SlideShare a Scribd company logo
An Energy & Environment
Conscious, Sustainable &
Prosperous Organization
SESA STERLITE LTD
4X600 MW IPP
1
Power Business Overview
Location Capacity
Jharsuguda IPP 4X600 MW
Jharsuguda CPP 9X135 MW
TSPL 3X650 MW
4X600 MW IPP Jharsuguda (Supplied by SEPCO -III)
Boiler Make HBC China
TG DFPS China
2
Sesa Sterlite – Power Overview
Contributing to India’s Energy
Security
An Energy & Environment Conscious Sustainable Organization
PROJECT - BOILER MODIFICATION FOR RELIABILITY AND
STATION HEAT RATE IMPROVEMENT
3
4X600 MW INDEPENDENT POWER PLANT
 First 600 MW Power Plant of Odisha
 ESP – FF Hybrid precipitator maintaining SPM < 50 mg/Nm3
 Plant supplied by SEPCO-III China (Boiler- Harbin , Turbine- DFPS)
 Plant equipped with modern online performance and combustion
Optimisation softwares.
 IPP has got accreditation with EnMS 50001:2011 , EMS 14001:2004 ,
QMS 9001:2008 and OHSAS 18001:2007 to ensure sustainability .
 Opportunities identified and executed for efficiency and reliability
4
5
Milestone
Particulars U#1 U#2 U#3 U#4
1st Light up 20-Dec-10 12-Jun-10 20-May-11 19-Feb-12
Date of
Synchronization
27-Dec-10 10-Aug-10 9-Jul-11 29-Mar-12
Date of Achieving
Full Load
28-Dec-10 14-Oct-10 16-Aug-11 25-April-12
Date of COD 30-Mar-11 9-Nov-10 19-Aug-11 26-Apr-12
MILESTONES OF SSL , JHARSUGUDA
 Guaranteed Station Heat Rate achieved in all the Units
 Saving Potential in SHR identified in three parameters
 High Superheat Spray 150 TPH w.r.t 65 TPH (rated)
 High Reheat Spray 33 TPH w.r.t 0 TPH (rated)
 Less RH Steam Temperature 525 w.r.t 538 DegC
 High metal temperature excursion causing tube failures
 Difficult to Control Operating Parameter With Top Mill
Operation.
6
OPPORTUNITIES IN BOILER
BOILER DETAILS
Boiler Make The China Harbin Boilers co. Ltd
Boiler Type
Subcritical , Reheat, Single Furnace ,
Single Reheat , Forced Circulation ,
Balanced Draft , Dry bottom ,
Tangential corner fired pulverised Fuel
Fired
SH Outlet Steam pressure (MPa) 17.5
Design Temp (DegC) 541
Boiler Capacity (TPH) 2060
RH Steam Outlet Pressure (MPa) 3.8
RH Steam Temperature (DegC) 541
Fuel consumption (TPH) 433
7
 Losses identified at early stage
 Initiatives started to counter the problem
 Combustion Experts Dr. V T Satyanathan (Ex-BHEL) conducted study
 Combustion Experts of Squam Power Plant Technical Consultancy
engaged for optimisation
 STEAG Germany combustion optimisation software installed
 Online trials conducted and detailed study carried out
8
CORRECTIVE MEASURES
 Trials conducted since 2011 to Dec 2012 mainly focused on
 (i) SADC tuning
 (ii) Burner Tilts
 (iii) OFA damper regulations
 (iv) Soot Blowing Optimisation
 Trials Conducted but desired result could not be achieved with
above Trials.
 Conclusion: SSL insisted Sepco-III to study and provide solution.
9
ENGAGEMENT OF HBC- OEM
 Sepco-III depuetd Combustion expert from Harbin Boiler
 Trial Conducted by Harbin Experts from 4-18th December 2012
 Operation and combustion expert exercised all the possible
combinations
 CONCLUSION :
 Improvement in performance parameter not achieved
 Harbin suspected the variation in fuel was leading to deviations
 Harbin referred the problem to design institute for review and solution.
