SlideShare a Scribd company logo
American Journal of Electrical and Electronic Engineering, 2016, Vol. 4, No. 6, 157-163
Available online at http://pubs.sciepub.com/ajeee/4/6/2
©Science and Education Publishing
DOI:10.12691/ajeee-4-6-2
Analysis of Transformer Loadings and Failure Rate in
Onitsha Electricity Distribution Network
Hachimenum N. Amadi*
, Fabian I. Izuegbunam
Department of Electrical & Electronic Engineering, Federal University of Technology, Owerri, Nigeria
*Corresponding author: amadihachy@gmail.com
Abstract This study investigated transformer loadings and failure rate in the Onitsha Electricity Distribution
Network by using the Electrical Transient Analysis Program (ETAP) software 12.6 and the Statistical Package for
the Social Sciences (SPSS) software 16.0. Data collected over the period 2011-2015 on the distribution network
were simulated on ETAP software using the Newton-Raphson (N-R) technique to determine the transformer
loadings while responses to 350 copies of questionnaire distributed among the technical staff were statistically
analysed on the SPSS software to ascertain the failure rate among transformers in the network. The findings of the
study show that during the 5 years period covered by the study, the sampled substations recorded transformer
average failure rate of 11.7 %. It was further revealed that besides insulation issues which accounted for 24.2% of all
the failures, overload (22.5%) was the next major cause of transformer breakdowns in the distribution network. The
study recommends installation of more transformer units, use of high quality transformers, balanced loading of the
transformers and proactive inspection and maintenance program of transformers units within the network. The
outcome of this work would help electricity utilities provide more reliable and cost effective services to customers.
Keywords: distribution network, electricity supply failures, failure rate, transformer failure, transformer loading
Cite This Article: Hachimenum N. Amadi, and Fabian I. Izuegbunam, “Analysis of Transformer Loadings
and Failure Rate in Onitsha Electricity Distribution Network.” American Journal of Electrical and Electronic
Engineering, vol. 4, no. 6 (2016): 157-163. doi: 10.12691/ajeee-4-6-2.
1. Introduction
The recent reforms in the Nigerian power sector pose
fresh challenges to the nation’s electricity industry such
that most electricity utilities now resort to increased
equipment utilization, deferred capital expenditures and
reduced maintenance expenditure in the provision of
electricity to the consumers. Transformers, for instance,
are now frequently operated beyond the nameplate rating
in order to meet increases in energy demand either on
short term emergency such as the loss of another
transformer in a substation or on a long term basis [1].
This happens because it is considered a more economic
strategy to overload an existing transformer than to install
a new transformer unit [2]. Consequently, while load on
each transformer continues to grow at about 2 % per year,
installation of new transformer unit keeps declining [3].
Certain factors such as the hot spot temperature, the top
oil temperature and the ratings of the ancillary equipment:
the bushings and the load tap changers (LTCs) determine
how much load the transformer can support beyond the
nameplate rating [1]. However, utilities now overlook
these factors and the safety of the transformer thereby
leading to increased cases of transformer failures and
cutting off of power supply to the service areas concerned.
According to ref [4], an average failure rate of
approximately 0.5 % is often designated to European
substation transformers while the U.S. Department of
Energy (DOE) estimate gives transformer constant failure
rate of 0.5 %/year due to lightning and other random
failures unrelated to transformer age [5]. Researches have
also put the failure rate of transformers in India and many
developing economies in the range 12% -15% as against
less than 1% in developed countries [6].
Power system experts had declared that given “ideal
conditions”, a transformer can last 30 to 40 years. Recent
studies, however, have found this claim not to be
completely true. A study carried out by Hartford Steam
Boiler (HSB) in 1975, for instance, revealed that
transformer average age at time of failure was 9.4 years. A
further research by HSB in 1985 indicated the average age
of a transformer as 11.4 years. Another related study
spanning a 10-year period from 1988-1997 still by HSB
put the transformer average age at 14.9 years [3]. These
statistics underscore the need to undertake periodic checks
on transformers to ascertain the operational condition and
proactively avert possible sudden breakdowns.
Recent researches have also pinpointed electrical
disturbances, lightning, insulation degradation, loose
connections and overload among the chief causes of
transformer failures in electrical distribution networks
[3,7,8]. According to ref [9], however, overload,
insulation oil degradation, thermal stress, humidity in
oil/paper and bushing defective are the major causes of
transformer problems. The term “Overload” describes a
situation whereby a transformer is subjected to voltages
and/or currents that exceed its nameplate rating such that
excess heat is generated which causes the insulation
158 American Journal of Electrical and Electronic Engineering
system to break down resulting in decreased life
expectancy of the transformer unit [10]. Transformer
overload in industries has always been traced to rapid
plant expansion without adequate capacity improvement.
Inadequate planning coupled with the presence of low
power factor and high harmonic currents generated by
inductive loads cause a transformer to become heavily
overloaded. It is widely acknowledged also that
overloaded transformers hinder future plant expansion
while the resulting excessive heat pose a potential fire
hazard [11]. Overloading leads to accelerated aging and
increased losses in transformers [12].
In this paper, the failure rate among transformers in the
Onitsha Electricity Distribution Network was investigated
and the loading on each transformer evaluated. Though
featured among vulnerable Nigerian Cities which are
susceptible to perennial flooding [13], Onitsha is an
economic hub for commerce and industry in Anambra
state; a major centre for trade between the coastal regions
and the north, as well as between eastern and western
Nigeria and across the West African region. The
metropolitan and high density areas of Onitsha include
Awada, Woliwo and 3-3. This strategic nature of the town
thus makes it imperative to carry out this research in order
to determine predominant factors that could contribute to
transformer failures and consequent sudden blackouts
thereby preventing unnecessary financial losses to both
utility and electricity customers within the network.
1.1. Overview of Transformers
Transformers perform the function of stepping up or
stepping down electrical voltages and are therefore a vital,
essential and one of the most expensive components in
any electrical network. Its cost varies between thousands
and millions of dollars depending on the design and size
of the unit [14]. Any failure of the transformer before
expiration of its designed lifespan results in unplanned outage,
production loss, unavailability of critical services and in most
cases huge financial losses to both utilities and customers.
Transformer winding insulation deteriorates as aging
sets in. Heat is a major cause of winding insulation
breakdowns. Overloading the transformer causes its
temperature to rise due to the resistive (I2
R) losses, stray,
and eddy current losses. Temperature is widely noted as
the main parameter affecting transformer insulation failure.
Hence, the heat produced through the process called
pyrolysis in the transformer as a result of loading and the
effect of ambient temperature is the important factor
affecting the life of the transformer [15]. Any increase in
temperature adversely influences the properties of the
winding insulation and the oil surrounding it. In other
words, overloading of transformer leads to increase in the
winding temperature, leading to deterioration of the
insulation material and subsequent reduction in the
transformer life span.
Routine testing and performing diagnostics can
minimize loss and down time of transformers. According
ref [16], the three categories of testing and diagnostics
required in determining transformer electrical, thermal,
and mechanical characteristics include:
(i) Performing acceptance test after installation and
commissioning of the transformer;
(ii) Predictive maintenance test during normal
operation of the transformer to ascertain that
electrical properties have not changed from design
specifications;
(iii) Failure test to identify breakdown cause of the
transformer.
Owing to limited data on transformer cycle, however,
statistical analysis only evaluates transformer failure rate
based on the operational experience. IEEE C57.125 is
considered an excellent guide for transformer failure
investigations [17].
