE, vol. 22, 
no. 3, pp. 28–35, 2005. 
[18] Y. Ren and K. Yeo, “Managing uncertainty in technology acquisition: the implications of complexity 
theory,” in Proceeding IEEE International, Engineering Management Conference, pp695-699, 
accessed, vol. 11, no. 07, 2005, p. 2011. 
[19] R. Atkinson, L. Crawford, and S. Ward, “Fundamental uncertainties in projects and the scope of 
project management,” International Journal of Project Management, vol. 24, no. 8, pp. 687–698, 
2006. 
[20] T. M. Chytka, B. A. Conway, and R. Unal, “An expert judgment approach for addressing uncertainty 
in high technology system design,” in Technology Management for the Global Future, 2006. PICMET 
2006, vol. 1. IEEE, 2006, pp. 444–449. 
[21] Q. Wang and J. Liu, “Project uncertainty, management practice and project performance: An 
empirical analysis on customized information systems development projects,” in Engineering 
Management Conference, 2006 IEEE International. IEEE, 2006, pp. 341–345. 
[22] C. Romito, D. Probert, and C. Farrukh, “Technology evaluation under information inadequacy,” in 
Management of Engineering and Technology, Portland International Center for. IEEE, 2007, pp. 
1672–1679. 
[23] C. H. Loch, M. E. Solt, and E. M. Bailey, “Diagnosing unforeseeable uncertainty in a new venture*,” 
Journal of Product Innovation Management, vol. 25, no. 1, pp. 28–46, 2008. 
[24] M. Levy and O. Hazzan, “Knowledge management in practice: the case of agile software 
development,” in Cooperative and Human Aspects on Software Engineering, 2009. CHASE’09. ICSE 
Workshop on. IEEE, 2009, pp. 60–65. 
[25] R. Sperry and A. Jetter, “Theoretical framework for managing the front end of innovation under 
uncertainty,” in Management of Engineering  Technology, 2009. PICMET 2009. Portland 
International Conference on. IEEE, 2009, pp. 2021–2028. 
[26] Y. Wang and F. Li, “How does project managers’ personality matter?: building the linkage between 
project managers’ personality and the success of software development projects,” in Proceedings of 
the 24th ACM SIGPLAN conference companion on Object oriented programming systems languages 
and applications. ACM, 2009, pp. 867–874. 
[27] C. H. Loch, A. DeMeyer, and M. T. Pich, Managing the unknown: A new approach to managing high 
uncertainty and risk in projects. John Wiley  Sons, 2011. 
[28] K. E. Weick and K. M. Sutcliffe, Managing the unexpected: Resilient performance in an age of 
uncertainty. John Wiley  Sons, 2011, vol. 8. 
[29] M. D. Cleden, Managing project uncertainty. Gower Publishing, Ltd., 2012. 
[30] W. Haider and A. Haider, Managing complexity in technology intensive projects. IEEE, 2012.
International Journal of Software Engineering  Applications (IJSEA), Vol.5, No.6, November 2014 
[31] M. Marinho, S. Sampaio, and H. Moura, “An approach related to uncertainty in software projects,” in 
Systems, Man, and Cybernetics (SMC), 2013 IEEE International Conference on. IEEE, 2013, pp. 
894–899. 
[32] G. C. O’Connor and M. P. Rice, “A comprehensive model of uncertainty associated with radical 
20 
innovation,” Journal of Product Innovation Management, vol. 30, no. S1, pp. 2–18, 2013. 
[33] R. d. F. S. M. Russo, R. Sbragia, and A. S. O. Yu, “Determining factors in the unforeseeable 
uncertainty management in innovation projects,” in Technology Management in the IT-Driven 
Services (PICMET), 2013 Proceedings of PICMET’13:. IEEE, 2013, pp. 623–634. 
[34] A. Shenhar, “One size does not fit all projects: Exploring classical contingency domains,” 
Management Science, pp. 394–414, 2001. 
[35] H. I. Ansoff, “Managing strategic surprise by response to weak signals.” California management 
review, vol. 18, no. 2, 1975. 
[36] I. O. Nikander and E. Eloranta, “Project management by early warnings,” International journal of 
project management, vol. 19, no. 7, pp. 385–399, 2001. 
[37] L. A. Kappelman, R. McKeeman, and L. Zhang, “Early warning signs of it project failure: The 
dominant dozen,” Information systems management, vol. 23, no. 4, pp. 31–36, 2006. 
[38] K. E. Weick and K. M. Sutcliffe, Managing the unexpected. Jossey-Bass San Francisco, 2001. 
[39] P. M. Institute, “A guide to the project management body of knowledge: PMBOK Guide.” Project 
Management Institute Newtown Square PA,USA, 2013. 
[40] T. Dyba, T. Dingsoyr, G. K. Hanssen, Applying systematic reviews to diverse study types: An 
experience report, in: Empirical Software Engineering and Measurement, 2007. ESEM 2007. First 
International Symposium on, IEEE, 2007, pp. 225–234. 
[41] S. Keele, Guidelines for performing systematic literature reviews in software engineering, Tech. rep., 
Technical report, EBSE Technical Report EBSE-2007-01 (2007). 
[42] B. J. Oates, G. Capper, Using systematic reviews and evidence-based software engineering with 
masters students, in: EASE, Vol. 9, 2009, pp.20–21. 
[43] G. H. Travassos, J. Biolchini, H. de Revisões Sistemáticas, Revisões sistemáticas aplicadas a 
engenharia de software, in: XXI SBES-Brazilian Symposium on Software Engineering, 2007. 
Authors 
Marcelo Marinho is currently assistant professor at Department of Informatics (DEINFO) at Federal Rural 
University of Pernambuco in Brazil (UFRPE). Conducts doctoral research at Informatics Center at Federal 
University of Pernambuco (CIn - UFPE). in Software Project Management area, where he investigates 
Uncertainty Management in Software Projects. He holds a Masters in Computer Science (CAPES Concept 
6) at University Federal of Pernambuco (UFPE) and graduated in Computer Science. He had been worked 
in the Software field for 10 years in which 6 with software project management. Besides, he has interest in 
the following lines of research: project management, software project management, strategic planning of 
information systems, software development process, IT management, software process and agile project. 
Suzana Sampaio has 17 years of experience on the software development industry, working for the last 9 
years as a consultant in process improvement, agile methodology and project management. She is currently 
a PhD candidate at Informatics’ Center at Federal University of Pernambuco (CIn-UFPE). Her 
research focuses on Software Project Management where she investigates software project actuality. Also 
works as an assistant professor at Department of Informatics (DEINFO) at Federal Rural University of 
Pernambuco in Brazil (UFRPE). She holds a Masters in Computer Science (CAPES Concept 6) at 
University Federal of Pernambuco (UFPE), on Software Development Productivity (2010) and graduated in 
Computer Science (2000). She is an ISO 9001:2008, ISO 29110 Lead Auditor, MR-MPS-SW and CMMI 
implementer and appraiser. Besides, she has interest in the following lines of research: project management, 
agile project management, process improvement and quality assurance. 
Telma Lima is lecturer at the Federal Rural University of Pernambuco (UFRPE), Brazil. She holds a 
Doctorate in Production Engineering from Federal University of Pernambuco (UFPE), Master in 
Production Engineering from UFPE and Bachelor in Mathematics from UFRPE, Brazil. She is currently 
acting as lecturer, teaching Decision Support Systems and Knowledge Management, and as researcher. Her 
research interests include negotiation, partnerships, innovation in new technologies, entrepreneurship,
International Journal of Software Engineering  Applications (IJSEA), Vol.5, No.6, November 2014 
21 
startups and knowledge management 
Hermano Moura is an Associate Professor and Prorector for Planning and Finance, Federal University of 
Pernambuco (Recife, Brazil). PhD in Computing Science (1993), University of Glasgow, Scotland. MSc in 
Computing Science (1989), Federal University of Pernambuco, Brazil. Electronic Engineer degree (1982) 
from Federal University of Pernambuco, Brazil. PMP – Project Management Professional (2003) by Project 
Management Institute. Research areas of interest includes: management of software projects; software 
process improvement; strategic planning of information systems. Acted as a consultant on various projects 
involving definition and implementation of processes for project management and software development.