10
Review and Proposal
 Design institute recommended modification
 Harbin proposed modification in three zones of boiler
 Reduction of Surface area of LTSH from 12944 to 7696 m2
 Reduction of radiation side wall Re-Heater width from 8191 to6268
mm
 Increase of Economiser surface from 215000ft2 to 277000 ft2
 Boiler efficiency and SHR will remain unaffected.
 All the performance test will be carried out after modification.
11
Review and Approval of Project
 SSL & Ex-BHEL design expert Mr. Sivaraman Krishnamurthy
reviewed the proposed modification
 Proposal review meeting held at Harbin China in March 2013.
 Challenge of pressure part alteration in limited access reviewed
 Unit outage for longer time > 60 Days
 Directorate of Factories & Boiler reviewed and approved the
project
 SSL approved the project anticipating long term gain in
Conservation of natural resource and reduction in carbon
emission.
12
REMOVAL OF PRESSURE PART
 Material received within 3 months of project approval from China
 120 Nos. tube Reheat radiation wall removed from each side
 Water wall LTRH headers replaced with new headers
 Lower group of LTSH Removed
13
Cutting of LTRH
Tube and Header
Removal of LTRH
Header
Economiser Tube
cutting
ERECTION OF PRESSURE PART
 Erection methodology was prepared by Harbin & Sepco-III
 Job safety analysis carried out in detail
 Each lifting tools to be used in project tested before
commencement of project
14
Steam Cleaning of
Tubes
Erection of
Economiser Coil
Lifting of water wall panel
through bottom ash
hopper
Erection of Pressure Part
 Detailed Quality assurance plan to ensure quality work
 Radiography conducted in 100% joint in RH and LTSH area
 Radiography in 20% joint of Economiser.
15
Readiness for
position eco tube
Economiser coil in
position
PROJECT – Boiler Modification
 First modification started in Boiler of Unit#3 w.e.f 12th July 2013
 Modification carried out during scheduled annual overhaul of Unit-3
 Sepco-III executed the modification project
 Material was supplied from China in short duration of 3 months
16
Removal of LTRH
Header Fitment of new
LTRH Header
Erection of new
LTRH link pipe
PROJECT – Boiler Modification
 Manpower engaged 250
 No of Days for project completion - 60
 Cost of Project Rs 500 millions INR
 No of Welding Joints 3485
17
Lifting of Economiser Coil Addition of Economiser bank New Added Economiser bank
Re-Commissioning & Demonstration
 Detailed programme prepared for Boiler flushing
 Flushing continued for 3 Days to bring the parameters in limits
 Post-modification demonstration carried out for
 Boiler Efficiency test
 Boiler efficiency test at design and worst coal
 Demonstration for Zero Reheat spray and rated Super heater spray
 Demonstration for top mill and bottom mill operation
 Reliability test for design unit load ramp up and ramp down
 14 Days reliability run by OEM
All the tests were successfully completed
18
Boiler Parameters After Modification
19
S.No Parameter Description UOM Design
Before
Modificatio
n
After
Modificatio
n
1 Power Generation MW 600 599 601
2 Coal flow TPH 420 411 383
3 Main Steam Pressure Mpa 16.7 16.37 16.66
4 Main steam Temperature DegC 538 539 539
5 RH steam Temperature DegC 538 536 538
6 RH Steam Pressure MPa 3.8 3.61 3.49
7 SH Spray TPH 65 150 66
8 RH Spray TPH 0 25 0
 SH Spray Reduced from 150 TPH to 66 TPH
 RH Spray Reduced from 33 TPH to Zero
 Top Mills Service operation became normal operation
 Improvement in SHR of 14Kcal/KWH achieved
 SHR Improvement contributed to saving of 87000 MT of coal per
annum
 Reduction in CO2 emission by 2.3 lacs MT emission due to
improvement in SHR.
20
Result Summary
CALCULATION OF GAIN AFTER MODIFICATION
S.No.
