the presentation over knowledge related Boiler Operation and Maintenance and all personnel specialized in boiler industry and personnel whom specialized in maintenance or operation
3. BOILER START UP
Boiler startup can be of two types:
• Startup of a cold boiler.
• Startup of warm / hot boiler
4. START UP OF COLD BOILER
• The boiler has been idle for more than three days.
• There is no pressure in the steam drum. Drum
Pressure is less than 2 Kg/cm 2 (g)
• Drum metal temperature is less than 70 Deg. C.
START UP OF WARM / HOT BOILER
• Starting of the boiler immediately after trip-Hot
Startup pressure >10 kg/cm2
• When the boiler is still in Hot / Warm with the
drum pressure more than 03 Kg / cm2 g - Warm
Startup.
5. Boiler Cold Start Up- Essentials
• HT Power (If Applicable)
• LT Power
• 24 v/110v Power, DCS,SCADA Panel
Readiness
• UPS
• Instrument air
• Service air
• Cooling water
• Fuel
• Panel & Field Operation team
6. Boiler Start Up Sequence
• Walk Down checks
• System line up
• Water filling
• Burner Checks
• Fuel gas charging
• Equipment (aux) in service
• Boiler start and pressurizing.
• Pressurizing and loading.
• Boiler auto operation
7. Burner Start Up & Shut Down
• Burner Management System (BMS)
• Preinterlocks to be satisfied
• Purge interlock to be satisfied
• Main interlocks to be satisfied
• Burner ready to start
• Burner on
• Flame monitoring
• Putting Controllers in auto mode
• Boiler Loading
• Burner stop/trip
• Gun Clearing
• Boiler shut down
8. BOILER OPERATING PROCEDURES
This subsection describes the boiler
operation as applicable for the
following boiler conditions:
Startup of a cold boiler.
Startup of warm / hot boiler.
Boiler shutdown.
9. STARTUP OF A COLD BOILER
Boiler startup can be termed as cold startup
when there is no pressure or when pressure
is less than 2-kg/cm2
G in the steam drum.
In a cold start up, possibilities of some
inspection or maintenance works having
been done is presumed. A walk down check
is required and the boiler and its auxiliaries
are to be prepared meticulously for a start
up from the DCS of the control room. Before
a walk down check ensure that all work
permits have been returned, tags are
removed and maintenance permission for
boiler start up is available.
10. WALK DOWN CHECKS
Using powerful torches or low voltage
inspection lamps, inspect the furnace and
the second pass of the boiler and ensure the
following:
BOILER
Furnace and second pass are clear, all
maintenance personnel have been
withdrawn and no scaffolding or inspection
devices have been left inside.
Furnace floor, water walls and second pass
convection tubes are clean and there is no
evidence of any water drips, slag or any
other deposits.
Steam and water drums are clear and
manholes are closed properly.
11. BOILER…..
Verify that all access doors, inspection doors
of furnace and wind box are tightly closed.
Verify that all peepholes have been tightly
closed and sealing/ cooling air connections
have been made and the air valves are open.
Verify that the air duct, wind-box, external
economiser and flue gas duct to stack is clear
and that all maintenance personnel have been
withdrawn. Ensure that the manhole doors are
closed properly.
Verify that the safety valves are not gagged.
Verify that the illuminators of local level
gauges are 'ON'. Inlet valves from steam and
water-side are open and their drain valves are
12. BOILER….
•Verify whether the Nitrogen purging valves
are open (connected to the steam drum and
main steam piping). If they are open, they
have to be closed before boiler light up.
BURNER
Verify that the pilot & fuel gas, fuel oil and
atomizing media flexible hoses are connected
to the burner at the proper locations.
Verify that the Igniter has been inserted in the
burner housing and that the HT cable has
been connected to the igniter.
13. BURNER……
•Verify that the Flame Scanners have been
installed properly, cooling air hoses are
connected and valves are open.
