Process furnaces
• Process furnaces are widely used in petroleum
refineries and petrochemicals. These are also called
fired heaters.
• They generate heat by combustion of fuels and
transfer to process fluid which is in side coil.
• The heat duty can be few Thousand MW to few
Million MW.
• Process fluid in side coil may either liquid or gas .
pramod_dixit@yahoo.com 2
A typical application of Furnace
(Crude distillation unit)
3
pramod_dixit@yahoo.com
CDU (Crude distillation Unit) Heater
1. CDU heater is direct fired heater. It converts most of
the hydrocarbon fractions in to vapour phase which
are separated in distillation column.
2. No cracking or reaction takes place in this heater.
3. Flame radiation & hot flue gases of combustion
transfers heat & raise temperature of process fluid.
4. Every heater is tailored / designed for its specific
application.
4
pramod_dixit@yahoo.com
Reaction Heaters
1. In reaction heaters , these are filled with catalyst and
perform reaction inside tubes, besides heating.
2. These are called reaction heaters.
e.g. : Hydrogen reformer
Methanol heater
Catalytic reformers
5
pramod_dixit@yahoo.com
Reformer Heater
6
pramod_dixit@yahoo.com
Heater Performance objectives
• Maximize heat delivery to feed
• Minimal fuel consumption
• Flexibility of operation with varying fuel type/ quality and
also process flow variation in heater tubes.
• Easy to operate with safe start-up, operation and shut down.
• Minimize stack emissions (HC, Nox, Sox also hot flue gases)
• Achieve maximum thermal efficiency.
7
pramod_dixit@yahoo.com
Reasons to save Energy
• Energy costs 60 to 65% of a Refinery / process plant.
Highest energy requirement is in Furnaces .
• Cost of energy going up every day compels plant
operators to make use of waste Off –Gas or oil.
• In today ‘s scenario waste ( Off gases) usage is
maximized saving clean fuels like Natural gas or LPG.
• Due to waste gases of combustion, we have to be more
careful of environment pollution.
8
pramod_dixit@yahoo.com
Heater Types
(based on their shape & geometry)
1. Vertical cylindrical furnaces.
2. Box type with vertical tubes
3. Cabin furnaces with horizontal tubes.
4. Radiant wall furnaces.
5. Double fired furnaces
6. Multi cell
7. All convection
pramod_dixit@yahoo.com 9
Few Heaters geometry
pramod_dixit@yahoo.com 10
Heater Sections
• BottomRadiant Section : where Tubes directly see the burners /
radiant wall.
• Coils : Carry process feed to be heated
• ConvectionSection: Packed bundle of bare/ finned tubes
absorbing balance heat of flue gas before it is goes to stack.
• Cross Over Section: Section in-between the radiant & convection
• Stack: Finally dischargesfue gas to atmosphere
• Air Pre-heaters: Used to preheat the fresh air feed to burners by
exchanging with flue gases being discharged
All above sectionsare confinedin a Caron Steelbody structure
designedto take care of all operation,wind and seismic loads
11
pramod_dixit@yahoo.com
Heater
Sections
(TOP)
12
pramod_dixit@yahoo.com
Heater
Sections
(Bottom
)
13
pramod_dixit@yahoo.com
Radiant section
1. The radiant section is where the tubes receive
almost all its heat by radiation from the flame
2. The tubes are a distance away from the Refractory
so radiation can be reflected back to tubes to
maintain a uniform tube wall temperature.
3. Tubes are held at one end & guided at another
end to allow them to expand. These can not have
fixed ends.
14
pramod_dixit@yahoo.com
Convection section
1. Located above radiant section where Heat transfer takes
place by convection .
2. Tubes are studded or finned to increase heat transfer
surface area.
3. The first two tube rows in the bottom of the convection
section are bare tubes called shield or shock tubes. They
protect the finned tubes from direct radiation.
15
pramod_dixit@yahoo.com
Crossover section
1. A crossover is the tube that connects from the convection
section outlet to the radiant section inlet.
2. The crossover piping is normally located outside so that the
temperature can be monitored and the efficiency of the
convection section can be calculated.
16
pramod_dixit@yahoo.com
Radiant section- photo from in side
17
pramod_dixit@yahoo.com
Vertical Cylindrical heaters
1. Largecylindrical radiant
section.
2. Tubes are oriented vertically
and in a largecircle
3. Burners fire from the floor.
4. Coil may be vertical or
helical coil (radiant and
convection)
pramod_dixit@yahoo.com 18
Example of vertical cylindrical heater
Vertical Cylindrical with convection Vertical cylindrical with helical coil.
19
pramod_dixit@yahoo.com
Example of Box type heater
Horizontal tubes Horizontal tubes single row Double fired
