Apple
Campus 2
(The Glass
Structure)
AVANI BORSADIYA (K00411)
ANAND THAKKAR
(K00412844)
KAVAN TADHANI
(K00422582)
SHREEKUMAR PATEL
(K00411525)
SUMIT PATEL (K00411648)
PARTH DESAI (K00383385)
Overview
 At first, Apple Inc. appointed two general contractors : DPR and Skanska in
2013.
 They were fired because of they were unable to come to an agreement
with the revised scope of work.
 The companies are replaced with Rudolph & Sletten and Holder
Construction.
Holder Construction
(General Contractor)
Seele Construction
(Sub-Contractor)
AHC Glass
(Sub-Contractor)
AHC Glass
 AHC is a local company situated in a bay area of Hayward, CA having
more than 20 years of experience in a design, fabrication and construction
of structural glasses.
 They have designed and fabricated materials, they naturally move on to
provide the installation service of the glass and its component.
 Contract: Installation of 350 heavy glasses in apple campus.
 Work started: May 2016
 Status: In progress
The ten
knowledge
areas of
construction
management
Project Integration Management
1
Develop
Project
Charter
2
Develop
Project
Manage-
ment Plan
3
Direct and
Manage
Project
Work
4
Monitor
and
Control
Project
Work
5
Perform
Integrated
Change
Control
6
Close
Project or
Phase
Integration
In 2008, Steve Jobs
thought to construct new
Apple campus, the whole
glass structure.
In 2011 Architectural
design was submitted to
city of Cupertino.
Legal documentation
work completed in 2013.
General Contractors and
Sub Contractors were
appointed.
Two general contractors
were fired and they were
replaced.
Glasses and related
materials to fix the
glasses were
manufactured and
imported by Seele from
Germany.
Seele gave guidelines to
AHC on all glass related
works
AHC experimented
different combination of
teams for different type of
work and finalized the
best teams to deal with
the work suitable to them
The work by AHC started
in May, 2016.
Project Scope
Management
 This knowledge area involves the
project scope, that is, the work that is
included within the project.
 Plan Scope Management
 Collect Requirements
 Define Scope
 Create WBS
 Validate Scope
 Control Scope
Scope
 Study the requirements presented by Apple Inc.
 Work according to the guidelines provided by Seele.
 Installation of all the 350 glasses within estimated time as well as in
budget.
 Work with 100% accuracy.
 Safety is the first.
 To achieve the scope,
 Various combinations of team.
 3 teams in operation : Installation of glasses, Caulking Process, Quality
Assurance
 Instant communication on completion of tasks and getting confirmation.
Work Breakdown Structure
AHC
Starting Phase
Define Scope
Identifying
resources
Appoint Project
Team
Storage space
for glass
Equipment
Arranging
Gantry Crane
Arranging
Lowboy Trailer
Arranging
Vacuum Glass
Lifter
Safety signs
Glass Work
Bottom Rail
Installation
Alignment
Measurement
Top Rail
Installation
Alignment
Measurement
Glass
installation
Adjusting Glass
Caulking
Final
measurement
Quality
Quality check
by AHC
Quality check
by Seele
Quality Check
by Holder
Quality check
by Apple Inc.
Communication
Assigning tasks
Reporting of
completed work
Getting
Confirmation
Punchlist
Site Clearance
Final Review
Project Time
Management
 This is usually the most time
consuming of the knowledge areas.
 During planning, the project manager
must divide the project into tasks and
create both a schedule (start and finish
dates for each task) and budget for
each task.
 Plan Schedule Management
 Define Activities
 Sequence Activities
 Estimate Activity Resources
 Estimate Activity Durations
 Develop Schedule
 Control Schedule
Project Time Management
 DPR and SKANSKA were fired by Apple and Apple hired new Company.
 Delay in construction and interior work, because of this AHC faced
problem in starting their work.
 Time increased due to changing of all glass door handles.
 Resources-Top Rail-Bottom Rail-Glass Fitting(2 days)-Site clearance.
 It takes 1-2 days to fit the glass.
 They review the progress every weekly.
 To manage scheduling problem, Employees are still working for 12 hours
since last 8 months.
Project Cost
Management
 The project budget is usually one of
the most sensitive parts of a project.
 Plan Cost Management
 Estimate Costs
 Determine Budget
 Control Costs
Project Cost
Management
 The budget for the glass:- 6 million.
 Around 17% of budget is for equipment.
 Major expanse is for gantry Crane(50-
50).
 They also make a cost-benefit graph.
 Over budgeting due to error in
estimation.
 Cost increased because 45 glasses