More Related Content

PDF
A guide to deal with uncertainties in software project management
PDF
Credible Future Studies Methods
DOCX
IBDP internal Investigation Coverpage with recommended Headings and Guidance ...
PDF
Applying a Reverse Induction Process for Improved Definition of Higher Educat...
PDF
Business research methods pp ts 11
PDF
An Overview: Critical Factors Affecting The Success of Construction Project i...
PDF
Ms 94 2018 solved assignment
PPTX
Chapter 2.pptx
A guide to deal with uncertainties in software project management
Credible Future Studies Methods
IBDP internal Investigation Coverpage with recommended Headings and Guidance ...
Applying a Reverse Induction Process for Improved Definition of Higher Educat...
Business research methods pp ts 11
An Overview: Critical Factors Affecting The Success of Construction Project i...
Ms 94 2018 solved assignment
Chapter 2.pptx

What's hot (17)

PPTX
Botor_project_research_methodology_2016
PDF
Research Method EMBA chapter 5
PDF
Research Method for Business ch 1
PDF
A sample proposal with comment
PPTX
Health planning and management
PDF
Scientific Research Introduction | Steps to Conduct Scientific Research | Hal...
PPTX
Plan Evaluation & Implementation
PDF
Research Method for Business chapter # 2
PDF
Week02 reading lechler_plan_and_changing
PPSX
Insights from Program Evaluation for Retrospective Reviews of regulations
PPTX
Innovative Study Designs for Implementation Research
PPTX
Modern management techniques
PPTX
Business research method ppt 1
PDF
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
PDF
Research Method for Business chapter 4
PPTX
Business research
Botor_project_research_methodology_2016
Research Method EMBA chapter 5
Research Method for Business ch 1
A sample proposal with comment
Health planning and management
Scientific Research Introduction | Steps to Conduct Scientific Research | Hal...
Plan Evaluation & Implementation
Research Method for Business chapter # 2
Week02 reading lechler_plan_and_changing
Insights from Program Evaluation for Retrospective Reviews of regulations
Innovative Study Designs for Implementation Research
Modern management techniques
Business research method ppt 1
A REVIEW ON FACTORS INFLUENCING CONSTRUCTION PROJECT SCHEDULING
Research Method for Business chapter 4
Business research
Ad

Viewers also liked (20)

PDF
Meffortmob a effort size measurement
PDF
Transaction handling in com, ejb and .net
PDF
Adaptive guidance model based similarity for software process development pro...
PDF
4213ijsea02
PDF
Integrating profiling into mde compilers
PDF
THE UNIFIED APPROACH FOR ORGANIZATIONAL NETWORK VULNERABILITY ASSESSMENT
PDF
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
PDF
Automatically inferring structure correlated variable set for concurrent atom...
PDF
An empirical evaluation of impact of refactoring on internal and external mea...
PDF
High quality implementation for
PDF
Combining the analytical hierarchy
PDF
SOFTWARE ENGINEERING FOR TAGGING SOFTWARE
PDF
4213ijsea08
PDF
DETECTION AND REFACTORING OF BAD SMELL CAUSED BY LARGE SCALE
PDF
Dependence flow graph for analysis
PDF
4213ijsea09
PDF
Rankingtherefactoring techniques
PDF
Software testing strategy
PDF
SOCIO-DEMOGRAPHIC DIFFERENCES IN THE PERCEPTIONS OF LEARNING MANAGEMENT SYSTE...
PDF
Is fortran still relevant comparing fortran with java and c++
Meffortmob a effort size measurement
Transaction handling in com, ejb and .net
Adaptive guidance model based similarity for software process development pro...
4213ijsea02
Integrating profiling into mde compilers
THE UNIFIED APPROACH FOR ORGANIZATIONAL NETWORK VULNERABILITY ASSESSMENT
STATISTICAL ANALYSIS FOR PERFORMANCE COMPARISON
Automatically inferring structure correlated variable set for concurrent atom...
An empirical evaluation of impact of refactoring on internal and external mea...
High quality implementation for
Combining the analytical hierarchy
SOFTWARE ENGINEERING FOR TAGGING SOFTWARE
4213ijsea08
DETECTION AND REFACTORING OF BAD SMELL CAUSED BY LARGE SCALE
Dependence flow graph for analysis
4213ijsea09
Rankingtherefactoring techniques
Software testing strategy
SOCIO-DEMOGRAPHIC DIFFERENCES IN THE PERCEPTIONS OF LEARNING MANAGEMENT SYSTE...
Is fortran still relevant comparing fortran with java and c++
Ad

Similar to A systematic review of uncertainties in (20)

PDF
A SYSTEMATIC REVIEW OF UNCERTAINTIES IN SOFTWARE PROJECT MANAGEMENT
DOCX
CHAPTER NINETEENProject ReviewsSubbu MurthyTHE PURPOSE OF PR.docx
PDF
Software engineering
DOCX
NUR 350 Journal Guidelines and Rubric Journal ac.docx
PDF
How did Software Got So Reliable Without Proof?
PDF
How Did Software Get So Reliable Without Proof?
PDF
How to Manage innovation projects? Paper REPM 2018-Bilbao
PDF
An Evaluation Study of General Software Project Risk Basedon Software Practit...
PDF
An Evaluation Study of General Software Project Risk Basedon Software Practit...
PDF
Software Defect Prediction Using Local and Global Analysis
PDF
10120140503005
PDF
Defect effort prediction models in software
PDF
Defect effort prediction models in software maintenance projects
PDF
On Using Network Science in Mining Developers Collaboration in Software Engin...
PDF
On Using Network Science in Mining Developers Collaboration in Software Engin...
PPTX
Software engineering ppt it will be useful for the people
PDF
STATISTICAL ANALYSIS OF METRICS FOR SOFTWARE QUALITY IMPROVEMENT
PDF
Episode an extreme programming method for innovative software based on system...
PDF
Distributed Software Development Process, Initiatives and Key Factors: A Syst...
PDF
AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...
A SYSTEMATIC REVIEW OF UNCERTAINTIES IN SOFTWARE PROJECT MANAGEMENT
CHAPTER NINETEENProject ReviewsSubbu MurthyTHE PURPOSE OF PR.docx
Software engineering
NUR 350 Journal Guidelines and Rubric Journal ac.docx
How did Software Got So Reliable Without Proof?
How Did Software Get So Reliable Without Proof?
How to Manage innovation projects? Paper REPM 2018-Bilbao
An Evaluation Study of General Software Project Risk Basedon Software Practit...
An Evaluation Study of General Software Project Risk Basedon Software Practit...
Software Defect Prediction Using Local and Global Analysis
10120140503005
Defect effort prediction models in software
Defect effort prediction models in software maintenance projects
On Using Network Science in Mining Developers Collaboration in Software Engin...
On Using Network Science in Mining Developers Collaboration in Software Engin...
Software engineering ppt it will be useful for the people
STATISTICAL ANALYSIS OF METRICS FOR SOFTWARE QUALITY IMPROVEMENT
Episode an extreme programming method for innovative software based on system...
Distributed Software Development Process, Initiatives and Key Factors: A Syst...
AN EVALUATION STUDY OF GENERAL SOFTWARE PROJECT RISK BASEDON SOFTWARE PRACTIT...

Recently uploaded (20)

PPT
Mechanical Engineering MATERIALS Selection
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
PPT on Performance Review to get promotions
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPTX
Artificial Intelligence
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PDF
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
UNIT 4 Total Quality Management .pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Mechanical Engineering MATERIALS Selection
Internet of Things (IOT) - A guide to understanding
Model Code of Practice - Construction Work - 21102022 .pdf
PPT on Performance Review to get promotions
CH1 Production IntroductoryConcepts.pptx
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Foundation to blockchain - A guide to Blockchain Tech
Artificial Intelligence
R24 SURVEYING LAB MANUAL for civil enggi
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
CYBER-CRIMES AND SECURITY A guide to understanding
OOP with Java - Java Introduction (Basics)
Operating System & Kernel Study Guide-1 - converted.pdf
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Human-AI Collaboration: Balancing Agentic AI and Autonomy in Hybrid Systems
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
UNIT 4 Total Quality Management .pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...

