SlideShare a Scribd company logo
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 1 of 63
Application of Systems Lifecycle Processes to Large, Complex
Engineering and Construction Programs 1
By Bob Prieto
Chairman & CEO
Strategic Program Management LLC
The complexity of megaprojects and programs continues to grow and with it the challenges
of delivering ever larger and more complex programs. These large complex programs open
the door to many new opportunities but also to increased challenges in delivery and
sustainment throughout their lifecycle. Prior articles have described the open nature of this
large complex program system2 and compared its attributes to many we find in the world
of relativistic physics3. These challenges must be addressed recognizing that they arise
from a combination of physical, fiscal and human attributes in a realm of complexity which
challenges the very foundations of project management theory.
This paper looks at hard systems aspects as contrasted with the soft system aspects
more characteristic of an open system. Its purpose is to adapt a systems engineering
framework associated with the hard closed elements of these large complex project
systems without losing site of the overall open systems nature of large complex programs.
The systems life cycle process codified in ISO 15288 lends itself to application in large
complex engineering and construction programs. It provides a framework to aid in the
integration of physical, fiscal and human factors from a lifecycle perspective. This life
cycle spans the assets initial conception through ultimate disposal of the consumed asset.
The table that follows identifies where specific outcomes and the associated activities to
accomplish them may reside. These have been defined as at a program level (PMC,
Program Management Consultant), project level (PM, Project Manager) or at a lower
project execution level (PExec). Several limitations should be noted. First, the standard
itself and the application as presented in this table do not do sufficient justice to the social
and environmental aspects of a triple bottom line perspective. Here the reader would
benefit from a closer view as can be seen in Prieto 20124. Second, the open systems
1
How to cite this paper: Prieto, R. (2020). Application of Systems Lifecycle Processes to Large, Complex
Engineering and Construction Programs; PM World Journal, Vol. IX, Issue X, October.
2
Prieto, R. (2020) Systems Nature of Large Complex Programs; PM World Journal, Vol. IX, Issue VIII, August
3
Prieto, R. (2020). A Deeper Look at the Physics of Large Complex Projects; A Neo-classical Project Management
Theory is Required; PM World Journal, Vol. IX, Issue VIII, August
4
Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March 2012;
https://www.researchgate.net/publication/272504721_Application_of_Life_Cycle_Analysis_in_the_Capital_Assets_
Industry
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 2 of 63
aspects of large complex programs are not truly covered and as such this may best be
regarded as a subset of a larger open system perspective related to large complex
programs.
The table follows the general format of ISO 15288, grouping system processes into four
groups:
• Agreement processes
• Enterprise processes
• Project processes
• Technical processes
The table is intended to provide a framework where each activity can be further broken
down into a series of tasks. In an earlier use IP under development related to the
management of large complex projects was mapped to this system life cycle process.
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
1.0 Agreement
Processes
1.1 Acquisition PMC,PM,PExec Acquisition
strategy
Acquisition plan
Supplier
selection
RFP
Supplier
communication
Supplier
dialogue
including
partnering
Supplier
justification
Supply
evaluation;
selection;
justification
Agreement for
product or
service
Negotiate/execut
e contract;
confirm contract
compliance
Acceptance of
product or
service
Resolution of
exceptions to
contract; final
acceptance
Payment Periodic and
final payments
1.2 Supply to
Client
Pre-Engagement Client
identification
Authorizing,
financing and
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 3 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
accepting client
elements
Respond to
client request
(RFQ;RFP)
Bid no-bid;
Identification of
contract
exceptions
requiring
resolution
Agreement for
work to be
performed
Negotiate and
execute
agreement
Communication
with client
Assess
execution of the
agreement
Project
execution per
contract and
agreed
procedures
Deliver project in
accordance with
agreement
Final
acceptance by
client
Transfer facility
Payment Accept and
acknowledge
payment
2.0 Enterprise
Processes
2.1 Enterprise
Environment
Management
PMC Policies and
procedures for
the strategic
management of
lifecycles
Establish top
level strategies
and plans that
will be
undertaken to
achieve strategic
business
objectives5
Define,
integrate,
communicate
the roles and
responsibilities,
5
National Academy of Construction Executive Insights; The Importance of Strategic Business Objectives
https://www.naocon.org/wp-content/uploads/The-Importance-of-Strategic-Business-Objectives.pdf
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 4 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
authorities to
implement
system life cycle
processes and
management
Define business
criteria that
control
progression
through the
system life cycle
(stage gate6
)
Accountability
and authority for
system life cycle
management
System life cycle
processes and
procedures
Policy to
improve system
lifecycle
processes
Conduct periodic
reviews of life
cycle model
Communicate to
projects policies
and procedures
2.2 Investment
management
Process
PMC Qualification and
selection of
investment
opportunities
Identify project
portfolio and
required
thresholds
Prioritize
projects
Define projects,
accountabilities
and authorities
(program view)
Identify
expected
projects
outcomes (link
to SBO)
6
PMO & the Tollgate Process; PM World Journal; May 2013;
https://www.researchgate.net/publication/272505052_PMO_the_Tollgate_Process
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 5 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Resource and
budget
identification and
allocation
Allocate
resources to
achievement of
project
outcomes
Project
Management
accountability
and authorities
defined
Clear
identification of
multi-project
interfaces
Project reporting
and review
requirements
Authorize project
execution
Projects meeting
agreement,
stakeholder and
organization
requirements
(SBO etc.) are
sustained
Evaluate
ongoing project
progress
Evaluate
compliance with
project directives
Evaluate
conformance
with system life
cycle plans and
procedures
Confirm
continuing
project necessity
and validity
(SBO test)
Projects not
meeting
agreement,
stakeholder and
organization
requirements
Evaluate
alternatives to
cancel, suspend
and redirect
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 6 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
are redirected or
terminated
2.3 System life
cycle process
management
PMC System life cycle
processes are
defined
Establish
standard sets of
system life cycle
processes for
applicable
system life cycle
stages
Policy to apply
processes are
defined
Establish
acceptable
tailoring and
application
policies and
procedures with
approval
requirements
Policy on
adapting defined
policies to
specific project
needs is defined
Establish
acceptable
tailoring and
application
policies and
procedures with
approval
requirements
Methods and
tools to support
life cycle
process
execution are
identified
Measures are
defined to
evaluate
application of
the system life
cycle process
Establish
performance
measures
Monitor process
execution and
identify
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 7 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
enterprise level
trends
Improvements to
the definition
and application
of system life
cycle
performances
are undertaken
Identify
opportunities for
improvement
Improve
processes,
methods and
tools
2.4 Resource
Management
Process
PMC Necessary
resources,
materials and
services are
provided to
projects
Map necessary
resources,
materials and
services to
project plans
and future
business/progra
m needs
Define
applicable
physical and
human factors
and how they
may change in
the future
Determine and
provide the
resource
infrastructure
support needed
and provide
project support
Obtain non
personnel
resources to
implement and
support projects
Maintain and
manage the pool
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 8 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
of personnel
necessary to
staff ongoing
projects
Skills of
personnel are
maintained and
enhanced
Manage
competency
throughout the
life cycle
Provision of
training and
education to
improve skill
sets and support
career path
Motivate staff
through career
development
and rewards
Conflicts in
multi-project
resource
demands are
resolved
Control multi-
project
resources to
resolve schedule
conflicts
2.5 Quality
Management
PMC Quality
management
policies and
procedures are
defined
Establish quality
management
policies,
standards and
procedures
(ISO 9001;
9004)
Quality goals
and objectives
are defined
Establish quality
management
goals and
objectives to
achieve SBO,
support top level
strategies and
achieve client
satisfaction
Quality
management
accountability
Define
responsibilities
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 9 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
and authority
defined
for quality
management
Status of client
and stakeholder
satisfaction is
monitored
Assess client
and stakeholder
satisfaction and
report
Corrective action
taken when
quality goals not
achieved
Conduct periodic
reviews of
project quality
plans assuring
quality
objectives based
on stakeholder
requirements
have been
established
Monitor the
status of quality
improvement
3.0 Project
Processes
3.1 Project
Planning
Process
PM Project plans
exist
Objectives and
constraints
identified
including
performance,
quality, cost,
time,
stakeholder
Objectives
sufficiently
defined to permit
selection and
implementation
of appropriate
processes and
activities
Define project
scope7
as
7
Prieto, R. (2019). The Primacy of the Scope Baseline in Engineering & Construction Projects; PM World Journal,
Vol. VIII, Issue IX, October;
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 10 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
established in
agreement
Define all
activities to
complete the
project
successfully
Establish a work
breakdown
structure
Define and
maintain a
project schedule
based on project
objectives and
work estimates.
Includes
duration,
relationship,
dependencies,
sequence,
achievement
milestones,
resources and
reviews.
Define project
achievement
criteria for life
cycle stage
decision gates,
delivery dates,
major
dependencies
on external
inputs or outputs
Define project
costs and plan a
budget
https://www.researchgate.net/publication/336496336_The_Primacy_of_the_Scope_Baseline_in_Engineering_Const
ruction_Projects
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 11 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Roles,
responsibilities
and authorities
are defined
Define the
project
organization,
staff
acquisitions,
staff skills
development
and work
methods
Establish the
structure of
authorities and
responsibilities
of project work
Resources and
services
necessary to
achieve project
objectives are
formally
requested
Define the
infrastructure
and services
required by the
project
Plan the
acquisition of
materials, goods
and enabling
system services
supplied from
outside the
project8
Technical
management
plan developed
and
communicated
(includes
reviews)
Project
performance
Define project
measures to be
used, data to be
8
National Academy of Construction Executive Insights; Procurement Management in Large Complex Programs
https://www.naocon.org/wp-content/uploads/Procurement-Management-in-Large-Complex-Programs.pdf
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 12 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
measures are
defined
collected
(including
sources),
validated and
analyzed9
Prepare project
quality plan
Project staff
directed in
accordance with
project plans
Conduct project
audits
3.2 Project
assessment
process
PMC,PM Project
performance
measures or
assessment
results are
available
Assess project
status against
plans to
determine actual
and projected
performance,
identifying
variations10
Perform quality
assurance in
accordance with
project plans
Adequacy of
roles
responsibilities
and authorities
assessed
Assess
effectiveness of
project team
structure, roles
and
responsibilities
Adequacy of
resources and
services
necessary
assessed
Assess
adequacy of
team member
competencies
9
Prieto, B. (2019). Impacts of Artificial Intelligence on Management of Large Complex Projects. PM World
Journal, Vol. VIII, Issue V, June;
https://www.researchgate.net/publication/334162272_Impacts_of_Artificial_Intelligence_on_Management_of_Larg
e_Complex_Projects
10
National Academy of Construction Executive Insights; Effective Project Review Meetings
https://www.naocon.org/wp-content/uploads/Effective-Project-Review-Meetings.pdf
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 13 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Assess
adequacy and
availability of the
project’s
supporting
infrastructure
Confirm intra-
organizational
commitments
are met
Deviations in
project
performance are
analyzed
Assess project
performance
using measured
achievement
and milestone
completion
Determine
effectiveness
and adequacy of
evolving
capabilities to
meet a range of
future needs
Conduct
required
management
and technical
reviews, audits
and inspection
to determine
readiness to
proceed to next
life cycle stage
or milestone11
Monitor critical
processes and
new work
methods and
technologies
11
National Academy of Construction Executive Insights, Owner Readiness https://www.naocon.org/wp-
content/uploads/Owner-Readiness.pdf
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 14 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Analyze data for
variations and
make
recommendation
for appropriate
action
Concerned
parties are
informed of
project status
Provide periodic
status and
required
deviation reports
3.3 Project
Control
Process
PM Corrective action
is defined and
directed when
achievement not
meeting targets
Manage project
requirements
and changes to
requirements in
accordance with
the project
plans.
