March 1, 2011 Future Corporate Office & Production Facility For PrimeNet Direct Marketing Solutions 7320 Bryan Dairy Road, Largo, FL  33777
March 9, 2011 Future Data Production Future Production Floor Future Home of Account Management Cubicles Future Production Floor Future Production Floor Future Data Center & Hand Assembly Areas
March 29, 2011 Future Front Entrance Front Office’s Have All Been Framed Break Room Parking Lot Break Room Front Office’s Have All Been Framed
March 29, 2011 Production Floor Secure Storage Area/Fulfillment/Machine Shop Fire Alarms – Have Been Installed Production Floor Production Floor Secure Storage Area/Fulfillment/Machine Shop
March 29, 2011 Demolition Begins Future Home of Receptionist Office Future Home of Training Room – Front Office Future Home of Prepress Department Front Office Corridor – Seen From Lobby Conference Room – Front Office
March 29, 2011 Demolition Continues Future Home of Data Processing & Laser Setup Future Home of Art Department Future Home of Account Management Cubicles Front Lobby Future Home of Art Department
April 4, 2011 Future Home of Client Conference Room Production Floor BuildBlocks for Data Center Break Room Hallway leading to Prepress, Art Department, Laser Offices & Production Production Floor – Future home of Heidelberg's
April 4, 2011 The new building is hurricane category 3 (CAT 3) certified.  Inside of the building, we are using BuildBlock insulating concrete forms to build the data center, which will also be Cat 3 certified. It’s an enclosed structure within the Brian Dairy facility. The cement block walls and ceiling are reinforced by rebar and filled with a special waterproof material.  Our state of the art Data Center will be made with
April 6, 2011 Future home of Heidelberg's BuildBlocks for Data Center New Heidelberg Offset Press Production Floor Production Floor BuildBlocks for Data Center
April 6, 2011 Future Home of Laser Production – 4 HLC Lasers Future Home of Data Processing & Laser Setup Marking The Locations Of The New Heidelberg Presses Future Home of Heidelberg Presses Production Floor Production Floor
April 13, 2011 Double Checking The Location Of The Two Heidelberg Presses The Cement Is Going To Be Cut To Put In Steel Rebar Footings To With Stand The Weight Of The Presses
April 13, 2011 Beginning To Cut The Cement For The New Presses  Wetting The Cement For The Cut! The First Cut Has been Made!
April 19, 2011 The Cement Has Been Cut For The  Future Home Of Our New Presses
April 19, 2011 Data Center Walls Have Arrived Lots Of BuildBlock For The Walls Of The Data Center Unpacking Of The Walls 1 st  Five Feet Of Data Center Walls Are Going Up!
April 19, 2011 Account Management Cubicles New Heidelberg Press Steel Rebar Is In Place For The Footings Of The Cement For The Heidelberg Press Entrance to Offices From Production Floor
April 27, 2011 Future home for 2 Xerox iGen, 4 Xerox HLC printers Steel Rebar Is In Place To Secure The BuildBlocks Used To Build The Walls Of The Data Center Future Home of Data Center Offices The Cement Has Been Poured For The Heidelberg Presses.
April 27, 2011 Entrance To The Data Center Receiving Dock The 1 st  Five Feet Of The Data Center Walls Are Stabilized Until The Cement Is Dry Laser
April 29, 2011 Old Data Center – Future Storage Inside Of The Data Center, The 2 nd  5 Feet of BuildBlocks Have Been Installed And Are Stabilized Until The Cement Is Dry. Account Management Data Center Offices
April 29, 2011 See The Cement IN The Walls Of The Data Center? Data Center Walls Data Processing & Laser Setup Data Center Walls Are Stabilized Until Cement Is Dry Laser Production – location of future HLC Printers
May 3, 2011 Data Center Interior 1 st  Shift Production Supervisor Office Future Home of Hand Assembly Area USPS & Production Offices Data Center Interior Future Home of Hand Assembly Area
May 4, 2011 Heidelberg Slabs waiting for cement pour for wiring
