Agile Capacity Management
Dale Feiste, Principal Consultant
Abstract
Waterfall and agile processes have been applied to software development for many years.
However, the same concepts can be applied to many other areas of business operation,
including general IT activities such as capacity management. Terms such as lean, scrum, sprint,
velocity, stories, etc. are used in agile development, and can be carried over into other areas
as well, where they fit. Where agile concepts do not fit well, a more conventional or hybrid
approach can be used. Underlying principles to improve efficiency is what should determine
the methods used.
Agile software development was formulated in 2001 by a group of developers who created
a manifesto based on their experience with software development. The manifesto contained
guiding principles the developers came to value in creating software. Mapping these concepts
over to other areas of business operation, where efficiency could be improved, was a natural
evolution. Primary factors for agile processes is that it be customer centric and fast. This paper
covers the idea of applying agile processes to the function of capacity management and real
experiences carrying out capacity management in a company that has embraced Scaled Agile
methodologies.
2Syncsort Confidential and Proprietary - do not copy or distribute
Contents
Agile processes from the beginning
Capacity management requirements
Mapping agile processes and executing them
Lessons learned
Future ideas
3Syncsort Confidential and Proprietary - do not copy or distribute
Agile processes from the beginning
Agile processes respond to
unpredictability through incremental,
iterative workflows and empirical
feedback. Agile processes can be an
alternative to waterfall, or traditional
sequential processes.
It advocates adaptive planning,
evolutionary creation, early
implementation, and continuous
improvement, and it encourages
rapid and flexible response to change.
4Syncsort Confidential and Proprietary - do not copy or distribute
Agile processes from the beginning
Agile methodologies provides opportunity
to assess the direction of value delivery
throughout the creation lifecycle.
Progress is achieved through periodic
iteration of work, known as sprints, at the
end of which team present a potentially
shippable functionality.
By focusing on repetition of abbreviated
work cycles, as well as functional output
produced, agile methodology can be
described as “iterative” and
“incremental.”
5Syncsort Confidential and Proprietary - do not copy or distribute
Agile processes from the beginning
A primary difference between agile methods and
other approaches, is that quality and value is
measured immediately after changes are made.
Because this happens in iterations, users of the
output can frequently use the new functionality
to validate value. After users know the real value
of the updated functionality, better decisions can
be made about what should be delivered in the
future.
Having retrospective sessions in each iteration,
Scrum typically has iterations of just two weeks,
helps the team continuously adapt its plans to
maximize the value it delivers.
6Syncsort Confidential and Proprietary - do not copy or distribute
Capacity management requirements
Mission
Ensuring the best use of the appropriate IT infrastructure to cost-
effectively meet the business needs both now and in the future
Understanding how IT services will be used and matching resources
to deliver services at agreed levels (SLAs) now and in the future
Syncsort Confidential and Proprietary - do not copy or distribute 7
Capacity management requirements
Key Task
Ensuring adequate capacity
Performance Monitoring
Tuning
Forecasting resource demands and service levels
Producing the Capacity Plan
8Syncsort Confidential and Proprietary - do not copy or distribute
Capacity management requirements
Objects
Ensure the right level of ITI investment
Identify and resolve bottlenecks
Evaluate tuning strategies
Improve and report/publish performance
“Right-size” or “consolidate”
Ensure accurate and timely procurements
Ensure effective service level management
Plan for workload growth, new apps / sites
Avoid performance disasters
9Syncsort Confidential and Proprietary - do not copy or distribute
Inputs OutputsSub-Process
Business
Service
Component