A systematic review of uncertainties in

  • 1. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 A SYSTEMATIC REVIEW OF UNCERTAINTIES IN SOFTWARE PROJECT MANAGEMENT Marcelo Marinho1, 2 , Suzana Sampaio2, Telma Lima3 and Hermano de Moura1 1Informatics Center (CIn), Federal University of Pernambuco (UFPE), Recife, PE, Brazil 2Statistics and Informatics Department (DEINFO), Federal Rural University of Pernambuco (UFRPE), Recife, PE, Brazil 3Administration Department (DADM), Federal Rural University of Pernambuco (UFRPE), Recife, PE, Brazil ABSTRACT It is no secret that many projects fail, regardless of the business sector, software projects are notoriously disaster victims, not necessarily because of technological failure, but more often due to their uncertainties. The threats identified by uncertainty in day-to-day of a project are real and immediate and the stakes in a project are often high. This paper presents a systematic review about software project management uncertainties. It helps to identify the difficulties and the actions that can minimize the uncertainties effects in the projects and how managers and teams can prepare themselves for the challenges of their projects scenario, with the aim of contributing to the improvement of project management in organizations as well as contributing to project success. KEYWORDS Software Project Management; Systematic literature review; Uncertainties in Projects Management; Uncertainty in Software Projects 1. INTRODUCTION Project management has been discussed by executives and academics as one of the possibilities for organizations for integrating complex efforts and bureaucracy reduction. Managing projects effectively is introduced as a solution and as well as a major challenge for the business world. That is why both projects and project management have a highly important role in society and have been used as scientific research objects. Such subject is being applied in new industries, countries and spheres. Project management has become a core business process for a large number of companies both at strategic and operational level. We may call a project any activity that is considered significant and necessary and each major project can include a series of sub-projects. Once software development involves a certain level of complexity and challenges, the techniques use, practices and project management tools have become common in software engineering. Nowadays it is very common for companies to deal with software development or service as a temporary project which needs to be planned, organized, conducted, monitored and controlled. DOI : 10.5121/ijsea.2014.5601 1
  • 2. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 The Standish Group [1] reported that on average only 39% of projects are delivered on time, within budget and with the agreed requirements (therefore those projects perceived as successful). 43% are delivered late, and/or over budget and/or under certain conditions and finally, 18% are cancelled on delivery and never used. More than a decade later, very little seems to have changed. Projects are seen as a strategic factors in organizations, even though, many projects still fail. One of the main reasons for such outcome is that project managers do not know how to deal with uncertainties [2]. Moreover, in project risk management literature, there is no common understanding as to what uncertainty is [3]. The term uncertainty may be understood broadly as “lack of certainty”, which means information absence. Therefore, it covers not only probabilistic or indefinite results, but also an ambiguity and clarity lack concerning a large number of factors. Uncertainty is simply an ambiguity expression and project indeterminacy [4]. A systematic review discovers, evaluates and interprets all available research relating to the particular question. A systematic review aims to better understand and explore the topic, which is a planned and ideally repeatable way of synthesizing results from the existing body of scientific literature which has been prepared. The authors developed a systematic review of related studies in the period from 1994 to 2013 guided by the research questions. The research aims to investigate: The relation of the uncertainty level associated with innovation projects; what the best practices to manage the uncertainties in software projects are; what are the sources of uncertainty perceived by studies; and what practices (techniques or strategies) are used for the problem nature recognition and uncertainties containment in projects. Following the introductory section, this paper is structured as follows: Section 2 is about Evidence-based-Software Engineering; Section 3presents the research method adopted for this study; Section 4 describes a data analysis extracted from the selected studies; in Section 5 the results for each research question are presented and summarized and finally Section 6 contains the conclusion. 2. EVIDENCE-BASED SOFTWARE ENGINEERING Evidence-based software engineering aims to provide means by which the best evidence from research can be integrated with practical experience and human values in the decision-making process considering the development and software maintenance [7]. The essence of evidence-based paradigm is systematically collect and analyze all available data about a phenomenon for a 2 more comprehensive and broader perspective than one can capture through a single study. The paradigm based on evidence gained forces initially Medicine (Evidence-based Medicine/EBM), which aims to integrate the best research evidence with clinical experience and assessment of patients. Work kitchenham et al. [5] was the first to establish a parallel between Medicine and Engineering Software regarding to evidence-based approach. Kitchenham et al. [5] believe that software engineering can provide evidence-based mechanisms needed to help the professional to adopt appropriate technologies and avoid unsuitable ones, aiming the best practices and procedures. Some studies suggest that software engineering professionals (researchers) must consider the use of evidence-based software engineering support to improve their decisions about which technologies to adopt [5],[6],[7],[8],[40],[41].
  • 3. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 Software engineering based on evidence gathers and evaluates existing evidence in a technology through a five-step methodology. The steps 1, 2, 3 and 4 their evaluation (step 5) is done through a systematic review [40]: • Transforming the problem or need for information on a research question; • Search the literature for the better available evidence to answer questions; • Critically evaluate the evidence about its validity, impact and applicability; • Integrate the evaluated evidence with practical experiences, values and clients 3 circumstances to make decisions; • Evaluate the steps of 1 to 4 performance and search for ways to improve them. 2.1. Systematic Literature Review Systematic literature reviews evaluate evidence in a systematic and transparent way. In a traditional literature review, the research strategy and results evaluation criteria are usually hidden from the reader, which means that the revision may perfectly be done in an unstructured way, ad hoc and evidence that do not support the researcher's preferred hypothesis might be ignored. However, in a systematic literature review the research strategy and the evaluation criteria are explicit and all relevant evidence are included in the evaluation [5],[6],[7]. A systematic literature review “is a way of evaluating and interpreting all available research relating to a particular research question, topic area, or phenomenon of interest” [42]. Travassos [43] believes systematic reviews “provide the means to perform comprehensive literature review and not biased, giving their results have scientific value”. Kitchenham [5] adds that systematic reviews aim to present a fair assessment of a research topic using a reliable, accurate and auditable methodology. Kitchenham [5] e Travassos [43] present some of the reasons for conducting a systematic review: • Summarize existing evidence about a phenomenon; • Identify gaps in current research; • Provide a framework to position new research; and • Support the generation of new hypotheses. According to Kitchenham [5], his early studies were based on the guidelines used in the medical field, however it is important to recognize that software engineering research have large differences from medical research, so an approach that incorporates guidelines of social science researchers was added in their studies and more current recommendations. Kitchenham [5] summarizes the steps of a systematic review in three main phases: Planning the review, Conducting the revision and Presenting the revision. These steps are described below. 2.2. Planning a Systematic Review As in any scientific endeavor, a systematic review of the literature needs a detailed protocol describing the process and the methods to be applied. The most important activity during the planning phase is the formulation of research questions to be answered as all the other aspects of the review process depend on them [40]. To Kitchenham cite{kitchenham2004procedures}, before undertaking a systematic review researchers must ensure that it is necessary and the protocol should be able to answer some questions: • What are the objectives of this review? • What sources were searched to identify primary studies? Were there any restrictions? • What were the criteria for inclusion / exclusion and how they are applied?