Initiate the
corrective
actions needed
to achieve the
goals and
outputs of
project tasks
that have
deviated
outside
acceptable or
defined limits.
Re-deployment
and re-
assignment of
personnel, tools
and project
infrastructure
assets when
inadequacy or
unavailability
has been
detected.
Initiate
preventive
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 15 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
actions, as
appropriate, to
ensure
achievement of
the goals and
outputs of the
project.
Initiate problem
resolution
actions to
correct non-
conformances.
Performing
corrective
actions to the
implementation
and execution of
the life cycle
processes when
non-
conformances
are traced to
them.
Project re-
planning is
initiated when
project
objectives or
constraints
change or
assumptions
invalidated or
migrated
Evolve with time
the scope,
definition and
the related
breakdown of
the work to be
carried out by
the project in
response to the
corrective action
decisions taken
and the
estimated
changes they
introduce.
Initiate change
actions when
there is a
contractual
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 16 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
change to cost,
time or quality
due to the
impact of client
or supplier
request.
Act to correct
defective
provision of
acquired goods
and services
through
constructive
interaction with
the supplier.
Project action to
advance to next
milestone is
authorized
Authorize the
project to
proceed toward
the next
milestone or
event if justified
Project
objectives are
achieved
Conduct project
audit12
3.4 Decision
Making
Processes
All Decision-making
strategy is
defined.
Define a
decision-making
strategy
including the
identification and
allocation of
responsibility for,
and authority to
make decisions.
Alternative
courses of
action are
defined.
Involve relevant
parties in the
decision-making
in order to draw
on experience
and knowledge.
12
Program Management Audit Checklist
https://www.researchgate.net/publication/273118616_Program_Management_Audit_Checklist
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 17 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Identify the
circumstances
and need for a
decision.
Record,
categorize and
promptly and
objectively
report problems
or opportunities
and the
alternative
courses of
action that will
resolve their
outcome.
Preferred course
of action is
selected.
Select and
declare the
decision-making
strategy for each
decision
situation. Identify
desired
outcomes and
measurable
success criteria.
Evaluate the
balance of
consequences
of alternative
actions, using
the defined
decision-making
strategy, to
arrive at an
optimization of,
or an
improvement in,
an identified
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 18 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
decision
situation.
Resolution,
decision
rationale and
assumptions are
captured and
reported.
Record, track,
evaluate and
report decision
outcomes to
confirm that
problems have
been effectively
resolved,
adverse trends
have been
reversed and
advantage has
been taken of
opportunities.
Maintain records
of problems and
opportunities
and their
disposition, as
stipulated in
agreements or
organizational
procedures and
in a manner that
permits auditing
and learning
from experience.
3.5 Risk
Management
Process
PMC,PM Risks are
identified and
categorized.
Establish a
systematic
approach to risk
identification,
assessment and
treatment.
Identify and
define the risks.
Identifying the
initiating events
associated with
each risk in each
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 19 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
risk category,
and defining the
interrelationship
s between
sources of risk.
The probabilities
and
consequence of
risks are
quantified.
Determine the
probability
associated with
risk occurrence
using
established risk
criteria. Criteria
can include
associated cost,
legal and
statutory
requirements,
socio-economic
and
environmental
aspects, the
concerns of
stakeholders,
priorities and
other inputs to
the assessment.
Evaluate the
risks in terms of
their possible
consequences
using the
established
criteria.
Prioritize the
risks in terms of
their probability
and
consequences.
Strategy to treat
each risk is
specified.
Determine the
risk treatment
strategies.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 20 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Define a
threshold of
acceptability for
each identified
risk.
Identify the risk
treatment
actions to follow
if the threshold
of acceptability
is exceeded.
For risks that
have high
consequences13
,
establish
contingency
plans that will be
initiated if
mitigation
actions are
unsuccessful.
Risk status is
available and
communicated.
Communicate
the risk
treatment
actions and their
status in
accordance with
the agreement,
policies and
procedures.
Maintain a
register of risk
throughout the
life cycle.
Register
includes a
definition of the
current
13
National Academy of Construction Executive Insights, Fat Tails
https://www.researchgate.net/publication/340949652_Risk_and_Opportunities_Fat_Tails_Key_Points
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 21 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
perception of
risks, and the
relationship to
risk treatment
actions and
budgets.
Risks that have
become
unacceptable
are acted upon
3.6
Configuration
Management
PMC, PM Configuration
management
strategy is
defined.
Define a
configuration
management
strategy
compatible with
the guidance
provided in ISO
10007.
Items requiring
configuration
management
are defined.
Identify items
that are subject
to configuration
control.
Configuration
baselines are
established.
Maintain
information on
configurations
with an
appropriate level
of integrity and
security.
Changes to
items under
configuration
management
are controlled.
Ensure that
configuration
information
permits forward
and backward
traceability to
other baselined
configuration
states.
The
configuration of
released items is
controlled.
Ensure that
changes to
configuration
baselines are
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 22 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
properly
identified,
recorded,
evaluated,
approved,
incorporated,
and verified.
Status of items
under
configuration
management is
made available
throughout the
life cycle.
Ensure that
changes to
configuration
baselines are
properly
identified,
recorded,
evaluated,
approved,
incorporated,
and verified.
Perform audits
to verify
conformance of
a baseline to
drawings,
interface control
documents and
other agreement
requirements.
3.7 Information
Management
Process
All Information to be
managed is
identified.
Define the items
of information
that will be
managed during
the system life
cycle and,
according to
organizational
policy or
legislation,
maintained for a
defined period
beyond.
Designate
authorities and
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 23 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
responsibilities
regarding the
origination,
generation,
capture,
archiving and
disposal of items
of information.
Define the
rights,
obligations and
commitments
regarding the
retention of,
transmission of
and access to
information
items.
Forms of the
information
representations
are defined.
Define the
content,
semantics,
formats and
medium for the
representation,
retention,
transmission
and retrieval of
information.
Information is
transformed and
disposed of as
required.
Obtain the
identified items
of information.
Status of
information is
recorded.
Maintain
information
items and their
storage records
according to
integrity, security
and privacy
requirements.
Information is
current,
Define
information
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 24 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
complete and
valid.
maintenance
actions.
Information is
made available
to designated
parties.
Retrieve and
distribute
information to
designated
parties as
required by
agreed
schedules or
defined
circumstances.
Provide official
documentation
as required.
Archive
designated
information, in
accordance with
the audit and
knowledge
retention
purposes.
Dispose of
unwanted,
invalid or
unverifiable
information
according to
organization
policy, and
security and
privacy
requirements.
4.0 Technical
Processes
4.1
Stakeholder
Requirements
Definition
Process
PMC, PM Required
characteristics
and context of
use of services
specified.
Identify the
individual
stakeholders or
stakeholder
classes who
have interest in
the system
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 25 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
throughout its
life cycle14
.
Elicit
stakeholder
requirements.
Constraints on a
system solution
are defined.
Define the
constraints on a
system solution
that are
unavoidable
consequences
of existing
agreements,
management
decisions and
technical
decisions.
Traceability of
stakeholder
requirements to
stakeholders
and their needs
is achieved.
Define a
representative
set of activity
sequences to
identify all
required
services that
correspond to
anticipated
operational and
support
scenarios and
environments.
Scenarios are
used to analyze
the operation of
the system in its
intended
environment in
order and to
identify
14
Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011
https://www.researchgate.net/publication/273119019_Stakeholder_Management_in_Large_Engineering_Constructi
on_Programs
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 26 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
requirements
that may not
have been
formally
specified by any
of the
stakeholders,
e.g. legal,
regulatory and
social
obligations.
Context of use
of the system is
identified and
analyzed.
Include in the
context analysis
the activities that
users perform to
achieve system
objectives, the
relevant
characteristics of
the end-users of
the system, the
physical
environment and
any equipment
to be used.
The social and
organizational
influences on
users that could
affect system
use or constrain
its design are
analyzed when
applicable.
Basis for
defining the
system
Identify the
interaction
between users
and the system.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 27 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
requirements is
described.
Usability
requirements
are determined,
establishing, as
a minimum, the
most effective,
efficient, and
reliable human
performance
and human-
system
interaction.
Define required
physical, mental,
and learned
capabilities
Define work
place,
environment and
facilities,
including other
equipment in the
context of use
Define normal,
unusual, and
emergency
conditions;
Define operator
and user
recruitment,
training and
culture
Basis for
validating the
conformance of
the services is
defined.
Specify health,
safety15
,
security,
environment and
other
15
National Academy of Construction Executive Insight, Safety Through Design
https://www.researchgate.net/publication/340949703_Safety_Through_Design_Key_Points
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 28 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
stakeholder
requirements
and functions
that relate to
critical qualities.
Identify safety
risk and specify
requirements
and functions to
provide safety.
Identify risks
associated with
methods of
operations and
support, health
and safety,
threats to
property and
environmental
influences.
Identify security
risk specify all
applicable areas
of system
security,
including
physical,
procedural,
communications,
computers,
programs, data
Identify functions
that could
impact the
security of the
system,
including access
and damage to
protected
personnel,
properties and
information,
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 29 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
compromise of
sensitive
information, and
denial of
approved
access to
property and
information.
Specify the
required security
functions,
including
mitigation and
containment,
referencing
applicable
standards and
practices
. Analyze the
complete set of
elicited
requirements.
Resolve
requirements
problems.
Feed back the
analyzed
requirements to
applicable
stakeholders to
ensure that the
needs and
expectations
have been
adequately
captured and
expressed.
Basis for
negotiating and
agreeing to
supply a service
Explain and
obtain
agreement to
the proposals to
resolve
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 30 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
or product is
provided
conflicting,
impractical and
unrealisable
stakeholder
requirements.
Establish with
stakeholders
that their
requirements
are expressed
correctly.
Confirm that
stakeholder
requirements
are
comprehensible
to originators
and that the
resolution of
conflict in the
requirements
has not
corrupted or
compromised
stakeholder
intentions.
Record the
stakeholder
requirements in
a form suitable
for requirements
management
through the life
cycle
Maintain
stakeholder
requirements
traceability to
the sources of
stakeholder
need.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 31 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Review
stakeholder
requirements at
key decision
times in the life
cycle
4.2
Requirements
Analysis
Process
PMC,PM,PExec The required
characteristics,
attributes, and
functional and
performance
requirements for
a solution are
specified.
Define the
functional
boundary of the
system in terms
of the behavior
and properties to
be provided.
Define each
function that the
system is
required to
perform, how
well the system,
including its
operators, is
required to
perform that
function, the
conditions under
which the
system is to be
capable of
performing the
function, the
conditions under
which the
system is to
commence
performing that
function and the
conditions under
which the
system is to
cease
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 32 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
performing that
function.