Technology
SLAs
Business Plans
Operations
Budgets…
Capacity Plan
SLA guidelines
Thresholds
Charging
Audits…
Inputs and Outputs
Capacity management requirements
10Syncsort Confidential and Proprietary - do not copy or distribute
Capacity management requirements
Inputs
Technology
SLAs, SLRs, and Service Catalogue
IT Plans and Strategy
Business Requirements and
Volumes
Operational Schedules
Deployment and Development
Plans
Forward Schedule of Changes
(Change Management)
11Syncsort Confidential and Proprietary - do not copy or distribute
Incidents and Problems
(Incident Management
and Change Management)
Service Reviews
SLA Breaches
Financial Plans
Budgets
Capacity management requirements
Outputs
Capacity Plan
Capacity Management Information System (CMIS)
Baselines and Profiles
Thresholds and Alarms
Capacity Reports (regular, ad-hoc, exception)
SLA and SLR recommendations
Costing and charging recommendations
Proactive changes and service improvements
Revised operational schedule
Effectiveness reviews
Audits
12Syncsort Confidential and Proprietary - do not copy or distribute
Activities
Business
Service
Component
Capacity
Plan
Capacity Management
Information System (CMIS)
Demand
Management
Modeling
Application
Sizing
Monitor
Analyze
Tune
Implement
Capacity management requirements
13Syncsort Confidential and Proprietary - do not copy or distribute
Service BusinessComponent
ServerUtilization
NetworkUtilization
ApplicationUsage
ServiceResponse
Transaction
volumes
ServiceLevel
Agreements
Businessforecasts
Businessstrategy
Facilities
Application Layer
Reporting
Service
Thresholds
Metric
Correlation
Analysis Tuning
Recommendations
Modeling
Planning
Capacity management information system (CMIS)
14Syncsort Confidential and Proprietary - do not copy or distribute
Waterfall Methodology ->
http://www.innovapptive.com/blog/wp-content/uploads/2013/10/agile_scrum_methodology.jpg
Mapping agile processes and executing them
15Syncsort Confidential and Proprietary - do not copy or distribute
Mapping agile processes and executing them
Scrum Roles
Product Owner
Scrum Master
Development Team
Scrum Activities and Artifacts
Product Backlog
Sprints
Sprint Planning
Sprint Execution
Daily Scrum
Sprint Review
Sprint Retrospective
16Syncsort Confidential and Proprietary - do not copy or distribute
 Scrum Storyboard
Scrum Burndown Chart 
Mapping agile processes and executing them
17Syncsort Confidential and Proprietary - do not copy or distribute
• Capacity Assurance
• Monitoring
• Tuning
• Forecasting
• Capacity Plans
Completing capacity management tasks with agile methodology follows the same
process as with other work, such as software development.
Product Backlog
Stories
• Capacity Plans
• CMIS
• Baselines
• Alarms
• Reports
• SLAs
• Recommendations
• Improvements
• Schedules
• Reviews
• Audits
Output
Mapping agile processes and executing them
18Syncsort Confidential and Proprietary - do not copy or distribute
http://www.scaledagileframework.com
Mapping agile processes and executing them - Scaled Agile
What is “Scaled Agile”?
Scaled Agile Framework (or SAFe) is an agile software development framework consisting of a
knowledge-base of integrated patterns intended for enterprise-scale Lean-Agile development.
Its proponents consider SAFe to be scalable and modular, allowing an organization to apply it
in a way that suits its need, including non-development areas like capacity management.
Before realizing SAFe rewards, organizations must embrace a Lean-Agile mindset, and
understand and apply Lean-Agile principles.
Achieving the business benefits of Lean-Agile processes at scale is not a trivial effort, and SAFe
is not a trivial framework.
19Syncsort Confidential and Proprietary - do not copy or distribute
Mapping agile processes and executing them - Scaled Agile
The Transition to Scaled Agile Framework
Went from project-driven to product-driven. Capacity Planning team merged with IT Facilities
and Monitoring to become Facilities, Capacity, Monitoring Service.
Infrastructure became service-oriented (Server, Storage, Middleware). No longer
Engineering/Operations split.
Essentially all of traditional IT switched to the Scaled Agile Framework (SAFe) as our new way
of working.
Individual Service/Product teams are using SCRUM or Kanban to track work.
Adoption rates vary across the organization.