Verify that the wind-box dampers fully
open and air supply to actuator is available.
Verify physically and in DCS that the fuel
shut off valves is fully closed and bleed
valves are open.
The manually operated fuel isolating valves
are to be verified for shut. These valves
have to be opened just before boiler start
up.
14. FD FAN
Check that the fan inspection doors are
closed.
Ensure that the bearing lubrication is
done properly.
Check that the coupling guards are
installed.
Ensure that the damper actuator is
properly fixed to the operating lever and
air supply is open to actuator and I/P
Converter.
15. GENERAL
Ensure that the battery limit valves are open
and following inputs are available:
Instrument air and Service air.
Feed water up to level control station.
Power up of feeders for FD fan motor and all
the other drives.
Fuel gas and pilot gas up to terminal point
isolation valve.
Chemical dosing supply at terminal point.
Cooling water supply at terminal point.
Refer the respective pump & fan vendor
manuals for the preparation and pre start up
checks to be done on the equipment.
16. SYSTEM LINE UP
PRELIMINARY REQUIREMENTS
Power supply: ensure that the power supply
is switched 'ON' and available for all the
motors and panels.
Operating station - DCS is to be ensured for
readiness.
As instrument air is necessary for the
operation of most of the valves and actuators,
charge the instrument air header, the branch
lines and instruments supply lines elsewhere.
Root valves of all Instruments (Pressure
gauges, Pressure transmitters, DP
transmitters, Level gauges, etc.,) must be kept
open and their drains if any are to be kept
closed.
Ensure that all the transmitters are lined up
17. BOILER
ECONOMISER
Keep the air vent on the outlet headers of
all the Economizer modules open. The vent
has to be closed as soon as air is vented
from modules and water comes out
continuously during initial filling of the
boiler.
Ensure that the drain valves of bottom
headers are kept closed.
STEAM AND WATER DRUM
Ensure that the drum vent valves are kept
open. These valves will have to be closed
when the drum pressure attains 2 kg/cm2
G.
Open the CBD line isolation valve and keep
18. STEAM AND WATER DRUM….
Open the IBD line isolation valves and keep
close the IBD valve.
Keep the phosphate dosing line isolation
valve open. However, the dosing will be
started after the boiler lightup.
Verify that drains and vents of Standpipes
provided for level transmitters, indicator &
gauges are closed.
Ensure that the drain and vent valves of the
rear wall panel header are closed.
Open the drain valves of drain header.
Once there is no water/ Condensate coming
out, these valves have to be closed. The
isolation valve from the drain header to the
common BD tank is to be kept open. Ensure
that the boiler fill-up line is kept closed.
19. SUPERHEATER….
Ensure that the drain valves of the outlet &
intermediate headers of the superheater &
the attemperator are kept open. This is to
ensure that the superheater coils are totally
drained before lightup of boiler.
Keep open the startup vent isolation valve.
The control valve has to be kept open
100%.
Ensure that the MSSV and pressure
equalization valves are in close position and
remote selected.
Keep the battery limit isolation valve close.
Open the drain valves on the steam line and
let the condensate get drained.
20. FEEDWATER SYSTEM
FEEDWATER AND SPRAY WATER LINE
Select the drum level and feed water flow
controllers in manual mode and close the 30% &
100% control valves.
Open the manual isolation valves of the feed-
water Flow Control Valves. Keep close MOV’s
Open the 30% Control Valve Motorized
isolation valve open, when CV is to be taken in
line.
Select the steam temperature controller into
manual mode and keep the output fully closed.
21. FEEDWATER AND SPRAY WATER LINE...
Open the manual isolation valves of the
spray water control valve. Keep the bypass
valve close.
The drain valves on the feed water and the
temperature control stations have to be
kept closed.
SAMPLE SYSTEM
All the sample lines isolation valves have to
be closed. Sample coolers can be taken into
service once the boiler is pressurized
(approx. 2-kg/cm2
).