Reference
states and
required modes
of operation of
the system.
Constraints that
will affect the
design of a
system and the
means to realize
it are specified.
Define
necessary
implementation
constraints that
are introduced
by stakeholder
requirements or
are unavoidable
solution
limitations.
Define technical
and quality in
use measures
that enable the
assessment of
technical
achievement.
Define critical
performance
parameters
associated with
each
effectiveness
measure
identified in the
stakeholder
requirements.
Analyze critical
performance
measures to
ensure
stakeholder
requirements
are met and to
ensure
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 33 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
identification of
project cost
Specify system
requirements
and functions
Analysis and
definition of
safety
considerations
Analyze security
considerations
including those
related to
compromise and
protection of
sensitive
information
Integrity and
traceability of
system
requirements to
stakeholder
requirements is
achieved
Analyze the
integrity of the
system
requirements to
ensure that each
requirement,
pairs of
requirements or
sets of
requirements
possess overall
integrity.
Check each
system
requirement
statement to
establish that it
is unique,
complete,
unambiguous,
consistent with
all other
requirements,
implementable
and verifiable.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 34 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Identify
deficiencies,
conflicts and
weaknesses and
resolve within
the complete set
of system
requirements.
Analyze
resulting system
requirements to
confirm that they
are complete,
consistent,
achievable
(given current
technologies or
knowledge of
technological
advances) and
expressed at an
appropriate level
of detail.
Confirm that
they are a
necessary and
sufficient
response to
stakeholder
requirements
and a necessary
and sufficient
input to other
processes, in
particular
design.
Basis for
verifying that the
system
requirements
are satisfied is
defined.
Demonstrate
traceability
between the
system
requirements
and the
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 35 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
stakeholder
requirements.
Maintain the set
of system
requirements
together with the
associated
rationale,
decisions and
assumptions
throughout the
system life
cycle.
4.3 Design
Process
PExec Design baseline
is established.
Define
appropriate
logical designs.
Define
appropriate
expanded basis
of design
(BODX
) 1617
Identify and
define derived
requirements for
describing
functional and
performance
requirements,
services and
attributes,
timeline
requirements,
data flow
requirements,
etc.
16
National Academy of Construction Executive Insights, Business Basis of Design
https://www.researchgate.net/publication/340949572_Business_Basis_of_Design_Key_Points
17
Prieto, R. (2014) Addressing Project Capital Efficiency through a Business Basis of Design; PM World Journal
https://www.researchgate.net/publication/264942989_Addressing_Project_Capital_Efficiency_through_a_Business_
Basis_of_Design
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 36 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Conflicts among
and between
various logical
descriptions are
resolved and
each element is
shown to be
complete and
consistent by
making mutual
traceability
checks with the
defined system
requirements.
Implementable
set of system
element
descriptions that
satisfy the
requirements for
the system are
specified.
Partition the
system functions
identified in
requirements
analysis and
allocate them to
elements of
system
architecture.
Generate
derived
requirements as
needed for the
allocations.
Analyze the
resulting design
to establish
design criteria
for each
element.
Determine which
system
requirements
are allocated to
operators.
Identify
limitations of
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 37 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
human
capabilities;
Identify human
actions critical to
safety and how
the
consequences
of error are
addressed;
Identify
integration of
human
performance into
systems and
their operation..
Interface
requirements
are incorporated
into design
solution.
Determine
whether
elements that
satisfy the
design and
interface criteria
are available off-
the-shelf.
Basis for
verifying the
system elements
is defined.
Evaluate design
elements that
are not readily
available in
order to
determine if an
element is to be
developed, or if
existing system
elements will be
re-used or
adapted.
Establish the
costs, schedule,
and technical
risks associated
with these
make/modify/bu
y decisions.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 38 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Evaluate
alternative
design solutions,
modeling them
to a level of
detail that
permits
comparison
against the
specifications
expressed in the
system
requirements
and the
performance,
costs, time
scales and risks
expressed in the
stakeholder
requirements.
Assess and
communicate
the emergence
of adverse
system
properties
resulting from
the interaction of
candidate
system elements
or from changes
in a system
element
Ensuring that
the constraints
of enabling
system are
taken account of
in the design
Perform
effectiveness
assessments,
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 39 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
trade-off
analyses and
risk analyses
that lead toward
realizing a
feasible,
effective, stable
and optimized
design.
Basis for the
integration of
system elements
is established.
Define and
document the
interfaces
between system
elements and at
the system
boundary with
external
systems.
Human-system
and human-
human
interfaces are
defined and
controlled
Specify the
selected
physical design
solution as a
design baseline
in terms of its
functions,
performance,
behavior,
interfaces and
unavoidable
implementation
constraints.
Traceability of
design to system
requirements is
established.
Record the
design
information
(structural and
functional
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 40 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
partitioning,
interface and
control
definitions and
the design
decisions and
conclusions,
with traceability
to the
requirements
baseline)
Maintain mutual
traceability
between design
and system
requirements.
4.4
Implementation
Process
PExec An
implementation
strategy is
defined.
Generate an
implementation
strategy.
Develop
implementation
procedures,
fabrication
processes, tools
and equipment,
implementation
tolerances and
verification
uncertainties.
Achieve
consistent and
repeatable
producibility in
reference design
elements and
modular
construction
Implementation
technology
constraints on
Identify the
constraints that
the
implementation
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 41 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
the design are
identified.
strategy and
implementation
technology
impose on the
design solution.
A system
element is
realized.
Realize or adapt
system elements
using enabling
systems
Deliver
appropriate
training to
prepare
operators for
performing tasks
in accordance
with required
performance
standards and
operational
procedures
Confirm that the
specified range
and level of
competence has
been attained.
Record evidence
that the system
element meets
supplier
agreements,
legislation and
organizational
policy.
A system
element is
packaged and
stored in
accordance with
an agreement
for its supply.
Package the
system element
and store as
appropriate.
Conveyance and
storage media,
and their
durations,
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 42 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
influence the
specified
containment.
4.5 Integration
Process
PMC,PM,PExec A system
integration
strategy is
defined.
Define an
assembly
sequence and
strategy that
minimizes
system
integration risks.
Unavoidable
constraints of
integration that
influence
requirements
are defined.
Identify the
constraints on
the design
arising from the
integration
strategy such as
accessibility,
integration
enabling
systems and
required
interfacing/interc
onnections for
intermediate
assembly
configurations.
Obtain
integration
enabling
systems and
specified
materials
according to the
defined
integration
procedures.
A system
capable of being
verified against
the specified
requirements
from design is
Obtain system
elements in
accordance with
agreed
schedules.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 43 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
assembled and
integrated.
Assure that the
system elements
have been
verified against
acceptance
criteria specified
in an agreement.
Integrate system
elements in
accordance with
applicable
interface control
descriptions and
defined
assembly
procedures
Non-
conformances
due to
integration
actions are
recorded.
Record
integration
information in an
appropriate
database.
4.6 Verification
Process
PMC,PM,PExec A verification
strategy is
defined.
Define the
strategy for
verifying the
systems
throughout the
life cycle.
Include the
context and
purpose for each
instance of
verification
action, e.g.
verifying the
design, ability to
build the design
correctly, ability
to reproduce the
system, ability to
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 44 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
correct a fault
arising, ability to
predict failures.
Define a
verification plan
based on
system
requirements.
Verification
constraints are
provided as
inputs to
requirements.
Identify and
communicate
potential
constraints on
design
decisions.
Ensure that the
enabling system
for verification is
available and
associated
facilities,
equipment and
operators are
prepared to
conduct the
verification.
Conduct
verification to
demonstrate
compliance to
the specified
design
requirements.
Data providing
information for
corrective action
is reported.
Make available
verification data
on the system.
Analyze, record
and report
verification,
discrepancy and
corrective action
information.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 45 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Conduct fault
diagnosis to a
level of
resolution
consistent with
cost effective
remedial action,
including re-
verification
following defect
correction,
and/or
organizational
quality
improvement
actions.
Objective
evidence
Verification data
is collected
Analyze
verification data
to detect
essential
features such as
trends and
patterns of
failure
4.7 Transition
Process
(Construction)
PMC, PM, PExec A system
transition
strategy is
defined.
Prepare a
transition
strategy.
A system is
installed in its
operational
location.
Prepare the site
of operation in
accordance with
installation
requirements.
Site preparation
is conducted in
accordance with
applicable
health, safety,
security and
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 46 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
environmental
regulations.
Deliver the
system for
installation at the
correct location
and time.
Install the
system in its
operational
location and
interfaced to its
environment
according to its
system
specification.
Demonstrate
proper
installation of the
system.
A system, when
operated, is
capable of
delivering
services.
Activate the
system.
Demonstrate the
installed system
is capable of
delivering its
required
services.
The
configuration as
installed is
recorded.
Record the
installation data,
including the
operational
configuration,
anomalies
detected,
actions taken
and lessons
learned.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 47 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Corrective action
reports are
recorded.
A service is
sustainable by
enabling
systems.
4.8 Validation
Process
PMC, PM, PExec A validation
strategy is
defined.
Define the
strategy for
validating the
services in the
operational
environment and
achieving
stakeholder
satisfaction.
Prepare a
validation plan.
Define validation
steps, e.g.
various
operational
states, scenarios
and missions
that
progressively
build confidence
in conformance
of the installed
system and
assist diagnosis
of any
discrepancies.
Specify methods
and techniques
needed to
implement the
validation
strategy and the
purpose,
conditions and
conformance
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 48 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
criteria for each
validation.
Ensure that any
operators,
enabling system
for validation
and associated
facilities are
ready in order to
conduct
validation
The availability
of services
required by
stakeholders is
confirmed.
Conduct
validation to
demonstrate
conformance of
services to
stakeholder
requirements.
Objectively
record and
approve
validation
actions and
results.
Confirm that the
system not only
satisfies all
operational,
functional and
usability
requirements,
but also satisfies
the often less
formally
expressed, but
sometimes
overriding,
attitudes,
experience and
subjective tests
that comprise
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 49 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
customer
satisfaction.
Validation data
is provided.
Make available
validation data
on the system
according to
legal, regulatory
or product sector
requirements.
As appropriate
to agreement
terms or
organizational
objectives,
conduct
validation to
isolate that part
of the system
giving rise to a
non-
conformance.
Conduct fault
diagnosis to a
level of
resolution
consistent with
cost effective
remedial action,
including
revalidation
Data capable of
providing
information for
corrective action
is reported.
Analyze, record
and report
validation data
according to
criteria defined
in the validation
strategy.
Categorize non-
conformances
according to
their source and
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 50 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
corrective action
owner.
Analyze
validation data
to detect
essential
features such as
trends and
patterns of
failure, evidence
of design errors
and emerging
threats to
services.
4.9 Operation
Process
PExec An operation
strategy is
defined.
Prepare a
strategy for
operation.
Define
availability of
services as they
are introduced,
routinely
operated and
withdrawn from
service.