The U.S. Department of Energy (DOE) defines
distribution transformer life as the age at which the
transformer retires from service, while the IEEE defines a
transformer failure as “The termination of the ability of a
transformer to perform its specific function” [17].
A transformer hardly fails as its insulation withstand
strength is usually higher than the normal operating or the
fault stress. But as the transformer ages, however, the
insulation withstand strength gradually reduces due to its
normal degradation and the cumulative effects from
transient events. This continues till a point where the
insulation withstand strength can no longer sustain the
high operational stress thus resulting to failure of the
transformer as illustrated in Figure 1. The impulses in the
actual stress curve indicate the sudden increased stresses
from transient events and because these events occur
randomly during transformer operation, there is often
likelihood of reduction in the insulation withstand strength
of the transformer [18]. Each step change in the insulation
withstand curve therefore indicates a slight reduction of
insulation withstand strength. It follows that as the load
increases, and/or a transient event occurs, the insulation
withstand strength reduces. The crossover point of
insulation withstand curve and operation stress curve in
Figure 1 shows the expected operation lifetime of a
transformer [18].
Every transformer is designed to withstand the expected
growing load and the system transient fault events [18].
However, given a rapidly growing load demand that is
faster than envisaged in Figure 1, or the more frequently
occurring transient event, or given that the fault stress
exceeds the insulation withstand strength, the transformer
fails before the designed age of 40. A transformer, which
failure occurred due to the significant effect from a
transient event before the designed life, is shown in Figure 2.
Figure 1. Transformer failure illustration [18]
American Journal of Electrical and Electronic Engineering 159
Figure 2. Transformer failure before expiration of designed life span [18]
Figure 3. Transformer failure beyond designed life span [18]
Operation experiences also show that given slower
increases in load and less frequent occurrences of transient
events, every transformer has insulation withstand
strength capable of sustaining the actual operation and
fault stress beyond the 40 years expected life-span [18, 19].
This is because under such condition, the insulation
strength reduces less than expected thereby making it
possible for the transformer to survive beyond the 40
years. A transformer post-lifespan failure caused by less
loaded condition is illustrated by solid curves in Figure 3.
The dash curves represent the expected operation
condition and the expected reduction of insulation
withstand strength [18].
Generally, therefore, transformer failure is determined
by individual design, loading experience, maintenance
culture and the environment in which it is installed and
operated and not on whether or not the transformer has
attained the designed life-span of 40 years [18].
1.2. Onitsha Electricity Distribution Network
Figure 4 shows Onitsha Electricity distribution network
in ETAP environment. The network consists of 45MVA;
132/33/11KV Transmission substation feeding seven (7)
Injection stations with variant capacities. Table 1 shows
the Injection Substations, their capacities and 11KV
feeders radiating from them. In addition to Table 1, there
are other feeders namely PPI/Enamel, IUNIT and Inland
11KV feeders which radiated directly from the 11KV bus
of the transmission substation located at the Onitsha
Works Centre.
Figure 4. ETAP Single line representation of Onitsha Electricity Distribution Network
Table 1. Onitsha Electricity Distribution Network Injection Substations, Capacities and Feeders
S/N Injection Substations Rating/Capacity 11KV Feeders
1. Ugwunwanosike 15 MVA, 33/11KV Toll gate, Mkpor and Ogidi
2. Army Baracks 15MVA, 33/11KV Omagba, Minaj, GRA and Army
3. Atani 2X15MVA, 33/11KV Market, Iweka, Water works, Uga, Industrial and Premier
4. GCM 7.5 MVA, 33/11KV Habour, Golden oil, GCM and Dozzy
5. Awada I 15 MVA, 33/11KV Woliwo and Nwaziki
6. Awada II 15 MVA, 33/11KV Ugwuagba and Mgbemena
7. 3-3 7.5 MVA, 33/11KV Housing and Nsugbe
160 American Journal of Electrical and Electronic Engineering
2. Materials and Methods
The study employed the qualitative and quantitative
approaches to investigate transformer failures in the
network using the Electrical Transient Analysis Program
(ETAP) software 12.6 and the Statistical Package for the
Social Sciences (SPSS) 16.0. Transformer reports from
2011 to 2015 on the seven injection substations in the
Onitsha Electricity Distribution network were accessed
from the Enugu Electricity Distribution Company (EEDC).
The Injection substations are Ugwunwanosike, Army
Barracks, Atani, GCM, 3-3, Awada I and Awada II (See
Table 1). The collected data include list of all transformers
rated 200KVA - 1.5MVA connected to each of the
injection substations, monthly maximum loadings on the
injection station feeders, number of transformers units that
failed, age of the failed transformers, cause of failure, the
number of outages caused by transformers failure, the
outage duration, voltage level etc. for the study period
covering 2011-2015. Additional data were collected
through 350 copies of a well structure questionnaire which
were served on the technical staff of the electricity
distribution companies. The network data and transformer
parameters were used in power flow simulation using
ETAP 12.6 software. The simulation results obtained were
used to evaluate the loadings on the transformers within
each of the injection substations, whereas the responses to
the questionnaire were statistically analysed on the SPSS
16.0 software to determine the failure rate and actual
causes of failure of the transformer units.
To determine the transformer failure rate, the following
formula was used [4,20]:
1
1
.100%
i
i
i
i
n
N
λ =
∑
∑
(1)
Where:
λ = Failure rate per annum (p.a) in percentage
in =Number of transformers that failed in the ith
year.
iN = Number of transformers in service during the ith
year
For the calculation of failure rates a constant
transformer population of 4500 was assumed for the
investigated failure time period.
3. Results and Discussion
The calculated transformer failure rates among the
injection substations are given in Table 2. The findings
show that out of a sampled 4,500 units of transformers
that were installed and in use within the Onitsha
distribution network during the 2011-2015 period of study,
a total of 525 units of the total transformer units (See
Table 2) failed owing to several cause factors (See Table 3).
This represents an average failure rate of 11.7% and is
close to failure rate of transformers in India which
according to ref [6] is in the range 12% - 15% but much
higher than 0.5 percent obtainable in the European
countries [5].
Table 2 indicates also that the Army Barracks Injection
Substation had the highest transformer failure rate of
23.8%. This was followed by GCM and Atani Injection
Substations with 22.7% and 20.6% failure rates
respectively.
Results of the analysis presented in Table 3 shows that
Insulation Issues topped the list of failure causes in the
distribution network with 24.2%. This was followed by
Overloading and Inadequate Maintenance with 22.5% and
16.4% respectively. The study thus established the
following causes of transformer failures in the Onitsha
electricity distribution network (See Table 3 and Figure 5):
1. Moisture - The moisture category includes failures
caused by leaky pipes, leaking roofs, water entering the
tanks through leaking bushings or fittings, and confirmed
presence of moisture in the insulating oil. Moisture could
be included in the inadequate maintenance or the
insulation failure category, but it is reported separately
here [7].
2. Overloading - This category includes failure arising
from established cases of overload and includes basically
transformers that experienced a small but sustained annual
increases in load (See Table 4) that exceeded the
nameplate capacity over time such that failure occurs [7].
Excessive load on a transformer can lead to increase in
temperature and deterioration of the winding insulation,
which if unchecked, can result in transformer failure after
a sustained period of time.