20Syncsort Confidential and Proprietary - do not copy or distribute
Mapping agile processes and executing them - Scaled Agile
21Syncsort Confidential and Proprietary - do not copy or distribute
Lessons learned
Unplanned work.
Areas of the organization that are not using same methodology or iteration/sprint schedule
Data Centers/Power Infrastructure may not always be “agile”
Huge backlog
Silos can get worse
In something like Scrum/SAFe, the ceremonies and formalities might seem heavy and killing
efficiency.
22Syncsort Confidential and Proprietary - do not copy or distribute
Lessons learned
Rapidly changing capacity requirements or lack thereof
Planning away the ability to be curious
Cadence of short sprints and capacity reporting work well together
More visibility into what we provide the business
Learning/Training – plan, show the value, do
Better teamwork
Less trying to predict resource needs from waterfall style development and delivery
Watch out for your company being sold “agile as a product” and not doing things how it
works best for your organization.
23Syncsort Confidential and Proprietary - do not copy or distribute
Future ideas
Timeframes rarely allow for a large, all-encompassing enterprise plan
Plans live through ongoing/incremental work items
Respond to change
24Syncsort Confidential and Proprietary - do not copy or distribute
Future ideas
Still need long-term data; unless you don’t
The plan and results achieved are much more visible
Any formal plans need to be kept much more simple, as things are changing much
more rapidly
25Syncsort Confidential and Proprietary - do not copy or distribute
Thank you for attending
Agile Capacity Management
Questions or comments?

More Related Content

PPTX
PPTX
Agile Estimation & Capacity Planning
PDF
Agile 101
PPTX
SAFe SCRUMxp Overview
PPTX
Agile Roles & responsibilities
PPT
Scrum In 15 Minutes
PPTX
Estimation techniques for Scrum Teams
PDF
Agile Methodology
Agile Estimation & Capacity Planning
Agile 101
SAFe SCRUMxp Overview
Agile Roles & responsibilities
Scrum In 15 Minutes
Estimation techniques for Scrum Teams
Agile Methodology

What's hot (20)

PDF
Scrum - Sprint Planning
PDF
Agile Coaching Workshop
PPTX
Scrum In Ten Slides (v2.0) 2018
PPTX
Agile manifesto - Agile - What is it?
PPSX
Scrum Agile Methodlogy
PDF
20220607 Introduction to Flight Levels
PDF
Agile & Scrum Training
PPT
What Is A Sprint Planning Meeting
PDF
Scrum Events and Artifacts in Action
PPTX
Scrum for Beginners
PPTX
Scrum In Ten Slides
PDF
Scrum Guide In One Slide
PDF
PDF
Agile Process Introduction
PDF
Introduction To Scrum
PPTX
Scrum 101
PDF
Scrum 101: Introduction to Scrum
PDF
Prioritizing Your Product Backlog
PDF
Agile Risk Management
PDF
Agile Transformation at Scale
Scrum - Sprint Planning
Agile Coaching Workshop
Scrum In Ten Slides (v2.0) 2018
Agile manifesto - Agile - What is it?
Scrum Agile Methodlogy
20220607 Introduction to Flight Levels
Agile & Scrum Training
What Is A Sprint Planning Meeting
Scrum Events and Artifacts in Action
Scrum for Beginners
Scrum In Ten Slides
Scrum Guide In One Slide
Agile Process Introduction
Introduction To Scrum
Scrum 101
Scrum 101: Introduction to Scrum
Prioritizing Your Product Backlog
Agile Risk Management
Agile Transformation at Scale
Ad

Similar to Agile Capacity Management (20)

PPT
Agile at scale
PDF
Agile Chennai 30-31Aug 2024 | AI and Agile - Pioneering Adaptability for the ...
PDF
CONIG® v1.5 Converged Information Governance
PDF
Conig® v1.5 Converged Information Governance
PDF
Michigan Agile Presentation
PDF
Agile = scrum = no project managers
PPTX
Agile = scrum = no Project Managers!