20
pramod_dixit@yahoo.com
Vertical Cylindrical
( Radiant with convection)
1. Vertical hairpin coil in firebox, Horizontal
tubes in convection section
2. Symmetrical & uniform heat absorption
3. Burners in a circle on floor
4. Vertically up firing
5. General use for low heat duty.
– Low cost
– Size small
– Low foot print
– Easy construction
21
pramod_dixit@yahoo.com
Cabin Type Heaters
1. Large Heat duty 60 to 80 MW or more
2. Cabin heaters have sloped arch, usually rectangular
cross section
3. Horizontal Cabin - Large rectangular radiant section
oriented horizontally.
4. Burners : Generally fired from the floor or side
walls.
5. Tubes : May be vertical or horizontal in radiant
section.
6. Convection section : contain multiple horizontal
bank of tubes of single or multiple products.
pramod_dixit@yahoo.com 22
Cabin Furnace with Horizontal Tubes
1. The generally radiation section has
parallel tubes with the greatest
length being horizontal.
2. Tubes placed horizontally on the
longer side walls.
3. The burners are located on the
floor on the lower part of the
longer side walls or at end walls
pramod_dixit@yahoo.com 23
24
pramod_dixit@yahoo.com
Burners
25
pramod_dixit@yahoo.com
Burners
Burners are most important players in heater
performance. Placed in lower radiant section.
Flue gases travel vertically through :
1. Radiant section
2. Convection section
3. Air pre-heater if required
4. Finally through stack.
26
pramod_dixit@yahoo.com
Burners and its accessories
The combustion components include:
• Burner
• Fuel supply Piping
• Flame Safety Supervision & Control System.
• Burner management system
• Low Nox and staged burning is a preferred choice
27
pramod_dixit@yahoo.com
Burners placement & types
Burners positioning
1. Single or double side
2. Floor mounted up-fired
3. Roof mounted or down fired
4. End of side wall fired
5. Multi-level fired
28
pramod_dixit@yahoo.com
Positioning of burners
29
pramod_dixit@yahoo.com
A Combination Burner
• A combination burner is
selected if we need to
use both type of fuels
(Gas as well as liquid)
pramod_dixit@yahoo.com 30
Burner Control Panel
Consistsof :
– Burner managementsystems
– Single loop controllers
– Limit controllers
– NFPA & local regulation requirements.
– The control system provides a pre-purgeand post-purge of the
heater, automatic ignition, low flame start (high turn down
burner), continuous main flame detected by UV sensor.
– Control options !!!!!! virtually limitless !!!!!
31
pramod_dixit@yahoo.com
Role of air pre-heaters in furnace
32
pramod_dixit@yahoo.com
Air Pre-heaters
• The purpose of the air pre-
heater is to recover the heat
from the furnace flue gas.
• This increases the thermal
efficiency of the furnace by
reducing the useful heat lost
in the flue gas.
• This also reduces high
temperature discharge to
atmosphere
• Shown here is glass tube type
APH.
pramod_dixit@yahoo.com 33
Air flow scheme with APH system
pramod_dixit@yahoo.com 34
Furnace types based on DRAFTs
Once we have APH in the system, we need to have a
draft control on Flue gas flow.
1.Natural ( no APH possible in this case)
2.Forced
3.Induced
4.Balanced
A word of caution :
Flue gas discharge temperature to atmosphere
should be above DEW POINT, to avoid acid attack
by gas condensation. Which corrodes the stack.
35
pramod_dixit@yahoo.com
Industrial process furnaces- Forced draft
36
pramod_dixit@yahoo.com
Fuel used in heaters
• Refinery waste gas
• Natural gas
• Fuel Oil / waste oil
• Process combustible gases ( like H2 )
pramod_dixit@yahoo.com 37
Refractory & Insulation
• Since all heater parts are associated with heat , suitable
Refractory is required to protect all CABIN structure as
well as prevent heat loss to atmosphere.
• Refractory radiates back the heat to tubes
• Materials : Fire bricks, insulating & heat resistant cast able,
ceramic fibre etc .
• Ceramic fibre is light and easy to apply, used for roof & wall,
not used for oil fired burners in radiant zone.
38
pramod_dixit@yahoo.com
Applicable Codes for Fired heater design
• API 535 : guidelines for the selection and/or evaluation of burners
installed in fired heaters in general refinery services.
• API 538 : recommendations for design, operation, and maintenance
considerations for industrial fired boilers.
• API 560 : Fired Heaters for General Refinery Service,
recommendations for the design, materials, fabrication, inspection,
testing, preparation for shipment, and erection of fired heaters, air pre-
heaters (APHs), fans etc.
• API 573 : inspection practices for fired boilers and process heaters.
39
pramod_dixit@yahoo.com
Thank you
40
pramod_dixit@yahoo.com