3. Flood – This category of causes are due to the
flooding of substation transformers sites such that there is
breakdown of the transformer. Onitsha is among
vulnerable Nigerian Cities which are susceptible to
perennial flooding [13].
Table 2. Transformer failure rate according to Injection Substations
during 2011-2015
S/N
Injection
Substations
No. of
Transformer
Units Installed
Failures
Frequency Percentage
1. Ugwunwanosike 717 97 18.5
2. Army Barracks 574 125 23.8
3. Atani 620 108 20.6
4. GCM 659 119 22.7
5. Awada I 673 37 7.1
6. Awada II 624 15 2.9
7. 3-3 533 24 4.6
Total 4500 525 100
Table 3. Classification of failure causes, frequency and percentage
during 2011-2015
Failure Cause
Failures
Frequency Percentage
Moisture 16 3.1
Overloading 118 22.5
Flood 4 0.76
Poor workmanship/ Loose Connections 17 3.24
Overheating 6 1.14
Insulation Issues 127 24.2
Lightning surges 43 8.2
Line surges/External short circuit 74 14.1
Inadequate maintenance 86 16.4
Vandalism 14 2.7
Others 20 3.81
Total 525 100
American Journal of Electrical and Electronic Engineering 161
Table 4. Transformer MVA Loadings (%) during 2011-2015
Injection Substation
Transformer Annual MVA Loadings (%)
Average MVA Loading (%)
2011 2012 2013 2014 2015
Ugwunwanosike 104.2 110.3 115.7 120.9 127.3 115.68
Army Barracks 137.5 138.2 140.4 145.7 149.8 142.32
Atani 125.6 127.4 130.3 138.1 141.6 132.6
GCM 130.9 133.5 136.8 140.4 144.1 137.14
Awada I 85 87.1 88.2 89.9 93.3 88.7
Awada II 23.5 25.7 28.9 34.6 39.5 30.44
3-3 56.1 58.2 60.1 66.4 70.2 62.2
4. Poor workmanship/ Loose connections – This category
though somewhat similar to Inadequate Maintenance
/Operation includes workmanship errors in making
electrical connections, for instance, the improper use of
dissimilar metals together or poor tightening of bolted
connections. Ordinarily, loose connections should have
been placed in the inadequate maintenance/operation
category, but this study had chosen to report it alongside
poor workmanship for purpose of emphasis.
5. Overheating -These are failure causes due to
excessive heating of the transformer which increases
transformer losses, weakens the insulation and finally
results in reduced transformer life. Due to abnormal
operation conditions such as excessive loads, transformer
windings could become overheated resulting in sudden
breakdown of the transformer unit.
6. Insulation Failures – These were the leading causes
of failure as affirmed by this study. This category excludes
those failures where there was evidence of a lightning or a
line surge. There are actually four factors that are
responsible for insulation deterioration: pyrolosis (heat),
oxidation, acidity, and moisture. But moisture is reported
separately. The average age of the transformers that failed
due to insulation Issues was 18 years. In this study,
insulation breakdown has been found to be the major
cause of transformer failures in the Onitsha electricity
distribution network followed closely by overload.
7. Lightning surges - are transformer failures due to
surges arising from a lightning strike. It is normal to first
confirm that there was a lightning strike before attributing
such transformer failure to lightning surges.
8. Line surges/External short circuit - This category of
faults includes switching surges, voltage spikes, line
faults/flashovers, and other transmission and distribution
(T&D) abnormalities resulting from poor surge protection
or inadequate coil clamping and short circuit strength.
9. Inadequate Maintenance /Operation - This category
of failure causes include accumulation of dirt, foreign matters
and oil, disconnected or improperly set controls, corrosion
and loss of coolant, which should have been promptly
identified and corrected. Early detection and correction of
abnormal conditions in and around electrical equipment often
help to prevent eventual breakdowns and loss of finances [7].
10. Vandalism - These are failures due to carting away
by vandals of vital parts of the transformer such as the
oil, copper and aluminium, etc. Electrical Infrastructure
vandalisation is a common occurrence among electricity
distribution networks in Nigeria including the Onitsha
distribution network.
11. Others –These are unclassified failure causes and
includes all transformer failure causes that are not easily
ascertainable.
The identified causes of the transformer failures in the
Onitsha electricity distribution network during the period
2011-2015 have been expressed in terms of percentages in
Figure 5.
Figure 5. Classification of failure cause by percentage during 2011-2015
0 20 40 60 80 100 120 140
Moisture
Flood
Overheating
Lightning surges
Inadequate maintenance
Others
Failure Causes in Percentages (%)
Percentage Frequency
162 American Journal of Electrical and Electronic Engineering
Figure 6. MVA Loading of transformers at the sampled Injection substations in Onitsha distribution network in 2015
The computed transformer MVA loadings in each of
the injection substations studied during the period 2011-
2015 are as presented in Table 4 while Figure 6 shows the
loadings for the year 2015 only.
Observe that many of the transformers are loaded well
above 100%. It is obvious also from Figure 6 that the
loadings on the transformers increased steadily over the
years as the power consumption increased leading
eventually to the failure of the affected transformer units.
The findings of the study showed that during the period
covered by the research, about 60% i.e. four out of the
seven Injection substations in the distribution network had
various transformer units loaded beyond the nameplate ratings.
It is obvious that this high percentage of overloaded
transformers contributed significantly to the rapid deterioration
of the transformers insulating materials and therefore the
high rate of transformer failures as recorded in the study.
4. Conclusion and Recommendations
This study investigated transformer failure rates and
failure causes in the Onitsha Electricity Distribution
Network using both the Electrical Transient Analysis
Program (ETAP) software 12.6 and the Statistical Package
for the Social Sciences (SPSS) software 16.0. Network
data and transformer parameters collected over the period
2011-2015 from substations within the distribution
network were simulated on the ETAP software using the
Newton-Raphson (N-R) technique to ascertain the
transformer loadings while responses to the research
questionnaire were statistically analysed on the SPSS
software to determine the causes and rate of transformer
failures. The findings of the study show that during the
five years period of study, injection substations in the
Onitsha Electricity Distribution Network recorded an
average failure rate of 11.7 % among the installed and
operational transformers. The study revealed also that
besides Insulation Issues (24.2%), Overloading (22.5%) is
the next major cause of transformer failures in the Onitsha
Electricity Distribution Network. The study found also
that the Army Barracks Injection Substation recorded the
highest transformer failure rate of 23.8%. This is followed
by GCM and Atani Injection substations with 22.7% and
20.6% failure rates respectively. It is obvious from the
responses to the structured questionnaire by the technical
staff of the distribution company that these high failure
rates were due to inadequate number of transformers
which necessitated the overloading of the available units.
The study therefore recommends installation of additional
transformer units in order to reduce the loads on the
existing transformer units within the area. The study also
suggests strict statutory legislation against vandalism,
good workmanship, balanced loading of the transformers,
use of quality transformers as well as proactive monitoring,
inspection and maintenance program of the transformers
within the network in order to ensure improvement in
transformer life span and increased availability of
electricity supply. The outcome of this work would help
electricity utilities in providing more reliable and cost
effective services to customers.
Statement of Competing Interests
The authors declare that no conflicting interests exist.
References
[1] Pasricha, A. (2015). "A Study into improving Transformer
Loading Capability beyond Nameplate Rating". Masters Theses.
Missouri University of Science and Technology, Missouri.
[2] Short, T. A. (2003). Electric Power Distribution Handbook. CRC
Press.