May 11, 2011 View Of The Cement Data Center Walls USPS & Production Offices Getting The Ceiling Rods In Place To Finalized The Data Center Data Center
May 13, 2011 Account Management Cubicles Future home of Account Management Laser Department Production Looking At Hand Assembly Area Future Home of Training Room Outside of Data Center
May 13, 2011 Future Offices of Purchasing and Accounting Roof of Data Center
May 16, 2011 Data Production & Laser Setup Wood for Machine Shop Tables Hand Assembly Area Production Area Production Area Hand Assembly & Staging Areas
May 16, 2011 Outside of Data Room Next to Account Management Air Conditioning Duct Installation? Future Home of Account Management Data Center Construction Data Center Construction Entrance To Data Center
May 16, 2011 From Offices Corridor Flooring Tiles
May 17, 2011 Inside of Hand Assembly Area Account Management Hand Assembly Area Outside of Data Room before Hand Assembly Built Outside of Data Room before Hand Assembly Built Data Center Interior w/cuts for the UPC’s
May 20, 2011 Building Supplies Going Into Lettershop From Account Managers Area Hand Fulfillment Area Walls & Floor In Process Future Warehouse Area More Building Supplies Heidelberg Press Slab before concrete pour for wiring
May 20, 2011 Handroom Old Server Room Being Converted to Storage Data Center Data Center Account Management
May 24, 2011 Break Room Training Room Hand Assembly Looking into the training room and IT Installation of New Heidelberg Presses
May 24, 2011 Pipe Drain For Presses Data Center Training Room
May 27, 2011 Laser Room
June 1, 2011 New Heidelberg Press  Air Pump For Press Secured Storage Area Wiring For Our House Compressed Air Air Distribution In Room Hallway Looking Into Laser
June 3, 2011 Break Room Front Entrance Accounting Office Getting Carpet Account Services Installation Sound Proofing The Ceiling Data Center Account Services
June 3, 2011 Voltage converter for new Heidelberg press Production Hand Room Hand Room Air Conditioning Into Data Center High Ceiling In Hand Room
June 3, 2011 Creative Services Office Laser Room Pre Press Production Floor Production Floor Data Production
June 7, 2011 Visitor Entrance Front Office Hallway Sales Conference Room Board Room Looking Into Visitor Lobby Board Room Data Production
June 7, 2011 Data Production Heidelberg Press Ready To Go President’s Office Laser Room Training Room Break Room
June 10, 2011 We have power Another security camera We have Internet 1 st  Security Camera Has Been Installed
June 17, 2011 Data Center Account Management Production – new press Data Center Break Room Main Hall way
June 17, 2011 Production Wall Furniture is starting to arrive Press Area Receiving Scissor Lift
June 20, 2011 Production Production More furniture Production Production Mark’s new desk
June 21, 2011 Forklift charger Data Center Production North wall Production Data Center
June 22, 2011 Cubicles Are Going Up In Account Services Production Floor is Taking Shape!
June 23, 2011 The Data Center is Coming Along!  The patch panels in the data center is installed as well as the Verizon FIOS, Cameras, UPS Unit and security systems….
June 24, 2011 Production Floor Cubicles For Account Management Conference Room A Storage Area On Production Floor Shipping Cubicles For Account Management
June 26, 2011 The Cubicles In Account Management Are Going Up Furniture Is Being Moved In  View from list/IT room looking into bunker/data center door Storage Area
June 26, 2011 Al Is Checking Out The Break Room More Stuff For The Data Center I Think She Spots A Tree Can Someone Open The Door Please?
June 29, 2011 View From Break Room The President Is Getting Settled In His New Office HVAC Work Is Being Done Cubicles Going Up For List/IT room
July 5, 2011 Reception Area Production Floor Heidelberg Is Ready To Go Training Room
July 14, 2011 The Perfect Temperature Furniture Is Arriving For The Handroom  President’s office at Palmetto office with no furniture! Account Management Cubicles Are Done IT bunker/data center