More Related Content

PPT
FIRED HEATERS .ppt
PPTX
Introduction of Fired heaters
PDF
Fired Heater Operation and Trouble Shooting.pdf
PPTX
Heater operation
PPT
36512435-Fired-Heater-Design.ppt
PPTX
furnace design
PPTX
BOILER PROBLEMS
PPS
Basics Of Instrumentation
FIRED HEATERS .ppt
Introduction of Fired heaters
Fired Heater Operation and Trouble Shooting.pdf
Heater operation
36512435-Fired-Heater-Design.ppt
furnace design
BOILER PROBLEMS
Basics Of Instrumentation

What's hot (20)

PDF
Start Up Procedures for Primary Reforming Catalyst
PDF
Shift Conversion Catalysts - Operating Manual
PDF
Steam Reforming - Common Problems
PDF
Principles of Pre-reforming Technology
PDF
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
PDF
Air Cooled Heat Exchanger Design
PDF
Steam Reforming - Practical Operations
PPTX
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
PDF
Steam Reforming - Types of Reformer Design
PDF
AIR COOLED HEAT EXCHANGER
PDF
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
PDF
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
PPT
Benfield system
PDF
Theory and Operation - Secondary Reformers -
PDF
Definition and selection of design temperature and pressure prg.gg.gen.0001
PDF
Steam Reforming - A Comprehensive Review
PDF
Ammonia CO2 Removal Systems
PDF
Catalyst Catastrophes in Syngas Production - II
PDF
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
PDF
Reduction and Start-Up of Steam Reforming Catalyst
Start Up Procedures for Primary Reforming Catalyst
Shift Conversion Catalysts - Operating Manual
Steam Reforming - Common Problems
Principles of Pre-reforming Technology
Fired Heaters-Key to Efficient Operation of Refineries and Petrochemicals
Air Cooled Heat Exchanger Design
Steam Reforming - Practical Operations
AIChE Smart Stack Damper Design Provides Better Control of Fired Heaters
Steam Reforming - Types of Reformer Design
AIR COOLED HEAT EXCHANGER
Steam Reformer Surveys - Techniques for Optimization of Primary Reformer Oper...
101 Things That Can Go Wrong on a Primary Reformer - Best Practices Guide
Benfield system
Theory and Operation - Secondary Reformers -
Definition and selection of design temperature and pressure prg.gg.gen.0001
Steam Reforming - A Comprehensive Review
Ammonia CO2 Removal Systems
Catalyst Catastrophes in Syngas Production - II
Amine Gas Treating Unit - Best Practices - Troubleshooting Guide
Reduction and Start-Up of Steam Reforming Catalyst
Ad

Similar to An introduction to Fired Heaters.pdf (20)