[3] Bartley, W.H. (1998). “An Analysis of Transformer Failures, Part
1 – 1988 through 1997.” Available at
https://www.hsb.com/TheLocomotive/AnAnalysisOfTransformer
FailuresPart1.aspx.
127.3
149.8
141.6
144.193.3
39.5
70.2
0
20
40
60
80
100
120
140
Ugwunwanosike
Army Barracks
Atani
GCMAwada I
Awada II
3-3 Inj SS
Transformer MVA (%) Loadings in 2015
MVA (%) Loading
American Journal of Electrical and Electronic Engineering 163
[4] Vahidi, F and Tenbohlen, S. Statistical Failure Analysis of
European Substation Transformers. Conference paper. November
2014. Available at:
https:www.researchgate.net/publication/272088767.
[5] Energy Efficiency and Renewable Energy Office (2013). Energy
Conservation Program: Energy Conservation Standards for
Distribution Transformers Rule. Available at:
https://www.regulations.gov/document?D=EERE-2010-BT-STD-
0048-0762.
[6] Electrical India (2015). Case Studies of the Transformers Failure
Analyses. Available at:
http://www.electricalindia.in/blog/post/id/5692/case-studies-of-
the-transformers-failure-analyses.
[7] Bartley, W.H. (2003). Analysis of Transformer Failures.
International Association of Engineering Insurers 36th Annual
Conference – Stockholm.
[8] Bartley, W.H. (2004). Investigating Transformer Failures. The
Hartford Steam Boiler Inspection & Insurance Co., Harford.
[9] Mirzai, M.; Gholami, A. and F. Aminifar (2006). Failures
Analysis and Reliability Calculation for Power Transformers.
Journal of Electrical Systems, 2-1, 1-12.
[10] What is the effect of “Overload”? Available at:
http//:www.hammondpowersolutions.com.
[11] Hershey Energy Systems. Available at:
http//:www.hersheyenergy.com.
[12] McCarthy, J. (2010). Analysis of Transformer Ratings in a Wind
Farm Environment. Dublin Institute of Technology, Dublin.
[13] Efobi, K. and Anierobi, C. (2013). Urban Flooding and
Vulnerability of Nigerian Cities: A Case Study of Awka and
Onitsha in Anambra State, Nigeria. Journal of Law, Policy and
Globalization, 19.
[14] Tahir, M. “Intelligent Condition Assessment of Power Transformer
Based on Data Mining Techniques” (2012). A Masters Thesis.
University of Waterloo, Ontario, Canada.
[15] Saad, F.A. M. (2011). Predicting Transformer End of Life using
Transformer Thermal Life Simulation Technique. Masters Thesis.
University Tun Hussein Onn, Malaysia.
[16] Jadeja, K.V. (2011). Transformer Testing and Fault Finding.
Available at:
http://www.brighthubengineering.com/power-generation-
distribution/126102-transformer-testing-and-fault-finding/.
[17] IEEE C57.125-1991 “IEEE Guide for Failure Investigation,
Documentation, and Analysis for Power Transformers and Shunt
Reactors”, Transformer Committee of the IEEE Power
Engineering Society, Copyright 1992 by the Institute of Electrical
and Electronics Engineers, Inc..
[18] Zhong, Q. (2011). Power Transformer End-of-Life Modelling:
Linking Statistics with Physical Aging. Doctoral Thesis. The
University of Manchester.
[19] Mtetwa, S. and Cormack, R. (2006). "Addressing the Requirements
of an Ageing Fleet of Transmission Transformers on the Eskom
Transmission Network," in CIGRE 2009 6th Southern Africa
Regional Conference Cape Town, South Africa.
[20] Chmura, L. (2014).Life-cycle assessment of high-voltage assets
using statistical tools, PhD thesis. Technical University, Delft.
[21] United Nations Human Settlements Programme (2012). Nigeria:
Onitsha Urban Profile. UN-Habitat. Available at:
http//:worldurbancampaign.org.

More Related Content

PDF
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
PPTX
transformer dignostics on high voltage
PDF
Review paper on Fault analysis and its Limiting Techniques.
PDF
Design and Mitigation Techniques of MV Capacitor Bank Switching Transients on...
PDF
Interpreting ieee-std-519-and-meeting-harmonic-limits-vf ds-pcic-2003-15
PDF
Methods to determine the overall health and condition of large power transfor...
PDF
11.methods to determine the overall health and condition of large power trans...
PDF
INSTANTANEOUS POWER AND CURRENT STRATEGIES FOR CURRENT HARMONICS CANCELLATION...
A Study of the Root Causes of High Failure Rate of Distribution Transformer -...
transformer dignostics on high voltage
Review paper on Fault analysis and its Limiting Techniques.
Design and Mitigation Techniques of MV Capacitor Bank Switching Transients on...
Interpreting ieee-std-519-and-meeting-harmonic-limits-vf ds-pcic-2003-15
Methods to determine the overall health and condition of large power transfor...
11.methods to determine the overall health and condition of large power trans...
INSTANTANEOUS POWER AND CURRENT STRATEGIES FOR CURRENT HARMONICS CANCELLATION...

What's hot (18)

PDF
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
PDF
Power Quality Improvement in Faulty Conditions using Tuned Harmonic Filters
PDF
Under voltage load shedding for contingency analysis to optimize power loss ...
PDF
A Review on Basic Concepts and Important Standards of Power Quality in Power ...
PDF
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
PDF
Harmonic Voltage Distortions in Power Systems Due to Non Linear Loads
PDF
L44086268
PDF
IRJET-Power Quality Effects on Nonlinear Loads
PDF
Frequency response analysis for transformer tap changer damage detection
PDF
Basics of facts
PDF
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
PDF
IRJET- Voltage Swells and Transient Research Considering ARC Load
PDF
Matlab/simulink simulation of unified power quality conditioner-battery energ...
PDF
191 ijitr 4-5-297
PDF
Power Flow Study and Performance of STATCOM and TCSC in Improvement Voltage S...
PDF
L030101066072
PDF
Effects of power electronics devices on the energy quality of an administrati...
PDF
An Overview of FACTS Controllers for Power Quality Improvement
A High-Performance SPWM Controller for Three-Phase UPS Systems Operating Unde...
Power Quality Improvement in Faulty Conditions using Tuned Harmonic Filters
Under voltage load shedding for contingency analysis to optimize power loss ...
A Review on Basic Concepts and Important Standards of Power Quality in Power ...
Improvement Transient Stability of Fixed Speed Wind Energy Conversion System ...
Harmonic Voltage Distortions in Power Systems Due to Non Linear Loads
L44086268
IRJET-Power Quality Effects on Nonlinear Loads
Frequency response analysis for transformer tap changer damage detection
Basics of facts
IRJET- Simulation and Experimental Verification of Single Phase Unity Power F...
IRJET- Voltage Swells and Transient Research Considering ARC Load
Matlab/simulink simulation of unified power quality conditioner-battery energ...
191 ijitr 4-5-297
Power Flow Study and Performance of STATCOM and TCSC in Improvement Voltage S...
L030101066072
Effects of power electronics devices on the energy quality of an administrati...
An Overview of FACTS Controllers for Power Quality Improvement
Ad

Similar to Analysis of Transformer Loadings and Failure Rate in Onitsha Electricity Distribution Network (20)

PDF
Monitoring of power transformers using thermal model and permission time of ...