  • 4. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 4 • What criteria were used to evaluate the quality of the primary studies? • How were the quality criteria applied? • How was the data extracted from primary studies? • How was the data synthesized? • What were the differences between studies investigated? • Because the data were combined? Through these and other questions, the researcher plans and documents all necessary information to carry out the systematic review. 2.3. Planning a Systematic Review Once the protocol has been defined and validated the review can begin. The primary studies selection, or else, the execution of the selection process defined in the protocol for the pursuit of studies and subsequently data extraction and evaluation are part of the implementation phase of the systematic review execution. For the studies selection, inclusion and exclusion criteria are used. The information extraction and evaluation are conducted through forms and may be supported by a software tool. The steps, according to Travassos [43], summarized for the review implementation are: • Searches in the defined sources: the process should be transparent, repeatable and documented, as well as the changes that occur in the process; • Primary studies selection with the inclusion and exclusion criteria defined; • Data extraction from general information studies to answers to the research questions. Forms are a good way to record all the necessary data and the use of a computational tool can support the data extraction and recording and subsequent analysis; • Assessing the studies quality is important to balance the importance of different studies, reduce bias (tendency to produce ``biased results'' that systematically separates from true results), maximize internal and external validity and guide recommendations for future research; • Data synthesis is performed according to the research questions, through tables to highlight the similarities and differences between studies. If quantitative data are available, making a meta-analysis can be considered. 2.4. Presenting the results The last step of a systematic review consists on writing a review report and its evaluation, according to the synthesis, and data analysis. Lately, the results are consistently presented with tabulated information and the research question, highlighting similarities and differences between the results, or else, highlighting the possible data combination and analyzes. 3. RESEARCH METHOD This section describes the research method according to Kitchenham methodological guideline for systematic reviews [8]. A systematic review protocol was written to describe the plan for the review. Details on the course of these steps are described in the following sub-sections. 3.2. Research questions These are research questions which guided the systematic review: • RQ 1: What is the relation between uncertainty and innovative projects? • RQ 2: What are the sources of uncertainty perceived? • RQ 3: How is it possible to reduce the uncertainty level in software projects?
  • 5. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 • RQ 4: What practices (techniques or strategies) can help reduce the uncertainties in 5 project management software? 3.2. Search environment A directory in the cloud was created before starting the research. A free web store service was used by the researchers to store all artifacts used. This enabled a total standardization and control, so all of them could access the material as if they were in the same environment, thought being remote. Furthermore, some datasheets were developed to be used in all phases. Those datasheets facilitated the data organization in many aspects; for example, a standard to enumerate searched publications, filters to extract objective information among others. 3.3. Generation of Search Strategy Aiming to identify and recover the smallest possible publications super group which meet the systematic review eligibility criteria, it incorporates a search strategy for a research. The eligibility criteria are conditions to determine if primary studies are about the systematic review research questions. The search results are transformed into in a sequential publication list of the chosen engines. Each resource has a different community, interests, language, examining issues and search syntaxes as well. Therefore, different resources might require different search strings. Next, we conducted initial studies for all phases of the major study, called “pilot studies”. These were performed to align a phase-to-phase understanding among researchers, all search engines mechanisms test and the adjust of some search terms. The study only proceed when the two researchers agreed with the pilot results. The resources used to searches are: IEEEXplore Digital Library (httt://ieeexplore.ieee.org/); ACM Digital Library (http://portal.acm.org); Elsevier ScienceDirect (www.sciencedirect.com); Springer Link (http://link.springer.com). Other sources were initially considered as potential for searches:Google, Google Scholar, Wiley InterScience, InspecDirect, Scopus and Scirus. However, these were later excluded from the final list of sources for some of the following reasons: • Some because they were not present in significant or systematic reviews or not having been recommended by experts; • Some for not allowing the viewing or downloading of the works without payment or license that the institution responsible for the work did not have; • Some because they were already indexed by some of the sources already listed in the search. To search all results from sources, the researchers grouped to search publications. The sources (engines) were divided among them. Each researcher was responsible to find results in their engine and, finally the papers were catalogued. Then, when the search was performed, there were identified 3,044 publications. The searches results were extracted in Bibtex files to merge in a datasheet developed to consolidate the results of all engines. After excluding duplicated results from the datasheet, we found 2,933 articles to start the first phase.
  • 6. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 6 3.4. Paper Selection The idealized selection process was done in two parts: an initial document selection of the research results that could reasonably satisfy the selection criteria based on a title and the articles abstract reading, followed by a final selection of the initially selected papers list that meet the pre-established criteria, based on the introduction and conclusion reading of the papers. To reduce potential bias, the process was conducted in pairs, in which both researchers worked individually on the inclusion or exclusion of the paper and then a comparison of spreadsheets was done. The possible divergence was discussed and finally a consensus was reached. If there was not a consensus, a third researcher should be consulted. In case doubts still remained, the work would be inserted in the list. In the pilot study performed before the first phase beginning, the first ten results from all engines were catalogued and the group read the titles and the abstracts and discussed about them to calibrate comprehension. Other pilot study was performed having more five publications done, because the researches were not ready to continue after the first pilot. After a reliability agreement, the first phase initiated. Each researcher read the publications` titles and abstracts to select or exclude them. They discussed about the results to gather them together according to a new datasheet agreement. Out of the initial selection of 2,933 papers, 111 articles were selected to the second phase. After the first and before second phase, a new pilot study was done. Then, we selected a single article to be read by researchers aiming a consensus for both. In this phase, the introduction and the conclusion should be read. Similarly to the first phase, each researcher read the articles individually and later discussed its results. After the phase two selection, the researches eliminated 88 and selected 23 papers out of 111 to be read for data extraction phase. 3.5. Study Quality Assessment In the data extraction phase, each publication methodological quality of was assessed. Three factors were assessed as follows, and each were marked yes or no: Does the publication mention the possibility of selection, publication, or experimenter bias?; Does the publication mention possible threats to internal validity? and Does the publication mention possible threats to external validity? The quality assessment was made only on the basis of whether the publication explicitly mentioned those issues. We did not make judgement about whether the publication had a “good” treatment of the issues. The results of the study quality assessment were not used to limit the selection of publications. 3.6. Data Extraction Beforehand, a new pilot was done to calibrate the stage. We selected two relevant articles and compared the extraction data performed so far with ours. Thus, a pitot was carried out with an article found with one of the 23 selected works. In the data extraction phase, researchers had to read the papers selected for extracting information according to the datasheet model. We had selected 23 works, but during the extraction phase we identified 2 articles that showed no relevant citations or possible reasons to be extracted, thus, there were 21 articles. For each publication there was extracted information.
  • 7. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 From each study, a list of shares was extracted, where each share described answered a research question. Or else, each simple sentence that answered one or more research question was considered a quota. We had a total of 165 quotas extracted from 21 studies. Finally, these shares were recorded on a datasheet. 7 3.7. Data Synthesis The two researchers worked on the synthesis work to generate combinations of quotas with answers of the research questions. There was a good level of inter-rater agreement, differences in opinion were discussed in a meeting, and it was easily solved without the need of involving a third arbitrating researcher, as planned. 4. SYSTEMATIC REVIEW RESULTS This section describes the analysis of the data extracted from our selected studies. Figure 1. Results obtained on each stage at systematic review process.