22. FILLING WATER IN BOILER
The following procedure is adapted for
filling the boiler:
During water filling, for assurance of
correct steam drum water level, post an
attendant at the drum level to monitor the
local gauges and to communicate to the
control room when the level of '50 mm'
below NWL is reached.
Operator to ensure that the feed water
control valves are closed and the controller
is in manual mode. The boiler fill-up line on
the drain header is opened and the
isolation valve to the BD tank on the drain
header is closed. The drain valves on the
front & rear wall panel bottom headers
have to be kept opened for the boiler fill-
23. FILLING WATER IN BOILER…….
• Request an attendant to close the air
vents on front & rear wall panel top
header as soon as water comes out from it
continuously. Water rises to the steam
drum through the furnace front & rear
wall header. It will take minutes to fill
water to the required level.
As water level in steam drum reaches '50
mm' below the NWL on local level gauge
(confirmation by the attendant) and in
level indicator, water filling can be
discontinued. Close the fill-up valve on the
drain header and also close the drain
valves on the furnace front & rear wall
24. FILLING WATER IN BOILER…….
Caution: Filling water temperature should
not be more than 38 deg-C of the boiler
metal temperature. During filling of a cold
boiler, the ambient temperature should be
used as an indicator of the boiler metal
temperature. Assuming an ambient
temperature of 40 deg C, the maximum
temperature of filling water shall be 78 deg
C.
25. BURNER CHECKS
Verify that the natural gas spuds of Burners has been
manually cleaned and inserted in the burner housing.
Verify that the natural gas pipeline has been connected
through flexible hoses to burner.
Verify that the Ignitor has been inserted in the burner
housing and connected to the pilot gas line through the
flexible hose. Verify that the HT cable has been
connected to the ignitor.
Verify that cooling air, sealing air connections to the
burner components.
Verify that the (UV+IR) Scanner has been inserted and
cooling air hose connected and valve is open.
Verify on DCS that natural gas shut valve,pilot gas
admission valve is open (DCS-BMS program). Also verify
the valve positions on BMS local panel.
The manually operated isolating valves are to be
verified shut. These valves are opened just before burner
light up.
Carry out similar checks for other Burners.
26. CHARGING OF NG
Natural gas lines must be checked carefully
before charging to ensure that there are no
possibilities of leak through flange joints,
valve bonnet, pressure gauge tapings etc.,
During charging if any minor leaks are
noticed, maintenance personnel must be
called to attend to the leaks. In case of
serious leaks, charging must be
abandoned, line to be depressurized,
purged and leaks to be attended before
proceeding further.
If gas leak detector is available, make use
of it.
27. CHARGING OF NATURAL GAS
The charging of the natural gas can be
done as follows -
•Close the Inert gas isolation valve.
Verify that the root valves of all the
instruments are open.
Verify that all the fuel gas and Pilot gas trip
valves (shut off valves) are in ‘close’ position
- physically at field and in DCS.
Open the Inlet and Outlet isolating valves
of the fuel gas Pressure Control Valve and
keep close the Flow control valve.
With information to the plant, crack open
the terminal point isolation valve, while
keep open the down stream valve.
28. CHARGING OF Natural GAS …...
•Observe gas flow upto Main Fuel Trip Valve in the
pressure indicators. Observe for leaks if any. Then
slowly increase the opening of the terminal point
isolation valve.
If the gas line upto burners is filled with inert gas, it
has to be purged out through the header vent valve
with the fuel gas just before burner light up. This can
be done by force opening the Main Fuel Trip and
start up PCV.
Once it is ensured that the fuel gas is available.
Normalize the Main Fuel Trip Valve & start up PCV.
Then open the burner natural gas manual isolation
valves for the burner to be fired. Keep isolated other
burners.
Open the isolation valve of pilot gas line. Observe
that the gas pressure is read by the indicators and
pilot gas pressure low alarm extinguishes.