Define co-
ordination with
pre-existing,
concurrent or
continuing
services
delivered by
other systems
that provide
identical or
similar services
Define staffing
strategy and
schedules for
operators.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 51 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Define the
release and re-
acceptance
criteria and
schedules of the
system to permit
modifications
that sustain
existing or
enhanced
services.
Services that
meet
stakeholder
requirements
are delivered.
Obtain other
services related
to operation of
the system.
Assign trained,
qualified
personnel to be
operators.
Activate the
system in its
intended
operational
situation to
deliver instances
of service or
continuous
service
according to its
intended
purpose.
Maintain
continuous
service capacity
and quality when
the system
replaces an
existing system
that is being
retired.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 52 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
During a
specified period
of changeover or
concurrent
operation,
manage the
transfer of
services so that
continuing
conformance to
stakeholder
needs is
achieved.
Consume
materials, as
required, to
sustain the
services.
Monitor
operation to
ensure that the
system is
operated in
accordance with
the operations
plans, in a safe
manner and
compliant with
legislated
guidelines
concerning
occupational
safety and
environmental
protection.
Monitor the
system
operation to
confirm that
service
performance is
within
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 53 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
acceptable
parameters.
Approved
corrective action
requests are
satisfactorily
completed.
Perform failure
identification
actions when a
non-compliance
has occurred in
the delivered
services.
Determine the
appropriate
course of action
when corrective
action is
required to
remedy failings
due to changed
need.
Introduce
remedial
changes to
operating
procedures, the
operator
environment,
human-machine
interfaces and
operator training
as appropriate
when human
error contributed
to failure.
Stakeholder
satisfaction is
maintained.
Continuously or
routinely
communicate
with users to
determine the
degree to which
delivered
services satisfy
their needs.
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 54 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
Analyze results
and take
required action
to restore or
amend services
in order to
provide
continued
stakeholder
4.10
Maintenance
Process
PExec Maintenance
strategy is
developed.
Prepare a
maintenance
strategy.
Define
schedules and
resources
required to
perform
corrective and
preventive
maintenance in
conformance
with operational
availability
requirements.
Develop
corrective and
preventive
maintenance
strategy to
sustain service
in the
operational
environment in
order to achieve
customer
satisfaction
Define
scheduled
preventive
maintenance
actions that
reduce the
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 55 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
likelihood of
system failure
without undue
loss of services
Define number
and type of
replacement
system elements
to be stored,
their storage
locations and
conditions, their
anticipated
replacement
rate, their
storage life and
renewal
frequency
Define skill and
personnel levels
required to effect
repairs and
replacements,
accounting for
maintenance
staff
requirements
and any relevant
legislation
regarding health
and safety,
security and the
environment.
Maintenance
constraints are
provided as
inputs to
requirements.
Define the
constraints on
system
requirements
that are
unavoidable
consequences
of the
maintenance
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 56 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
strategy.
Replacement
system elements
are made
available.
Obtain the
enabling
systems, system
elements and
services to be
used during
maintenance of
the system.
Confirm that
logistics actions
satisfy the
required
replenishment
levels so that
stored system
elements meet
repair rates and
planned
schedules.
Monitor the
quality and
availability of
spares, their
transportation
and their
continued
integrity during
storage.
Services
meeting
stakeholder
requirements
are sustained.
Implement
problem
reporting and
incident
recording to
guide diagnosis
of individual
events and
histories to
support future
corrective,
adaptive,
perfective and
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 57 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
preventive
maintenance.
Implement the
procedures for
correction of
random faults
and/or
scheduled
replacement of
system
elements.
Perform
preventive
maintenance by
replacing or
servicing system
elements prior to
failure,
according to
planned
schedules and
maintenance
procedures.
Need for
corrective
design changes
is reported.
Initiate
corrective action
to remedy
previously
undetected
design errors.
Failure and
lifetime data is
recorded.
Perform failure
identification
actions when a
non-compliance
has occurred in
the system.
Maintain a
history of
problem reports,
corrective
actions and
trends to inform
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 58 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
operations and
maintenance
personnel, and
other projects,
that are creating
or utilizing
similar system
elements
4.11 Disposal
Process
PMC,PM,PExec System disposal
strategy is
defined.
Define a
disposal strategy
for the system,
to include each
system element
and any
resulting waste
products.
Disposal
constraints are
provided as
inputs to
requirements.
Communicate
unavoidable
constraints on
the system
design arising
from the
disposal
strategy.
Define issues
related to
disassembly,
including their
associated
enabling
systems, access
to and
availability of
storage
locations and
available skill
levels.
System
elements are
destroyed,
stored,
Acquire the
enabling
systems or
services to be
used during
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 59 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
reclaimed or
recycled.
disposal of a
system.
Deactivate the
system to
prepare it for
removal from
operation.
Address
interfaces to
other systems
(power, fuel, are
disconnected in
accordance with
disassembly
instructions and
relevant health,
safety, security
and privacy
legislation)
Withdraw
operating staff
from the system
and record
relevant
operating
knowledge.
Disassemble the
system into
manageable
elements to
facilitate its
removal for
reuse, recycling,
reconditioning,
overhaul,
archiving or
destruction.
Environment is
returned to its
original or an
agreed state.
Remove the
system from the
operational
environment for
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 60 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
reuse, recycling,
reconditioning,
overhaul or
destruction.
Specify
containment
facilities, storage
locations,
inspection
criteria and
storage periods
if the system is
to be stored.
Conduct
destruction of
the system, as
necessary, to
reduce the
amount of waste
treatment or to
make the waste
easier to handle.
Obtain
destruction
services
required in order
to melt, crush,
incinerate or
demolish the
system or its
elements as
necessary.
Safeguard and
secure
knowledge and
skills possessed
by operators.
Confirm that no
detrimental
health, safety,
security and
environmental
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 61 of 63
Process Group Process Level
(PMC,PM,PExec)
Outcomes Activities
factors exist
following
disposal.
Records
allowing
knowledge
retention of
disposal actions
and the analysis
of long-term
hazards are
available.
Archive
information
gathered
through the
lifetime of the
system to permit
audits and
reviews in the
event of long-
term hazards to
health, safety,
security and the
environment,
and to permit
future system
creators and
users to build a
knowledge base
from past
experiences.
References
BS ISO/IEC 15288:2002 Systems engineering – System life cycle processes
ISO/IEC/IEEE. 2015. Systems and Software Engineering -- System Life Cycle Processes
Prieto, R. (2012) Application of Life Cycle Analysis in the Capital Assets Industry; PM World
Today; March 2012;
https://www.researchgate.net/publication/272504721_Application_of_Life_Cycle_Analysis_in_th
e_Capital_Assets_Industry
Prieto, R. (2020) Systems Nature of Large Complex Programs; PM World Journal, Vol. IX, Issue
VIII, August
Prieto, R. (2020). A Deeper Look at the Physics of Large Complex Projects; A Neo-classical
Project Management Theory is Required; PM World Journal, Vol. IX, Issue VIII, August
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 62 of 63
National Academy of Construction Executive Insights; The Importance of Strategic Business
Objectives https://www.naocon.org/wp-content/uploads/The-Importance-of-Strategic-Business-
Objectives.pdf
PMO & the Tollgate Process; PM World Journal; May 2013;
https://www.researchgate.net/publication/272505052_PMO_the_Tollgate_Process
Prieto, R. (2019). The Primacy of the Scope Baseline in Engineering & Construction Projects;
PM World Journal, Vol. VIII, Issue IX, October;
https://www.researchgate.net/publication/336496336_The_Primacy_of_the_Scope_Baseline_in
_Engineering_Construction_Projects
National Academy of Construction Executive Insights; Procurement Management in Large
Complex Programs https://www.naocon.org/wp-content/uploads/Procurement-Management-in-
Large-Complex-Programs.pdf
Prieto, B. (2019). Impacts of Artificial Intelligence on Management of Large Complex Projects.
PM World Journal, Vol. VIII, Issue V, June;
https://www.researchgate.net/publication/334162272_Impacts_of_Artificial_Intelligence_on_Ma
nagement_of_Large_Complex_Projects
National Academy of Construction Executive Insights; Effective Project Review Meetings
https://www.naocon.org/wp-content/uploads/Effective-Project-Review-Meetings.pdf
National Academy of Construction Executive Insights, Owner Readiness
https://www.naocon.org/wp-content/uploads/Owner-Readiness.pdf
Program Management Audit Checklist
https://www.researchgate.net/publication/273118616_Program_Management_Audit_Checklist
National Academy of Construction Executive Insights, Fat Tails
https://www.researchgate.net/publication/340949652_Risk_and_Opportunities_Fat_Tails_Key_
Points
Stakeholder Management in Large Engineering & Construction Programs; PM World Today;
October 2011
https://www.researchgate.net/publication/273119019_Stakeholder_Management_in_Large_Eng
ineering_Construction_Programs
National Academy of Construction Executive Insight, Safety Through Design
https://www.researchgate.net/publication/340949703_Safety_Through_Design_Key_Points
National Academy of Construction Executive Insights, Business Basis of Design
https://www.researchgate.net/publication/340949572_Business_Basis_of_Design_Key_Points
Prieto, R. (2014) Addressing Project Capital Efficiency through a Business Basis of Design; PM
World Journal
https://www.researchgate.net/publication/264942989_Addressing_Project_Capital_Efficiency_th
rough_a_Business_Basis_of_Design
PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large,
Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs
www.pmworldjournal.com Featured Paper by Bob Prieto
© 2020 Robert Prieto www.pmworldlibrary.net Page 63 of 63
About the Author
Bob Prieto
Chairman & CEO
Strategic Program Management LLC
Jupiter, Florida, USA
Bob Prieto is a senior executive effective in shaping and executing business strategy and
a recognized leader within the infrastructure, engineering and construction industries.
Currently Bob heads his own management consulting practice, Strategic Program
Management LLC. He previously served as a senior vice president of Fluor, one of the
largest engineering and construction companies in the world. He focuses on the
development and delivery of large, complex projects worldwide and consults with owners
across all market sectors in the development of programmatic delivery strategies. He is
author of nine books including “Strategic Program Management”, “The Giga Factor:
Program Management in the Engineering and Construction Industry”, “Application of Life
Cycle Analysis in the Capital Assets Industry”, “Capital Efficiency: Pull All the Levers” and,
most recently, “Theory of Management of Large Complex Projects” published by the
Construction Management Association of America (CMAA) as well as over 700 other
papers and presentations.
Bob is an Independent Member of the Shareholder Committee of Mott MacDonald. He is a
member of the ASCE Industry Leaders Council, National Academy of Construction, a
Fellow of the Construction Management Association of America and member of several
university departmental and campus advisory boards. Bob served until 2006 as a U.S.
presidential appointee to the Asia Pacific Economic Cooperation (APEC) Business
Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape
the framework for trade and economic growth. He had previously served as both as
Chairman of the Engineering and Construction Governors of the World Economic Forum
and co-chair of the infrastructure task force formed after September 11th by the New York
City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff
(PB) and a non-executive director of Cardno (ASX)
Bob serves as an honorary global advisor for the PM World Journal and Library and can be
contacted at rpstrategic@comcast.net.