PDF
Different Types of Boilers and it's terminology,
PPTX
Furnaces design performance operation.pptx
DOCX
PDF
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
PPTX
Government polytechnic Process Engineering.pptx
PPT
Coalfiredelectricpowerplants23 131208122612-phpapp01
PPTX
Waste heat recovery
PDF
Thermal power plant
PDF
Improve fired heaters performance and reliabilty
PPT
Heat emitters
PPTX
Unit 2
PPTX
Understanding Industrial Heater-Aeliya Marine Tech
PPTX
THERMAL-POWER-PLANT-plant new spt-1.pptx
PPT
presentation report on steam boiler
PPT
Unit-1-Coal Based Thermal Power Plants.ppt
PPTX
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
PPTX
471771292-17-THERMAL-POWER-PLANT-ppt-1.pptx
PPT
Coal fired electric power plants23
PPTX
Gas Power Plant for Power Generation System
PPT
FIRED HEATERS.ppt
Different Types of Boilers and it's terminology,
Furnaces design performance operation.pptx
Process Heaters, Furnaces and Fired Heaters: Improving Efficiency and Reducin...
Government polytechnic Process Engineering.pptx
Coalfiredelectricpowerplants23 131208122612-phpapp01
Waste heat recovery
Thermal power plant
Improve fired heaters performance and reliabilty
Heat emitters
Unit 2
Understanding Industrial Heater-Aeliya Marine Tech
THERMAL-POWER-PLANT-plant new spt-1.pptx
presentation report on steam boiler
Unit-1-Coal Based Thermal Power Plants.ppt
firedheateroperationandtroubleshooting-220910180339-c7fe10c5 (1).pptx
471771292-17-THERMAL-POWER-PLANT-ppt-1.pptx
Coal fired electric power plants23
Gas Power Plant for Power Generation System
FIRED HEATERS.ppt
Ad

More from Karnav Rana (20)

PDF
40 DUTIES OF A SAFETY OFFICER.pdf
PDF
5S Introduction .pdf
PDF
cooling towers system .pdf
PDF
pump calculation pdf .pdf
PDF
ETP.pdf
PDF
PTW.pdf
PDF
Rotating equipment maintenance .pdf
PDF
Steam traps
PDF
Steam ejector working principle
PDF
Rules of thumb for process engineer
PDF
Pid symbols
PDF
Permit to work training
PDF
Heat exchangers
PDF
Floating head heat exchanger components & maintenance
PDF
Centrifugal pump formula
PPTX
Basics hazard-communication
PPTX
Risk Management and Safety
PPT
carbon cycle
PPT
ideal reactors
PPT
Nutrient cycles
40 DUTIES OF A SAFETY OFFICER.pdf
5S Introduction .pdf
cooling towers system .pdf
pump calculation pdf .pdf
ETP.pdf
PTW.pdf
Rotating equipment maintenance .pdf
Steam traps
Steam ejector working principle
Rules of thumb for process engineer
Pid symbols
Permit to work training
Heat exchangers
Floating head heat exchanger components & maintenance
Centrifugal pump formula
Basics hazard-communication
Risk Management and Safety
carbon cycle
ideal reactors
Nutrient cycles

Recently uploaded (20)

PPTX
Internet of Things (IOT) - A guide to understanding
PPTX
Construction Project Organization Group 2.pptx
PPT
Mechanical Engineering MATERIALS Selection
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
additive manufacturing of ss316l using mig welding
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PPTX
Artificial Intelligence
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
Well-logging-methods_new................
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPT
Total quality management ppt for engineering students
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Internet of Things (IOT) - A guide to understanding
Construction Project Organization Group 2.pptx
Mechanical Engineering MATERIALS Selection
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
R24 SURVEYING LAB MANUAL for civil enggi
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
additive manufacturing of ss316l using mig welding
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
Safety Seminar civil to be ensured for safe working.
UNIT 4 Total Quality Management .pptx
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
UNIT-1 - COAL BASED THERMAL POWER PLANTS
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Artificial Intelligence
Fundamentals of Mechanical Engineering.pptx
Well-logging-methods_new................
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Total quality management ppt for engineering students
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...