Burner inlet pilot gas manual isolation valves shall
be opened.
29. PLACING FD FAN IN SERVICE
Check lubrication of the fan bearings.
Check that the fans are free to rotate.
Check that the flaps on their discharge ducts are in
the closed position and are free to swing.
Check that the fan inspection doors are closed.
Check that the suction dampers are in the closed
position.
Ensure that the power supply is available for the
feeder in MCC (Motor driven FD Fan).
Ensure the oil level in the bearing housing.
FD fan can be started either from DCS or from local
burner panel. The remote / local selector switch to be
positioned according to the startup location decided.
Start the FD fan after selecting the airflow controller
30. PLACE FD FAN IN SERVICE….
On giving START command
Observe that the fan runs up to speed and comes into
service.
Observe that there are no excessive vibrations (by feel)
in the bearings and no abnormal noise from the fan,
turbine & gear-box or motor.
Observe the bearing temperature stabilize.
Observe that the motor casing temperature is normal.
Now the fan is ready for furnace purge. Purge start
command may be given if required.
31. CHARGING OF PILOT GAS
If the Natural Gas is available then the
isolation valve for pilot gas line is to be
opened and the pilot gas to be charged.The
discharge pressure of the PCV is to be
maintained to around 1 Barg. (This will be
again set finally as per reqt during
commissioning). If required, suitably adjust
the self-acting PCV.
LPG back-up has been provided in case NG
is not available and burner needs to be
started with oil firing.
32. BOILER STARTUP AND
PRESSURISING
The preparations for a boiler start up so far
described can be summarized as below:
Walk down checks of the boiler, economiser, FD
fan, air & flue ducts and pipelines.
System/ valves line up of the boiler & economiser,
feed water system, steam line and drain lines.
Filling the boiler with feed water and normalizing
the drum level.
Charging the fuel oil , fuel gas & pilot gas lines.
Now the boiler is ready for light up. Before light up it
is necessary to understand BMS logic.
33. BOILER PRESSURISATION AND LOADING
Once the burner is ON, Boiler will be pressurized
according to the pressurizing curve.
After establishing flame in burner, the operator takes
care of the following:
Operator has to take care of proper fuel to air
supply.
Operator has to inspect the flame in the furnace
through peepholes. Clear furnace with proper
flame is important.
Monitor the steam drum water level.
Monitor the parameters, which can cause a boiler
trip as explained in BMS logic.
Line up the phosphate dosing to steam drum at a
slow rate.
34. BOILER PRESSURISATION AND LOADING….
• Operator has to be on alert for swelling of drum level
when the boiler water temperature builds up to 90 0
C.
Open the IBD valve and regulate such that the water
level is within limits. IBD Valve is to be closed once the
water level is normalized.
Modulate the firing / fuel flow so that the boiler
pressurization is following the pressurization curve.
Firing rate has to be increased manually from DCS
console. Positive air fuel ratio has to be maintained
during modulation. In the process second burner may
be started.
Start vent/ pressure control valve may have to be
throttled in the process of pressurization. Aim is to
attain rated steam flow with the rated steam pressure
and temperature.
35. BOILER PRESSURISATION AND
LOADING….
At 2 kg/cm2
G drum pressure drum vent valves have to be
closed.
At 2 kg/cm2
G drum pressure superheater drain valves
have to be closed.
Once the swelling is over and the drum level normalizes,
select the drum level controller into single element
control and into auto mode with set point corresponding
to the NWL. Monitor that the drum level controller is
maintaining the level automatically.
Operator shall have a walk down check of feedwater line,
fuel gas line, the boiler and the valves. Any water, steam
leakages (through valve glands, bonnets, flanges) and
other minor abnormalities noted can be corrected when
the boiler pressure is less than 5 kg/cm2
G.
36. BOILER PRESSURISATION AND
LOADING….
