CRM Projects: Odyssey of Fixed Bid executions

Dears,
Imagine a CRM consulting project with inadequately specified requirements, no clear
internal project manager, and ill-defined success criteria. Your consultant bids it on a time
and materials (T&M) basis. You're in a rush, no time for a detailed RFP - you know the
consultant can do the job, but you need a budgetary number to get approval. We've all been
through this drill: somebody brilliant suggests that this has to be fixed price, it'll be easier
to get project approval and manage to conclusion that way. You know, just like it would be
when buying servers.
But you're not buying servers: you're buying services. While 80% of CRM projects are
formulaic and could be bid as a "standard project," the other 80% of the project work is not
only a one-off, but an unknown. Nobody actually knows the requirements, or the
ramifications of "something simple," or the shape of your data, or the tricky parts of
external interfaces. You may think you're signing up for a three-hour tour, but you're on the
way to Gilligan's Island.
While fixed price projects are easy to measure, the simplistic calendar-and-budget
approach misses the point. Will the project result in any value to the business? Did it satisfy
the letter of the requirements without solving any real problems? Let's look at this a little
deeper.
You don't want to pay too much, so you get competitive bids. But all consultants have a
powerful incentive to bid too high: they need the LEG room to manage the risk of scope
creep, weak project management, and ambiguous success criteria. This is particularly
endemic in CRM projects that have to satisfy right-brained types in Sales and Marketing.
Look at it from the consultants' economic perspective: a fixed price project must be more
profitable to compensate for the extra risk.
Let's say you get lucky. Your consultant made a low fixed price bid. You win...except you
don't. The consultants will be spending all their time during the project trying to figure out
how to deliver as little as possible and develop some engineering change orders (ECOs) or
other tricks to get you to pay more on their money-losing bid.
Now let's say the consultant is a saint. They don't try to up sell you, and they eat the losses
on the project. What happens next? They lose their talent. And no, those people won't come
to work for you. So all the institutional knowledge they brought and the business process
expertise they developed for you on the project is gone. You get to pay for the learning
curve all over again.
What do you think the chances are that the consultant's bid is within 10% of the effort
required to make your team happy? Or that you had the foresight to tell the consultant at
least 90% of your actual requirements before the statement of work? And what about the
rubber yardstick of satisfying your users? Do you really think you can do that consistently,
even when your own staff hasn't even analyzed your database before getting the bid?
Fixed Price Discovery, T&M Tasks
A common solution for these issues is to have the discovery and detailed requirements
setting phase of the engagement be fixed price (perhaps 10% of the expected project
value), with the actual implementation tasks as T&M. Even if the follow-on tasks are done
as fixed price, this is a good step forward in containing risk on both sides of the table.
This approach provides incentives for both the consultant and the internal project manager
to manage scope creep, make sensible tradeoffs, and apply some "value engineering." But
there's still the issue of the unknown: the subtle data corruption or the API glitch or the
political subterfuge coming from the Sales team (who - for reasons that are never clear subtly oppose the project). In CRM projects of any size, these unknowns and unpleasant
surprises can account for 25% of the effort. Still think your team's initial task estimation is
within 10% of the optimal outcome (where the users are actually satisfied, but without
unneeded bells and whistles)?
There's an old adage in politics, "If you can get the other side working on the wrong
question, it doesn't matter what answer they come up with." Maybe "how do I get it
done at for $X" is asking the wrong question. All too often, the word "it" isn't tightly
defined, guaranteeing a suboptimal answer. And the unspoken issue is trust and tight
management.
Agile Fixed Price?
You may not practice Agile in your organization. Fine. But know that CRM system
deployments are best done in this incremental, user-centered style. Salesforce.com and
SugarCRM even build their products that way. If an incremental deployment style is the
right way to do CRM, how does that fit with a fixed price project? Agile projects do have
fixed budgets and schedules - in fact, proper Agile projects have a better record of meeting
those targets than conventional IT projects do. But Agile projects dont have a predetermined set of features for any specific delivery. The requirement "cards" and "stories"
are continuously evaluated and re-prioritized through the life of the project. Why? Because
the business doesn't really know what's going to be valuable until it sees it, or even uses it
for a while. In a perverse way, Agile is an ideal fit for CRM work precisely because the
details and ramifications of your requirements are seldom known until the project is
underway.
So an Agile project would have fixed price and a time-boxed schedule, but a variable set of
deliverables. You get the most valuable deliverables that could be produced for a given
budget, but you don't get a fixed SOW.
Making Agile work for consulting engagements will require the same project management
skills and attitude adjustment that it does for internal projects. But most consultants are
living the Agile lifestyle already. So maybe the right question to be asking here isn't "how
do we get it for $X?" but "given our fixed resources, how do we get the business payback
from CRM in the fastest way?"
Good Luck and Welcome your thoughts
Your P&C
DC*