An introduction to Fired Heaters.pdf

  • 1. Furnaces in Refinery and Petrochemicals - an Introduction pramod_dixit@yahoo.com 1
  • 2. Process furnaces • Process furnaces are widely used in petroleum refineries and petrochemicals. These are also called fired heaters. • They generate heat by combustion of fuels and transfer to process fluid which is in side coil. • The heat duty can be few Thousand MW to few Million MW. • Process fluid in side coil may either liquid or gas . pramod_dixit@yahoo.com 2
  • 3. A typical application of Furnace (Crude distillation unit) 3 pramod_dixit@yahoo.com
  • 4. CDU (Crude distillation Unit) Heater 1. CDU heater is direct fired heater. It converts most of the hydrocarbon fractions in to vapour phase which are separated in distillation column. 2. No cracking or reaction takes place in this heater. 3. Flame radiation & hot flue gases of combustion transfers heat & raise temperature of process fluid. 4. Every heater is tailored / designed for its specific application. 4 pramod_dixit@yahoo.com
  • 5. Reaction Heaters 1. In reaction heaters , these are filled with catalyst and perform reaction inside tubes, besides heating. 2. These are called reaction heaters. e.g. : Hydrogen reformer Methanol heater Catalytic reformers 5 pramod_dixit@yahoo.com
  • 7. Heater Performance objectives • Maximize heat delivery to feed • Minimal fuel consumption • Flexibility of operation with varying fuel type/ quality and also process flow variation in heater tubes. • Easy to operate with safe start-up, operation and shut down. • Minimize stack emissions (HC, Nox, Sox also hot flue gases) • Achieve maximum thermal efficiency. 7 pramod_dixit@yahoo.com
  • 8. Reasons to save Energy • Energy costs 60 to 65% of a Refinery / process plant. Highest energy requirement is in Furnaces . • Cost of energy going up every day compels plant operators to make use of waste Off –Gas or oil. • In today ‘s scenario waste ( Off gases) usage is maximized saving clean fuels like Natural gas or LPG. • Due to waste gases of combustion, we have to be more careful of environment pollution. 8 pramod_dixit@yahoo.com
  • 9. Heater Types (based on their shape & geometry) 1. Vertical cylindrical furnaces. 2. Box type with vertical tubes 3. Cabin furnaces with horizontal tubes. 4. Radiant wall furnaces. 5. Double fired furnaces 6. Multi cell 7. All convection pramod_dixit@yahoo.com 9
  • 11. Heater Sections • BottomRadiant Section : where Tubes directly see the burners / radiant wall. • Coils : Carry process feed to be heated • ConvectionSection: Packed bundle of bare/ finned tubes absorbing balance heat of flue gas before it is goes to stack. • Cross Over Section: Section in-between the radiant & convection • Stack: Finally dischargesfue gas to atmosphere • Air Pre-heaters: Used to preheat the fresh air feed to burners by exchanging with flue gases being discharged All above sectionsare confinedin a Caron Steelbody structure designedto take care of all operation,wind and seismic loads 11 pramod_dixit@yahoo.com
  • 14. Radiant section 1. The radiant section is where the tubes receive almost all its heat by radiation from the flame 2. The tubes are a distance away from the Refractory so radiation can be reflected back to tubes to maintain a uniform tube wall temperature. 3. Tubes are held at one end & guided at another end to allow them to expand. These can not have fixed ends. 14 pramod_dixit@yahoo.com
  • 15. Convection section 1. Located above radiant section where Heat transfer takes place by convection . 2. Tubes are studded or finned to increase heat transfer surface area. 3. The first two tube rows in the bottom of the convection section are bare tubes called shield or shock tubes. They protect the finned tubes from direct radiation. 15 pramod_dixit@yahoo.com
  • 16. Crossover section 1. A crossover is the tube that connects from the convection section outlet to the radiant section inlet. 2. The crossover piping is normally located outside so that the temperature can be monitored and the efficiency of the convection section can be calculated. 16 pramod_dixit@yahoo.com
  • 17. Radiant section- photo from in side 17 pramod_dixit@yahoo.com
  • 18. Vertical Cylindrical heaters 1. Largecylindrical radiant section. 2. Tubes are oriented vertically and in a largecircle 3. Burners fire from the floor. 4. Coil may be vertical or helical coil (radiant and convection) pramod_dixit@yahoo.com 18
  • 19. Example of vertical cylindrical heater Vertical Cylindrical with convection Vertical cylindrical with helical coil. 19 pramod_dixit@yahoo.com