When the boiler is in service, the Operator has to be
alert to the alarms appearing on DCS. When an
alarm registers, the Operator has to check the cause
for the alarm. Corrective steps have to be taken
wherever necessary to restore normal values. Quick
action by the Operator prevents further
deterioration of values to the boiler trip level.
Steam temperature controller shall be put into auto
mode in DCS console with the set point.
At around rated super heater outlet pressure MSSV
bypass valve can be opened to warm-up the main
steam line to plant or to equalize the pressure. The
trap units in the main steam piping to be lined up.
37. BOILER PRESSURISATION AND
LOADING….
Line up of battery limit isolation valve. If the
downstream of the battery limit valve is in pressurised
condition, pressurize the upstream by opening the
MSSV bypass valve. Once the pressure is equalized on
both the sides of, MSSV can be opened. If the
downstream of is not under pressurised condition, it
can be opened just before opening the MSSV.
When the boiler main steam line pressure reaches
rated pressure and steam flow above 25 % MCR, MSSV
can be opened to connect the boiler with plant main.
As the MSSV is opened the start-up vent valve shall be
closed. MSSV bypass pressure equalization valve shall
be closed.
Once the steam flow is reached above 30% MCR,
drum level control shall be changed over to 3-Element
38. Now, Combustion control shall be taken into auto
mode (Boiler master pressure control. )
Depending on requirement, required no. of burner
can be started. Other burners can be started either
from DCS or from LBP by keeping the combustion
control either in auto mode or temporarily keeping it
in manual mode.
Operator to adjust flow through SH steam,
saturated steam and boiler water sample coolers so
that a small stream of cold samples are obtained
from them. Call for a laboratory analysis of the SH
steam, boiler water and boiler feed water sample.
Necessary water & steam parameters to be
maintained by adjusting the chemical dosing rate
BOILER PRESSURISATION AND
LOADING….
40. HOT STARTUP
Restarting a boiler immediately after a trip when the boiler
is still hot is termed as a hot restart. Restart of the boiler
above a steam pressure of 10 kg/cm2
G is termed as a Hot
startup.
In a Hot restart, as the boiler was in service till the trip out,
the required valve line up (as stated for the cold start up)
will be available and can be quickly checked by visual
inspection. Hot restart requires operations to be done fast,
within the maximum permissible firing rates so as to obtain
quickly the required main steam pressure and temperature
conditions.
Following are the steps involved in the hot startup:
•Normalize the steam drum level by modulating the feed
water flow control valve.
41. HOT STARTUP….
• As soon as the burner is started open the Start up vent
valve.
• Once the flame is stabilised, increase the firing rate
according to the rate of pressurisation specified in the
pressurisation curve.
• Maintain the drum level.
• Once rated pressure and temperature is reached
connect the boiler to the main header and close the
start up vent.
Note:
• On a trip of Boiler, it is not always necessary to close
the main steam valve stop valve. A non-return valve
ensures that there will be no back flow of HP steam
from the plant mains to Boiler. However during restart,
care must be taken to build steam temperature along
with steam pressure so that, when steam starts flowing
to the plant mains it is of acceptable temperature.
43. WARM START-UP
Re-start of the boiler with steam pressure not less
than 03-kg/cm2
(g) is termed as a warm start-up.
The preparations and valve line up required is as for
Hot restart. However as the HRSG has been idle for
several hours, the valve line up requires to be verified
Super heater drain operations as for hot restart
Opening HP steam line drain, start up valve, dump
valve as for hot restart. The time taken for a warm
start may be more than that hot start but less than
that of a cold start all other operations as for cold
start apply.
45. BOILER OPERATION
WALK DOWN CHECK LIST
BOILER
• Check for unusual noises. This may be from steam or
water leakages.
Check for steam or water leaks from valves,
connections and fittings.
Check for unusual traces of water on floor.
Check for air / flue leakage from windbox, boiler
casing and ducting.
Walk around the furnace exterior and observe for
any hot spots or gas leaks.
