Barriers to Distributed
  Renewable Energy
  efficient | economical | equitable



                             John Farrell, Senior Researcher
Total Installed Capacity


                        47,000 MW



     4,034 MW




Together = 3.3% of U.S. sales
How Much Community-Owned?


                       47,000 MW

   5%? 10%?     25%?
     4,034 MW
Community-Owned

    just 1%
Why Community-Owned?

                                               2
 Community-Owned = distributed



(distributed generation) x (distributed ownership)
Barriers to Distributed Generation


• Tradition
• Capital
• Cash Flow
• Legal
• Utility
Tradition
    Utility Perspective                                                        Reality


   Centralized Power                                  Clean, local power
                                                                                      Solar PV
                                                                                     power plant



                                                                     Storage      Storage
            Transmission network


                                                           Storage

                                                                                    Storage
    House
                                         Local CHP plant

            Distribution network                                                                    House with
                                                                                                   domestic CHP




                                                                                  Wind
                                                                                  power
  Factory                   Commercial                                            plant
                             building
Barriers to Distributed Generation


• Tradition
• Capital
• Cash Flow
• Legal
• Utility
Capital



           ...buy this?

How can
 they...
Rules for Raising Capital

• Full registration
• Regulation D
• Regulation A
• Intra-State
• Private
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None



               $30,000                        Accredited investors;
Regulation D   -50,000
                             $10,000/yr
                                               prior relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr        $5 million offering


               $50,000
Intra-State    -75,000
                           $10,000/yr (MN)        In-state only



                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None



               $30,000                        Accredited investors;
Regulation D   -50,000
                             $10,000/yr
                                               prior relationship
    9%
  3%
               $50,000
Regulation A   -75,000
                             $10,000/yr        $5 million offering

   Project Cost
               $50,000
   Upfront
Intra-State    -75,000
                           $10,000/yr (MN)        In-state only
   Compliance
                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr          None



               $30,000                        Accredited investors;
Regulation D   -50,000
                             $10,000/yr
                                               prior relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr        $5 million offering


59%
Intra-State 19%$50,000
                           $10,000/yr (MN)        In-state only
               -75,000

   Project Cost
                               Prior relationship; no
  Private
   Upfront     Minimal Minimal
                                    advertising
   Compliance Too costly for small projects
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None


                                                  Accredited
               $30,000                          investors; prior
Regulation D   -50,000
                             $10,000/yr
                                                relationship w/
                                                   investors

               $50,000
Regulation A   -75,000
                             $10,000/yr        $5 million offering


               $50,000
Intra-State    -75,000
                           $10,000/yr (MN)        In-state only



                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None


                                                   Accredited
               $30,000
Regulation D   -50,000
                             $10,000/yr         investors; prior
                                                  relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr       $5 million offering


               $50,000
Intra-State    -75,000
                           $10,000/yr (MN)        In-state only



                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None


                                                   Accredited
               $30,000
Regulation D   -50,000
                             $10,000/yr         investors; prior
                                                  relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr       $5 million offering



Intra-State    $50,000
               -75,000            ≤ 2 turbines
                           $10,000/yr (MN)        In-state only



                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

                $100,000-
  Full SEC       125,000
                            Over $400,000/yr           None


                                                    Accredited
                $30,000
    5%
Regulation D    -50,000
                              $10,000/yr         investors; prior
                                                   relationship
27%
                $50,000
Regulation A    -75,000
                              $10,000/yr        $5 million offering


                $50,000
 Intra-State
   Project Cost -75,000
                            $10,000/yr (MN)        In-state only

   Upfront
   Compliance                                  Prior relationship; no
   Private      Minimal         Minimal
                                                    advertising
                   Still costly for small projects
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr           None


                                                   Accredited
               $30,000
Regulation D   -50,000
                             $10,000/yr         investors; prior
                                                  relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr       $5 million offering


               $50,000
Intra-State    -75,000
                           $10,000/yr (MN)        In-state only



                                              Prior relationship; no
  Private      Minimal         Minimal
                                                   advertising
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs
       5%
                $100,000-
 27% SEC
  Full           125,000
                            Over $400,000/yr           None


                                                    Accredited
         Project Cost
               $30,000
Regulation D    -50,000
                              $10,000/yr         investors; prior
         Upfront                                   relationship
         Compliance
                $50,000
Regulation A    -75,000
                              $10,000/yr       $5 million offering