were damage and because of increased
rate of rental machinery due to error in
scheduling.
Project Quality
Management
 Quality is one of the triple constraints
of Time, Cost, and Quality. As such,
when you need better quality you need
to put in more time or cost.
 Plan Quality Management
 Perform Quality Assurance
 Control Quality
 Quality work checking by following authorities
 AHC glass inc.
 Seele Company.
 Holder Company.
 Apple (Randomly).
 The typical glass have 1/8 inch tolerance but apple
demanded THE 1/32 inch tolerance.
 The gap :- 5 mm (< 1mm allowable).
 Glass work- Noise(ITU-R 468 noise weighting).
 Even worker wear gloves to touch the material
which we can touch without gloves.
Project Quality
Management
Project Human
Resource
Management
 The Project team is usually one of the
most important factors in the success
of a project.
 If you have a good team, you will have
a successful project. This knowledge
area is concerned with acquiring the
right team, ensuring their satisfaction,
and tracking their performance.
 Plan Human Resource Management
 Acquire Project Team
 Develop Project Team
 Manage Project Team
 15-16 members.
 20 members team for Apple Campus 2 at site.
 Different Combination – Final Team on base on output.
 Seele taught the worker of AHC.
 4 Manager.
 Site Manager.
 Safety Manager.
 Project Manager.
 Project Co-ordinater.
 4 types of labours
 Apparatus
 Journey Man
 Lead Man
 Forman
Project Human
Resource
Management
Material Management
 Warehouse 1:- AHC warehouse(5000 sf).
 Warehouse 2:- 3 time larger than AHC one.
 Equipment:-
 Lowboy Trailer.
 Gantry Truck.
 Gang Box.
 Vacuum Glass Lifter.
 Laser Machine for alignment.
Project
Communication
Management
 Communication with stakeholders is
often the key factor that allows
stakeholders to be satisfied even when
unexpected changes happen.
 It is essential to develop
communication plan to keep all
stakeholders “in the loop” throughout
the project and communicate early and
often when unexpected issues occur.
 Plan Communications Management
 Manage Communications
 Control Communications
Project Communication Management
 Email through.
 Report within 5 min of the completion of work.
 Quality Check at the same day of completion (by 3 members).
 Weekly and Monthly Meetings.
 Walkie Talkie communication while construction.
 Develop software(Park-2.0) to cumulate the work process.
 Daily schedules-Whatsapp-Email-Text.
Project Risk
Management
 Managing project risk is one of the
most underrated aspects of project
management. Major risk are very
seldom identified up front and analyzed
within the project management plan,
but when they are project stakeholders
tend to forgive the unexpected issues
much quicker.
 Plan Risk Management
 Identify Risks
 Perform Qualitative Risk Analysis
 Perform Quantitative Risk Analysis
 Plan Risk Responses
 Control Risks
Project Risk Management
 Handling of Vacuum Glass Lifter
(Weight-limited space).
 Safety risk for material and man
power(45- glass damaged).
 It’s challenging when you’re doing
first-of’s.
 They certainly have a lot more
schedule and cost risk associated
with them.
Project
Procurement
Management
 Almost all projects have some form
of outside procurement. Hiring
subcontractors can get the job done
quicker or with better expertise but
sacrifices the ability to control the
quality, schedule, or other factors.
 Plan Procurement Management
 Conduct Procurements
 Control Procurements
 Close Procurements
 Procurement for machinery from another company
 Procurement for glass which they are getting from Germany
 Procurement for safety
Project
Stakeholder
Management
 There is nothing more important than
the project’s stakeholders.
 You could, in theory, declare a project
a success if the stakeholders are
satisfied but the project was a disaster
if the stake holders are not satisfied.
 The stakeholders should be actively
managed and addressed within the
project management plan.
 Identify Stakeholders
 Plan Stakeholder Management
 Manage Stakeholder Engagement
 Control Stakeholder Engagement
Project Stakeholder Management
 Apple-Monthly meeting.
 Holder-Monthly meeting.
 Seele- weekly meeting.
 Also workers was taught for
new technique.
Delivery Methods
 AHC – Design Bid Built.
Constructor:- Unite Price
Apple
Foster &
Partner
Holder
Seele
AHC
Glass Inc.
Organization Structure
 Balanced Matrix Organization Structure
Seele Manager 1 Seele Manager 2 Seele Manager 3
Holder Manager 1 AHC Manager AHC Manager AHC Manager
Holder Manager 2 AHC Manager AHC Manager AHC Manager
Thank You