  • 20. Example of Box type heater Horizontal tubes Horizontal tubes single row Double fired 20 pramod_dixit@yahoo.com
  • 21. Vertical Cylindrical ( Radiant with convection) 1. Vertical hairpin coil in firebox, Horizontal tubes in convection section 2. Symmetrical & uniform heat absorption 3. Burners in a circle on floor 4. Vertically up firing 5. General use for low heat duty. – Low cost – Size small – Low foot print – Easy construction 21 pramod_dixit@yahoo.com
  • 22. Cabin Type Heaters 1. Large Heat duty 60 to 80 MW or more 2. Cabin heaters have sloped arch, usually rectangular cross section 3. Horizontal Cabin - Large rectangular radiant section oriented horizontally. 4. Burners : Generally fired from the floor or side walls. 5. Tubes : May be vertical or horizontal in radiant section. 6. Convection section : contain multiple horizontal bank of tubes of single or multiple products. pramod_dixit@yahoo.com 22
  • 23. Cabin Furnace with Horizontal Tubes 1. The generally radiation section has parallel tubes with the greatest length being horizontal. 2. Tubes placed horizontally on the longer side walls. 3. The burners are located on the floor on the lower part of the longer side walls or at end walls pramod_dixit@yahoo.com 23
  • 26. Burners Burners are most important players in heater performance. Placed in lower radiant section. Flue gases travel vertically through : 1. Radiant section 2. Convection section 3. Air pre-heater if required 4. Finally through stack. 26 pramod_dixit@yahoo.com
  • 27. Burners and its accessories The combustion components include: • Burner • Fuel supply Piping • Flame Safety Supervision & Control System. • Burner management system • Low Nox and staged burning is a preferred choice 27 pramod_dixit@yahoo.com
  • 28. Burners placement & types Burners positioning 1. Single or double side 2. Floor mounted up-fired 3. Roof mounted or down fired 4. End of side wall fired 5. Multi-level fired 28 pramod_dixit@yahoo.com
  • 30. A Combination Burner • A combination burner is selected if we need to use both type of fuels (Gas as well as liquid) pramod_dixit@yahoo.com 30
  • 31. Burner Control Panel Consistsof : – Burner managementsystems – Single loop controllers – Limit controllers – NFPA & local regulation requirements. – The control system provides a pre-purgeand post-purge of the heater, automatic ignition, low flame start (high turn down burner), continuous main flame detected by UV sensor. – Control options !!!!!! virtually limitless !!!!! 31 pramod_dixit@yahoo.com
  • 32. Role of air pre-heaters in furnace 32 pramod_dixit@yahoo.com
  • 33. Air Pre-heaters • The purpose of the air pre- heater is to recover the heat from the furnace flue gas. • This increases the thermal efficiency of the furnace by reducing the useful heat lost in the flue gas. • This also reduces high temperature discharge to atmosphere • Shown here is glass tube type APH. pramod_dixit@yahoo.com 33
  • 34. Air flow scheme with APH system pramod_dixit@yahoo.com 34
  • 35. Furnace types based on DRAFTs Once we have APH in the system, we need to have a draft control on Flue gas flow. 1.Natural ( no APH possible in this case) 2.Forced 3.Induced 4.Balanced A word of caution : Flue gas discharge temperature to atmosphere should be above DEW POINT, to avoid acid attack by gas condensation. Which corrodes the stack. 35 pramod_dixit@yahoo.com
  • 36. Industrial process furnaces- Forced draft 36 pramod_dixit@yahoo.com
  • 37. Fuel used in heaters • Refinery waste gas • Natural gas • Fuel Oil / waste oil • Process combustible gases ( like H2 ) pramod_dixit@yahoo.com 37
  • 38. Refractory & Insulation • Since all heater parts are associated with heat , suitable Refractory is required to protect all CABIN structure as well as prevent heat loss to atmosphere. • Refractory radiates back the heat to tubes • Materials : Fire bricks, insulating & heat resistant cast able, ceramic fibre etc . • Ceramic fibre is light and easy to apply, used for roof & wall, not used for oil fired burners in radiant zone. 38 pramod_dixit@yahoo.com
  • 39. Applicable Codes for Fired heater design • API 535 : guidelines for the selection and/or evaluation of burners installed in fired heaters in general refinery services. • API 538 : recommendations for design, operation, and maintenance considerations for industrial fired boilers. • API 560 : Fired Heaters for General Refinery Service, recommendations for the design, materials, fabrication, inspection, testing, preparation for shipment, and erection of fired heaters, air pre- heaters (APHs), fans etc. • API 573 : inspection practices for fired boilers and process heaters. 39 pramod_dixit@yahoo.com