PDF
Power Transformer Failures – Causes & Prevention.pdf
PDF
Why transformers fail_final
PDF
Distribution Transformer Failure Analysis in Gujarat DISCOM
PDF
G04714245
PDF
MV Transformer Replacement Decisions
PDF
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
PPTX
Failure and repair of transformer.pptx
PDF
nine steps to_TR reliability_SDMYERS.pdf
PDF
Fault identification in transformer winding
PDF
Fault identification in transformer winding
DOCX
Edwin Newsletter on transformer failures on 13 October 2015
PPT
O & M OF POWER TRANSFORMERS in substations.ppt
PPT
Trans & Swg maint.ppt
PPT
Transfomer diagnostics/sanjeet-1308143
PPT
01 Overview of Power transformers - Remedial Measures.ppt
PDF
Failure analysis of a power transformer using dissolved gas analysis – a case...
PDF
The Importance Of Power Transformer Testing.pdf
PPTX
electricalsystemprotection-transformerprotection-190111055726.pptx
Monitoring of power transformers using thermal model and permission time of ...
Power Transformer Failures – Causes & Prevention.pdf
Why transformers fail_final
Distribution Transformer Failure Analysis in Gujarat DISCOM
G04714245
MV Transformer Replacement Decisions
Ensuring Optimal Performance With The Right Transformer Maintenance Procedure...
Failure and repair of transformer.pptx
nine steps to_TR reliability_SDMYERS.pdf
Fault identification in transformer winding
Fault identification in transformer winding
Edwin Newsletter on transformer failures on 13 October 2015
O & M OF POWER TRANSFORMERS in substations.ppt
Trans & Swg maint.ppt
Transfomer diagnostics/sanjeet-1308143
01 Overview of Power transformers - Remedial Measures.ppt
Failure analysis of a power transformer using dissolved gas analysis – a case...
The Importance Of Power Transformer Testing.pdf
electricalsystemprotection-transformerprotection-190111055726.pptx
Ad

More from Dr. Hachimenum Amadi (10)

PPTX
Technical_Paper_Presentation_Sample_Template_Abuja_2023_Update[1].pptx
PDF
Evaluation of losses in distribution networks of selected industrial cities i...
PDF
Assessment of Impact of Outages in Selected Electricity Intensive Industries ...
PDF
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
PDF
The Effects of Technical and Non Technical Losses on Power Outages in Nigeria
PDF
The Effects of Technical and Non-Technical Losses on Power Outages in Nigeria
PDF
The direct assessment and captive costs methods for estimating the economic c...
PDF
Effective Earthing System in the Corrosive Soil of Niger Delta
PDF
Power Outages in Port Harcourt City: Problems and Solutions
PDF
Impact of power outages on developing countries evidence from rural household...
Technical_Paper_Presentation_Sample_Template_Abuja_2023_Update[1].pptx
Evaluation of losses in distribution networks of selected industrial cities i...
Assessment of Impact of Outages in Selected Electricity Intensive Industries ...
Assessment of Energy Losses and Cost Implications in the Nigerian Distributio...
The Effects of Technical and Non Technical Losses on Power Outages in Nigeria
The Effects of Technical and Non-Technical Losses on Power Outages in Nigeria
The direct assessment and captive costs methods for estimating the economic c...
Effective Earthing System in the Corrosive Soil of Niger Delta
Power Outages in Port Harcourt City: Problems and Solutions
Impact of power outages on developing countries evidence from rural household...

Recently uploaded (20)

PPTX
UNIT 4 Total Quality Management .pptx
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
DOCX
573137875-Attendance-Management-System-original
PDF
PPT on Performance Review to get promotions
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PPTX
Geodesy 1.pptx...............................................
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
737-MAX_SRG.pdf student reference guides
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
PPTX
Sustainable Sites - Green Building Construction
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPT
introduction to datamining and warehousing
PPTX
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx
UNIT 4 Total Quality Management .pptx
Safety Seminar civil to be ensured for safe working.
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
573137875-Attendance-Management-System-original
PPT on Performance Review to get promotions
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
Geodesy 1.pptx...............................................
Embodied AI: Ushering in the Next Era of Intelligent Systems
Internet of Things (IOT) - A guide to understanding
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
737-MAX_SRG.pdf student reference guides
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Foundation to blockchain - A guide to Blockchain Tech
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
keyrequirementskkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkkk
Sustainable Sites - Green Building Construction
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
introduction to datamining and warehousing
M Tech Sem 1 Civil Engineering Environmental Sciences.pptx

Analysis of Transformer Loadings and Failure Rate in Onitsha Electricity Distribution Network

  • 1. American Journal of Electrical and Electronic Engineering, 2016, Vol. 4, No. 6, 157-163 Available online at http://pubs.sciepub.com/ajeee/4/6/2 ©Science and Education Publishing DOI:10.12691/ajeee-4-6-2 Analysis of Transformer Loadings and Failure Rate in Onitsha Electricity Distribution Network Hachimenum N. Amadi* , Fabian I. Izuegbunam Department of Electrical & Electronic Engineering, Federal University of Technology, Owerri, Nigeria *Corresponding author: amadihachy@gmail.com Abstract This study investigated transformer loadings and failure rate in the Onitsha Electricity Distribution Network by using the Electrical Transient Analysis Program (ETAP) software 12.6 and the Statistical Package for the Social Sciences (SPSS) software 16.0. Data collected over the period 2011-2015 on the distribution network were simulated on ETAP software using the Newton-Raphson (N-R) technique to determine the transformer loadings while responses to 350 copies of questionnaire distributed among the technical staff were statistically analysed on the SPSS software to ascertain the failure rate among transformers in the network. The findings of the study show that during the 5 years period covered by the study, the sampled substations recorded transformer average failure rate of 11.7 %. It was further revealed that besides insulation issues which accounted for 24.2% of all the failures, overload (22.5%) was the next major cause of transformer breakdowns in the distribution network. The study recommends installation of more transformer units, use of high quality transformers, balanced loading of the transformers and proactive inspection and maintenance program of transformers units within the network. The outcome of this work would help electricity utilities provide more reliable and cost effective services to customers. Keywords: distribution network, electricity supply failures, failure rate, transformer failure, transformer loading Cite This Article: Hachimenum N. Amadi, and Fabian I. Izuegbunam, “Analysis of Transformer Loadings and Failure Rate in Onitsha Electricity Distribution Network.” American Journal of Electrical and Electronic Engineering, vol. 4, no. 6 (2016): 157-163. doi: 10.12691/ajeee-4-6-2. 