More Related Content

DOCX
Crm project enabling agility beyond challenges
DOCX
How to help gear your company towards cutting the right costs
PPTX
Top 10 Reasons Why CRM Implementations Fail
PPTX
30% - 60% of CRM Projects Fail
PDF
Inspiring positivity: Managing attitudes towards CRM adoption
PDF
How do I get the project brief right?
PDF
SAFe Rollout: Patterns for success in Retail by Ashwinee Kalkura
PPTX
Agile ME20119 SAFe rollout patterns
Crm project enabling agility beyond challenges
How to help gear your company towards cutting the right costs
Top 10 Reasons Why CRM Implementations Fail
30% - 60% of CRM Projects Fail
Inspiring positivity: Managing attitudes towards CRM adoption
How do I get the project brief right?
SAFe Rollout: Patterns for success in Retail by Ashwinee Kalkura
Agile ME20119 SAFe rollout patterns

What's hot (20)

PPTX
The power of the humble context diagram
PDF
The 10 Most Important Questions to Ask When Selecting the Right CRM Partner
PPT
IT BA Pre Sale Consulting
PDF
How Technology Can Help Win Government Bids
PPT
Business Process Professional: Dream Job of the Future
DOCX
Why sandy got fired
PPTX
Introducing Trisotech BPMN Process Animator bpmNEXT 2014
PPTX
Different ways to pay for product development presentation
PPTX
Different ways to pay for product development presentation
PDF
Delivery Partners
PDF
Procurement & Contract for IT Projects
PPTX
Why CRM Fails: How thinking data-first can accelerate sales transformation
PDF
Proceedit 20121217 top 10 end customer objections and how to face them succes...
PPT
Presentation2
PPTX
bbc building business capability October28thver2
PPTX
CxGroup Customer experience consulting
PPT
Managing International CRM Projects
PDF
17 rules of CRM
PDF
360 Degree Customer Experience: A Practical Approach to Holistic CX
DOCX
How to Achieve Per-Project Profitability
The power of the humble context diagram
The 10 Most Important Questions to Ask When Selecting the Right CRM Partner
IT BA Pre Sale Consulting
How Technology Can Help Win Government Bids
Business Process Professional: Dream Job of the Future
Why sandy got fired
Introducing Trisotech BPMN Process Animator bpmNEXT 2014
Different ways to pay for product development presentation
Different ways to pay for product development presentation
Delivery Partners
Procurement & Contract for IT Projects
Why CRM Fails: How thinking data-first can accelerate sales transformation
Proceedit 20121217 top 10 end customer objections and how to face them succes...
Presentation2
bbc building business capability October28thver2
CxGroup Customer experience consulting
Managing International CRM Projects
17 rules of CRM
360 Degree Customer Experience: A Practical Approach to Holistic CX
How to Achieve Per-Project Profitability
Ad

Viewers also liked (8)

DOCX
Are you socially challenged
DOCX
Achilles heel of crm
DOCX
Befriend your crm workforce
DOCX
Photoshop
DOCX
Assembling customer information
DOCX
Book review steve jobs way
DOCX
Are you socially challenged
Achilles heel of crm
Befriend your crm workforce
Photoshop
Assembling customer information
Book review steve jobs way
Ad

Similar to CX (20)

PPTX
Андрій Просов "Fixed Price Agile Projects: Challenges for Project Manager" Kh...
PPTX
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
PPTX
Pricing Strategies in Consulting Industry.pptx
PDF
Offers & Pricing
PPT
8 trends of successful crm(customer relationship management)2
PDF
Selecting consultants - the process
PDF
USING CRM SOLUTIONS TO INCREASE SALES AND RETAIN VALUABLE CUSTOMERS
PDF
Pivotal CRM - CRM Initiatives
PPTX
Agile Contracts
PDF
An Agile Twist: Fixed-Bid Pricing
PPTX
How to get an Internal Buy-In for a CRM software
PDF
The crm discovery kit
DOCX
Crm case study
PDF
How to Develop Budget-Friendly Custom CRM Software_.pdf
PPTX
TwistedMinds.in
PPTX
Crm budgets
DOCX
Fixed price vs time and material
PDF
How to successfully execute fixed price agile projects
PPTX
Dynamics CRM - how to succeed
PDF
Everything Guide to Choosing the Right CRM
Андрій Просов "Fixed Price Agile Projects: Challenges for Project Manager" Kh...
Андрій Просов “Fixed Price Agile Projects: Lessons Learned” Kyiv Project Man...
Pricing Strategies in Consulting Industry.pptx
Offers & Pricing
8 trends of successful crm(customer relationship management)2
Selecting consultants - the process
USING CRM SOLUTIONS TO INCREASE SALES AND RETAIN VALUABLE CUSTOMERS
Pivotal CRM - CRM Initiatives
Agile Contracts
An Agile Twist: Fixed-Bid Pricing
How to get an Internal Buy-In for a CRM software
The crm discovery kit
Crm case study
How to Develop Budget-Friendly Custom CRM Software_.pdf
TwistedMinds.in
Crm budgets
Fixed price vs time and material
How to successfully execute fixed price agile projects
Dynamics CRM - how to succeed
Everything Guide to Choosing the Right CRM