                $50,000
 Intra-State    -75,000
                            $10,000/yr (MN)        In-state only



                                               Prior relationship; no
  Private       Minimal         Minimal
                                                    advertising
                   Still costly for small projects
Type of      Upfront Compliance
                                  Restrictions
registration    Cost     Costs

               $100,000-
  Full SEC      125,000
                           Over $400,000/yr          None


                                                  Accredited
               $30,000
Regulation D   -50,000
                             $10,000/yr        investors; prior
                                                 relationship


               $50,000
Regulation A   -75,000
                             $10,000/yr       $5 million offering


               $50,000
Intra-State    -75,000
                           $10,000/yr (MN)       In-state only



                                              Prior relationship;
  Private      Minimal         Minimal
                                                no advertising
Capital is HARD

• Full = EXPENSIVE
• Regulation D = RICH FOLKS
• Regulation A = SIZE/COST
• Intra-State = COSTLY
• Private = LIMITED
Hope: Crowdfunding
    • 2012 federal JOBS Act
    • $1 million limit
    • Minimal compliance
    • Lower upfront cost: $10-15k
Example




          Private	
  Placement
Barriers to Distributed Generation


• Tradition
• Capital
• Cash Flow
• Legal
• Utility
complex...
Minnesota Commercial Solar Project Cash Flow




       30%         25%         25%         20%




 0%          25%         50%         75%         100%




      Federal tax credit             Depreciation
      State rebate                   Net metering
Germany/Ontario Commercial Solar Project Cash Flow




                       100%




    0%       25%       50%           75%   100%




                    Feed-In Tariff
Feed-In Tariff


• Long-term, fixed price contract
• Guaranteed, simple grid connection
• Price sufficient for small profit
Policy Shapes Cost
    High


                                           U.S.
Return




                 Ontario

           Germany
    Low




           Low             Risk             High
Policy Shapes Participation




                               80%


of German solar is on small rooftops
U.S. Exception




      University Park community solar
Barriers to Distributed Generation


• Tradition
• Capital
• Cash Flow
• Legal
• Utility
Which Makes Sense for
 Community Solar?
A.Nonprofit
B.City
C. County
D.Cooperative
E. All of the Above
Which Makes Sense for
 Community Solar?
A.Nonprofit
B.City
C. County
D.Cooperative
E.All of the Above
Which One Works?
A.Nonprofit
B.City
C. County
D.Cooperative
E. All of the Above
Which One Works?
A.Nonprofit
B.City
C. County
D.Cooperative
E. All of the Above
F.None of the Above
Minnesota Nonprofit Solar Project Cash Flow




     15%   15%     25%         25%         20%




0%         25%           50%         75%         100%



      Federal tax credit             Middleman
      Depreciation                   State rebate
      Net metering
Exception
     Mt. Pleasant Solar Cooperative




          Group purchase, no legal entity
Exception
       South Dakota Wind Partners




7 turbines, 600 owners, 1 expired cash grant
Barriers to Distributed Generation


• Tradition
• Capital
• Cash Flow
• Legal
• Utility
True or false?


In 2012, most utilities measure how much
electricity is used during peak periods and
during minimum use periods on their own
grid.
True or false?


In 2012, most utilities measure how much
electricity is used during peak periods and
during minimum use periods on their own
grid.
               FALSE
How Local Solar Gets Capped


≤
    1. A Limit on Local Power Generation
    Utilities always want local power generation to be less
    than local minimum electricity demand so that
    electricity will not flow out of neighborhoods and back
    onto the grid.*




?
    2. A Guesstimate of Minimum Demand                                    Peak use
    Whoops! Utilities assume minimum demand
    is about 30% of peak demand, because they
    don’t measure minimum demand.




÷
2   3. An Arbitrary Safety Margin
    Utilities take this 30% threshold and
    divide by 2 to get a 15% cap on local solar.
                                                                           “Minimum”(30%)

                                                                           ÷2
                                                      Default cap of 15%
    *Also addressed with 2-way electrical equipment
                                                         Percent of peak power allowed from local solar
How States Can Raise the Cap (Hawaii)

                                                         Hawaii’s Update (2011)
    1. A Daytime Minimum
    How much solar power is produced at 4 AM?
                                                         Hawaii estimates the minimum
    None. But that’s the time of day utilities used      demand during daytime.
    for their minimum demand calculation.