1. Introduction The recent reforms in the Nigerian power sector pose fresh challenges to the nation’s electricity industry such that most electricity utilities now resort to increased equipment utilization, deferred capital expenditures and reduced maintenance expenditure in the provision of electricity to the consumers. Transformers, for instance, are now frequently operated beyond the nameplate rating in order to meet increases in energy demand either on short term emergency such as the loss of another transformer in a substation or on a long term basis [1]. This happens because it is considered a more economic strategy to overload an existing transformer than to install a new transformer unit [2]. Consequently, while load on each transformer continues to grow at about 2 % per year, installation of new transformer unit keeps declining [3]. Certain factors such as the hot spot temperature, the top oil temperature and the ratings of the ancillary equipment: the bushings and the load tap changers (LTCs) determine how much load the transformer can support beyond the nameplate rating [1]. However, utilities now overlook these factors and the safety of the transformer thereby leading to increased cases of transformer failures and cutting off of power supply to the service areas concerned. According to ref [4], an average failure rate of approximately 0.5 % is often designated to European substation transformers while the U.S. Department of Energy (DOE) estimate gives transformer constant failure rate of 0.5 %/year due to lightning and other random failures unrelated to transformer age [5]. Researches have also put the failure rate of transformers in India and many developing economies in the range 12% -15% as against less than 1% in developed countries [6]. Power system experts had declared that given “ideal conditions”, a transformer can last 30 to 40 years. Recent studies, however, have found this claim not to be completely true. A study carried out by Hartford Steam Boiler (HSB) in 1975, for instance, revealed that transformer average age at time of failure was 9.4 years. A further research by HSB in 1985 indicated the average age of a transformer as 11.4 years. Another related study spanning a 10-year period from 1988-1997 still by HSB put the transformer average age at 14.9 years [3]. These statistics underscore the need to undertake periodic checks on transformers to ascertain the operational condition and proactively avert possible sudden breakdowns. Recent researches have also pinpointed electrical disturbances, lightning, insulation degradation, loose connections and overload among the chief causes of transformer failures in electrical distribution networks [3,7,8]. According to ref [9], however, overload, insulation oil degradation, thermal stress, humidity in oil/paper and bushing defective are the major causes of transformer problems. The term “Overload” describes a situation whereby a transformer is subjected to voltages and/or currents that exceed its nameplate rating such that excess heat is generated which causes the insulation
  • 2. 158 American Journal of Electrical and Electronic Engineering system to break down resulting in decreased life expectancy of the transformer unit [10]. Transformer overload in industries has always been traced to rapid plant expansion without adequate capacity improvement. Inadequate planning coupled with the presence of low power factor and high harmonic currents generated by inductive loads cause a transformer to become heavily overloaded. It is widely acknowledged also that overloaded transformers hinder future plant expansion while the resulting excessive heat pose a potential fire hazard [11]. Overloading leads to accelerated aging and increased losses in transformers [12]. In this paper, the failure rate among transformers in the Onitsha Electricity Distribution Network was investigated and the loading on each transformer evaluated. Though featured among vulnerable Nigerian Cities which are susceptible to perennial flooding [13], Onitsha is an economic hub for commerce and industry in Anambra state; a major centre for trade between the coastal regions and the north, as well as between eastern and western Nigeria and across the West African region. The metropolitan and high density areas of Onitsha include Awada, Woliwo and 3-3. This strategic nature of the town thus makes it imperative to carry out this research in order to determine predominant factors that could contribute to transformer failures and consequent sudden blackouts thereby preventing unnecessary financial losses to both utility and electricity customers within the network. 1.1. Overview of Transformers Transformers perform the function of stepping up or stepping down electrical voltages and are therefore a vital, essential and one of the most expensive components in any electrical network. Its cost varies between thousands and millions of dollars depending on the design and size of the unit [14]. Any failure of the transformer before expiration of its designed lifespan results in unplanned outage, production loss, unavailability of critical services and in most cases huge financial losses to both utilities and customers. Transformer winding insulation deteriorates as aging sets in. Heat is a major cause of winding insulation breakdowns. Overloading the transformer causes its temperature to rise due to the resistive (I2 R) losses, stray, and eddy current losses. Temperature is widely noted as the main parameter affecting transformer insulation failure. Hence, the heat produced through the process called pyrolysis in the transformer as a result of loading and the effect of ambient temperature is the important factor affecting the life of the transformer [15]. Any increase in temperature adversely influences the properties of the winding insulation and the oil surrounding it. In other words, overloading of transformer leads to increase in the winding temperature, leading to deterioration of the insulation material and subsequent reduction in the transformer life span. Routine testing and performing diagnostics can minimize loss and down time of transformers. According ref [16], the three categories of testing and diagnostics required in determining transformer electrical, thermal, and mechanical characteristics include: (i) Performing acceptance test after installation and commissioning of the transformer; (ii) Predictive maintenance test during normal operation of the transformer to ascertain that electrical properties have not changed from design specifications; (iii) Failure test to identify breakdown cause of the transformer. Owing to limited data on transformer cycle, however, statistical analysis only evaluates transformer failure rate based on the operational experience. IEEE C57.125 is considered an excellent guide for transformer failure investigations [17]. The U.S. Department of Energy (DOE) defines distribution transformer life as the age at which the transformer retires from service, while the IEEE defines a transformer failure as “The termination of the ability of a transformer to perform its specific function” [17]. A transformer hardly fails as its insulation withstand strength is usually higher than the normal operating or the fault stress. But as the transformer ages, however, the insulation withstand strength gradually reduces due to its normal degradation and the cumulative effects from transient events. This continues till a point where the insulation withstand strength can no longer sustain the high operational stress thus resulting to failure of the transformer as illustrated in Figure 1. The impulses in the actual stress curve indicate the sudden increased stresses from transient events and because these events occur randomly during transformer operation, there is often likelihood of reduction in the insulation withstand strength of the transformer [18]. Each step change in the insulation withstand curve therefore indicates a slight reduction of insulation withstand strength. It follows that as the load increases, and/or a transient event occurs, the insulation withstand strength reduces. The crossover point of insulation withstand curve and operation stress curve in Figure 1 shows the expected operation lifetime of a transformer [18]. Every transformer is designed to withstand the expected growing load and the system transient fault events [18]. However, given a rapidly growing load demand that is faster than envisaged in Figure 1, or the more frequently occurring transient event, or given that the fault stress exceeds the insulation withstand strength, the transformer fails before the designed age of 40. A transformer, which failure occurred due to the significant effect from a transient event before the designed life, is shown in Figure 2. Figure 1. Transformer failure illustration [18]