  • 8. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 8 4.1. Data Search In the Data Search phase the searches were conducted in four sources. The Figure 1 shows the results obtained on each stage at systematic review process. 4.2. Data Selection The Data Selection was divided in two phases: Phase 1: Title and Abstract analyses; and, Phase 2: Introduction and the Conclusion analyses. In Phase 1, after checking the titles and abstracts, 111 articles were selected for the next phase. A total of 2,822 articles were eliminated. Among the criteria used, we may highlight: “0 - Not applicable” (this is a research non related with management or uncertainties), with 52%; “Outside the uncertainties in project management area”, with 38% and “2 -It is about this risks in projects” with 10%. In Phase 2, after reading the introduction and conclusion, just 23 papers were selected for the extraction phase. A total of 88 articles were eliminated. Among the criteria used we highlight: “1- Outside the uncertainties in project management area” with 59% , “2 - It is about this risks in projects'' with 34%, followed by “0 - Not applicable”, with 7%. Table 1. List of engines and its absolute contributions. Engine Automatic Selection 1 Selection 2 Extraction ACM 548 10 2 2 IEEE 722 63 15 13 ScienceDirect 569 11 4 4 Springerlink 1094 27 2 2 Total 2933 111 23 21 4.3. Data Extraction and Quality Assessment In the Data Extraction and Quality Assessment each research read a full paper for the quotes extraction, at the same time they did the paper quality assessment. At the quality assessment phase three factors were assessed as follows, and were each researcher marked YES or NO: i) Does the publication discuss the possibility of selection, experimenter, or publication bias?; ii) Does the publication discuss threats to internal validity?; and, iii) Does the publication discuss threats to external validity? The quality assessment was made only on the basis of whether the publication itself mentions with these issues – we did not assess whether the publications had a treatment of these issues. Out of 23 works selected in the previous stage, the researchers worked with 21 articles. Two were eliminated for not answering the research questions. Additional studies were identified by search technique snowball, or else, covering the studies references already found. This technique allowed us to identify high-quality works that were not found by the automatic search. 6 works that contributed to the discussion were added to be held in Section 5. 6 works out of 4 are books and 2 are journals that are not indexed by engines the selected research. It is worth pointing out that some of the non-selected studies for extraction phase were considered so, because they confused risk with uncertainty. Note that although the risk and uncertainty are
  • 9. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 related, they are not the same thing. The uncertainty is the unknown, whereas risk is what can go wrong. Clearly, much of the risk of the project depends on the uncertainty, but there are other factors that contribute to the risk of the project, including deadlines, lack of resources and inadequate skills. Several of the articles report “uncertainties in the estimates” when in fact they are trying to estimate risks in the project process. 9 4.4. Data Synthesis Considering the studies evaluated in the extraction and adding the works found by snowball in the Synthesis phase 165 quotas were analyzed, in which 18 answer the first research question; 44 the second; 30 the third and 73 the last. Figure 2 represents the distribution of works by continent. The geographical distribution of the uncertainties related to studies in project management was as follows: The United States was ahead with 13 articles; England, with 3; Brazil, China and Singapore with 2; and Australia, Scotland, Philadelphia, Israel and Pakistan, with 1. We note that in the last 10 years it has been published 20 out of 27 of the papers included in the study. It demonstrates and confirms that research on uncertainties in project management have been growing since the last decade. Figure 3 illustrates the distribution of studies identified by selection process throughout the years. Figure 2. Distribution by continent. Figure 3. Distribution by years.
  • 10. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 10 Figure 4. Distribution by engines. Figure 5. Distribution by type of publication. Figure 4 shows the distribution of documents found by search engines and Figure 5 shows the distribution of jobs by type of publication, showing that most of the studies, 44%, were published in journals, following a 41% of the annals of events (Conferences, Workshops and symposia) and 15% in books. Figure 6 shows the papers`methodologies adopted. Table 2 displays a list with the number of studies returned by event. It can be noticed that most of the studies were published in some editions of the PICMET annals Portland International Conference on Management of Engineering and Technology, followed by the IJPM periodicals International journal of project management and the third, JPIM Journal of Product Innovation Management. Figure 6. Distribution by methodologies. 5. FINDINGS All evidence is properly referenced by 27 studies [9], [10], [11], [12], [13], [14], [15], [16], [17],[18], [19], [20], [21], [22], [2], [23], [3], [24], [25], [26], [27],[28], [29], [30], [31], [32], [33]. In this section, the results for each research question are presented. In Section 5.1 the evidence that the uncertainties become larger and larger as the project is more innovative are presented. In Section 5.2 sources of uncertainties are perceived in the studies. In Section 5.3 the evidences are presented about the possibility of reducing the uncertainties in software projects. In Section 5.4 evidences on how the techniques or strategies that favor uncertainties reduction in project management are presented.
  • 11. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 11 Table 2. List with the number of studies returned by event. Published in Amount Portland International Conference on Management of Engineering & 5 Technology International journal of project management 4 Books 4 Journal of Product Innovation Management 3 Engineering Management Conference 2 International Conference onSoftware Engineering -Workshop on Cooperative and Human Aspects on Software Engineering 1 IEEE International Conference on Systems, Man, and Cybernetics (SMC) 1 IEEE Software 1 IEEE Transactions on Engineering Management 1 IEEE Transactions on Systems, Man and Cybernetics 1 International Conference on System Sciences 1 MIT Sloan Management Review 1 Small Business Economics 1 SIGPLAN conference companion on object oriented programming 1 systems languages and applications 5.1. What is the relation between uncertainty and innovative projects? This question sought to investigate the relationship of the uncertainties with innovative projects and aspects of how we manage these projects. One of the findings is that the evidence report that innovative projects are more likely the occurrence of uncertainties. The following evidence of the studies is reported. Innovation and projects aimed at the innovation development, being them a new product, process or service, should be on the executive diary, along with the understanding of the business environment changes and the action plan needed to respond to these changes or influence them [31]. Various perspectives emerge from the literature to explain why companies have difficulty in managing the various sources of uncertainty associated with converting innovations in innovative companies. Understanding the innovative project characteristics and the uncertainty nature that permeates them is critical for developing appropriate management practices [32]. Each project has different characteristics, so the uncertainty level is varied. High-risk projects, typically innovation projects, which normally pursue ambitious goals and high failure probability, will have a high uncertainty capacity [4]. Low uncertainty projects typically create limited opportunities, whereas a project of high uncertainty will be evaluated primarily on their commercial effect and long-term, rather than measures of time and budget [34]. The largest uncertainty occurs in projects in which the company has no previous experience or existing project on which to build. On the contrary, the projects in which only a small amount from the existing project is changed, the uncertainty to the development teams is reduced [14].
  • 12. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 Where uncertainty about future events is high, tolerance of uncertainty may be particularly necessary [19]. Management practices that are effective in established companies are often ineffective and even destructive when applied to innovative projects because of high levels of uncertainty inherent in these projects [32]. Flexibility is required on projects where goals are unclear or open to negotiation, the strategy is emerging and the project is highly subject to external influences. Keeping options open, and adopt a flexible and robust management approach can be much more effective than prematurely freeze projects plans relying on conventional control mechanisms to measure performance [19]. Strategies, techniques, best practices are important to manage or contain the uncertainties in innovative projects. The recognition of the uncertainty sources in projects can be a determining factor in the success of the project. You need to clarify what can be done, decide what should be done, and to ensure that management is carried out based on the uncertainty level observed in the project. 12 5.2. What are the sources of uncertainty perceived? This question sought to investigate what the sources of perceived uncertainty in software projects are. From the 27 studies analyzed, 44 quotes was found. In the studies surveyed there is not a single label to the sources, it is common in some articles to speak from a particular source that is a single uncertainty, but classified differently, for example: market source [21], [17], [25], [22], [31], [32], external source [33] and novel source [11],[2] represent a single source of uncertainty. For doing so, we try to group the uncertainty and create a unique classification for these sources. Among those quotas found (they could cite more than one source, if they are in the same sentence), we find: 16 references to market uncertainty; 15 references to technological uncertainty; 14 for environment uncertainty and 9 for socio-human uncertainty. The following describes the sources of uncertainties grouped by research: 5.2.1. Market Market uncertainty indicates how news products are to the market, to consumers and to potential users. It represents the extent to which buyers and users are familiar with this type of product, its benefits and how they can use it. The level of market uncertainty indicates the external uncertainty, and also reflects the uncertainty of the project goal. It also indicates the easiness of knowing what to do or what to build and how to introduce consumers to the product. The market uncertainty comprehends client, suppliers, partners and current market situation [11],[13], [21], [17], [25], [22], [2], [29], [31], [32], [33]. 5.2.2. Technological Technological uncertainty depends on the extent to which the project uses new technology or mature technology. The level of project technological uncertainty is not universal, but subjective, and depends not only on what technology exists, but also what is accessible to the organization. It is therefore a measure of the amount of existing new technology compared to mature technology available for use in the project. The technological uncertainty causes, among other things, an impact in the project, in the communication, in the freezing time of the plan and the number of planning cycles. It can also affect the technical expertise that the project manager and their team members need to have [10], [11], [13], [16], [17], [21], [22],[25], [31], [32].