DOCX
Agile methodology Interview Question Document File
PDF
Innovate agl 1601-case-study-rtc-sa-fe
PPTX
Scaled Agile Framework
PPT
Sap Implementation Presentation
PDF
Innovate session-2333
DOCX
Shawn Carlson Enterprise Transformation Leader CV
PPTX
Integrated Enterprise PPM, ALM and APM on force.com cloud
PPTX
Agile Development Process
PDF
Principle 11 needs to go! by Ken France at #AgileIndia2019
PDF
A Practical Guide to Scaling Agile
PDF
The Myriad faces of Agile Training & Certification
PDF
Managing Hard Times With Quality & Project Management
PDF
Solit 2014, Agile ValueTeam, учимся понимать Scrum, Семенченко Антон
Agile at scale
Agile Chennai 30-31Aug 2024 | AI and Agile - Pioneering Adaptability for the ...
CONIG® v1.5 Converged Information Governance
Conig® v1.5 Converged Information Governance
Michigan Agile Presentation
Agile = scrum = no project managers
Agile = scrum = no Project Managers!
Agile methodology Interview Question Document File
Innovate agl 1601-case-study-rtc-sa-fe
Scaled Agile Framework
Sap Implementation Presentation
Innovate session-2333
Shawn Carlson Enterprise Transformation Leader CV
Integrated Enterprise PPM, ALM and APM on force.com cloud
Agile Development Process
Principle 11 needs to go! by Ken France at #AgileIndia2019
A Practical Guide to Scaling Agile
The Myriad faces of Agile Training & Certification
Managing Hard Times With Quality & Project Management
Solit 2014, Agile ValueTeam, учимся понимать Scrum, Семенченко Антон
Ad

More from Precisely (20)

PDF
The Future of Automation: AI, APIs, and Cloud Modernization.pdf
PDF
Unlock new opportunities with location data.pdf
PDF
Reimagining Insurance: Connected Data for Confident Decisions.pdf
PDF
Introducing Syncsort™ Storage Management.pdf
PDF
Enable Enterprise-Ready Security on IBM i Systems.pdf
PDF
A Day in the Life of Location Data - Turning Where into How.pdf
PDF
Get More from Fiori Automation - What’s New, What Works, and What’s Next.pdf
PDF
Solving the CIO’s Dilemma: Speed, Scale, and Smarter SAP Modernization.pdf
PDF
Solving the Data Disconnect: Why Success Hinges on Pre-Linked Data.pdf
PDF
Cooking Up Clean Addresses - 3 Ways to Whip Messy Data into Shape.pdf
PDF
Building Confidence in AI & Analytics with High-Integrity Location Data.pdf
PDF
SAP Modernization Strategies for a Successful S/4HANA Journey.pdf
PDF
Precisely Demo Showcase: Powering ServiceNow Discovery with Precisely Ironstr...
PDF
The 2025 Guide on What's Next for Automation.pdf
PDF
Outdated Tech, Invisible Expenses – How Data Silos Undermine Operational Effi...
PDF
Modernización de SAP: Maximizando el Valor de su Migración a SAP S/4HANA.pdf
PDF
Outdated Tech, Invisible Expenses – The Hidden Cost of Disconnected Data Syst...
PDF
Migration vers SAP S/4HANA: Un levier stratégique pour votre transformation d...
PDF
Outdated Tech, Invisible Expenses: The Hidden Cost of Poor Data Integration o...
PDF
The Changing Compliance Landscape in 2025.pdf
The Future of Automation: AI, APIs, and Cloud Modernization.pdf
Unlock new opportunities with location data.pdf
Reimagining Insurance: Connected Data for Confident Decisions.pdf
Introducing Syncsort™ Storage Management.pdf
Enable Enterprise-Ready Security on IBM i Systems.pdf
A Day in the Life of Location Data - Turning Where into How.pdf
Get More from Fiori Automation - What’s New, What Works, and What’s Next.pdf
Solving the CIO’s Dilemma: Speed, Scale, and Smarter SAP Modernization.pdf
Solving the Data Disconnect: Why Success Hinges on Pre-Linked Data.pdf
Cooking Up Clean Addresses - 3 Ways to Whip Messy Data into Shape.pdf
Building Confidence in AI & Analytics with High-Integrity Location Data.pdf
SAP Modernization Strategies for a Successful S/4HANA Journey.pdf
Precisely Demo Showcase: Powering ServiceNow Discovery with Precisely Ironstr...