  • 3. American Journal of Electrical and Electronic Engineering 159 Figure 2. Transformer failure before expiration of designed life span [18] Figure 3. Transformer failure beyond designed life span [18] Operation experiences also show that given slower increases in load and less frequent occurrences of transient events, every transformer has insulation withstand strength capable of sustaining the actual operation and fault stress beyond the 40 years expected life-span [18, 19]. This is because under such condition, the insulation strength reduces less than expected thereby making it possible for the transformer to survive beyond the 40 years. A transformer post-lifespan failure caused by less loaded condition is illustrated by solid curves in Figure 3. The dash curves represent the expected operation condition and the expected reduction of insulation withstand strength [18]. Generally, therefore, transformer failure is determined by individual design, loading experience, maintenance culture and the environment in which it is installed and operated and not on whether or not the transformer has attained the designed life-span of 40 years [18]. 1.2. Onitsha Electricity Distribution Network Figure 4 shows Onitsha Electricity distribution network in ETAP environment. The network consists of 45MVA; 132/33/11KV Transmission substation feeding seven (7) Injection stations with variant capacities. Table 1 shows the Injection Substations, their capacities and 11KV feeders radiating from them. In addition to Table 1, there are other feeders namely PPI/Enamel, IUNIT and Inland 11KV feeders which radiated directly from the 11KV bus of the transmission substation located at the Onitsha Works Centre. Figure 4. ETAP Single line representation of Onitsha Electricity Distribution Network Table 1. Onitsha Electricity Distribution Network Injection Substations, Capacities and Feeders S/N Injection Substations Rating/Capacity 11KV Feeders 1. Ugwunwanosike 15 MVA, 33/11KV Toll gate, Mkpor and Ogidi 2. Army Baracks 15MVA, 33/11KV Omagba, Minaj, GRA and Army 3. Atani 2X15MVA, 33/11KV Market, Iweka, Water works, Uga, Industrial and Premier 4. GCM 7.5 MVA, 33/11KV Habour, Golden oil, GCM and Dozzy 5. Awada I 15 MVA, 33/11KV Woliwo and Nwaziki 6. Awada II 15 MVA, 33/11KV Ugwuagba and Mgbemena 7. 3-3 7.5 MVA, 33/11KV Housing and Nsugbe
  • 4. 160 American Journal of Electrical and Electronic Engineering 2. Materials and Methods The study employed the qualitative and quantitative approaches to investigate transformer failures in the network using the Electrical Transient Analysis Program (ETAP) software 12.6 and the Statistical Package for the Social Sciences (SPSS) 16.0. Transformer reports from 2011 to 2015 on the seven injection substations in the Onitsha Electricity Distribution network were accessed from the Enugu Electricity Distribution Company (EEDC). The Injection substations are Ugwunwanosike, Army Barracks, Atani, GCM, 3-3, Awada I and Awada II (See Table 1). The collected data include list of all transformers rated 200KVA - 1.5MVA connected to each of the injection substations, monthly maximum loadings on the injection station feeders, number of transformers units that failed, age of the failed transformers, cause of failure, the number of outages caused by transformers failure, the outage duration, voltage level etc. for the study period covering 2011-2015. Additional data were collected through 350 copies of a well structure questionnaire which were served on the technical staff of the electricity distribution companies. The network data and transformer parameters were used in power flow simulation using ETAP 12.6 software. The simulation results obtained were used to evaluate the loadings on the transformers within each of the injection substations, whereas the responses to the questionnaire were statistically analysed on the SPSS 16.0 software to determine the failure rate and actual causes of failure of the transformer units. To determine the transformer failure rate, the following formula was used [4,20]: 1 1 .100% i i i i n N λ = ∑ ∑ (1) Where: λ = Failure rate per annum (p.a) in percentage in =Number of transformers that failed in the ith year. iN = Number of transformers in service during the ith year For the calculation of failure rates a constant transformer population of 4500 was assumed for the investigated failure time period. 3. Results and Discussion The calculated transformer failure rates among the injection substations are given in Table 2. The findings show that out of a sampled 4,500 units of transformers that were installed and in use within the Onitsha distribution network during the 2011-2015 period of study, a total of 525 units of the total transformer units (See Table 2) failed owing to several cause factors (See Table 3). This represents an average failure rate of 11.7% and is close to failure rate of transformers in India which according to ref [6] is in the range 12% - 15% but much higher than 0.5 percent obtainable in the European countries [5]. Table 2 indicates also that the Army Barracks Injection Substation had the highest transformer failure rate of 23.8%. This was followed by GCM and Atani Injection Substations with 22.7% and 20.6% failure rates respectively. Results of the analysis presented in Table 3 shows that Insulation Issues topped the list of failure causes in the distribution network with 24.2%. This was followed by Overloading and Inadequate Maintenance with 22.5% and 16.4% respectively. The study thus established the following causes of transformer failures in the Onitsha electricity distribution network (See Table 3 and Figure 5): 1. Moisture - The moisture category includes failures caused by leaky pipes, leaking roofs, water entering the tanks through leaking bushings or fittings, and confirmed presence of moisture in the insulating oil. Moisture could be included in the inadequate maintenance or the insulation failure category, but it is reported separately here [7]. 2. Overloading - This category includes failure arising from established cases of overload and includes basically transformers that experienced a small but sustained annual increases in load (See Table 4) that exceeded the nameplate capacity over time such that failure occurs [7]. Excessive load on a transformer can lead to increase in temperature and deterioration of the winding insulation, which if unchecked, can result in transformer failure after a sustained period of time. 3. Flood – This category of causes are due to the flooding of substation transformers sites such that there is breakdown of the transformer. Onitsha is among vulnerable Nigerian Cities which are susceptible to perennial flooding [13]. Table 2. Transformer failure rate according to Injection Substations during 2011-2015 S/N Injection Substations No. of Transformer Units Installed Failures Frequency Percentage 1. Ugwunwanosike 717 97 18.5 2. Army Barracks 574 125 23.8 3. Atani 620 108 20.6 4. GCM 659 119 22.7 5. Awada I 673 37 7.1 6. Awada II 624 15 2.9 7. 3-3 533 24 4.6 Total 4500 525 100 Table 3. Classification of failure causes, frequency and percentage during 2011-2015 Failure Cause Failures Frequency Percentage Moisture 16 3.1 Overloading 118 22.5 Flood 4 0.76 Poor workmanship/ Loose Connections 17 3.24 Overheating 6 1.14 Insulation Issues 127 24.2 Lightning surges 43 8.2 Line surges/External short circuit 74 14.1 Inadequate maintenance 86 16.4 Vandalism 14 2.7 Others 20 3.81 Total 525 100
  • 5. American Journal of Electrical and Electronic Engineering 161 Table 4. Transformer MVA Loadings (%) during 2011-2015 Injection Substation Transformer Annual MVA Loadings (%) Average MVA Loading (%) 2011 2012 2013 2014 2015 Ugwunwanosike 104.2 110.3 115.7 120.9 127.3 115.68 Army Barracks 137.5 138.2 140.4 145.7 149.8 142.32 Atani 125.6 127.4 130.3 138.1 141.6 132.6 GCM 130.9 133.5 136.8 140.4 144.1 137.14 Awada I 85 87.1 88.2 89.9 93.3 88.7 Awada II 23.5 25.7 28.9 34.6 39.5 30.44 3-3 56.1 58.2 60.1 66.4 70.2 62.2 4. Poor workmanship/ Loose connections – This category though somewhat similar to Inadequate Maintenance /Operation includes workmanship errors in making electrical connections, for instance, the improper use of dissimilar metals together or poor tightening of bolted connections. Ordinarily, loose connections should have been placed in the inadequate maintenance/operation category, but this study had chosen to report it alongside poor workmanship for purpose of emphasis. 5. Overheating -These are failure causes due to excessive heating of the transformer which increases transformer losses, weakens the insulation and finally results in reduced transformer life. Due to abnormal operation conditions such as excessive loads, transformer windings could become overheated resulting in sudden breakdown of the transformer unit. 6. Insulation Failures – These were the leading causes of failure as affirmed by this study. This category excludes those failures where there was evidence of a lightning or a line surge. There are actually four factors that are responsible for insulation deterioration: pyrolosis (heat), oxidation, acidity, and moisture. But moisture is reported separately. The average age of the transformers that failed due to insulation Issues was 18 years. In this study, insulation breakdown has been found to be the major cause of transformer failures in the Onitsha electricity distribution network followed closely by overload. 7. Lightning surges - are transformer failures due to surges arising from a lightning strike. It is normal to first confirm that there was a lightning strike before attributing such transformer failure to lightning surges. 