IMPROVEMENT
AREA
UOM
Before
Modification
After
Modification
Improve
ment
Gain in
Heat
Rate
(Kcal/K
wh)
Net Saving
in Millions
(INR)Per
annum
Net
Saving
of Fuel
Per
Annum
(MT)
1 Av . Power Generation MW 600 600 0 0 0 0
2 Reheat Temperature DegC 525 538 13 6.7 24 10534
3 Reheat Spray % 2.4 0 2.4 7 26 11088
4 SH Spray % 8.6 3.5 5.1 0.12 0.44 190
Total Savings Per unit per Annum (@90% PLF , 3000 Kcal/Kg GCV) 50 21812
Total Saving Per Annum for 4X600 MW 201 87247
21
Thank You
22

More Related Content

PPT
Air heater
PDF
Power plant
PPT
Energy performance assessment of boilers
PPTX
MET 401 Chapter 2 -_updated_simple_ideal_rankine_cycle
PDF
Effect of Coal Quality and Performance of Coal pulverisers / Mills
PPTX
Turbine Operation Issues.pptx
PDF
Definition and selection of design temperature and pressure prg.gg.gen.0001
PPT
Cooling towers
Air heater
Power plant
Energy performance assessment of boilers
MET 401 Chapter 2 -_updated_simple_ideal_rankine_cycle
Effect of Coal Quality and Performance of Coal pulverisers / Mills
Turbine Operation Issues.pptx
Definition and selection of design temperature and pressure prg.gg.gen.0001
Cooling towers

What's hot (20)

PPT
Relief and safety valves for thermal power plants
PPTX
fuel systems_PPT_NPTI(3).pptx
PPTX
Introduction to Stress Analysis and Piping Vibration Analysis
PPSX
Cooling water (CW) system
PPT
Boiler efficiency by loss Method
PPT
Basic steam engineering nucleate boiling ppt
PDF
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
PPTX
Boiler Presentation
PDF
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
PDF
GAS TURBINE MAJOR INSPECTION
PDF
Thermal Power Plant Simulator Hands-on Malfunctions
PPTX
Electrohydraulic governing system
PPT
C&i systems
PPSX
Excitation System & capability curve of synchronous generator
PPTX
Classification of boiler
PPTX
Boiler turbe failores
DOCX
500 MW synchronous generator rotor construction report
PPTX
Accumulation and Over-pressure: difference between accumulation and overpressure
PPT
Internal combustion engine (ja304) chapter 2
PDF
Standard erection manual (pressure parts)
Relief and safety valves for thermal power plants
fuel systems_PPT_NPTI(3).pptx
Introduction to Stress Analysis and Piping Vibration Analysis
Cooling water (CW) system
Boiler efficiency by loss Method
Basic steam engineering nucleate boiling ppt
Ntpc (national thermal power corporation) sipat boiler haxxo24 i~i
Boiler Presentation
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
GAS TURBINE MAJOR INSPECTION
Thermal Power Plant Simulator Hands-on Malfunctions
Electrohydraulic governing system
C&i systems
Excitation System & capability curve of synchronous generator
Classification of boiler
Boiler turbe failores
500 MW synchronous generator rotor construction report
Accumulation and Over-pressure: difference between accumulation and overpressure
Internal combustion engine (ja304) chapter 2
Standard erection manual (pressure parts)
Ad

Similar to Boiler Modification for SHR & Reliability Improvement SSL (IPP) (20)

PDF
Paper cid-furnace-feed-maxmization
PPTX
Jisc con optimisation, improved sustainability across the estate through us...
PDF
Assement of-bag-filter-vs-esp-cpcb
PPT
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
DOCX
Resume yogesh
PPTX
Another 30 years, thermal power plant R&M
PDF
India study i g c c
PDF
PS_1.1. plant upgrade Boryeong Unit 1, 2 TPP Upgrade (Korea)
PDF
'Study and Analysis of Boiler System Performance' - Case Study reports_0.pdf
PDF
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
PDF
WHITE PAPER-Best Practices in Syngas Plant Optimization.pdf
PDF
METHANOL PLANT ARC RETROFIT Case Study
PPTX
Prajwal Patil
PDF
Improved power plant performance, Sulzer Technical Review, 2009
PPTX
QIT 2024( OLD ).pptxaadadadsdsasdadsasda
PDF
A practical approach to pharmaceutical HVAC energy reduction
PDF
Partial List of Past SAVvy Engineering Projects
PDF
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
DOC
ntpc unchahar
DOC
Steve Davidson Engineering Resume
Paper cid-furnace-feed-maxmization
Jisc con optimisation, improved sustainability across the estate through us...