    Hawaii solar advocates negotiated a change: to
    estimate minimum demand when the sun is
    up (Sundays at noon).
                                                                  “Daytime min.”
    Even though utilities maintain the arbitrary
    “division by 2” safety margin, this change
                                                                          ÷2
    could allow nearly twice as much local solar
    on the grid.



                                      Cap is raised to ~25%
                                                      Percent of peak power allowed from local solar
How States Can Raise the Cap (California)

     1. A Measured Daytime Minimum                               California’s Update (2012)
     Utilities must actually measure the minimum                 Measured daytime demand
     demand on a power line between 9 AM and 4 PM                     No “division by 2”
     and no longer use peak demand as a proxy.




÷
2
     2. No “Division by 2”
     Utilities can’t arbitrarily divide the cap by 2, now
     that the power line capacity is actually measured.


     The result could nearly triple the original                     Daytime minimum
     15% cap on local solar power.




                                    Cap is raised to                      ~50%
                                                            Percent of peak power allowed from local solar
Utilities also Want Limits on Total Net Metering




                                                  LEGEND
                                       no statutory net metering limit
 Lets	
  customers	
  pay	
            aggregate limit higher than 1%
“net”	
  of	
  own	
  use	
  and	
     of peak demand
                                       aggregate limit 1% of peak
  own	
  generation                    demand or less
Exception




    Replicable
 community solar!
Distributed Generation
     Barriers             Exceptions
    • Tradition   •   Mt. Pleasant Solar Coop
                  •   Clean Energy Collective
    • Capital
                  •   Maryland Solar LLC
    • Cash Flow
                  •   SD Wind Partners
    • Legal
    • Utility

      Learn more at
EnergySelfReliantStates.org

More Related Content

PDF
Providence wealth partners long term care strategies
PPT
Distributed Renewable Energy Systems and Impacts to Performance
PDF
Value of solar report
PDF
Kingspan power panel
PPTX
Solar slide
PDF
SolarEdge Company Presentation
PPT
Zam Energy Services Presentation
Providence wealth partners long term care strategies
Distributed Renewable Energy Systems and Impacts to Performance
Value of solar report
Kingspan power panel
Solar slide
SolarEdge Company Presentation
Zam Energy Services Presentation

Viewers also liked (16)

PPT
Sustainable Energy Myths and Realities
PPT
Solar power plant
PDF
Integrated Distributed Solar and Storage
PDF
Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...
PDF
Sunpowerd - Distributed Solar in Ghana
PDF
Local Power, Local Control
PDF
A Review of Solar PV Benefit and Cost Studies
PPT
Njatc Pv Powerpoint Acte Naae
PDF
Lucintel globalcompositemarketanalysis-acma2012-educationalsession
PDF
Driving Clean Energy in MENA / GCC Region - 2nd kuwait Investment Summit – Fe...
PDF
IRENA GPCA presentation 2015 1012
PPT
Concentrated Solar Power Course - Session 1 : Fundamentals
PDF
Renewable Energy Sector
PDF
Roof top solar project
PPT
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
PPTX
Grid connected Solar Rooftop
Sustainable Energy Myths and Realities
Solar power plant
Integrated Distributed Solar and Storage
Optimizing Commercial Solar PV Systems : How much energy lost from Partial Sh...
Sunpowerd - Distributed Solar in Ghana
Local Power, Local Control
A Review of Solar PV Benefit and Cost Studies
Njatc Pv Powerpoint Acte Naae
Lucintel globalcompositemarketanalysis-acma2012-educationalsession
Driving Clean Energy in MENA / GCC Region - 2nd kuwait Investment Summit – Fe...
IRENA GPCA presentation 2015 1012
Concentrated Solar Power Course - Session 1 : Fundamentals
Renewable Energy Sector
Roof top solar project
DISTRIBUTED GENERATION ENVIRONMENT WITH SMART GRID
Grid connected Solar Rooftop
Ad

More from John Farrell (20)