  • 13. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 13 5.2.3. Environment This source indicates the degree of uncertainty of the external and internal organizational environment. Organizational theories emphasize that organizations must adapt to their environment if they are to remain viable. Environmental uncertainty can arise from the actions of different organizations (suppliers, competitors, consumers, government, shareholders, etc.) and this may affect the project. Doubts about the probability or nature of changes in the environment (socio-cultural trends, demographic changes) can lead to a number of environmental uncertainties [11], [16], [21], [29], [31], [32]. 5.2.4. Socio-Human Although modern organizations have technological tools that can meet most needs and structural deficiencies, it alone is not enough to ensure the acquisition of individual and group knowledge. This is due to cognitive factors intrinsically related to how people perceive, learn, remember and think about information. Projects can be a unique way of helping organizational processes to change, innovate and adapt to competitive market reality. Human relations are often viewed as fuzzy in the management process. When misunderstood, they can lead to conflicts that can threaten project development, especially in technological innovation projects that present a high degree of complexity and uncertainty. This kind of challenge requires creativity and flexibility in project teams [31]. The socio-human source considers the relationships between people within an organization. It is necessary to consider religious issues, politics, different values, personal experiences and cultural training. Any of the mentioned factors can affect project performance and results. Project managers need to deal with social differences and avail themselves of each team member's particularity and their potential in order to assist in the project success everyone [26], [28], [30], [31]. 5.3. How can you reduce the uncertainty level in software projects? This question aimed to investigate the possibility of reducing the uncertainty level in software projects. From 27 studies analyzed, 30 quotes were found and classified. There are 5 ways to manage uncertainties in projects identified by the research. They are: 9 approach adopting techniques and strategies to facilitate the uncertainties reduction; 8 address adapting management style to the projects type; 6 approach dealing with uncertainty when they happen; 5 approach understanding the uncertainty sources to better manage each type of project; 2 address identifying uncertainties in order to turn them into risks. 5.3.1. Adopting techniques and strategies to facilitate the uncertainty reduction It is tempting to wish to eliminate all uncertainty, but the high levels of necessary resources even to get close to project goal are, in the most exceptional cases, unjustified. In fact, great efforts in the uncertainty sources eradication often divert attention from the real goals. Eradication is rarely the answer, it is more feasible to manage uncertainty within acceptable levels. This leads to another guiding principle for the uncertainty management: The objective is the uncertainty containment, not its elimination [13],[18], [22], [2], [23], [3], [29], [33]. Although there are no easy answers or fast solutions, we may say that uncertainty can be ``tamed'', part of the answer lies in recognizing the nature of the problem and select the right
  • 14. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 technique (or strategy) to work. Like any good craftsman, the project manager must have of a set of comprehensive tools for managing uncertainty and - equally important - a good knowledge of the capabilities and limitations of those tools [29]. For different types of problems, the manager and the team should have strategies, mindset and different paradigms [18]. 14 5.3.2. Adapting management style to the type of projects Many projects with all the ingredients for success still fail. The reason for this is that executives, project managers and the project teams are not used to assessing and analyzing uncertainties, so they fail to adapt their management style to the situation. Shenhar et al [34] affirms that “the same size does not fit all”, meaning that every project is unique, and that one must understand how they differ and take the proper actions according to the particular needs of the organization and the project. The authors described the importance of evaluating and analyzing a project’s uncertainties and complexities and so, adapting their management style to situation [31]. It is also addressed in some studies that projects fail because managers applied the wrong management style to the project [18]. It is important to point out that project managers cannot predict the future, but can perceive the uncertainty degree in their projects and choose an appropriate management style to use [10],[13]. 5.3.3. Dealing with uncertainty when they happen Some uncertainty types cannot simply be solved through an analytical approach. Such as: a number of events, random combinations, may contribute to an unexpected result. Pharmaceutical companies have struggled with this problem. Despite extensive testing programme, there is always the risk of an unlikely combination of external factors (other drugs usually administered by the patient) to react causing harmful side effects [21], [22], [2], [3]. Project managers can try to contain uncertainty at its font but they can hardly ever have a hundred percent of success. Therefore, a project needs strength and should be able to rapidly detect and respond to unexpected events. A project manager must decide how best to cope with unexpected results [29],[31]. 5.3.4. Understand the sources of uncertainty to better manage each type of project Uncertainty can arise from deficiencies in various sources, such as contextual information about the project, our understanding of underlying processes, past events explanations and speed (or time) change. We may ask where these factors happen within a project and what aspects of a project plan are particularly vulnerable to each uncertainty type. To answer those questions, first it is interesting to see the elements that make a typical project. Then, we need to examine what happens when the scale and complexity of the model increases. Thus, it is possible to choose styles and strategies to manage the project properly [11], [13], [22], [15], [2], [23], [31]. 5.3.5. Identify uncertainties in order to turn it into risk Strategies can be used to contain the uncertainties. These strategies can help you learn more about the nature of uncertainty, for example, through the formulation of the problem that it represents or the modeling of future scenarios to prepare for them. Once an uncertainty is revealed, analytical techniques, such as risk management can be used in project management [11], [23].
  • 15. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 5.4. What practices (techniques or strategies) can help reduce the uncertainties in project management software? This question sought to identify practices to support the software projects management that help reduce the uncertainties in innovative projects. Out of 73 quotas extracted for that matter, 18 practices for managing projects focusing on reducing uncertainties were found. These practices are described below together with their references of studies that support each of them. We presented an evidence before the explanation. 15 5.4.1. Identifying the project type to adopt appropriate management “It is necessary to understand in what way projects are different from each other in order to suit the right situation to the particular project.”[31] To reduce the failure probability of a project it is important to characterize it properly, so knowing in advance if there is a related uncertainty to their goals and solutions adopting a management model that fits the project type. [9], [10],[18], [19], [2], [23], [3], [29], [27], [28], [31], [33]. 5.4.2. Managing the stakeholders’ expectations so that they flexibly accept changes “With uncontrolled uncertainty, a lot of time and effort must go into managing relationships with stakeholders and getting them to accept and respond to unplanned changes.” [18] “A lot of time and effort must go into managing relationships with stakeholders and getting them to accept unplanned changes.”[13] Innovative projects can create high expectations for clients. You need to manage them, keeping clients informed and aware of the project uncertainties, as well as creating a bond of trust between project members and clients [13], [18], [19], [21], [23], [3], [24], [27], [33]. 5.4.3. Ability to formulate qualitative measures of success “Ability to formulate qualitative success measures for projects is another tool that should be added to the project management armoury to assist in managing softer projects.”[19] Projects with low uncertainty can often be assessed through quantitative success measurement, such as time and cost, and tangible performance measurement related to their tangible final deliverables. Projects with high levels of uncertainty require different forms of performance evaluation that recognize the validity of different perspectives and worldviews [19], [2]. 5.4.4. Identifying early warning signs to manage the uncertainties “to identify unforeseeable uncertainties is through the perception of early signs.”[33] The objective is to identify the cause of problems and the solutions for each early signal [22], [3], [28], [33]. 5.4.5. Sensemaking “understanding and sensemaking affect strategic decisions, and consequently, performance of the firm.”[3] Sensemaking is the process by which organizations and individuals work out uncertainties, ambiguities, changes and problem situations generating inventions and new situations that end up in actions that lead to problem solution and environmental stability. [22], [3], [28], [33].