More from Dr.Dinesh Chandrasekar PhD(hc) (20)

PDF
Dr Dinesh Chandrasekar LinkedIn Profile May 2020
PDF
CIO Review - Dinesh Chandrasekar Article on IoT
PDF
SQL Architect posting 8th April 2018 /parimala.rekha@pactera.com
PDF
Everyday Life Champion - A Book by Dinesh Chandrasekar
PDF
Emerging Leader 101 by Dinesh Chandrasekar
PDF
Big Data Customer Experience Analytics -- The Next Big Opportunity for You
PDF
Everyday Customer Experience (CX) Champion by Dinesh Chandrasekar DC*
DOCX
Celebrate success at work
DOCX
Cart before the horse
DOCX
Building the responsive crm
DOCX
Building a business case for crm upgrade
DOCX
Brotherhood of master data
DOCX
Brand relationship management
DOCX
Being second in race and first in quality
DOCX
Automotive dealership crm
DOCX
DOCX
DOCX
Apples , oranges & crm software selection
DOCX
2010 crm reflections
Dr Dinesh Chandrasekar LinkedIn Profile May 2020
CIO Review - Dinesh Chandrasekar Article on IoT
SQL Architect posting 8th April 2018 /parimala.rekha@pactera.com
Everyday Life Champion - A Book by Dinesh Chandrasekar
Emerging Leader 101 by Dinesh Chandrasekar
Big Data Customer Experience Analytics -- The Next Big Opportunity for You
Everyday Customer Experience (CX) Champion by Dinesh Chandrasekar DC*
Celebrate success at work
Cart before the horse
Building the responsive crm
Building a business case for crm upgrade
Brotherhood of master data
Brand relationship management
Being second in race and first in quality
Automotive dealership crm
Apples , oranges & crm software selection
2010 crm reflections

Recently uploaded (20)

PDF
Ôn tập tiếng anh trong kinh doanh nâng cao
PDF
Unit 1 Cost Accounting - Cost sheet
PDF
Business model innovation report 2022.pdf
PDF
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
PPTX
HR Introduction Slide (1).pptx on hr intro
DOCX
Euro SEO Services 1st 3 General Updates.docx
PPTX
Lecture (1)-Introduction.pptx business communication
PPTX
Probability Distribution, binomial distribution, poisson distribution
DOCX
Business Management - unit 1 and 2
PDF
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
PDF
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
PDF
How to Get Funding for Your Trucking Business
PDF
Chapter 5_Foreign Exchange Market in .pdf
DOCX
unit 1 COST ACCOUNTING AND COST SHEET
PDF
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
PPT
Data mining for business intelligence ch04 sharda
PDF
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
PPTX
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
DOCX
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
PPTX
5 Stages of group development guide.pptx
Ôn tập tiếng anh trong kinh doanh nâng cao
Unit 1 Cost Accounting - Cost sheet
Business model innovation report 2022.pdf
SIMNET Inc – 2023’s Most Trusted IT Services & Solution Provider
HR Introduction Slide (1).pptx on hr intro
Euro SEO Services 1st 3 General Updates.docx
Lecture (1)-Introduction.pptx business communication
Probability Distribution, binomial distribution, poisson distribution
Business Management - unit 1 and 2
BsN 7th Sem Course GridNNNNNNNN CCN.pdf
pdfcoffee.com-opt-b1plus-sb-answers.pdfvi
How to Get Funding for Your Trucking Business
Chapter 5_Foreign Exchange Market in .pdf
unit 1 COST ACCOUNTING AND COST SHEET
20250805_A. Stotz All Weather Strategy - Performance review July 2025.pdf
Data mining for business intelligence ch04 sharda
Elevate Cleaning Efficiency Using Tallfly Hair Remover Roller Factory Expertise
The Marketing Journey - Tracey Phillips - Marketing Matters 7-2025.pptx
unit 2 cost accounting- Tender and Quotation & Reconciliation Statement
5 Stages of group development guide.pptx