PDF
Which Costs Less? A Surprising Comparison of Utility-Scale, Community, and Ro...
PDF
Which Costs Less? A Surprising Comparison of Utility-Scale, Community, and Ro...
PDF
Community Power Opportunities
PDF
Energy Self-Reliant States - 3rd edition
PDF
Energy Democracy: How the deciders in the energy system are changing
PDF
Energy Democracy for Puerto Rico
PDF
Choosing the Electric Avenue: Unlocking Savings, Emissions Reductions, and Co...
PDF
Reverse Power Flow: How solar+batteries shift electric grid decision making f...
PDF
Local Power for Decorah, Iowa
PDF
Local Power for the Local Economy
PDF
A Vision for Minnesota Solar: Lessons and Barriers from the North Star State
PDF
ILSR's Energy Democracy Initiative Overview
PDF
AERO Presentation: How Communities Use Clean Energy to Build Local Power
PDF
Will the Feds Preserve Electricity Market Competition?
PDF
Choosing the Electric Avenue - Webinar Presentation
PDF
Choosing the Electric Avenue - Webinar Presentation
PPTX
February 2017 - NARUC Debate on Distributed Generation
PDF
Is Bigger Best in Renewable Energy? Webinar Presentation
PDF
Mighty Microgrids - BioCycle REFOR16 Presentation
PDF
Mighty Microgrids: How Small Grids Could Become a Big Deal
Which Costs Less? A Surprising Comparison of Utility-Scale, Community, and Ro...
Which Costs Less? A Surprising Comparison of Utility-Scale, Community, and Ro...
Community Power Opportunities
Energy Self-Reliant States - 3rd edition
Energy Democracy: How the deciders in the energy system are changing
Energy Democracy for Puerto Rico
Choosing the Electric Avenue: Unlocking Savings, Emissions Reductions, and Co...
Reverse Power Flow: How solar+batteries shift electric grid decision making f...
Local Power for Decorah, Iowa
Local Power for the Local Economy
A Vision for Minnesota Solar: Lessons and Barriers from the North Star State
ILSR's Energy Democracy Initiative Overview
AERO Presentation: How Communities Use Clean Energy to Build Local Power
Will the Feds Preserve Electricity Market Competition?
Choosing the Electric Avenue - Webinar Presentation
Choosing the Electric Avenue - Webinar Presentation
February 2017 - NARUC Debate on Distributed Generation
Is Bigger Best in Renewable Energy? Webinar Presentation
Mighty Microgrids - BioCycle REFOR16 Presentation
Mighty Microgrids: How Small Grids Could Become a Big Deal
Ad

Recently uploaded (20)

PDF
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
PDF
Univ-Connecticut-ChatGPT-Presentaion.pdf
PPTX
Group 1 Presentation -Planning and Decision Making .pptx
PDF
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
PDF
WOOl fibre morphology and structure.pdf for textiles
PDF
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
NewMind AI Weekly Chronicles – August ’25 Week III
PPTX
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
PDF
Getting Started with Data Integration: FME Form 101
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PDF
A novel scalable deep ensemble learning framework for big data classification...
PDF
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
PDF
DP Operators-handbook-extract for the Mautical Institute
PPTX
The various Industrial Revolutions .pptx
PPTX
Chapter 5: Probability Theory and Statistics
PDF
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
PDF
Architecture types and enterprise applications.pdf
PPTX
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
PDF
2021 HotChips TSMC Packaging Technologies for Chiplets and 3D_0819 publish_pu...
DASA ADMISSION 2024_FirstRound_FirstRank_LastRank.pdf
Univ-Connecticut-ChatGPT-Presentaion.pdf
Group 1 Presentation -Planning and Decision Making .pptx
Transform Your ITIL® 4 & ITSM Strategy with AI in 2025.pdf
WOOl fibre morphology and structure.pdf for textiles
TrustArc Webinar - Click, Consent, Trust: Winning the Privacy Game
Zenith AI: Advanced Artificial Intelligence
NewMind AI Weekly Chronicles – August ’25 Week III
TechTalks-8-2019-Service-Management-ITIL-Refresh-ITIL-4-Framework-Supports-Ou...
Getting Started with Data Integration: FME Form 101
Final SEM Unit 1 for mit wpu at pune .pptx
A novel scalable deep ensemble learning framework for big data classification...
Profit Center Accounting in SAP S/4HANA, S4F28 Col11
DP Operators-handbook-extract for the Mautical Institute
The various Industrial Revolutions .pptx
Chapter 5: Probability Theory and Statistics
Microsoft Solutions Partner Drive Digital Transformation with D365.pdf
Architecture types and enterprise applications.pdf
MicrosoftCybserSecurityReferenceArchitecture-April-2025.pptx
2021 HotChips TSMC Packaging Technologies for Chiplets and 3D_0819 publish_pu...