More Related Content

PDF
The Shard, Skyscraper - Architectural Case Study
PPTX
Sabarmati riverfront development
PDF
DLF Cyber city (integrated business district)
PPTX
Construction Management Case Study on Burj Khalifa
PPTX
ITC Green Centre Gurgaon
PPT
Sustainable Architecture PPT
 
PPTX
Suzlon One Earth Case Study by Ameya Gumaste
The Shard, Skyscraper - Architectural Case Study
Sabarmati riverfront development
DLF Cyber city (integrated business district)
Construction Management Case Study on Burj Khalifa
ITC Green Centre Gurgaon
Sustainable Architecture PPT
 
Suzlon One Earth Case Study by Ameya Gumaste

What's hot (20)

PPTX
District center (college projects)
PPTX
Project management for engineers and architects
PDF
Indira paryavaran bhawan and griha
PPTX
internship report on architecture
PPTX
School Design
PPTX
CII green building
PDF
Sabarmati Riverfront Development Project
PPSX
Case study of sacube
PPTX
Development controls and Chandigarh Architectural controls
PPTX
Christopher alexander
PPTX
What are Development controls
PPTX
INFOSYS GREEN BUILDING
PDF
Opera sydney case study analysis
PPTX
PPTX
Mini sky city, china
PPTX
City center - An Urban Lifestyle Center
PPTX
Inorbit malad-vashi-case study
PPTX
Bhubaneswar- Urban Planning
PPTX
Chhatrapati Shivaji International Airport
PDF
TEL AVIV CASE STUDY
District center (college projects)
Project management for engineers and architects
Indira paryavaran bhawan and griha
internship report on architecture
School Design
CII green building
Sabarmati Riverfront Development Project
Case study of sacube
Development controls and Chandigarh Architectural controls
Christopher alexander
What are Development controls
INFOSYS GREEN BUILDING
Opera sydney case study analysis
Mini sky city, china
City center - An Urban Lifestyle Center
Inorbit malad-vashi-case study
Bhubaneswar- Urban Planning
Chhatrapati Shivaji International Airport
TEL AVIV CASE STUDY
Ad

Similar to Apple campus 2 Project management (20)