CX

  • 1. CRM Projects: Odyssey of Fixed Bid executions Dears, Imagine a CRM consulting project with inadequately specified requirements, no clear internal project manager, and ill-defined success criteria. Your consultant bids it on a time and materials (T&M) basis. You're in a rush, no time for a detailed RFP - you know the consultant can do the job, but you need a budgetary number to get approval. We've all been through this drill: somebody brilliant suggests that this has to be fixed price, it'll be easier to get project approval and manage to conclusion that way. You know, just like it would be when buying servers. But you're not buying servers: you're buying services. While 80% of CRM projects are formulaic and could be bid as a "standard project," the other 80% of the project work is not only a one-off, but an unknown. Nobody actually knows the requirements, or the ramifications of "something simple," or the shape of your data, or the tricky parts of external interfaces. You may think you're signing up for a three-hour tour, but you're on the way to Gilligan's Island. While fixed price projects are easy to measure, the simplistic calendar-and-budget approach misses the point. Will the project result in any value to the business? Did it satisfy the letter of the requirements without solving any real problems? Let's look at this a little deeper. You don't want to pay too much, so you get competitive bids. But all consultants have a powerful incentive to bid too high: they need the LEG room to manage the risk of scope creep, weak project management, and ambiguous success criteria. This is particularly endemic in CRM projects that have to satisfy right-brained types in Sales and Marketing. Look at it from the consultants' economic perspective: a fixed price project must be more profitable to compensate for the extra risk. Let's say you get lucky. Your consultant made a low fixed price bid. You win...except you don't. The consultants will be spending all their time during the project trying to figure out how to deliver as little as possible and develop some engineering change orders (ECOs) or other tricks to get you to pay more on their money-losing bid. Now let's say the consultant is a saint. They don't try to up sell you, and they eat the losses on the project. What happens next? They lose their talent. And no, those people won't come to work for you. So all the institutional knowledge they brought and the business process expertise they developed for you on the project is gone. You get to pay for the learning curve all over again. What do you think the chances are that the consultant's bid is within 10% of the effort required to make your team happy? Or that you had the foresight to tell the consultant at least 90% of your actual requirements before the statement of work? And what about the
  • 2. rubber yardstick of satisfying your users? Do you really think you can do that consistently, even when your own staff hasn't even analyzed your database before getting the bid? Fixed Price Discovery, T&M Tasks A common solution for these issues is to have the discovery and detailed requirements setting phase of the engagement be fixed price (perhaps 10% of the expected project value), with the actual implementation tasks as T&M. Even if the follow-on tasks are done as fixed price, this is a good step forward in containing risk on both sides of the table. This approach provides incentives for both the consultant and the internal project manager to manage scope creep, make sensible tradeoffs, and apply some "value engineering." But there's still the issue of the unknown: the subtle data corruption or the API glitch or the political subterfuge coming from the Sales team (who - for reasons that are never clear subtly oppose the project). In CRM projects of any size, these unknowns and unpleasant surprises can account for 25% of the effort. Still think your team's initial task estimation is within 10% of the optimal outcome (where the users are actually satisfied, but without unneeded bells and whistles)? There's an old adage in politics, "If you can get the other side working on the wrong question, it doesn't matter what answer they come up with." Maybe "how do I get it done at for $X" is asking the wrong question. All too often, the word "it" isn't tightly defined, guaranteeing a suboptimal answer. And the unspoken issue is trust and tight management. Agile Fixed Price? You may not practice Agile in your organization. Fine. But know that CRM system deployments are best done in this incremental, user-centered style. Salesforce.com and SugarCRM even build their products that way. If an incremental deployment style is the right way to do CRM, how does that fit with a fixed price project? Agile projects do have fixed budgets and schedules - in fact, proper Agile projects have a better record of meeting those targets than conventional IT projects do. But Agile projects dont have a predetermined set of features for any specific delivery. The requirement "cards" and "stories" are continuously evaluated and re-prioritized through the life of the project. Why? Because the business doesn't really know what's going to be valuable until it sees it, or even uses it for a while. In a perverse way, Agile is an ideal fit for CRM work precisely because the details and ramifications of your requirements are seldom known until the project is underway. So an Agile project would have fixed price and a time-boxed schedule, but a variable set of deliverables. You get the most valuable deliverables that could be produced for a given budget, but you don't get a fixed SOW. Making Agile work for consulting engagements will require the same project management skills and attitude adjustment that it does for internal projects. But most consultants are
  • 3. living the Agile lifestyle already. So maybe the right question to be asking here isn't "how do we get it for $X?" but "given our fixed resources, how do we get the business payback from CRM in the fastest way?" Good Luck and Welcome your thoughts Your P&C DC*