  • 16. International Journal of Software Engineering & Applications (IJSEA), Vol.5, No.6, November 2014 16 5.4.6. Management flexibility and ability to respond to changes “Each manager tends to build his or her own's mental model of the project and its challenges, albeit based on his or her experience and professional judgement” [12] The flexibility and ability to communicate the changes is fundamental. Complex and uncertain projects changes require greater flexibility and reflection. The project manager and the team performance should change as the profile and the uncertainty evolve. [12], [13], [17], [20], [21], [2], [3], [31]. 5.4.7. Managerial ability to perceive uncertainty and deal with them A preliminary observation of the areas of uncertainty can help project managers and teams to conduct a successful project.” [31] The ability the project manager should have to take reasonable decisions to ensure there is necessary support to get everyone involved in the project; they must have personal ability, such as intuition and trial to perceive uncertainties [18], [12], [13], [21], [3], [26], [31]. 5.4.8. Team willing to learn and develop new ideas in order to generate knowledge “When enough new information arises, they must be willing to learn and then formulate new solutions.” [13] Crisis management and continuous observation of threats and/or opportunities must be controlled by the team . When new information arises, everyone should be willing to learn and then formulate new solutions [12], [13], [18], [3], [24], [31], [33]. 5.4.9. The creation of flexible contracts “The manager’s job is to anticipate and soften resistance by creating flexible contracts and keeping stakeholders well informed” [13] Creating flexible contracts for innovative projects help mitigating resistance to changes necessary for the project. In order to keep project stakeholders well informed, it is obviously important to have a flexible contract [13],[33]. 5.4.10. Building trust between team, management and customer “The relationship is characterized by trust.”[13] The relationship between clients, managers and teams is characterized by trust. Once it is conquered, helps facilitate the strategies change during the project [13],[21],[28]. 5.4.11. Verify information outside environment of the project “Judging the source and relevance of information that comes from the outer project environment and, thus, represent contextual uncertainty is an intuitive process rather than a rational one, since the rational processes are isolated from the surrounding world.” [3] Relevant actions to organizations or groups within the organization (suppliers, competitors, consumers, government, shareholders, etc) can affect the product, as well as doubts about the likelihood or nature of changes in the environment general condition (socio-cultural trends, demographic changes) [3],[13], [2], [28], [31], [32]. 5.4.12. Understanding the sources of uncertainties
  • 17. International Journal of Software Engineering Applications (IJSEA), Vol.5, No.6, November 2014 “it is necessary to understand the areas of uncertainty in a project to be able to contribute to its success.” [31] Project management can be conducted focusing on solving the project uncertainties; for doing so, it is necessary to understand where the uncertainties of projects can arise, ie, what the possible sources of uncertainty are. Understanding the sources we may be able to make the necessary changes as the project progresses [14], [2], [31], [32]. 17 5.4.13. Project Managers must incorporate the investigation of uncertainties in projects “The use of uncertainty management within project management can be a determining factor in project success.” [31] Ongoing uncertainties investigation is important for projects members act in a proactive way and for the organization benefit strategically. The articles show that managerial knowledge aligned with research uncertainties may contribute to transformation of uncertainties in risk [20], [2], [31], [32], [33]. 5.4.14. Learning method “learning strategies: give the project manager, and the organization as a whole, the ability to improve and benefit from experience over time.” [4] This is about experimentation and improvisation. The more we experience knowledge of a particular subject the more we reduce uncertainty. Improvisation itself can be a differentiator for innovative projects to deviate from uncertainties, leading to new goals [4],[18],[28],[33]. 5.4.15. Creativity techniques “Encourage diversity and stimulate the creativity of empowered team members.” [18] Some articles suggest techniques to obtain knowledge such as: brainstorming, feasibility study, market research [18],[28],[33]. 5.4.16. Managers should facilitate communication within the organization “Managers need to participate in and facilitate freeflowing communication and conversations which are absolutely critical to success.” [18] Some articles suggest that innovative projects with small teams and located in the same environment easily pass on the information received [13], [17], [18], [3]. 5.4.17. Managers should facilitate self-organization and the team adaptability “The managers should facilitate evolutionary, double-loop learning, and facilitate self-organization, innovation, and adaptability” [18] They need to encourage diversity of thought and interaction, breaking organizational and hierarchical structures. The team need to adapt to changes and to interact getting feedback with market and technology providers constantly. The managerial focus should be on group dynamics to keep large project objectives in mind, instead of labor control [18], [28]. 5.4.18. The Collaborative Work “The development team is collocated in a collaborative workspace” [24]
  • 18. International Journal of Software Engineering Applications (IJSEA), Vol.5, No.6, November 2014 The democratic management style is best appropriated; very tight control might lead an innovative project clutter and the project vision become an illusion. Collaborative working is essential in projects with many uncertainties [18], [2], [24]. 18 6. CONCLUSIONS This paper presented a systematic review of uncertainties in project management software. Various approaches to project management does not consider the impact that uncertainty has on project management. The threats posed by uncertainty are real and immediate and the stakes in a project are often important. The project manager faces a dilemma: decisions must be made now about future situations that are inherently uncertain. The use of uncertainty management in project management can be a determining factor in the success of the project. This research aimed to contribute with to the uncertainties management in project management software, contribute to software engineering based on evidence. The paper presented a detailed process for conducting a systematic review of literature that can be followed by other researchers for other works. Finally, the results of this research contribute to the project management software in two ways. Firstly, the results of the systematic review provide to the academic community a better understanding of the challenges of dealing with uncertainties in project management and, thus, show gaps in the area that may be good opportunities for future research. Secondly, how to deal with the uncertainties, the techniques and strategies presented and sources of uncertainties that can support practitioners and researchers in identifying relevant challenges and developing solutions for projects, making use of the best practices that have been tested by other primary studies in experimental and industrial environments. ACKNOWLEDGEMENTS Authors would like to thank CAPES for supporting the development of this work as well as the reviewers. REFERENCES [1] “Standish group international,” 2013, [Online; accessed 02-Ago-2014].[Online]. Available: http://standishgroup.com [2] A. Shenhar and D. Dvir, Reinventing project management: the diamond approach to successful growth and innovation. Harvard Business Press,2007. [3] O. Perminova, M. Gustafsson, and K. Wikstr¨om, “Defining uncertainty in projects–a new perspective,” International Journal of Project Management, vol. 26, no. 1, pp. 73–79, 2008. [4] D. Cleden, Managing project uncertainty. Gower Publishing Company, 2009. [5] B. A. Kitchenham, T. Dyba, and M. Jorgensen, “Evidence-based software engineering,” in Software Engineering, 2004. ICSE 2004. Proceedings.26th International Conference on. IEEE, 2004, pp. 273– 281. [6] B. J. Oates and G. Capper, “Using systematic reviews and evidence based software engineering with masters students,” in EASE, vol. 9, 2009, pp. 20–21. [7] B. Kitchenham, O. Pearl Brereton, D. Budgen, M. Turner, J. Bailey, and S. Linkman, “Systematic literature reviews in software engineering–a systematic literature review,” Information and software technology, vol. 51, no. 1, pp. 7–15, 2009. [8] B. Kitchenham, “Procedures for performing systematic reviews,” Keele,UK, Keele University, vol. 33, p. 2004, 2004.