More Related Content

PDF
Improving infrastructure project success
PDF
KHass Resume 2015 with CV
PDF
Rethinking Interface Management
PDF
Rework in Engineering & Construction Projects
PDF
Systems nature of large complex projects
PDF
Large complex project success
PDF
Governance of mega and giga programs
PDF
Strengthen outcome based capital project delivery
Improving infrastructure project success
KHass Resume 2015 with CV
Rethinking Interface Management
Rework in Engineering & Construction Projects
Systems nature of large complex projects
Large complex project success
Governance of mega and giga programs
Strengthen outcome based capital project delivery

What's hot (20)

PDF
Complexity in large engineering & construction programs
PDF
Engineering and construction project startup
DOC
Gus Caporusso6 12 Resume
PDF
Chapter 9
DOCX
Rami A.docResumeFeb-2015
PDF
Robert Kennedy Resume
PDF
Reading week09 lechler_cc
DOC
Management Principles Associated with I.T. Project Success
PPT
Introduction to project management
PDF
Mis2008 1 1
PPT
Chapter 3: The Project Management Process Groups: A Case Study
PPT
Ch01
PDF
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
PDF
Role of Functional Organization in Large Engineering and Construction Programs
PPT
Project management and information technology context
PDF
IRJET- Management of Stakeholder in Infrastructure Projects
PDF
A review paper
PPTX
project management process groups
PDF
PMC2
Complexity in large engineering & construction programs
Engineering and construction project startup
Gus Caporusso6 12 Resume
Chapter 9
Rami A.docResumeFeb-2015
Robert Kennedy Resume
Reading week09 lechler_cc
Management Principles Associated with I.T. Project Success
Introduction to project management
Mis2008 1 1
Chapter 3: The Project Management Process Groups: A Case Study
Ch01
IRJET- A Review Paper on Quantifay the Different Constraints for Delays in In...
Role of Functional Organization in Large Engineering and Construction Programs
Project management and information technology context
IRJET- Management of Stakeholder in Infrastructure Projects
A review paper
project management process groups
PMC2
Ad

Similar to Application of system life cycle processes to large complex engineering and construction programs (20)

PPTX
The six phase comprehensive project life cycle model-2013
PPT
L02 pm & it context
PDF
Project Management in Practice 4th Edition Samuel J. Mantel
PDF
Project Management in Practice 4th Edition Samuel J. Mantel
PDF
Project Management in Practice 4th Edition Samuel J. Mantel
PDF
Project Management for Business Engineering and Technology Third Edition John...
PPTX
PGCS 2019 Master Class Integrating SE with PPM
PDF
Project Management For Business Engineering And Technology Principles And Pra...
PPTX
Pmo, project objectives and project life cycles
PDF
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
PDF
1. introduction
PPTX
management system development and planning
PPTX
SE1 - Integrating SE and PPM to Increase the Probability of Success
PPTX
PM 01 - Introduction to Project Management
PDF
INCOSE Systems Engineering Handbook A Guide for System Life Cycle Processes a...
PDF
Presentation3a
PDF
INCOSE Systems Engineering Handbook A Guide for System Life Cycle Processes a...
PDF
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
PDF
Essentials of Entry Level Project Management - Rev A
PDF
ePMO & Enterprise Implementations
The six phase comprehensive project life cycle model-2013
L02 pm & it context
Project Management in Practice 4th Edition Samuel J. Mantel
Project Management in Practice 4th Edition Samuel J. Mantel
Project Management in Practice 4th Edition Samuel J. Mantel
Project Management for Business Engineering and Technology Third Edition John...
PGCS 2019 Master Class Integrating SE with PPM
Project Management For Business Engineering And Technology Principles And Pra...
Pmo, project objectives and project life cycles
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
1. introduction
management system development and planning
SE1 - Integrating SE and PPM to Increase the Probability of Success
PM 01 - Introduction to Project Management
INCOSE Systems Engineering Handbook A Guide for System Life Cycle Processes a...
Presentation3a
INCOSE Systems Engineering Handbook A Guide for System Life Cycle Processes a...
Solution Manual for Project Management: Achieving Competitive Advantage, 3/E ...
Essentials of Entry Level Project Management - Rev A
ePMO & Enterprise Implementations
Ad

More from Bob Prieto (20)

PDF
Deeper look at the physics of projects
PDF
Reversing Global Warming
PDF
Impact of correlation on risks in programs and projects
PDF
Decision Making Under Uncertainty
DOCX
Post Dorian Engineering & Construction in the Bahamas
PDF
Debating project decisions in an ai enabled environment
PDF
Chapters 11 12 13
PDF
Chapter 10
PDF
Chapter 8
PDF
Theory of Management of Large Complex Projects - Chapter 7
PDF
Theory of Management of Large Complex Projects - Chapter 6
PDF
Theory of Management of Large Complex Projects - Chapter 5
PDF
Theory of Management of Large Complex Projects - Chapter 4
PDF
Theory of Management of Large Complex Projects - Chapter 3
PDF
Theory of Management of Large Complex Projects - Introduction and Chapter 1
DOCX
Sources of complexity
DOCX
Classes of coupling in large complex engineering & construction projects
DOCX
??? (Rutgers Innovation Key Note)
PDF
Program management audit checklist
DOCX
Suggestions to enhance infrastructure innovation
Deeper look at the physics of projects
Reversing Global Warming
Impact of correlation on risks in programs and projects
Decision Making Under Uncertainty
Post Dorian Engineering & Construction in the Bahamas
Debating project decisions in an ai enabled environment
Chapters 11 12 13
Chapter 10
Chapter 8
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 5
Theory of Management of Large Complex Projects - Chapter 4
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Introduction and Chapter 1
Sources of complexity
Classes of coupling in large complex engineering & construction projects
??? (Rutgers Innovation Key Note)
Program management audit checklist
Suggestions to enhance infrastructure innovation

Recently uploaded (20)

PPTX
web development for engineering and engineering
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT
introduction to datamining and warehousing
PDF
Digital Logic Computer Design lecture notes
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PPTX
Lecture Notes Electrical Wiring System Components
PDF
composite construction of structures.pdf
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PPT
Project quality management in manufacturing
PPTX
OOP with Java - Java Introduction (Basics)
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Safety Seminar civil to be ensured for safe working.
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
web development for engineering and engineering
R24 SURVEYING LAB MANUAL for civil enggi
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
introduction to datamining and warehousing
Digital Logic Computer Design lecture notes
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
Lecture Notes Electrical Wiring System Components
composite construction of structures.pdf
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Foundation to blockchain - A guide to Blockchain Tech
Project quality management in manufacturing
OOP with Java - Java Introduction (Basics)
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Operating System & Kernel Study Guide-1 - converted.pdf
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Safety Seminar civil to be ensured for safe working.
Embodied AI: Ushering in the Next Era of Intelligent Systems
UNIT-1 - COAL BASED THERMAL POWER PLANTS

Application of system life cycle processes to large complex engineering and construction programs

  • 1. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 1 of 63 Application of Systems Lifecycle Processes to Large, Complex Engineering and Construction Programs 1 By Bob Prieto Chairman & CEO Strategic Program Management LLC The complexity of megaprojects and programs continues to grow and with it the challenges of delivering ever larger and more complex programs. These large complex programs open the door to many new opportunities but also to increased challenges in delivery and sustainment throughout their lifecycle. Prior articles have described the open nature of this large complex program system2 and compared its attributes to many we find in the world of relativistic physics3. These challenges must be addressed recognizing that they arise from a combination of physical, fiscal and human attributes in a realm of complexity which challenges the very foundations of project management theory. This paper looks at hard systems aspects as contrasted with the soft system aspects more characteristic of an open system. Its purpose is to adapt a systems engineering framework associated with the hard closed elements of these large complex project systems without losing site of the overall open systems nature of large complex programs. The systems life cycle process codified in ISO 15288 lends itself to application in large complex engineering and construction programs. It provides a framework to aid in the integration of physical, fiscal and human factors from a lifecycle perspective. This life cycle spans the assets initial conception through ultimate disposal of the consumed asset. The table that follows identifies where specific outcomes and the associated activities to accomplish them may reside. These have been defined as at a program level (PMC, Program Management Consultant), project level (PM, Project Manager) or at a lower project execution level (PExec). Several limitations should be noted. First, the standard itself and the application as presented in this table do not do sufficient justice to the social and environmental aspects of a triple bottom line perspective. Here the reader would benefit from a closer view as can be seen in Prieto 20124. Second, the open systems 1 How to cite this paper: Prieto, R. (2020). Application of Systems Lifecycle Processes to Large, Complex Engineering and Construction Programs; PM World Journal, Vol. IX, Issue X, October. 2 Prieto, R. (2020) Systems Nature of Large Complex Programs; PM World Journal, Vol. IX, Issue VIII, August 3 Prieto, R. (2020). A Deeper Look at the Physics of Large Complex Projects; A Neo-classical Project Management Theory is Required; PM World Journal, Vol. IX, Issue VIII, August 4 Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March 2012; https://www.researchgate.net/publication/272504721_Application_of_Life_Cycle_Analysis_in_the_Capital_Assets_ Industry
  • 2. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 2 of 63 aspects of large complex programs are not truly covered and as such this may best be regarded as a subset of a larger open system perspective related to large complex programs. The table follows the general format of ISO 15288, grouping system processes into four groups: • Agreement processes • Enterprise processes • Project processes • Technical processes The table is intended to provide a framework where each activity can be further broken down into a series of tasks. In an earlier use IP under development related to the management of large complex projects was mapped to this system life cycle process. Process Group Process Level (PMC,PM,PExec) Outcomes Activities 1.0 Agreement Processes 1.1 Acquisition PMC,PM,PExec Acquisition strategy Acquisition plan Supplier selection RFP Supplier communication Supplier dialogue including partnering Supplier justification Supply evaluation; selection; justification Agreement for product or service Negotiate/execut e contract; confirm contract compliance Acceptance of product or service Resolution of exceptions to contract; final acceptance Payment Periodic and final payments 1.2 Supply to Client Pre-Engagement Client identification Authorizing, financing and
  • 3. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 3 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities accepting client elements Respond to client request (RFQ;RFP) Bid no-bid; Identification of contract exceptions requiring resolution Agreement for work to be performed Negotiate and execute agreement Communication with client Assess execution of the agreement Project execution per contract and agreed procedures Deliver project in accordance with agreement Final acceptance by client Transfer facility Payment Accept and acknowledge payment 2.0 Enterprise Processes 2.1 Enterprise Environment Management PMC Policies and procedures for the strategic management of lifecycles Establish top level strategies and plans that will be undertaken to achieve strategic business objectives5 Define, integrate, communicate the roles and responsibilities, 5 National Academy of Construction Executive Insights; The Importance of Strategic Business Objectives https://www.naocon.org/wp-content/uploads/The-Importance-of-Strategic-Business-Objectives.pdf
  • 4. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 4 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities authorities to implement system life cycle processes and management Define business criteria that control progression through the system life cycle (stage gate6 ) Accountability and authority for system life cycle management System life cycle processes and procedures Policy to improve system lifecycle processes Conduct periodic reviews of life cycle model Communicate to projects policies and procedures 2.2 Investment management Process PMC Qualification and selection of investment opportunities Identify project portfolio and required thresholds Prioritize projects Define projects, accountabilities and authorities (program view) Identify expected projects outcomes (link to SBO) 6 PMO & the Tollgate Process; PM World Journal; May 2013; https://www.researchgate.net/publication/272505052_PMO_the_Tollgate_Process
  • 5. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 5 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Resource and budget identification and allocation Allocate resources to achievement of project outcomes Project Management accountability and authorities defined Clear identification of multi-project interfaces Project reporting and review requirements Authorize project execution Projects meeting agreement, stakeholder and organization requirements (SBO etc.) are sustained Evaluate ongoing project progress Evaluate compliance with project directives Evaluate conformance with system life cycle plans and procedures Confirm continuing project necessity and validity (SBO test) Projects not meeting agreement, stakeholder and organization requirements Evaluate alternatives to cancel, suspend and redirect
  • 6. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 6 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities are redirected or terminated 2.3 System life cycle process management PMC System life cycle processes are defined Establish standard sets of system life cycle processes for applicable system life cycle stages Policy to apply processes are defined Establish acceptable tailoring and application policies and procedures with approval requirements Policy on adapting defined policies to specific project needs is defined Establish acceptable tailoring and application policies and procedures with approval requirements Methods and tools to support life cycle process execution are identified Measures are defined to evaluate application of the system life cycle process Establish performance measures Monitor process execution and identify
  • 7. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 7 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities enterprise level trends Improvements to the definition and application of system life cycle performances are undertaken Identify opportunities for improvement Improve processes, methods and tools 2.4 Resource Management Process PMC Necessary resources, materials and services are provided to projects Map necessary resources, materials and services to project plans and future business/progra m needs Define applicable physical and human factors and how they may change in the future Determine and provide the resource infrastructure support needed and provide project support Obtain non personnel resources to implement and support projects Maintain and manage the pool