Check position of fan suction and discharge damper
and check for obstruction.
Check for passing from safety valves at normal
operating pressure. Check that the drain lines and
drip pans are not plugged.
46. BOILER…..
Check for clear & bright flame and clear stack
Check to see that proper water level is being shown
by the direct water level gauge. Check for water or
steam leak from ports or drain connections, which
will cause a false water level in the gauge glass.
Inspect the glass for discoloration or fouling
Check for any obstruction for thermal expansion
ROTARY EQUIPMENTS
Listen for any unusual noises
Feel and inspect for vibration regularly
Inspect bearing temperature
Inspect for lubrication level
Check for any abnormality in couplings
Check current and voltage of motors
47. LOG SHEET
It is suggested to record the boiler parameters during
startup and normal operation. Observed
abnormalities (if any) recorded can be used for
analysis, troubleshooting and maintenance purposes.
Log sheet to be filled once in every hour by the
operating staff.
Feed water, boiler water quality are also to be noted
once in four hours.
Total gas consumption and steam production of a day
to be noted.
Logbook should furnish the details about
Boiler trips with reasons and time.
Boiler running hours.
Boiler shut down details (forced or planned, outage
hours, jobs carried out, etc.,)
48. EMERGENCY PROCEDURES
LOW WATER LEVEL
CAUSES
Feedwater control system failure.
BFP failure
Tube leak
ACTION
• Compare control room indication with gauge glass
level. If the water level falls out of sight due to
momentary failure of water supply system, due to
negligence of the operator, due to momentary
fluctuations that might occur with extraordinary
changes in load, appropriate action should be taken
at once to trip the fuel. Any decision to continue to
operate, even if only for a short time at a reduced
rating, would have to be made by someone in
authority who is thoroughly familiar with the
circumstances that led to the emergency and
positively certain that the water level can be restored
49. LOW WATER LEVEL…..
In the absence of such a decision
Stop the burner immediately
Shut off steam flow
Simultaneously, if feedwater has become available
and the operator is assured that no pressure part has
been damaged
Take the feedwater control system into manual
mode
Allow the water flow to boiler gradually to normal
water level. (Do not hurry up which may lead to
sudden quenching and tube leak) if pressure part
damage is suspected
Reduce the steam pressure gradually
Open the drum air vent when the pressure drops
below 2 kg/cm2
50. LOW WATER LEVEL….
• Cool the boiler so as to examine the extent of
damage
Drain the boiler after cooling
If any tube rupture and bulging is observed rectify
the same
If any tube leakages were observed in convection
bank near drums, re-roll the leaking tubes
After the repairs conduct hydrotest
Determine the cause of low water
51. HIGH WATER LEVEL
CAUSES
Feedwater control malfunction
Operator error
Instrument air supply failure
Foaming
ACTION
Take the drum level control loop into manual
mode
Reduce the water level immediately by operating
the intermittent blow down to maintain the
drum level
Reduce the steam discharge rate, if necessary
Start the stand by compressor if required
52. FURNACE PUFFING & BACK FIRING
CAUSES
Uncontrolled feeding of fuel into the furnace
Sudden increase in FD fan air
Tube rupture
ACTION
Take airflow control system into manual mode
and maintain the furnace pressure
Never increase fuel / air flow suddenly. Always
increase air first then gas while taking boiler on
load
In case of tube failure take the boiler out of
service immediately
Keep the water wall tubes clean by monitoring
the combustion conditions and water quality
53. BOILER EXPLOSION
CAUSES
Accumulation of fuel in the furnace due to
incomplete combustion
Loss of ignition
Fuel block valve leakage
Frequent unsuccessful startups
In-sufficient purging of furnace
With the mixture of unburned fuel with air in
explosive proportions and the application of heat
sufficient enough to raise the temperature of the
mixture to ignition point.