Barriers to Distributed Renewable Energy

  • 1. Barriers to Distributed Renewable Energy efficient | economical | equitable John Farrell, Senior Researcher
  • 2. Total Installed Capacity 47,000 MW 4,034 MW Together = 3.3% of U.S. sales
  • 3. How Much Community-Owned? 47,000 MW 5%? 10%? 25%? 4,034 MW
  • 4. Community-Owned just 1%
  • 5. Why Community-Owned? 2 Community-Owned = distributed (distributed generation) x (distributed ownership)
  • 6. Barriers to Distributed Generation • Tradition • Capital • Cash Flow • Legal • Utility
  • 7. Tradition Utility Perspective Reality Centralized Power Clean, local power Solar PV power plant Storage Storage Transmission network Storage Storage House Local CHP plant Distribution network House with domestic CHP Wind power Factory Commercial plant building
  • 8. Barriers to Distributed Generation • Tradition • Capital • Cash Flow • Legal • Utility
  • 9. Capital ...buy this? How can they...
  • 10. Rules for Raising Capital • Full registration • Regulation D • Regulation A • Intra-State • Private
  • 11. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None $30,000 Accredited investors; Regulation D -50,000 $10,000/yr prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising
  • 12. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None $30,000 Accredited investors; Regulation D -50,000 $10,000/yr prior relationship 9% 3% $50,000 Regulation A -75,000 $10,000/yr $5 million offering Project Cost $50,000 Upfront Intra-State -75,000 $10,000/yr (MN) In-state only Compliance Prior relationship; no Private Minimal Minimal advertising
  • 13. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None $30,000 Accredited investors; Regulation D -50,000 $10,000/yr prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering 59% Intra-State 19%$50,000 $10,000/yr (MN) In-state only -75,000 Project Cost Prior relationship; no Private Upfront Minimal Minimal advertising Compliance Too costly for small projects
  • 14. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 investors; prior Regulation D -50,000 $10,000/yr relationship w/ investors $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising
  • 15. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 Regulation D -50,000 $10,000/yr investors; prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising
  • 16. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 Regulation D -50,000 $10,000/yr investors; prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering Intra-State $50,000 -75,000 ≤ 2 turbines $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising
  • 17. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 5% Regulation D -50,000 $10,000/yr investors; prior relationship 27% $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State Project Cost -75,000 $10,000/yr (MN) In-state only Upfront Compliance Prior relationship; no Private Minimal Minimal advertising Still costly for small projects
  • 18. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 Regulation D -50,000 $10,000/yr investors; prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising
  • 19. Type of Upfront Compliance Restrictions registration Cost Costs 5% $100,000- 27% SEC Full 125,000 Over $400,000/yr None Accredited Project Cost $30,000 Regulation D -50,000 $10,000/yr investors; prior Upfront relationship Compliance $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; no Private Minimal Minimal advertising Still costly for small projects
  • 20. Type of Upfront Compliance Restrictions registration Cost Costs $100,000- Full SEC 125,000 Over $400,000/yr None Accredited $30,000 Regulation D -50,000 $10,000/yr investors; prior relationship $50,000 Regulation A -75,000 $10,000/yr $5 million offering $50,000 Intra-State -75,000 $10,000/yr (MN) In-state only Prior relationship; Private Minimal Minimal no advertising
  • 21. Capital is HARD • Full = EXPENSIVE • Regulation D = RICH FOLKS • Regulation A = SIZE/COST • Intra-State = COSTLY • Private = LIMITED
  • 22. Hope: Crowdfunding • 2012 federal JOBS Act • $1 million limit • Minimal compliance • Lower upfront cost: $10-15k
  • 23. Example Private  Placement
  • 24. Barriers to Distributed Generation • Tradition • Capital • Cash Flow • Legal • Utility