  • 8. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 8 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities of personnel necessary to staff ongoing projects Skills of personnel are maintained and enhanced Manage competency throughout the life cycle Provision of training and education to improve skill sets and support career path Motivate staff through career development and rewards Conflicts in multi-project resource demands are resolved Control multi- project resources to resolve schedule conflicts 2.5 Quality Management PMC Quality management policies and procedures are defined Establish quality management policies, standards and procedures (ISO 9001; 9004) Quality goals and objectives are defined Establish quality management goals and objectives to achieve SBO, support top level strategies and achieve client satisfaction Quality management accountability Define responsibilities
  • 9. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 9 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities and authority defined for quality management Status of client and stakeholder satisfaction is monitored Assess client and stakeholder satisfaction and report Corrective action taken when quality goals not achieved Conduct periodic reviews of project quality plans assuring quality objectives based on stakeholder requirements have been established Monitor the status of quality improvement 3.0 Project Processes 3.1 Project Planning Process PM Project plans exist Objectives and constraints identified including performance, quality, cost, time, stakeholder Objectives sufficiently defined to permit selection and implementation of appropriate processes and activities Define project scope7 as 7 Prieto, R. (2019). The Primacy of the Scope Baseline in Engineering & Construction Projects; PM World Journal, Vol. VIII, Issue IX, October;
  • 10. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 10 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities established in agreement Define all activities to complete the project successfully Establish a work breakdown structure Define and maintain a project schedule based on project objectives and work estimates. Includes duration, relationship, dependencies, sequence, achievement milestones, resources and reviews. Define project achievement criteria for life cycle stage decision gates, delivery dates, major dependencies on external inputs or outputs Define project costs and plan a budget https://www.researchgate.net/publication/336496336_The_Primacy_of_the_Scope_Baseline_in_Engineering_Const ruction_Projects
  • 11. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 11 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Roles, responsibilities and authorities are defined Define the project organization, staff acquisitions, staff skills development and work methods Establish the structure of authorities and responsibilities of project work Resources and services necessary to achieve project objectives are formally requested Define the infrastructure and services required by the project Plan the acquisition of materials, goods and enabling system services supplied from outside the project8 Technical management plan developed and communicated (includes reviews) Project performance Define project measures to be used, data to be 8 National Academy of Construction Executive Insights; Procurement Management in Large Complex Programs https://www.naocon.org/wp-content/uploads/Procurement-Management-in-Large-Complex-Programs.pdf
  • 12. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 12 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities measures are defined collected (including sources), validated and analyzed9 Prepare project quality plan Project staff directed in accordance with project plans Conduct project audits 3.2 Project assessment process PMC,PM Project performance measures or assessment results are available Assess project status against plans to determine actual and projected performance, identifying variations10 Perform quality assurance in accordance with project plans Adequacy of roles responsibilities and authorities assessed Assess effectiveness of project team structure, roles and responsibilities Adequacy of resources and services necessary assessed Assess adequacy of team member competencies 9 Prieto, B. (2019). Impacts of Artificial Intelligence on Management of Large Complex Projects. PM World Journal, Vol. VIII, Issue V, June; https://www.researchgate.net/publication/334162272_Impacts_of_Artificial_Intelligence_on_Management_of_Larg e_Complex_Projects 10 National Academy of Construction Executive Insights; Effective Project Review Meetings https://www.naocon.org/wp-content/uploads/Effective-Project-Review-Meetings.pdf
  • 13. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 13 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Assess adequacy and availability of the project’s supporting infrastructure Confirm intra- organizational commitments are met Deviations in project performance are analyzed Assess project performance using measured achievement and milestone completion Determine effectiveness and adequacy of evolving capabilities to meet a range of future needs Conduct required management and technical reviews, audits and inspection to determine readiness to proceed to next life cycle stage or milestone11 Monitor critical processes and new work methods and technologies 11 National Academy of Construction Executive Insights, Owner Readiness https://www.naocon.org/wp- content/uploads/Owner-Readiness.pdf
  • 14. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 14 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Analyze data for variations and make recommendation for appropriate action Concerned parties are informed of project status Provide periodic status and required deviation reports 3.3 Project Control Process PM Corrective action is defined and directed when achievement not meeting targets Manage project requirements and changes to requirements in accordance with the project plans. Initiate the corrective actions needed to achieve the goals and outputs of project tasks that have deviated outside acceptable or defined limits. Re-deployment and re- assignment of personnel, tools and project infrastructure assets when inadequacy or unavailability has been detected. Initiate preventive
  • 15. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 15 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities actions, as appropriate, to ensure achievement of the goals and outputs of the project. Initiate problem resolution actions to correct non- conformances. Performing corrective actions to the implementation and execution of the life cycle processes when non- conformances are traced to them. Project re- planning is initiated when project objectives or constraints change or assumptions invalidated or migrated Evolve with time the scope, definition and the related breakdown of the work to be carried out by the project in response to the corrective action decisions taken and the estimated changes they introduce. Initiate change actions when there is a contractual
  • 16. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 16 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities change to cost, time or quality due to the impact of client or supplier request. Act to correct defective provision of acquired goods and services through constructive interaction with the supplier. Project action to advance to next milestone is authorized Authorize the project to proceed toward the next milestone or event if justified Project objectives are achieved Conduct project audit12 3.4 Decision Making Processes All Decision-making strategy is defined. Define a decision-making strategy including the identification and allocation of responsibility for, and authority to make decisions. Alternative courses of action are defined. Involve relevant parties in the decision-making in order to draw on experience and knowledge. 12 Program Management Audit Checklist https://www.researchgate.net/publication/273118616_Program_Management_Audit_Checklist
  • 17. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 17 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Identify the circumstances and need for a decision. Record, categorize and promptly and objectively report problems or opportunities and the alternative courses of action that will resolve their outcome. Preferred course of action is selected. Select and declare the decision-making strategy for each decision situation. Identify desired outcomes and measurable success criteria. Evaluate the balance of consequences of alternative actions, using the defined decision-making strategy, to arrive at an optimization of, or an improvement in, an identified
  • 18. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 18 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities decision situation. Resolution, decision rationale and assumptions are captured and reported. Record, track, evaluate and report decision outcomes to confirm that problems have been effectively resolved, adverse trends have been reversed and advantage has been taken of opportunities. Maintain records of problems and opportunities and their disposition, as stipulated in agreements or organizational procedures and in a manner that permits auditing and learning from experience. 3.5 Risk Management Process PMC,PM Risks are identified and categorized. Establish a systematic approach to risk identification, assessment and treatment. Identify and define the risks. Identifying the initiating events associated with each risk in each
  • 19. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 19 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities risk category, and defining the interrelationship s between sources of risk. The probabilities and consequence of risks are quantified. Determine the probability associated with risk occurrence using established risk criteria. Criteria can include associated cost, legal and statutory requirements, socio-economic and environmental aspects, the concerns of stakeholders, priorities and other inputs to the assessment. Evaluate the risks in terms of their possible consequences using the established criteria. Prioritize the risks in terms of their probability and consequences. Strategy to treat each risk is specified. Determine the risk treatment strategies.
  • 20. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 20 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Define a threshold of acceptability for each identified risk. Identify the risk treatment actions to follow if the threshold of acceptability is exceeded. For risks that have high consequences13 , establish contingency plans that will be initiated if mitigation actions are unsuccessful. Risk status is available and communicated. Communicate the risk treatment actions and their status in accordance with the agreement, policies and procedures. Maintain a register of risk throughout the life cycle. Register includes a definition of the current 13 National Academy of Construction Executive Insights, Fat Tails https://www.researchgate.net/publication/340949652_Risk_and_Opportunities_Fat_Tails_Key_Points
  • 21. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 21 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities perception of risks, and the relationship to risk treatment actions and budgets. Risks that have become unacceptable are acted upon 3.6 Configuration Management PMC, PM Configuration management strategy is defined. Define a configuration management strategy compatible with the guidance provided in ISO 10007. Items requiring configuration management are defined. Identify items that are subject to configuration control. Configuration baselines are established. Maintain information on configurations with an appropriate level of integrity and security. Changes to items under configuration management are controlled. Ensure that configuration information permits forward and backward traceability to other baselined configuration states. The configuration of released items is controlled. Ensure that changes to configuration baselines are
  • 22. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 22 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities properly identified, recorded, evaluated, approved, incorporated, and verified. Status of items under configuration management is made available throughout the life cycle. Ensure that changes to configuration baselines are properly identified, recorded, evaluated, approved, incorporated, and verified. Perform audits to verify conformance of a baseline to drawings, interface control documents and other agreement requirements. 3.7 Information Management Process All Information to be managed is identified. Define the items of information that will be managed during the system life cycle and, according to organizational policy or legislation, maintained for a defined period beyond. Designate authorities and
  • 23. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 23 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities responsibilities regarding the origination, generation, capture, archiving and disposal of items of information. Define the rights, obligations and commitments regarding the retention of, transmission of and access to information items. Forms of the information representations are defined. Define the content, semantics, formats and medium for the representation, retention, transmission and retrieval of information. Information is transformed and disposed of as required. Obtain the identified items of information. Status of information is recorded. Maintain information items and their storage records according to integrity, security and privacy requirements. Information is current, Define information
  • 24. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 24 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities complete and valid. maintenance actions. Information is made available to designated parties. Retrieve and distribute information to designated parties as required by agreed schedules or defined circumstances. Provide official documentation as required. Archive designated information, in accordance with the audit and knowledge retention purposes. Dispose of unwanted, invalid or unverifiable information according to organization policy, and security and privacy requirements. 4.0 Technical Processes 4.1 Stakeholder Requirements Definition Process PMC, PM Required characteristics and context of use of services specified. Identify the individual stakeholders or stakeholder classes who have interest in the system
  • 25. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 25 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities throughout its life cycle14 . Elicit stakeholder requirements. Constraints on a system solution are defined. Define the constraints on a system solution that are unavoidable consequences of existing agreements, management decisions and technical decisions. Traceability of stakeholder requirements to stakeholders and their needs is achieved. Define a representative set of activity sequences to identify all required services that correspond to anticipated operational and support scenarios and environments. Scenarios are used to analyze the operation of the system in its intended environment in order and to identify 14 Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011 https://www.researchgate.net/publication/273119019_Stakeholder_Management_in_Large_Engineering_Constructi on_Programs
  • 26. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 26 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities requirements that may not have been formally specified by any of the stakeholders, e.g. legal, regulatory and social obligations. Context of use of the system is identified and analyzed. Include in the context analysis the activities that users perform to achieve system objectives, the relevant characteristics of the end-users of the system, the physical environment and any equipment to be used. The social and organizational influences on users that could affect system use or constrain its design are analyzed when applicable. Basis for defining the system Identify the interaction between users and the system.