ACTION
Trip the burner immediately
Purge the furnace extensively
Analyze the reasons for explosion and rectify the
system
Evacuate or clean the furnace to the possible extend
54. OPERATIONAL PRECAUTIONS FOR SAFETY
The handling and burning of any fuel is
potentially hazardous. Some fuels ignite
more readily than others do. Safe handling
and operation demands knowledge of the
characteristics of the fuel and careful
observance of necessary precautions.
Because of the rapid diffusion of gas, any
leak of gas into an enclosed space may
result in an explosive mixture of air and gas.
One of the requirements of good
combustion is intimate mixing of fuel and
air. In case of gaseous fuels such mixtures
are potentially explosive and can be
expected to ignite from a single spark.
Therefore these mixtures must never be
allowed to exist except inside the
combustion chamber
55. OPERATIONAL PRECAUTIONS FOR
SAFETY….
• Never allow fuel to accumulate anywhere,
other than in lines that form a part of a fuel
supply system. Steps should be taken
immediately to clean or purge the area
thoroughly and then locate the source. Carry
out routine checks to detect leaking fuel
Purge the furnace completely before
introducing any light or spark
Maintain a positive airflow through the burners
into the furnace and up the stack
Ensure operation staff is alert to all abnormal
conditions.
56. OPERATIONAL PRECAUTIONS FOR SAFETY…
To observe the above rules, automatic control
instruction include
Purge interlocks e.g. requiring a
specified minimum airflow for a specific
time period sufficient to purge the
setting before the burner is started
Flame Detector for the burner
connected to an alarm and interlocked
to shut-off the fuel to the burner, it
serves upon flame failure
Closed position switches for burner
shut-off valve, requiring that fuel shut-
off valve be closed to permit opening the
fuel trip valve.
Shut-off of fuel on failure of FD fan
Shut off of fuel in the event of electric
power failure or instrument Air failure
57. OPERATIONAL PRECAUTIONS FOR
SAFETY….
Operating the boiler with low feedwater
temperature will result in corrosion of
economizer coils.
The raising and lowering of steam parameters
should be restricted to the value given in the
starting diagram. Exceeding these values will
result in reduced fatigue life of pressure parts.
In case of tube failure, which can be identified by
hearing the noise in the boiler gallery and
increase in draught pressure, flue gas and steam
temperature, and the boiler should be shutdown
at the earliest by regular procedure for
maintenance work. Otherwise large number of
tubes may fail due to steam erosion and
58. OPERATIONAL PRECAUTIONS FOR
SAFETY….
Boiler salt in the wet steam will accelerate
corrosion.
Always use deaerated de-mineralized water for
boiler feeding.
Carryover of salt in steam occurs either due to
mechanical or vapor carryover from steam
drum. Efficient drum internals can only reduce
mechanical carry over. Silica is always carried
over in vaporous form. Continuous monitoring
of sodium and silica in boiler water and steam is
desirable.
Before operating a boiler, ensure complete
knowledge of water chemistry.
Whenever boiler is started after a shutdown of
more than 3 days, check all safety interlocks
before boiler start up for proper functioning
59. OPERATIONAL PRECAUTIONS FOR
SAFETY….
The steam drum should normally be filled up to the
point when water is showing in the bottom part of
the gauge glass. This is to allow for the swell on
heating and to reduce any blowing down resulting
from this cause to a minimum.
Once the boiler is boxed up, the water level in the
steam drum must be raised to the very top of the
drum. Filling the drum like this will prevent
excessive temperature differentials along the drum
wall. The water is then shut-off and the boiler is
allowed to cool.
While raising pressure on boilers, continuous firing
is recommended, since intermittent firing may
result in re-condensation in the tube loops.
60. TUBE FAILURES
Operating the boiler with a known tube leak is not
recommended. Steam or water escaping from a small leak
at pressure can cut other tubes by impingement and set up
a chain reaction of tube failures. Large leaks can be
dangerous. The boiler water may be lost, the ignition may
be lost and boiler casing can get damaged.