8. Line surges/External short circuit - This category of faults includes switching surges, voltage spikes, line faults/flashovers, and other transmission and distribution (T&D) abnormalities resulting from poor surge protection or inadequate coil clamping and short circuit strength. 9. Inadequate Maintenance /Operation - This category of failure causes include accumulation of dirt, foreign matters and oil, disconnected or improperly set controls, corrosion and loss of coolant, which should have been promptly identified and corrected. Early detection and correction of abnormal conditions in and around electrical equipment often help to prevent eventual breakdowns and loss of finances [7]. 10. Vandalism - These are failures due to carting away by vandals of vital parts of the transformer such as the oil, copper and aluminium, etc. Electrical Infrastructure vandalisation is a common occurrence among electricity distribution networks in Nigeria including the Onitsha distribution network. 11. Others –These are unclassified failure causes and includes all transformer failure causes that are not easily ascertainable. The identified causes of the transformer failures in the Onitsha electricity distribution network during the period 2011-2015 have been expressed in terms of percentages in Figure 5. Figure 5. Classification of failure cause by percentage during 2011-2015 0 20 40 60 80 100 120 140 Moisture Flood Overheating Lightning surges Inadequate maintenance Others Failure Causes in Percentages (%) Percentage Frequency
  • 6. 162 American Journal of Electrical and Electronic Engineering Figure 6. MVA Loading of transformers at the sampled Injection substations in Onitsha distribution network in 2015 The computed transformer MVA loadings in each of the injection substations studied during the period 2011- 2015 are as presented in Table 4 while Figure 6 shows the loadings for the year 2015 only. Observe that many of the transformers are loaded well above 100%. It is obvious also from Figure 6 that the loadings on the transformers increased steadily over the years as the power consumption increased leading eventually to the failure of the affected transformer units. The findings of the study showed that during the period covered by the research, about 60% i.e. four out of the seven Injection substations in the distribution network had various transformer units loaded beyond the nameplate ratings. It is obvious that this high percentage of overloaded transformers contributed significantly to the rapid deterioration of the transformers insulating materials and therefore the high rate of transformer failures as recorded in the study. 4. Conclusion and Recommendations This study investigated transformer failure rates and failure causes in the Onitsha Electricity Distribution Network using both the Electrical Transient Analysis Program (ETAP) software 12.6 and the Statistical Package for the Social Sciences (SPSS) software 16.0. Network data and transformer parameters collected over the period 2011-2015 from substations within the distribution network were simulated on the ETAP software using the Newton-Raphson (N-R) technique to ascertain the transformer loadings while responses to the research questionnaire were statistically analysed on the SPSS software to determine the causes and rate of transformer failures. The findings of the study show that during the five years period of study, injection substations in the Onitsha Electricity Distribution Network recorded an average failure rate of 11.7 % among the installed and operational transformers. The study revealed also that besides Insulation Issues (24.2%), Overloading (22.5%) is the next major cause of transformer failures in the Onitsha Electricity Distribution Network. The study found also that the Army Barracks Injection Substation recorded the highest transformer failure rate of 23.8%. This is followed by GCM and Atani Injection substations with 22.7% and 20.6% failure rates respectively. It is obvious from the responses to the structured questionnaire by the technical staff of the distribution company that these high failure rates were due to inadequate number of transformers which necessitated the overloading of the available units. The study therefore recommends installation of additional transformer units in order to reduce the loads on the existing transformer units within the area. The study also suggests strict statutory legislation against vandalism, good workmanship, balanced loading of the transformers, use of quality transformers as well as proactive monitoring, inspection and maintenance program of the transformers within the network in order to ensure improvement in transformer life span and increased availability of electricity supply. The outcome of this work would help electricity utilities in providing more reliable and cost effective services to customers. Statement of Competing Interests The authors declare that no conflicting interests exist. References [1] Pasricha, A. (2015). "A Study into improving Transformer Loading Capability beyond Nameplate Rating". Masters Theses. Missouri University of Science and Technology, Missouri. [2] Short, T. A. (2003). Electric Power Distribution Handbook. CRC Press. [3] Bartley, W.H. (1998). “An Analysis of Transformer Failures, Part 1 – 1988 through 1997.” Available at https://www.hsb.com/TheLocomotive/AnAnalysisOfTransformer FailuresPart1.aspx. 127.3 149.8 141.6 144.193.3 39.5 70.2 0 20 40 60 80 100 120 140 Ugwunwanosike Army Barracks Atani GCMAwada I Awada II 3-3 Inj SS Transformer MVA (%) Loadings in 2015 MVA (%) Loading
  • 7. American Journal of Electrical and Electronic Engineering 163 [4] Vahidi, F and Tenbohlen, S. Statistical Failure Analysis of European Substation Transformers. Conference paper. November 2014. Available at: https:www.researchgate.net/publication/272088767. [5] Energy Efficiency and Renewable Energy Office (2013). Energy Conservation Program: Energy Conservation Standards for Distribution Transformers Rule. Available at: https://www.regulations.gov/document?D=EERE-2010-BT-STD- 0048-0762. [6] Electrical India (2015). Case Studies of the Transformers Failure Analyses. Available at: http://www.electricalindia.in/blog/post/id/5692/case-studies-of- the-transformers-failure-analyses. [7] Bartley, W.H. (2003). Analysis of Transformer Failures. International Association of Engineering Insurers 36th Annual Conference – Stockholm. [8] Bartley, W.H. (2004). Investigating Transformer Failures. The Hartford Steam Boiler Inspection & Insurance Co., Harford. [9] Mirzai, M.; Gholami, A. and F. Aminifar (2006). Failures Analysis and Reliability Calculation for Power Transformers. Journal of Electrical Systems, 2-1, 1-12. [10] What is the effect of “Overload”? Available at: http//:www.hammondpowersolutions.com. [11] Hershey Energy Systems. Available at: http//:www.hersheyenergy.com. [12] McCarthy, J. (2010). Analysis of Transformer Ratings in a Wind Farm Environment. Dublin Institute of Technology, Dublin. [13] Efobi, K. and Anierobi, C. (2013). Urban Flooding and Vulnerability of Nigerian Cities: A Case Study of Awka and Onitsha in Anambra State, Nigeria. Journal of Law, Policy and Globalization, 19. [14] Tahir, M. “Intelligent Condition Assessment of Power Transformer Based on Data Mining Techniques” (2012). A Masters Thesis. University of Waterloo, Ontario, Canada. [15] Saad, F.A. M. (2011). Predicting Transformer End of Life using Transformer Thermal Life Simulation Technique. Masters Thesis. University Tun Hussein Onn, Malaysia. [16] Jadeja, K.V. (2011). Transformer Testing and Fault Finding. Available at: http://www.brighthubengineering.com/power-generation- distribution/126102-transformer-testing-and-fault-finding/. [17] IEEE C57.125-1991 “IEEE Guide for Failure Investigation, Documentation, and Analysis for Power Transformers and Shunt Reactors”, Transformer Committee of the IEEE Power Engineering Society, Copyright 1992 by the Institute of Electrical and Electronics Engineers, Inc.. [18] Zhong, Q. (2011). Power Transformer End-of-Life Modelling: Linking Statistics with Physical Aging. Doctoral Thesis. The University of Manchester. [19] Mtetwa, S. and Cormack, R. (2006). "Addressing the Requirements of an Ageing Fleet of Transmission Transformers on the Eskom Transmission Network," in CIGRE 2009 6th Southern Africa Regional Conference Cape Town, South Africa. [20] Chmura, L. (2014).Life-cycle assessment of high-voltage assets using statistical tools, PhD thesis. Technical University, Delft. [21] United Nations Human Settlements Programme (2012). Nigeria: Onitsha Urban Profile. UN-Habitat. Available at: http//:worldurbancampaign.org.