  • 26. Minnesota Commercial Solar Project Cash Flow 30% 25% 25% 20% 0% 25% 50% 75% 100% Federal tax credit Depreciation State rebate Net metering
  • 27. Germany/Ontario Commercial Solar Project Cash Flow 100% 0% 25% 50% 75% 100% Feed-In Tariff
  • 28. Feed-In Tariff • Long-term, fixed price contract • Guaranteed, simple grid connection • Price sufficient for small profit
  • 29. Policy Shapes Cost High U.S. Return Ontario Germany Low Low Risk High
  • 30. Policy Shapes Participation 80% of German solar is on small rooftops
  • 31. U.S. Exception University Park community solar
  • 32. Barriers to Distributed Generation • Tradition • Capital • Cash Flow • Legal • Utility
  • 33. Which Makes Sense for Community Solar? A.Nonprofit B.City C. County D.Cooperative E. All of the Above
  • 34. Which Makes Sense for Community Solar? A.Nonprofit B.City C. County D.Cooperative E.All of the Above
  • 35. Which One Works? A.Nonprofit B.City C. County D.Cooperative E. All of the Above
  • 36. Which One Works? A.Nonprofit B.City C. County D.Cooperative E. All of the Above F.None of the Above
  • 37. Minnesota Nonprofit Solar Project Cash Flow 15% 15% 25% 25% 20% 0% 25% 50% 75% 100% Federal tax credit Middleman Depreciation State rebate Net metering
  • 38. Exception Mt. Pleasant Solar Cooperative Group purchase, no legal entity
  • 39. Exception South Dakota Wind Partners 7 turbines, 600 owners, 1 expired cash grant
  • 40. Barriers to Distributed Generation • Tradition • Capital • Cash Flow • Legal • Utility
  • 41. True or false? In 2012, most utilities measure how much electricity is used during peak periods and during minimum use periods on their own grid.
  • 42. True or false? In 2012, most utilities measure how much electricity is used during peak periods and during minimum use periods on their own grid. FALSE
  • 43. How Local Solar Gets Capped ≤ 1. A Limit on Local Power Generation Utilities always want local power generation to be less than local minimum electricity demand so that electricity will not flow out of neighborhoods and back onto the grid.* ? 2. A Guesstimate of Minimum Demand Peak use Whoops! Utilities assume minimum demand is about 30% of peak demand, because they don’t measure minimum demand. ÷ 2 3. An Arbitrary Safety Margin Utilities take this 30% threshold and divide by 2 to get a 15% cap on local solar. “Minimum”(30%) ÷2 Default cap of 15% *Also addressed with 2-way electrical equipment Percent of peak power allowed from local solar
  • 44. How States Can Raise the Cap (Hawaii) Hawaii’s Update (2011) 1. A Daytime Minimum How much solar power is produced at 4 AM? Hawaii estimates the minimum None. But that’s the time of day utilities used demand during daytime. for their minimum demand calculation. Hawaii solar advocates negotiated a change: to estimate minimum demand when the sun is up (Sundays at noon). “Daytime min.” Even though utilities maintain the arbitrary “division by 2” safety margin, this change ÷2 could allow nearly twice as much local solar on the grid. Cap is raised to ~25% Percent of peak power allowed from local solar
  • 45. How States Can Raise the Cap (California) 1. A Measured Daytime Minimum California’s Update (2012) Utilities must actually measure the minimum Measured daytime demand demand on a power line between 9 AM and 4 PM No “division by 2” and no longer use peak demand as a proxy. ÷ 2 2. No “Division by 2” Utilities can’t arbitrarily divide the cap by 2, now that the power line capacity is actually measured. The result could nearly triple the original Daytime minimum 15% cap on local solar power. Cap is raised to ~50% Percent of peak power allowed from local solar
  • 46. Utilities also Want Limits on Total Net Metering LEGEND no statutory net metering limit Lets  customers  pay   aggregate limit higher than 1% “net”  of  own  use  and   of peak demand aggregate limit 1% of peak own  generation demand or less
  • 47. Exception Replicable community solar!
  • 48. Distributed Generation Barriers Exceptions • Tradition • Mt. Pleasant Solar Coop • Clean Energy Collective • Capital • Maryland Solar LLC • Cash Flow • SD Wind Partners • Legal • Utility Learn more at EnergySelfReliantStates.org