The 2025 Guide on What's Next for Automation.pdf
Outdated Tech, Invisible Expenses – How Data Silos Undermine Operational Effi...
Modernización de SAP: Maximizando el Valor de su Migración a SAP S/4HANA.pdf
Outdated Tech, Invisible Expenses – The Hidden Cost of Disconnected Data Syst...
Migration vers SAP S/4HANA: Un levier stratégique pour votre transformation d...
Outdated Tech, Invisible Expenses: The Hidden Cost of Poor Data Integration o...
The Changing Compliance Landscape in 2025.pdf

Recently uploaded (20)

PDF
Modernizing your data center with Dell and AMD
PDF
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
PDF
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
PDF
Agricultural_Statistics_at_a_Glance_2022_0.pdf
PDF
NewMind AI Weekly Chronicles - August'25 Week I
PPTX
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
PDF
Spectral efficient network and resource selection model in 5G networks
PPTX
Digital-Transformation-Roadmap-for-Companies.pptx
PDF
Building Integrated photovoltaic BIPV_UPV.pdf
PDF
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
PDF
Review of recent advances in non-invasive hemoglobin estimation
PDF
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
PDF
Per capita expenditure prediction using model stacking based on satellite ima...
PDF
Empathic Computing: Creating Shared Understanding
PDF
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
PPTX
20250228 LYD VKU AI Blended-Learning.pptx
PDF
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
PDF
Encapsulation_ Review paper, used for researhc scholars
PPTX
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
PPTX
A Presentation on Artificial Intelligence
Modernizing your data center with Dell and AMD
How UI/UX Design Impacts User Retention in Mobile Apps.pdf
Blue Purple Modern Animated Computer Science Presentation.pdf.pdf
Agricultural_Statistics_at_a_Glance_2022_0.pdf
NewMind AI Weekly Chronicles - August'25 Week I
Detection-First SIEM: Rule Types, Dashboards, and Threat-Informed Strategy
Spectral efficient network and resource selection model in 5G networks
Digital-Transformation-Roadmap-for-Companies.pptx
Building Integrated photovoltaic BIPV_UPV.pdf
Bridging biosciences and deep learning for revolutionary discoveries: a compr...
Review of recent advances in non-invasive hemoglobin estimation
7 ChatGPT Prompts to Help You Define Your Ideal Customer Profile.pdf
Per capita expenditure prediction using model stacking based on satellite ima...
Empathic Computing: Creating Shared Understanding
Build a system with the filesystem maintained by OSTree @ COSCUP 2025
20250228 LYD VKU AI Blended-Learning.pptx
Architecting across the Boundaries of two Complex Domains - Healthcare & Tech...