DOCX
William Richards
PPT
01-Introduction to Project Management.ppt
PDF
ACHAL_JOSHI_Academic_Profile
PDF
Introduction to Project Management
PPT
Project Management ORION Systems
PPT
Critical Chain Basics
PPT
Northern Finishing School: IT Project Managment
PPTX
Operations Management (Project Management).pptx
PPTX
Project Management Framework
PPT
Lci la chapter lean intro 071410 no pics
PPT
Adaptive Management
PPT
Risk Management
DOCX
Creek Vista Marine FARAAZ KHAN WORK Report.docx
PPT
Cms solution 08072010
PPT
Project Management For The Curious
PPT
Pm fundamentals
PPT
Agile Methods: Fact or Fiction
DOC
Gyasi Brown Resume 6-8-16
PPTX
Project presentation - Filing Cabinet Project
PPT
The project plan
William Richards
01-Introduction to Project Management.ppt
ACHAL_JOSHI_Academic_Profile
Introduction to Project Management
Project Management ORION Systems
Critical Chain Basics
Northern Finishing School: IT Project Managment
Operations Management (Project Management).pptx
Project Management Framework
Lci la chapter lean intro 071410 no pics
Adaptive Management
Risk Management
Creek Vista Marine FARAAZ KHAN WORK Report.docx
Cms solution 08072010
Project Management For The Curious
Pm fundamentals
Agile Methods: Fact or Fiction
Gyasi Brown Resume 6-8-16
Project presentation - Filing Cabinet Project
The project plan
Ad

Recently uploaded (20)

PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
Visual Aids for Exploratory Data Analysis.pdf
PPTX
Feature types and data preprocessing steps
PDF
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
PPTX
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
August 2025 - Top 10 Read Articles in Network Security & Its Applications
PPTX
Fundamentals of Mechanical Engineering.pptx
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PPTX
Management Information system : MIS-e-Business Systems.pptx
PPTX
Current and future trends in Computer Vision.pptx
PPTX
Software Engineering and software moduleing
PDF
Abrasive, erosive and cavitation wear.pdf
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PDF
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
PDF
distributed database system" (DDBS) is often used to refer to both the distri...
PDF
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
PDF
737-MAX_SRG.pdf student reference guides
PPTX
Nature of X-rays, X- Ray Equipment, Fluoroscopy
PPTX
communication and presentation skills 01
Automation-in-Manufacturing-Chapter-Introduction.pdf
Visual Aids for Exploratory Data Analysis.pdf
Feature types and data preprocessing steps
Influence of Green Infrastructure on Residents’ Endorsement of the New Ecolog...
Sorting and Hashing in Data Structures with Algorithms, Techniques, Implement...
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
August 2025 - Top 10 Read Articles in Network Security & Its Applications
Fundamentals of Mechanical Engineering.pptx
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Management Information system : MIS-e-Business Systems.pptx
Current and future trends in Computer Vision.pptx
Software Engineering and software moduleing
Abrasive, erosive and cavitation wear.pdf
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Accra-Kumasi Expressway - Prefeasibility Report Volume 1 of 7.11.2018.pdf
distributed database system" (DDBS) is often used to refer to both the distri...
Artificial Superintelligence (ASI) Alliance Vision Paper.pdf
737-MAX_SRG.pdf student reference guides
Nature of X-rays, X- Ray Equipment, Fluoroscopy
communication and presentation skills 01