Small leaks can sometime be detected by the loss of water in
the cycle or system. A loss of boiler water chemicals or by
the noise made by the leak. If a leak is suspected the boiler
should be shut down as soon as possible by following the
normal shutdown procedure.
After the exact location of the leak or leaks is located, the
leaks may be repaired by replacing the failed tube or by
splicing in a new section of tube, conforming to relevant
ASME code.
61. TUBE FAILURES…..
An investigation of the tube failure is very important
so that the condition causing the tube failure can be
eliminated and future failures can be prevented. This
investigation should include a careful visual
inspection of the failed tube and in some cases a lab
analysis.
It is recommended that every effort be made to find
the cause of tube failures before operation is
resumed.
62. BOILER SHUTDOWN
A Boiler shut down can be of two types:
Planned shut down where the Operator gets
advance notice and adequate time to shut
down the boiler in an orderly manner, for
inspection, maintenance or for cold reserve.
Boiler Trip on interlock protection or
emergency shutdown by the Operator.
63. PLANNED SHUT DOWN
On a planned shut down operator to carryout the
following activities in the sequence:
• Reduce the boiler load gradually. This is to be done
in such a manner that while reducing the firing as
the oil/gas pressure approaches minimum
prescribed value burners are to be withdrawn one
by one from top.
• Close the MSSV. Take the combustion control loop
into manual mode.
• Then stop the bottom burner manually from DCS.
• Close the start-up vent isolation valve. Ensure that
the pressure control valve is closed and select the
controller into manual mode.
• Carry out the furnace purge.
• Stop the FD fan and close the suction damper.
64. PLANNED SHUT DOWN …..
• Continue to feed water to the boiler to maintain
normal water level. Drum level controller shall be
changed to single element mode and maintain the
level. Once the level is normalised, take the feed
water / drum level controller in to manual mode and
close the valve (output as 0 %).
• Stop phosphate dosing. Close the CBD valve.
• Verify the EBD valve is closed.
• Allow the boiler to cool naturally.
• Scanner cooling air supply is continued till the
furnace temperature falls below 100 0
C or for at
least 8 hours.
• If the proposed shut down of the boiler is for more
than 8 hours, fuel supply has to be isolated.
• When the steam drum pressure drops to 2-bar (g),
open the steam drum vent and the start-up vent.
65. BOILER EMERGENCY TRIP
Sometime boiler trips either by a protection or due
to a power failure or by an emergency trip
command by the operator causing the fuel block
valve to close and abruptly stopping the firing.
• Under such emergency trip conditions the operator
action is -
• For protecting the boiler
• For investigating the cause of trip and if
possible to eliminate the cause
If the cause is eliminated, to restart the boiler
If the cause cannot be immediately eliminated to
continue the shutdown till it is done
66. BOILER PROTECTION AFTER A TRIP
BOILER PROTECTION AFTER A TRIP
• Close main steam stop valve immediately
• Continue to feed the water if level requires to be
maintained
• Check that fuel block valves are closed
• Check that there is no flame in the furnace
• Carry out post trip purge of the furnace
67. BOILER SHUTDOWN DURING SUDDEN
TUBE FAILURE
• In case of a tube rupture followed by a severe loss
of drum water level, it is advised immediately to
stop the burners, purge the furnace and also isolate
the steam & feedwater system. This is to avoid
undue thermal stresses on pressure parts. The
drum vent & start up vent have to be opened as the
pressure falls to 2 Bar (g). The extent of the damage
is to be ascertained after cooling the boiler
completely.
• In case of a sudden tube failure, if the water level
could be maintained and flame is not lost, it is
recommended that the boiler be taken out of
service as soon as possible. The impingement of
steam & water from a leaking tube on adjacent
tubes can cause additional failure of tubes. In such
cases, the normal planned shutdown procedure is
immediately implemented.