Assement of-bag-filter-vs-esp-cpcb
APP_PEER_REV_Australia-INDIA PERSPECTIVE 23 June.ppt
Resume yogesh
Another 30 years, thermal power plant R&M
India study i g c c
PS_1.1. plant upgrade Boryeong Unit 1, 2 TPP Upgrade (Korea)
'Study and Analysis of Boiler System Performance' - Case Study reports_0.pdf
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
WHITE PAPER-Best Practices in Syngas Plant Optimization.pdf
METHANOL PLANT ARC RETROFIT Case Study
Prajwal Patil
Improved power plant performance, Sulzer Technical Review, 2009
QIT 2024( OLD ).pptxaadadadsdsasdadsasda
A practical approach to pharmaceutical HVAC energy reduction
Partial List of Past SAVvy Engineering Projects
FINAL YEAR INDUSTRIAL TRAINING REPORT-ALBARIO ENGINEERING NANDIPUR 435 Combin...
ntpc unchahar
Steve Davidson Engineering Resume
Ad

Recently uploaded (20)

PPTX
Relationship Management Presentation In Banking.pptx
PPTX
Human Mind & its character Characteristics
PPTX
FINAL TEST 3C_OCTAVIA RAMADHANI SANTOSO-1.pptx
PPTX
PHIL.-ASTRONOMY-AND-NAVIGATION of ..pptx
PPTX
Project and change Managment: short video sequences for IBA
PPT
First Aid Training Presentation Slides.ppt
PDF
COLEAD A2F approach and Theory of Change
PDF
6.-propertise of noble gases, uses and isolation in noble gases
PPTX
Intro to ISO 9001 2015.pptx wareness raising
DOCX
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
PPTX
ANICK 6 BIRTHDAY....................................................
PDF
Nykaa-Strategy-Case-Fixing-Retention-UX-and-D2C-Engagement (1).pdf
PPTX
AcademyNaturalLanguageProcessing-EN-ILT-M02-Introduction.pptx
PPTX
Impressionism_PostImpressionism_Presentation.pptx
PDF
Yusen Logistics Group Sustainability Report 2024.pdf
PDF
Tunisia's Founding Father(s) Pitch-Deck 2022.pdf
PPTX
Introduction-to-Food-Packaging-and-packaging -materials.pptx
PPTX
NORMAN_RESEARCH_PRESENTATION.in education
PPTX
Self management and self evaluation presentation
PPTX
Hydrogel Based delivery Cancer Treatment
Relationship Management Presentation In Banking.pptx
Human Mind & its character Characteristics
FINAL TEST 3C_OCTAVIA RAMADHANI SANTOSO-1.pptx
PHIL.-ASTRONOMY-AND-NAVIGATION of ..pptx
Project and change Managment: short video sequences for IBA
First Aid Training Presentation Slides.ppt
COLEAD A2F approach and Theory of Change
6.-propertise of noble gases, uses and isolation in noble gases
Intro to ISO 9001 2015.pptx wareness raising
ENGLISH PROJECT FOR BINOD BIHARI MAHTO KOYLANCHAL UNIVERSITY
ANICK 6 BIRTHDAY....................................................