Apple campus 2 Project management

  • 1. TEXAS A&M UNIVERSITY- KINGSVILLE CEEN 5303 CONSTRUTION MANAGEMENT
  • 2. Apple Campus 2 (The Glass Structure) AVANI BORSADIYA (K00411) ANAND THAKKAR (K00412844) KAVAN TADHANI (K00422582) SHREEKUMAR PATEL (K00411525) SUMIT PATEL (K00411648) PARTH DESAI (K00383385)
  • 3. Overview  At first, Apple Inc. appointed two general contractors : DPR and Skanska in 2013.  They were fired because of they were unable to come to an agreement with the revised scope of work.  The companies are replaced with Rudolph & Sletten and Holder Construction. Holder Construction (General Contractor) Seele Construction (Sub-Contractor) AHC Glass (Sub-Contractor)
  • 4. AHC Glass  AHC is a local company situated in a bay area of Hayward, CA having more than 20 years of experience in a design, fabrication and construction of structural glasses.  They have designed and fabricated materials, they naturally move on to provide the installation service of the glass and its component.  Contract: Installation of 350 heavy glasses in apple campus.  Work started: May 2016  Status: In progress
  • 6. Project Integration Management 1 Develop Project Charter 2 Develop Project Manage- ment Plan 3 Direct and Manage Project Work 4 Monitor and Control Project Work 5 Perform Integrated Change Control 6 Close Project or Phase
  • 7. Integration In 2008, Steve Jobs thought to construct new Apple campus, the whole glass structure. In 2011 Architectural design was submitted to city of Cupertino. Legal documentation work completed in 2013. General Contractors and Sub Contractors were appointed. Two general contractors were fired and they were replaced. Glasses and related materials to fix the glasses were manufactured and imported by Seele from Germany. Seele gave guidelines to AHC on all glass related works AHC experimented different combination of teams for different type of work and finalized the best teams to deal with the work suitable to them The work by AHC started in May, 2016.
  • 8. Project Scope Management  This knowledge area involves the project scope, that is, the work that is included within the project.  Plan Scope Management  Collect Requirements  Define Scope  Create WBS  Validate Scope  Control Scope
  • 9. Scope  Study the requirements presented by Apple Inc.  Work according to the guidelines provided by Seele.  Installation of all the 350 glasses within estimated time as well as in budget.  Work with 100% accuracy.  Safety is the first.  To achieve the scope,  Various combinations of team.  3 teams in operation : Installation of glasses, Caulking Process, Quality Assurance  Instant communication on completion of tasks and getting confirmation.
  • 10. Work Breakdown Structure AHC Starting Phase Define Scope Identifying resources Appoint Project Team Storage space for glass Equipment Arranging Gantry Crane Arranging Lowboy Trailer Arranging Vacuum Glass Lifter Safety signs Glass Work Bottom Rail Installation Alignment Measurement Top Rail Installation Alignment Measurement Glass installation Adjusting Glass Caulking Final measurement Quality Quality check by AHC Quality check by Seele Quality Check by Holder Quality check by Apple Inc. Communication Assigning tasks Reporting of completed work Getting Confirmation Punchlist Site Clearance Final Review
  • 11. Project Time Management  This is usually the most time consuming of the knowledge areas.  During planning, the project manager must divide the project into tasks and create both a schedule (start and finish dates for each task) and budget for each task.  Plan Schedule Management  Define Activities  Sequence Activities  Estimate Activity Resources  Estimate Activity Durations  Develop Schedule  Control Schedule
  • 12. Project Time Management  DPR and SKANSKA were fired by Apple and Apple hired new Company.  Delay in construction and interior work, because of this AHC faced problem in starting their work.  Time increased due to changing of all glass door handles.  Resources-Top Rail-Bottom Rail-Glass Fitting(2 days)-Site clearance.  It takes 1-2 days to fit the glass.  They review the progress every weekly.  To manage scheduling problem, Employees are still working for 12 hours since last 8 months.
  • 13. Project Cost Management  The project budget is usually one of the most sensitive parts of a project.  Plan Cost Management  Estimate Costs  Determine Budget  Control Costs
  • 14. Project Cost Management  The budget for the glass:- 6 million.  Around 17% of budget is for equipment.  Major expanse is for gantry Crane(50- 50).  They also make a cost-benefit graph.  Over budgeting due to error in estimation.  Cost increased because 45 glasses were damage and because of increased rate of rental machinery due to error in scheduling.