Encapsulation_ Review paper, used for researhc scholars
PA Analog/Digital System: The Backbone of Modern Surveillance and Communication
A Presentation on Artificial Intelligence

Agile Capacity Management

  • 1. Agile Capacity Management Dale Feiste, Principal Consultant
  • 2. Abstract Waterfall and agile processes have been applied to software development for many years. However, the same concepts can be applied to many other areas of business operation, including general IT activities such as capacity management. Terms such as lean, scrum, sprint, velocity, stories, etc. are used in agile development, and can be carried over into other areas as well, where they fit. Where agile concepts do not fit well, a more conventional or hybrid approach can be used. Underlying principles to improve efficiency is what should determine the methods used. Agile software development was formulated in 2001 by a group of developers who created a manifesto based on their experience with software development. The manifesto contained guiding principles the developers came to value in creating software. Mapping these concepts over to other areas of business operation, where efficiency could be improved, was a natural evolution. Primary factors for agile processes is that it be customer centric and fast. This paper covers the idea of applying agile processes to the function of capacity management and real experiences carrying out capacity management in a company that has embraced Scaled Agile methodologies. 2Syncsort Confidential and Proprietary - do not copy or distribute
  • 3. Contents Agile processes from the beginning Capacity management requirements Mapping agile processes and executing them Lessons learned Future ideas 3Syncsort Confidential and Proprietary - do not copy or distribute
  • 4. Agile processes from the beginning Agile processes respond to unpredictability through incremental, iterative workflows and empirical feedback. Agile processes can be an alternative to waterfall, or traditional sequential processes. It advocates adaptive planning, evolutionary creation, early implementation, and continuous improvement, and it encourages rapid and flexible response to change. 4Syncsort Confidential and Proprietary - do not copy or distribute
  • 5. Agile processes from the beginning Agile methodologies provides opportunity to assess the direction of value delivery throughout the creation lifecycle. Progress is achieved through periodic iteration of work, known as sprints, at the end of which team present a potentially shippable functionality. By focusing on repetition of abbreviated work cycles, as well as functional output produced, agile methodology can be described as “iterative” and “incremental.” 5Syncsort Confidential and Proprietary - do not copy or distribute
  • 6. Agile processes from the beginning A primary difference between agile methods and other approaches, is that quality and value is measured immediately after changes are made. Because this happens in iterations, users of the output can frequently use the new functionality to validate value. After users know the real value of the updated functionality, better decisions can be made about what should be delivered in the future. Having retrospective sessions in each iteration, Scrum typically has iterations of just two weeks, helps the team continuously adapt its plans to maximize the value it delivers. 6Syncsort Confidential and Proprietary - do not copy or distribute
  • 7. Capacity management requirements Mission Ensuring the best use of the appropriate IT infrastructure to cost- effectively meet the business needs both now and in the future Understanding how IT services will be used and matching resources to deliver services at agreed levels (SLAs) now and in the future Syncsort Confidential and Proprietary - do not copy or distribute 7
  • 8. Capacity management requirements Key Task Ensuring adequate capacity Performance Monitoring Tuning Forecasting resource demands and service levels Producing the Capacity Plan 8Syncsort Confidential and Proprietary - do not copy or distribute
  • 9. Capacity management requirements Objects Ensure the right level of ITI investment Identify and resolve bottlenecks Evaluate tuning strategies Improve and report/publish performance “Right-size” or “consolidate” Ensure accurate and timely procurements Ensure effective service level management Plan for workload growth, new apps / sites Avoid performance disasters 9Syncsort Confidential and Proprietary - do not copy or distribute
  • 10. Inputs OutputsSub-Process Business Service Component Technology SLAs Business Plans Operations Budgets… Capacity Plan SLA guidelines Thresholds Charging Audits… Inputs and Outputs Capacity management requirements 10Syncsort Confidential and Proprietary - do not copy or distribute
  • 11. Capacity management requirements Inputs Technology SLAs, SLRs, and Service Catalogue IT Plans and Strategy Business Requirements and Volumes Operational Schedules Deployment and Development Plans Forward Schedule of Changes (Change Management) 11Syncsort Confidential and Proprietary - do not copy or distribute Incidents and Problems (Incident Management and Change Management) Service Reviews SLA Breaches Financial Plans Budgets