  • 27. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 27 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities requirements is described. Usability requirements are determined, establishing, as a minimum, the most effective, efficient, and reliable human performance and human- system interaction. Define required physical, mental, and learned capabilities Define work place, environment and facilities, including other equipment in the context of use Define normal, unusual, and emergency conditions; Define operator and user recruitment, training and culture Basis for validating the conformance of the services is defined. Specify health, safety15 , security, environment and other 15 National Academy of Construction Executive Insight, Safety Through Design https://www.researchgate.net/publication/340949703_Safety_Through_Design_Key_Points
  • 28. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 28 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities stakeholder requirements and functions that relate to critical qualities. Identify safety risk and specify requirements and functions to provide safety. Identify risks associated with methods of operations and support, health and safety, threats to property and environmental influences. Identify security risk specify all applicable areas of system security, including physical, procedural, communications, computers, programs, data Identify functions that could impact the security of the system, including access and damage to protected personnel, properties and information,
  • 29. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 29 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities compromise of sensitive information, and denial of approved access to property and information. Specify the required security functions, including mitigation and containment, referencing applicable standards and practices . Analyze the complete set of elicited requirements. Resolve requirements problems. Feed back the analyzed requirements to applicable stakeholders to ensure that the needs and expectations have been adequately captured and expressed. Basis for negotiating and agreeing to supply a service Explain and obtain agreement to the proposals to resolve
  • 30. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 30 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities or product is provided conflicting, impractical and unrealisable stakeholder requirements. Establish with stakeholders that their requirements are expressed correctly. Confirm that stakeholder requirements are comprehensible to originators and that the resolution of conflict in the requirements has not corrupted or compromised stakeholder intentions. Record the stakeholder requirements in a form suitable for requirements management through the life cycle Maintain stakeholder requirements traceability to the sources of stakeholder need.
  • 31. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 31 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Review stakeholder requirements at key decision times in the life cycle 4.2 Requirements Analysis Process PMC,PM,PExec The required characteristics, attributes, and functional and performance requirements for a solution are specified. Define the functional boundary of the system in terms of the behavior and properties to be provided. Define each function that the system is required to perform, how well the system, including its operators, is required to perform that function, the conditions under which the system is to be capable of performing the function, the conditions under which the system is to commence performing that function and the conditions under which the system is to cease
  • 32. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 32 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities performing that function. Reference states and required modes of operation of the system. Constraints that will affect the design of a system and the means to realize it are specified. Define necessary implementation constraints that are introduced by stakeholder requirements or are unavoidable solution limitations. Define technical and quality in use measures that enable the assessment of technical achievement. Define critical performance parameters associated with each effectiveness measure identified in the stakeholder requirements. Analyze critical performance measures to ensure stakeholder requirements are met and to ensure
  • 33. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 33 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities identification of project cost Specify system requirements and functions Analysis and definition of safety considerations Analyze security considerations including those related to compromise and protection of sensitive information Integrity and traceability of system requirements to stakeholder requirements is achieved Analyze the integrity of the system requirements to ensure that each requirement, pairs of requirements or sets of requirements possess overall integrity. Check each system requirement statement to establish that it is unique, complete, unambiguous, consistent with all other requirements, implementable and verifiable.
  • 34. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 34 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Identify deficiencies, conflicts and weaknesses and resolve within the complete set of system requirements. Analyze resulting system requirements to confirm that they are complete, consistent, achievable (given current technologies or knowledge of technological advances) and expressed at an appropriate level of detail. Confirm that they are a necessary and sufficient response to stakeholder requirements and a necessary and sufficient input to other processes, in particular design. Basis for verifying that the system requirements are satisfied is defined. Demonstrate traceability between the system requirements and the
  • 35. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 35 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities stakeholder requirements. Maintain the set of system requirements together with the associated rationale, decisions and assumptions throughout the system life cycle. 4.3 Design Process PExec Design baseline is established. Define appropriate logical designs. Define appropriate expanded basis of design (BODX ) 1617 Identify and define derived requirements for describing functional and performance requirements, services and attributes, timeline requirements, data flow requirements, etc. 16 National Academy of Construction Executive Insights, Business Basis of Design https://www.researchgate.net/publication/340949572_Business_Basis_of_Design_Key_Points 17 Prieto, R. (2014) Addressing Project Capital Efficiency through a Business Basis of Design; PM World Journal https://www.researchgate.net/publication/264942989_Addressing_Project_Capital_Efficiency_through_a_Business_ Basis_of_Design
  • 36. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 36 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Conflicts among and between various logical descriptions are resolved and each element is shown to be complete and consistent by making mutual traceability checks with the defined system requirements. Implementable set of system element descriptions that satisfy the requirements for the system are specified. Partition the system functions identified in requirements analysis and allocate them to elements of system architecture. Generate derived requirements as needed for the allocations. Analyze the resulting design to establish design criteria for each element. Determine which system requirements are allocated to operators. Identify limitations of
  • 37. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 37 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities human capabilities; Identify human actions critical to safety and how the consequences of error are addressed; Identify integration of human performance into systems and their operation.. Interface requirements are incorporated into design solution. Determine whether elements that satisfy the design and interface criteria are available off- the-shelf. Basis for verifying the system elements is defined. Evaluate design elements that are not readily available in order to determine if an element is to be developed, or if existing system elements will be re-used or adapted. Establish the costs, schedule, and technical risks associated with these make/modify/bu y decisions.
  • 38. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 38 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Evaluate alternative design solutions, modeling them to a level of detail that permits comparison against the specifications expressed in the system requirements and the performance, costs, time scales and risks expressed in the stakeholder requirements. Assess and communicate the emergence of adverse system properties resulting from the interaction of candidate system elements or from changes in a system element Ensuring that the constraints of enabling system are taken account of in the design Perform effectiveness assessments,
  • 39. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 39 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities trade-off analyses and risk analyses that lead toward realizing a feasible, effective, stable and optimized design. Basis for the integration of system elements is established. Define and document the interfaces between system elements and at the system boundary with external systems. Human-system and human- human interfaces are defined and controlled Specify the selected physical design solution as a design baseline in terms of its functions, performance, behavior, interfaces and unavoidable implementation constraints. Traceability of design to system requirements is established. Record the design information (structural and functional
  • 40. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 40 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities partitioning, interface and control definitions and the design decisions and conclusions, with traceability to the requirements baseline) Maintain mutual traceability between design and system requirements. 4.4 Implementation Process PExec An implementation strategy is defined. Generate an implementation strategy. Develop implementation procedures, fabrication processes, tools and equipment, implementation tolerances and verification uncertainties. Achieve consistent and repeatable producibility in reference design elements and modular construction Implementation technology constraints on Identify the constraints that the implementation
  • 41. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 41 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities the design are identified. strategy and implementation technology impose on the design solution. A system element is realized. Realize or adapt system elements using enabling systems Deliver appropriate training to prepare operators for performing tasks in accordance with required performance standards and operational procedures Confirm that the specified range and level of competence has been attained. Record evidence that the system element meets supplier agreements, legislation and organizational policy. A system element is packaged and stored in accordance with an agreement for its supply. Package the system element and store as appropriate. Conveyance and storage media, and their durations,
  • 42. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 42 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities influence the specified containment. 4.5 Integration Process PMC,PM,PExec A system integration strategy is defined. Define an assembly sequence and strategy that minimizes system integration risks. Unavoidable constraints of integration that influence requirements are defined. Identify the constraints on the design arising from the integration strategy such as accessibility, integration enabling systems and required interfacing/interc onnections for intermediate assembly configurations. Obtain integration enabling systems and specified materials according to the defined integration procedures. A system capable of being verified against the specified requirements from design is Obtain system elements in accordance with agreed schedules.
  • 43. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 43 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities assembled and integrated. Assure that the system elements have been verified against acceptance criteria specified in an agreement. Integrate system elements in accordance with applicable interface control descriptions and defined assembly procedures Non- conformances due to integration actions are recorded. Record integration information in an appropriate database. 4.6 Verification Process PMC,PM,PExec A verification strategy is defined. Define the strategy for verifying the systems throughout the life cycle. Include the context and purpose for each instance of verification action, e.g. verifying the design, ability to build the design correctly, ability to reproduce the system, ability to
  • 44. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 44 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities correct a fault arising, ability to predict failures. Define a verification plan based on system requirements. Verification constraints are provided as inputs to requirements. Identify and communicate potential constraints on design decisions. Ensure that the enabling system for verification is available and associated facilities, equipment and operators are prepared to conduct the verification. Conduct verification to demonstrate compliance to the specified design requirements. Data providing information for corrective action is reported. Make available verification data on the system. Analyze, record and report verification, discrepancy and corrective action information.
  • 45. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 45 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Conduct fault diagnosis to a level of resolution consistent with cost effective remedial action, including re- verification following defect correction, and/or organizational quality improvement actions. Objective evidence Verification data is collected Analyze verification data to detect essential features such as trends and patterns of failure 4.7 Transition Process (Construction) PMC, PM, PExec A system transition strategy is defined. Prepare a transition strategy. A system is installed in its operational location. Prepare the site of operation in accordance with installation requirements. Site preparation is conducted in accordance with applicable health, safety, security and
  • 46. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 46 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities environmental regulations. Deliver the system for installation at the correct location and time. Install the system in its operational location and interfaced to its environment according to its system specification. Demonstrate proper installation of the system. A system, when operated, is capable of delivering services. Activate the system. Demonstrate the installed system is capable of delivering its required services. The configuration as installed is recorded. Record the installation data, including the operational configuration, anomalies detected, actions taken and lessons learned.