  • 19. International Journal of Software Engineering Applications (IJSEA), Vol.5, No.6, November 2014 [9] A. J. Shenhar and D. Dvir, “Managing technology projects: a contingent exploratory approach,” in System Sciences, 1995. Proceedings of the Twenty-Eighth Hawaii International Conference on, vol. 3. IEEE, 1995, pp. 494–503. [10] A. J. Shenhar and Z. Bonen, “The new taxonomy of systems: Toward an adaptive systems engineering framework,” Systems, Man and Cybernetics, Part A: Systems and Humans, IEEE Transactions on, vol. 27, no. 2, pp. 137–145, 1997. [11] M. V. Tatikonda and S. R. Rosenthal, “Technology novelty, project complexity, and product development project execution success: a deeper look at task uncertainty in product innovation,” Engineering Management, IEEE Transactions on, vol. 47, no. 1, pp. 74–87, 2000. [12] A. Jaafari, “Management of risks, uncertainties and opportunities on projects: time for a fundamental 19 shift,” International journal of project management, vol. 19, no. 2, pp. 89–101, 2001. [13] A. De Meyer, C. H. Loch, and M. T. Pich, “From variation to chaos,” MIT Sloan Management Review, vol. 43, pp. 60–7, 2002. [14] A. MacCormack and R. Verganti, “Managing the sources of uncertainty: Matching process and context in software development,” Journal of Product Innovation Management, vol. 20, no. 3, pp. 217–232, 2003. [15] S. Ward and C. Chapman, “Transforming project risk management into project uncertainty management,” International Journal of Project Management, vol. 21, no. 2, pp. 97–105, 2003. [16] M. S. Freel, “Perceived environmental uncertainty and innovation in small firms,” Small Business Economics, vol. 25, no. 1, pp. 49–64, 2005. [17] T. Little, “Context-adaptive agility: managing complexity and uncertainty,” Software, IEEE, vol. 22, no. 3, pp. 28–35, 2005. [18] Y. Ren and K. Yeo, “Managing uncertainty in technology acquisition: the implications of complexity theory,” in Proceeding IEEE International, Engineering Management Conference, pp695-699, accessed, vol. 11, no. 07, 2005, p. 2011. [19] R. Atkinson, L. Crawford, and S. Ward, “Fundamental uncertainties in projects and the scope of project management,” International Journal of Project Management, vol. 24, no. 8, pp. 687–698, 2006. [20] T. M. Chytka, B. A. Conway, and R. Unal, “An expert judgment approach for addressing uncertainty in high technology system design,” in Technology Management for the Global Future, 2006. PICMET 2006, vol. 1. IEEE, 2006, pp. 444–449. [21] Q. Wang and J. Liu, “Project uncertainty, management practice and project performance: An empirical analysis on customized information systems development projects,” in Engineering Management Conference, 2006 IEEE International. IEEE, 2006, pp. 341–345. [22] C. Romito, D. Probert, and C. Farrukh, “Technology evaluation under information inadequacy,” in Management of Engineering and Technology, Portland International Center for. IEEE, 2007, pp. 1672–1679. [23] C. H. Loch, M. E. Solt, and E. M. Bailey, “Diagnosing unforeseeable uncertainty in a new venture*,” Journal of Product Innovation Management, vol. 25, no. 1, pp. 28–46, 2008. [24] M. Levy and O. Hazzan, “Knowledge management in practice: the case of agile software development,” in Cooperative and Human Aspects on Software Engineering, 2009. CHASE’09. ICSE Workshop on. IEEE, 2009, pp. 60–65. [25] R. Sperry and A. Jetter, “Theoretical framework for managing the front end of innovation under uncertainty,” in Management of Engineering Technology, 2009. PICMET 2009. Portland International Conference on. IEEE, 2009, pp. 2021–2028. [26] Y. Wang and F. Li, “How does project managers’ personality matter?: building the linkage between project managers’ personality and the success of software development projects,” in Proceedings of the 24th ACM SIGPLAN conference companion on Object oriented programming systems languages and applications. ACM, 2009, pp. 867–874. [27] C. H. Loch, A. DeMeyer, and M. T. Pich, Managing the unknown: A new approach to managing high uncertainty and risk in projects. John Wiley Sons, 2011. [28] K. E. Weick and K. M. Sutcliffe, Managing the unexpected: Resilient performance in an age of uncertainty. John Wiley Sons, 2011, vol. 8. [29] M. D. Cleden, Managing project uncertainty. Gower Publishing, Ltd., 2012. [30] W. Haider and A. Haider, Managing complexity in technology intensive projects. IEEE, 2012.
  • 20. International Journal of Software Engineering Applications (IJSEA), Vol.5, No.6, November 2014 [31] M. Marinho, S. Sampaio, and H. Moura, “An approach related to uncertainty in software projects,” in Systems, Man, and Cybernetics (SMC), 2013 IEEE International Conference on. IEEE, 2013, pp. 894–899. [32] G. C. O’Connor and M. P. Rice, “A comprehensive model of uncertainty associated with radical 20 innovation,” Journal of Product Innovation Management, vol. 30, no. S1, pp. 2–18, 2013. [33] R. d. F. S. M. Russo, R. Sbragia, and A. S. O. Yu, “Determining factors in the unforeseeable uncertainty management in innovation projects,” in Technology Management in the IT-Driven Services (PICMET), 2013 Proceedings of PICMET’13:. IEEE, 2013, pp. 623–634. [34] A. Shenhar, “One size does not fit all projects: Exploring classical contingency domains,” Management Science, pp. 394–414, 2001. [35] H. I. Ansoff, “Managing strategic surprise by response to weak signals.” California management review, vol. 18, no. 2, 1975. [36] I. O. Nikander and E. Eloranta, “Project management by early warnings,” International journal of project management, vol. 19, no. 7, pp. 385–399, 2001. [37] L. A. Kappelman, R. McKeeman, and L. Zhang, “Early warning signs of it project failure: The dominant dozen,” Information systems management, vol. 23, no. 4, pp. 31–36, 2006. [38] K. E. Weick and K. M. Sutcliffe, Managing the unexpected. Jossey-Bass San Francisco, 2001. [39] P. M. Institute, “A guide to the project management body of knowledge: PMBOK Guide.” Project Management Institute Newtown Square PA,USA, 2013. [40] T. Dyba, T. Dingsoyr, G. K. Hanssen, Applying systematic reviews to diverse study types: An experience report, in: Empirical Software Engineering and Measurement, 2007. ESEM 2007. First International Symposium on, IEEE, 2007, pp. 225–234. [41] S. Keele, Guidelines for performing systematic literature reviews in software engineering, Tech. rep., Technical report, EBSE Technical Report EBSE-2007-01 (2007). [42] B. J. Oates, G. Capper, Using systematic reviews and evidence-based software engineering with masters students, in: EASE, Vol. 9, 2009, pp.20–21. [43] G. H. Travassos, J. Biolchini, H. de Revisões Sistemáticas, Revisões sistemáticas aplicadas a engenharia de software, in: XXI SBES-Brazilian Symposium on Software Engineering, 2007. Authors Marcelo Marinho is currently assistant professor at Department of Informatics (DEINFO) at Federal Rural University of Pernambuco in Brazil (UFRPE). Conducts doctoral research at Informatics Center at Federal University of Pernambuco (CIn - UFPE). in Software Project Management area, where he investigates Uncertainty Management in Software Projects. He holds a Masters in Computer Science (CAPES Concept 6) at University Federal of Pernambuco (UFPE) and graduated in Computer Science. He had been worked in the Software field for 10 years in which 6 with software project management. Besides, he has interest in the following lines of research: project management, software project management, strategic planning of information systems, software development process, IT management, software process and agile project. Suzana Sampaio has 17 years of experience on the software development industry, working for the last 9 years as a consultant in process improvement, agile methodology and project management. She is currently a PhD candidate at Informatics’ Center at Federal University of Pernambuco (CIn-UFPE). Her research focuses on Software Project Management where she investigates software project actuality. Also works as an assistant professor at Department of Informatics (DEINFO) at Federal Rural University of Pernambuco in Brazil (UFRPE). She holds a Masters in Computer Science (CAPES Concept 6) at University Federal of Pernambuco (UFPE), on Software Development Productivity (2010) and graduated in Computer Science (2000). She is an ISO 9001:2008, ISO 29110 Lead Auditor, MR-MPS-SW and CMMI implementer and appraiser. Besides, she has interest in the following lines of research: project management, agile project management, process improvement and quality assurance. Telma Lima is lecturer at the Federal Rural University of Pernambuco (UFRPE), Brazil. She holds a Doctorate in Production Engineering from Federal University of Pernambuco (UFPE), Master in Production Engineering from UFPE and Bachelor in Mathematics from UFRPE, Brazil. She is currently acting as lecturer, teaching Decision Support Systems and Knowledge Management, and as researcher. Her research interests include negotiation, partnerships, innovation in new technologies, entrepreneurship,
  • 21. International Journal of Software Engineering Applications (IJSEA), Vol.5, No.6, November 2014 21 startups and knowledge management Hermano Moura is an Associate Professor and Prorector for Planning and Finance, Federal University of Pernambuco (Recife, Brazil). PhD in Computing Science (1993), University of Glasgow, Scotland. MSc in Computing Science (1989), Federal University of Pernambuco, Brazil. Electronic Engineer degree (1982) from Federal University of Pernambuco, Brazil. PMP – Project Management Professional (2003) by Project Management Institute. Research areas of interest includes: management of software projects; software process improvement; strategic planning of information systems. Acted as a consultant on various projects involving definition and implementation of processes for project management and software development.