  • 12. Capacity management requirements Outputs Capacity Plan Capacity Management Information System (CMIS) Baselines and Profiles Thresholds and Alarms Capacity Reports (regular, ad-hoc, exception) SLA and SLR recommendations Costing and charging recommendations Proactive changes and service improvements Revised operational schedule Effectiveness reviews Audits 12Syncsort Confidential and Proprietary - do not copy or distribute
  • 13. Activities Business Service Component Capacity Plan Capacity Management Information System (CMIS) Demand Management Modeling Application Sizing Monitor Analyze Tune Implement Capacity management requirements 13Syncsort Confidential and Proprietary - do not copy or distribute
  • 15. Waterfall Methodology -> http://www.innovapptive.com/blog/wp-content/uploads/2013/10/agile_scrum_methodology.jpg Mapping agile processes and executing them 15Syncsort Confidential and Proprietary - do not copy or distribute
  • 16. Mapping agile processes and executing them Scrum Roles Product Owner Scrum Master Development Team Scrum Activities and Artifacts Product Backlog Sprints Sprint Planning Sprint Execution Daily Scrum Sprint Review Sprint Retrospective 16Syncsort Confidential and Proprietary - do not copy or distribute
  • 17.  Scrum Storyboard Scrum Burndown Chart  Mapping agile processes and executing them 17Syncsort Confidential and Proprietary - do not copy or distribute
  • 18. • Capacity Assurance • Monitoring • Tuning • Forecasting • Capacity Plans Completing capacity management tasks with agile methodology follows the same process as with other work, such as software development. Product Backlog Stories • Capacity Plans • CMIS • Baselines • Alarms • Reports • SLAs • Recommendations • Improvements • Schedules • Reviews • Audits Output Mapping agile processes and executing them 18Syncsort Confidential and Proprietary - do not copy or distribute
  • 19. http://www.scaledagileframework.com Mapping agile processes and executing them - Scaled Agile What is “Scaled Agile”? Scaled Agile Framework (or SAFe) is an agile software development framework consisting of a knowledge-base of integrated patterns intended for enterprise-scale Lean-Agile development. Its proponents consider SAFe to be scalable and modular, allowing an organization to apply it in a way that suits its need, including non-development areas like capacity management. Before realizing SAFe rewards, organizations must embrace a Lean-Agile mindset, and understand and apply Lean-Agile principles. Achieving the business benefits of Lean-Agile processes at scale is not a trivial effort, and SAFe is not a trivial framework. 19Syncsort Confidential and Proprietary - do not copy or distribute
  • 20. Mapping agile processes and executing them - Scaled Agile The Transition to Scaled Agile Framework Went from project-driven to product-driven. Capacity Planning team merged with IT Facilities and Monitoring to become Facilities, Capacity, Monitoring Service. Infrastructure became service-oriented (Server, Storage, Middleware). No longer Engineering/Operations split. Essentially all of traditional IT switched to the Scaled Agile Framework (SAFe) as our new way of working. Individual Service/Product teams are using SCRUM or Kanban to track work. Adoption rates vary across the organization. 20Syncsort Confidential and Proprietary - do not copy or distribute
  • 21. Mapping agile processes and executing them - Scaled Agile 21Syncsort Confidential and Proprietary - do not copy or distribute
  • 22. Lessons learned Unplanned work. Areas of the organization that are not using same methodology or iteration/sprint schedule Data Centers/Power Infrastructure may not always be “agile” Huge backlog Silos can get worse In something like Scrum/SAFe, the ceremonies and formalities might seem heavy and killing efficiency. 22Syncsort Confidential and Proprietary - do not copy or distribute
  • 23. Lessons learned Rapidly changing capacity requirements or lack thereof Planning away the ability to be curious Cadence of short sprints and capacity reporting work well together More visibility into what we provide the business Learning/Training – plan, show the value, do Better teamwork Less trying to predict resource needs from waterfall style development and delivery Watch out for your company being sold “agile as a product” and not doing things how it works best for your organization. 23Syncsort Confidential and Proprietary - do not copy or distribute
  • 24. Future ideas Timeframes rarely allow for a large, all-encompassing enterprise plan Plans live through ongoing/incremental work items Respond to change 24Syncsort Confidential and Proprietary - do not copy or distribute
  • 25. Future ideas Still need long-term data; unless you don’t The plan and results achieved are much more visible Any formal plans need to be kept much more simple, as things are changing much more rapidly 25Syncsort Confidential and Proprietary - do not copy or distribute
  • 26. Thank you for attending Agile Capacity Management Questions or comments?