Nykaa-Strategy-Case-Fixing-Retention-UX-and-D2C-Engagement (1).pdf
AcademyNaturalLanguageProcessing-EN-ILT-M02-Introduction.pptx
Impressionism_PostImpressionism_Presentation.pptx
Yusen Logistics Group Sustainability Report 2024.pdf
Tunisia's Founding Father(s) Pitch-Deck 2022.pdf
Introduction-to-Food-Packaging-and-packaging -materials.pptx
NORMAN_RESEARCH_PRESENTATION.in education
Self management and self evaluation presentation
Hydrogel Based delivery Cancer Treatment

Boiler Modification for SHR & Reliability Improvement SSL (IPP)

  • 1. An Energy & Environment Conscious, Sustainable & Prosperous Organization SESA STERLITE LTD 4X600 MW IPP 1
  • 2. Power Business Overview Location Capacity Jharsuguda IPP 4X600 MW Jharsuguda CPP 9X135 MW TSPL 3X650 MW 4X600 MW IPP Jharsuguda (Supplied by SEPCO -III) Boiler Make HBC China TG DFPS China 2 Sesa Sterlite – Power Overview Contributing to India’s Energy Security An Energy & Environment Conscious Sustainable Organization
  • 3. PROJECT - BOILER MODIFICATION FOR RELIABILITY AND STATION HEAT RATE IMPROVEMENT 3
  • 4. 4X600 MW INDEPENDENT POWER PLANT  First 600 MW Power Plant of Odisha  ESP – FF Hybrid precipitator maintaining SPM < 50 mg/Nm3  Plant supplied by SEPCO-III China (Boiler- Harbin , Turbine- DFPS)  Plant equipped with modern online performance and combustion Optimisation softwares.  IPP has got accreditation with EnMS 50001:2011 , EMS 14001:2004 , QMS 9001:2008 and OHSAS 18001:2007 to ensure sustainability .  Opportunities identified and executed for efficiency and reliability 4
  • 5. 5 Milestone Particulars U#1 U#2 U#3 U#4 1st Light up 20-Dec-10 12-Jun-10 20-May-11 19-Feb-12 Date of Synchronization 27-Dec-10 10-Aug-10 9-Jul-11 29-Mar-12 Date of Achieving Full Load 28-Dec-10 14-Oct-10 16-Aug-11 25-April-12 Date of COD 30-Mar-11 9-Nov-10 19-Aug-11 26-Apr-12 MILESTONES OF SSL , JHARSUGUDA
  • 6.  Guaranteed Station Heat Rate achieved in all the Units  Saving Potential in SHR identified in three parameters  High Superheat Spray 150 TPH w.r.t 65 TPH (rated)  High Reheat Spray 33 TPH w.r.t 0 TPH (rated)  Less RH Steam Temperature 525 w.r.t 538 DegC  High metal temperature excursion causing tube failures  Difficult to Control Operating Parameter With Top Mill Operation. 6 OPPORTUNITIES IN BOILER
  • 7. BOILER DETAILS Boiler Make The China Harbin Boilers co. Ltd Boiler Type Subcritical , Reheat, Single Furnace , Single Reheat , Forced Circulation , Balanced Draft , Dry bottom , Tangential corner fired pulverised Fuel Fired SH Outlet Steam pressure (MPa) 17.5 Design Temp (DegC) 541 Boiler Capacity (TPH) 2060 RH Steam Outlet Pressure (MPa) 3.8 RH Steam Temperature (DegC) 541 Fuel consumption (TPH) 433 7
  • 8.  Losses identified at early stage  Initiatives started to counter the problem  Combustion Experts Dr. V T Satyanathan (Ex-BHEL) conducted study  Combustion Experts of Squam Power Plant Technical Consultancy engaged for optimisation  STEAG Germany combustion optimisation software installed  Online trials conducted and detailed study carried out 8 CORRECTIVE MEASURES
  • 9.  Trials conducted since 2011 to Dec 2012 mainly focused on  (i) SADC tuning  (ii) Burner Tilts  (iii) OFA damper regulations  (iv) Soot Blowing Optimisation  Trials Conducted but desired result could not be achieved with above Trials.  Conclusion: SSL insisted Sepco-III to study and provide solution. 9
  • 10. ENGAGEMENT OF HBC- OEM  Sepco-III depuetd Combustion expert from Harbin Boiler  Trial Conducted by Harbin Experts from 4-18th December 2012  Operation and combustion expert exercised all the possible combinations  CONCLUSION :  Improvement in performance parameter not achieved  Harbin suspected the variation in fuel was leading to deviations  Harbin referred the problem to design institute for review and solution. 10