  • 47. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 47 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Corrective action reports are recorded. A service is sustainable by enabling systems. 4.8 Validation Process PMC, PM, PExec A validation strategy is defined. Define the strategy for validating the services in the operational environment and achieving stakeholder satisfaction. Prepare a validation plan. Define validation steps, e.g. various operational states, scenarios and missions that progressively build confidence in conformance of the installed system and assist diagnosis of any discrepancies. Specify methods and techniques needed to implement the validation strategy and the purpose, conditions and conformance
  • 48. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 48 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities criteria for each validation. Ensure that any operators, enabling system for validation and associated facilities are ready in order to conduct validation The availability of services required by stakeholders is confirmed. Conduct validation to demonstrate conformance of services to stakeholder requirements. Objectively record and approve validation actions and results. Confirm that the system not only satisfies all operational, functional and usability requirements, but also satisfies the often less formally expressed, but sometimes overriding, attitudes, experience and subjective tests that comprise
  • 49. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 49 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities customer satisfaction. Validation data is provided. Make available validation data on the system according to legal, regulatory or product sector requirements. As appropriate to agreement terms or organizational objectives, conduct validation to isolate that part of the system giving rise to a non- conformance. Conduct fault diagnosis to a level of resolution consistent with cost effective remedial action, including revalidation Data capable of providing information for corrective action is reported. Analyze, record and report validation data according to criteria defined in the validation strategy. Categorize non- conformances according to their source and
  • 50. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 50 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities corrective action owner. Analyze validation data to detect essential features such as trends and patterns of failure, evidence of design errors and emerging threats to services. 4.9 Operation Process PExec An operation strategy is defined. Prepare a strategy for operation. Define availability of services as they are introduced, routinely operated and withdrawn from service. Define co- ordination with pre-existing, concurrent or continuing services delivered by other systems that provide identical or similar services Define staffing strategy and schedules for operators.
  • 51. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 51 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Define the release and re- acceptance criteria and schedules of the system to permit modifications that sustain existing or enhanced services. Services that meet stakeholder requirements are delivered. Obtain other services related to operation of the system. Assign trained, qualified personnel to be operators. Activate the system in its intended operational situation to deliver instances of service or continuous service according to its intended purpose. Maintain continuous service capacity and quality when the system replaces an existing system that is being retired.
  • 52. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 52 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities During a specified period of changeover or concurrent operation, manage the transfer of services so that continuing conformance to stakeholder needs is achieved. Consume materials, as required, to sustain the services. Monitor operation to ensure that the system is operated in accordance with the operations plans, in a safe manner and compliant with legislated guidelines concerning occupational safety and environmental protection. Monitor the system operation to confirm that service performance is within
  • 53. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 53 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities acceptable parameters. Approved corrective action requests are satisfactorily completed. Perform failure identification actions when a non-compliance has occurred in the delivered services. Determine the appropriate course of action when corrective action is required to remedy failings due to changed need. Introduce remedial changes to operating procedures, the operator environment, human-machine interfaces and operator training as appropriate when human error contributed to failure. Stakeholder satisfaction is maintained. Continuously or routinely communicate with users to determine the degree to which delivered services satisfy their needs.
  • 54. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 54 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities Analyze results and take required action to restore or amend services in order to provide continued stakeholder 4.10 Maintenance Process PExec Maintenance strategy is developed. Prepare a maintenance strategy. Define schedules and resources required to perform corrective and preventive maintenance in conformance with operational availability requirements. Develop corrective and preventive maintenance strategy to sustain service in the operational environment in order to achieve customer satisfaction Define scheduled preventive maintenance actions that reduce the
  • 55. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 55 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities likelihood of system failure without undue loss of services Define number and type of replacement system elements to be stored, their storage locations and conditions, their anticipated replacement rate, their storage life and renewal frequency Define skill and personnel levels required to effect repairs and replacements, accounting for maintenance staff requirements and any relevant legislation regarding health and safety, security and the environment. Maintenance constraints are provided as inputs to requirements. Define the constraints on system requirements that are unavoidable consequences of the maintenance
  • 56. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 56 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities strategy. Replacement system elements are made available. Obtain the enabling systems, system elements and services to be used during maintenance of the system. Confirm that logistics actions satisfy the required replenishment levels so that stored system elements meet repair rates and planned schedules. Monitor the quality and availability of spares, their transportation and their continued integrity during storage. Services meeting stakeholder requirements are sustained. Implement problem reporting and incident recording to guide diagnosis of individual events and histories to support future corrective, adaptive, perfective and
  • 57. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 57 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities preventive maintenance. Implement the procedures for correction of random faults and/or scheduled replacement of system elements. Perform preventive maintenance by replacing or servicing system elements prior to failure, according to planned schedules and maintenance procedures. Need for corrective design changes is reported. Initiate corrective action to remedy previously undetected design errors. Failure and lifetime data is recorded. Perform failure identification actions when a non-compliance has occurred in the system. Maintain a history of problem reports, corrective actions and trends to inform
  • 58. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 58 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities operations and maintenance personnel, and other projects, that are creating or utilizing similar system elements 4.11 Disposal Process PMC,PM,PExec System disposal strategy is defined. Define a disposal strategy for the system, to include each system element and any resulting waste products. Disposal constraints are provided as inputs to requirements. Communicate unavoidable constraints on the system design arising from the disposal strategy. Define issues related to disassembly, including their associated enabling systems, access to and availability of storage locations and available skill levels. System elements are destroyed, stored, Acquire the enabling systems or services to be used during
  • 59. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 59 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities reclaimed or recycled. disposal of a system. Deactivate the system to prepare it for removal from operation. Address interfaces to other systems (power, fuel, are disconnected in accordance with disassembly instructions and relevant health, safety, security and privacy legislation) Withdraw operating staff from the system and record relevant operating knowledge. Disassemble the system into manageable elements to facilitate its removal for reuse, recycling, reconditioning, overhaul, archiving or destruction. Environment is returned to its original or an agreed state. Remove the system from the operational environment for
  • 60. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 60 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities reuse, recycling, reconditioning, overhaul or destruction. Specify containment facilities, storage locations, inspection criteria and storage periods if the system is to be stored. Conduct destruction of the system, as necessary, to reduce the amount of waste treatment or to make the waste easier to handle. Obtain destruction services required in order to melt, crush, incinerate or demolish the system or its elements as necessary. Safeguard and secure knowledge and skills possessed by operators. Confirm that no detrimental health, safety, security and environmental
  • 61. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 61 of 63 Process Group Process Level (PMC,PM,PExec) Outcomes Activities factors exist following disposal. Records allowing knowledge retention of disposal actions and the analysis of long-term hazards are available. Archive information gathered through the lifetime of the system to permit audits and reviews in the event of long- term hazards to health, safety, security and the environment, and to permit future system creators and users to build a knowledge base from past experiences. References BS ISO/IEC 15288:2002 Systems engineering – System life cycle processes ISO/IEC/IEEE. 2015. Systems and Software Engineering -- System Life Cycle Processes Prieto, R. (2012) Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March 2012; https://www.researchgate.net/publication/272504721_Application_of_Life_Cycle_Analysis_in_th e_Capital_Assets_Industry Prieto, R. (2020) Systems Nature of Large Complex Programs; PM World Journal, Vol. IX, Issue VIII, August Prieto, R. (2020). A Deeper Look at the Physics of Large Complex Projects; A Neo-classical Project Management Theory is Required; PM World Journal, Vol. IX, Issue VIII, August
  • 62. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 62 of 63 National Academy of Construction Executive Insights; The Importance of Strategic Business Objectives https://www.naocon.org/wp-content/uploads/The-Importance-of-Strategic-Business- Objectives.pdf PMO & the Tollgate Process; PM World Journal; May 2013; https://www.researchgate.net/publication/272505052_PMO_the_Tollgate_Process Prieto, R. (2019). The Primacy of the Scope Baseline in Engineering & Construction Projects; PM World Journal, Vol. VIII, Issue IX, October; https://www.researchgate.net/publication/336496336_The_Primacy_of_the_Scope_Baseline_in _Engineering_Construction_Projects National Academy of Construction Executive Insights; Procurement Management in Large Complex Programs https://www.naocon.org/wp-content/uploads/Procurement-Management-in- Large-Complex-Programs.pdf Prieto, B. (2019). Impacts of Artificial Intelligence on Management of Large Complex Projects. PM World Journal, Vol. VIII, Issue V, June; https://www.researchgate.net/publication/334162272_Impacts_of_Artificial_Intelligence_on_Ma nagement_of_Large_Complex_Projects National Academy of Construction Executive Insights; Effective Project Review Meetings https://www.naocon.org/wp-content/uploads/Effective-Project-Review-Meetings.pdf National Academy of Construction Executive Insights, Owner Readiness https://www.naocon.org/wp-content/uploads/Owner-Readiness.pdf Program Management Audit Checklist https://www.researchgate.net/publication/273118616_Program_Management_Audit_Checklist National Academy of Construction Executive Insights, Fat Tails https://www.researchgate.net/publication/340949652_Risk_and_Opportunities_Fat_Tails_Key_ Points Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011 https://www.researchgate.net/publication/273119019_Stakeholder_Management_in_Large_Eng ineering_Construction_Programs National Academy of Construction Executive Insight, Safety Through Design https://www.researchgate.net/publication/340949703_Safety_Through_Design_Key_Points National Academy of Construction Executive Insights, Business Basis of Design https://www.researchgate.net/publication/340949572_Business_Basis_of_Design_Key_Points Prieto, R. (2014) Addressing Project Capital Efficiency through a Business Basis of Design; PM World Journal https://www.researchgate.net/publication/264942989_Addressing_Project_Capital_Efficiency_th rough_a_Business_Basis_of_Design
  • 63. PM World Journal (ISSN: 2330-4480) Application of Systems Lifecycle Processes to Large, Vol. IX, Issue X – October 2020 Complex Engineering and Construction Programs www.pmworldjournal.com Featured Paper by Bob Prieto © 2020 Robert Prieto www.pmworldlibrary.net Page 63 of 63 About the Author Bob Prieto Chairman & CEO Strategic Program Management LLC Jupiter, Florida, USA Bob Prieto is a senior executive effective in shaping and executing business strategy and a recognized leader within the infrastructure, engineering and construction industries. Currently Bob heads his own management consulting practice, Strategic Program Management LLC. He previously served as a senior vice president of Fluor, one of the largest engineering and construction companies in the world. He focuses on the development and delivery of large, complex projects worldwide and consults with owners across all market sectors in the development of programmatic delivery strategies. He is author of nine books including “Strategic Program Management”, “The Giga Factor: Program Management in the Engineering and Construction Industry”, “Application of Life Cycle Analysis in the Capital Assets Industry”, “Capital Efficiency: Pull All the Levers” and, most recently, “Theory of Management of Large Complex Projects” published by the Construction Management Association of America (CMAA) as well as over 700 other papers and presentations. Bob is an Independent Member of the Shareholder Committee of Mott MacDonald. He is a member of the ASCE Industry Leaders Council, National Academy of Construction, a Fellow of the Construction Management Association of America and member of several university departmental and campus advisory boards. Bob served until 2006 as a U.S. presidential appointee to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth. He had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he served as Chairman at Parsons Brinckerhoff (PB) and a non-executive director of Cardno (ASX) Bob serves as an honorary global advisor for the PM World Journal and Library and can be contacted at rpstrategic@comcast.net.