  • 15. Project Quality Management  Quality is one of the triple constraints of Time, Cost, and Quality. As such, when you need better quality you need to put in more time or cost.  Plan Quality Management  Perform Quality Assurance  Control Quality
  • 16.  Quality work checking by following authorities  AHC glass inc.  Seele Company.  Holder Company.  Apple (Randomly).  The typical glass have 1/8 inch tolerance but apple demanded THE 1/32 inch tolerance.  The gap :- 5 mm (< 1mm allowable).  Glass work- Noise(ITU-R 468 noise weighting).  Even worker wear gloves to touch the material which we can touch without gloves. Project Quality Management
  • 17. Project Human Resource Management  The Project team is usually one of the most important factors in the success of a project.  If you have a good team, you will have a successful project. This knowledge area is concerned with acquiring the right team, ensuring their satisfaction, and tracking their performance.  Plan Human Resource Management  Acquire Project Team  Develop Project Team  Manage Project Team
  • 18.  15-16 members.  20 members team for Apple Campus 2 at site.  Different Combination – Final Team on base on output.  Seele taught the worker of AHC.  4 Manager.  Site Manager.  Safety Manager.  Project Manager.  Project Co-ordinater.  4 types of labours  Apparatus  Journey Man  Lead Man  Forman Project Human Resource Management
  • 19. Material Management  Warehouse 1:- AHC warehouse(5000 sf).  Warehouse 2:- 3 time larger than AHC one.  Equipment:-  Lowboy Trailer.  Gantry Truck.  Gang Box.  Vacuum Glass Lifter.  Laser Machine for alignment.
  • 20. Project Communication Management  Communication with stakeholders is often the key factor that allows stakeholders to be satisfied even when unexpected changes happen.  It is essential to develop communication plan to keep all stakeholders “in the loop” throughout the project and communicate early and often when unexpected issues occur.  Plan Communications Management  Manage Communications  Control Communications
  • 21. Project Communication Management  Email through.  Report within 5 min of the completion of work.  Quality Check at the same day of completion (by 3 members).  Weekly and Monthly Meetings.  Walkie Talkie communication while construction.  Develop software(Park-2.0) to cumulate the work process.  Daily schedules-Whatsapp-Email-Text.
  • 22. Project Risk Management  Managing project risk is one of the most underrated aspects of project management. Major risk are very seldom identified up front and analyzed within the project management plan, but when they are project stakeholders tend to forgive the unexpected issues much quicker.  Plan Risk Management  Identify Risks  Perform Qualitative Risk Analysis  Perform Quantitative Risk Analysis  Plan Risk Responses  Control Risks
  • 23. Project Risk Management  Handling of Vacuum Glass Lifter (Weight-limited space).  Safety risk for material and man power(45- glass damaged).  It’s challenging when you’re doing first-of’s.  They certainly have a lot more schedule and cost risk associated with them.
  • 24. Project Procurement Management  Almost all projects have some form of outside procurement. Hiring subcontractors can get the job done quicker or with better expertise but sacrifices the ability to control the quality, schedule, or other factors.  Plan Procurement Management  Conduct Procurements  Control Procurements  Close Procurements
  • 25.  Procurement for machinery from another company  Procurement for glass which they are getting from Germany  Procurement for safety
  • 26. Project Stakeholder Management  There is nothing more important than the project’s stakeholders.  You could, in theory, declare a project a success if the stakeholders are satisfied but the project was a disaster if the stake holders are not satisfied.  The stakeholders should be actively managed and addressed within the project management plan.  Identify Stakeholders  Plan Stakeholder Management  Manage Stakeholder Engagement  Control Stakeholder Engagement
  • 27. Project Stakeholder Management  Apple-Monthly meeting.  Holder-Monthly meeting.  Seele- weekly meeting.  Also workers was taught for new technique.
  • 28. Delivery Methods  AHC – Design Bid Built. Constructor:- Unite Price Apple Foster & Partner Holder Seele AHC Glass Inc.
  • 29. Organization Structure  Balanced Matrix Organization Structure Seele Manager 1 Seele Manager 2 Seele Manager 3 Holder Manager 1 AHC Manager AHC Manager AHC Manager Holder Manager 2 AHC Manager AHC Manager AHC Manager