  • 11. Review and Proposal  Design institute recommended modification  Harbin proposed modification in three zones of boiler  Reduction of Surface area of LTSH from 12944 to 7696 m2  Reduction of radiation side wall Re-Heater width from 8191 to6268 mm  Increase of Economiser surface from 215000ft2 to 277000 ft2  Boiler efficiency and SHR will remain unaffected.  All the performance test will be carried out after modification. 11
  • 12. Review and Approval of Project  SSL & Ex-BHEL design expert Mr. Sivaraman Krishnamurthy reviewed the proposed modification  Proposal review meeting held at Harbin China in March 2013.  Challenge of pressure part alteration in limited access reviewed  Unit outage for longer time > 60 Days  Directorate of Factories & Boiler reviewed and approved the project  SSL approved the project anticipating long term gain in Conservation of natural resource and reduction in carbon emission. 12
  • 13. REMOVAL OF PRESSURE PART  Material received within 3 months of project approval from China  120 Nos. tube Reheat radiation wall removed from each side  Water wall LTRH headers replaced with new headers  Lower group of LTSH Removed 13 Cutting of LTRH Tube and Header Removal of LTRH Header Economiser Tube cutting
  • 14. ERECTION OF PRESSURE PART  Erection methodology was prepared by Harbin & Sepco-III  Job safety analysis carried out in detail  Each lifting tools to be used in project tested before commencement of project 14 Steam Cleaning of Tubes Erection of Economiser Coil Lifting of water wall panel through bottom ash hopper
  • 15. Erection of Pressure Part  Detailed Quality assurance plan to ensure quality work  Radiography conducted in 100% joint in RH and LTSH area  Radiography in 20% joint of Economiser. 15 Readiness for position eco tube Economiser coil in position
  • 16. PROJECT – Boiler Modification  First modification started in Boiler of Unit#3 w.e.f 12th July 2013  Modification carried out during scheduled annual overhaul of Unit-3  Sepco-III executed the modification project  Material was supplied from China in short duration of 3 months 16 Removal of LTRH Header Fitment of new LTRH Header Erection of new LTRH link pipe
  • 17. PROJECT – Boiler Modification  Manpower engaged 250  No of Days for project completion - 60  Cost of Project Rs 500 millions INR  No of Welding Joints 3485 17 Lifting of Economiser Coil Addition of Economiser bank New Added Economiser bank
  • 18. Re-Commissioning & Demonstration  Detailed programme prepared for Boiler flushing  Flushing continued for 3 Days to bring the parameters in limits  Post-modification demonstration carried out for  Boiler Efficiency test  Boiler efficiency test at design and worst coal  Demonstration for Zero Reheat spray and rated Super heater spray  Demonstration for top mill and bottom mill operation  Reliability test for design unit load ramp up and ramp down  14 Days reliability run by OEM All the tests were successfully completed 18
  • 19. Boiler Parameters After Modification 19 S.No Parameter Description UOM Design Before Modificatio n After Modificatio n 1 Power Generation MW 600 599 601 2 Coal flow TPH 420 411 383 3 Main Steam Pressure Mpa 16.7 16.37 16.66 4 Main steam Temperature DegC 538 539 539 5 RH steam Temperature DegC 538 536 538 6 RH Steam Pressure MPa 3.8 3.61 3.49 7 SH Spray TPH 65 150 66 8 RH Spray TPH 0 25 0
  • 20.  SH Spray Reduced from 150 TPH to 66 TPH  RH Spray Reduced from 33 TPH to Zero  Top Mills Service operation became normal operation  Improvement in SHR of 14Kcal/KWH achieved  SHR Improvement contributed to saving of 87000 MT of coal per annum  Reduction in CO2 emission by 2.3 lacs MT emission due to improvement in SHR. 20 Result Summary
  • 21. CALCULATION OF GAIN AFTER MODIFICATION S.No. IMPROVEMENT AREA UOM Before Modification After Modification Improve ment Gain in Heat Rate (Kcal/K wh) Net Saving in Millions (INR)Per annum Net Saving of Fuel Per Annum (MT) 1 Av . Power Generation MW 600 600 0 0 0 0 2 Reheat Temperature DegC 525 538 13 6.7 24 10534 3 Reheat Spray % 2.4 0 2.4 7 26 11088 4 SH Spray % 8.6 3.5 5.1 0.12 0.44 190 Total Savings Per unit per Annum (@90% PLF , 3000 Kcal/Kg GCV) 50 21812 Total Saving Per Annum for 4X600 MW 201 87247 21