More Related Content

PPT
Bryan dairy progress
PPT
Bryan Dairy Progress
PPTX
Final office presentation to management
PPT
Bryan dairy progress 6-13-11
PPT
Bryan dairy progress
PPT
Bryan dairy progress 6-13-11
PDF
How to read ct
PPT
Bryan dairy progress
Bryan dairy progress
Bryan Dairy Progress
Final office presentation to management
Bryan dairy progress 6-13-11
Bryan dairy progress
Bryan dairy progress 6-13-11
How to read ct
Bryan dairy progress

Viewers also liked (15)

PPSX
Pres Gpdef Uk 3 3
PPTX
Програма "Софія"
PPTX
Mi familii
PPTX
Portfolio 2
PPTX
Pres gpdef uk_3-4_prez-2-film
PDF
Sakförsäkringar Bra Miljöval
PPTX
Exporting contacts 2
PDF
Social media marketing plan
DOC
Impaction of teeth-Notes
PPTX
Suture materials & suturing techniques dr.ayesha
PDF
Learn BEM: CSS Naming Convention
PPTX
How to Build a Dynamic Social Media Plan
PDF
SEO: Getting Personal
PDF
Lightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika Aldaba
PDF
Succession “Losers”: What Happens to Executives Passed Over for the CEO Job?
Pres Gpdef Uk 3 3
Програма "Софія"
Mi familii
Portfolio 2
Pres gpdef uk_3-4_prez-2-film
Sakförsäkringar Bra Miljöval
Exporting contacts 2
Social media marketing plan
Impaction of teeth-Notes
Suture materials & suturing techniques dr.ayesha
Learn BEM: CSS Naming Convention
How to Build a Dynamic Social Media Plan
SEO: Getting Personal
Lightning Talk #9: How UX and Data Storytelling Can Shape Policy by Mika Aldaba
Succession “Losers”: What Happens to Executives Passed Over for the CEO Job?
Ad

Similar to Bryan dairy progress2 (10)

PPTX
Swiss pass chapter deck - zurich - april 2011
PPTX
Abilitics-Microsoft Days 11-Case Ctudy: Where SharePoint, Silverlight & BI me...
PDF
5 Data Integration Techniques to Improve Your Excel Data
PDF
5 Data Integration Techniques to Improve Your Excel Data
PPT
07 su 2007office1
PPTX
Sharepoint conf 5 - g mills
PPTX
DMDW 1. Student Presentation - Access 2007
ODP
Introduction to web design
PPT
Should I Stay Or Go
PPT
Should I Stay Or Go
Swiss pass chapter deck - zurich - april 2011
Abilitics-Microsoft Days 11-Case Ctudy: Where SharePoint, Silverlight & BI me...
5 Data Integration Techniques to Improve Your Excel Data
5 Data Integration Techniques to Improve Your Excel Data
07 su 2007office1
Sharepoint conf 5 - g mills
DMDW 1. Student Presentation - Access 2007
Introduction to web design
Should I Stay Or Go
Should I Stay Or Go
Ad

Recently uploaded (20)

PPTX
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
PDF
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
PDF
Keppel_Proposed Divestment of M1 Limited
DOCX
FINALS-BSHhchcuvivicucucucucM-Centro.docx
PPT
Lecture notes on Business Research Methods
DOCX
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
PDF
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
PPTX
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
PPTX
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
PPTX
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
PDF
Ron Thomas - Top Influential Business Leaders Shaping the Modern Industry – 2025
PDF
NEW - FEES STRUCTURES (01-july-2024).pdf
DOCX
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
PDF
Kishore Vora - Best CFO in India to watch in 2025.pdf
PDF
ICv2 White Paper - Gen Con Trade Day 2025
PPT
Lecture 3344;;,,(,(((((((((((((((((((((((
PDF
Chapter 2 - AI chatbots and prompt engineering.pdf
PDF
income tax laws notes important pakistan
PPTX
chapter 2 entrepreneurship full lecture ppt
PDF
Charisse Litchman: A Maverick Making Neurological Care More Accessible
TRAINNING, DEVELOPMENT AND APPRAISAL.pptx
Family Law: The Role of Communication in Mediation (www.kiu.ac.ug)
Keppel_Proposed Divestment of M1 Limited
FINALS-BSHhchcuvivicucucucucM-Centro.docx
Lecture notes on Business Research Methods
Center Enamel A Strategic Partner for the Modernization of Georgia's Chemical...
ANALYZING THE OPPORTUNITIES OF DIGITAL MARKETING IN BANGLADESH TO PROVIDE AN ...
svnfcksanfskjcsnvvjknsnvsdscnsncxasxa saccacxsax
BUSINESS CYCLE_INFLATION AND UNEMPLOYMENT.pptx
Board-Reporting-Package-by-Umbrex-5-23-23.pptx
Ron Thomas - Top Influential Business Leaders Shaping the Modern Industry – 2025
NEW - FEES STRUCTURES (01-july-2024).pdf
Handbook of Entrepreneurship- Chapter 5: Identifying business opportunity.docx
Kishore Vora - Best CFO in India to watch in 2025.pdf
ICv2 White Paper - Gen Con Trade Day 2025
Lecture 3344;;,,(,(((((((((((((((((((((((
Chapter 2 - AI chatbots and prompt engineering.pdf
income tax laws notes important pakistan
chapter 2 entrepreneurship full lecture ppt
Charisse Litchman: A Maverick Making Neurological Care More Accessible

Bryan dairy progress2

  • 1. March 1, 2011 Future Corporate Office & Production Facility For PrimeNet Direct Marketing Solutions 7320 Bryan Dairy Road, Largo, FL 33777
  • 2. March 9, 2011 Future Data Production Future Production Floor Future Home of Account Management Cubicles Future Production Floor Future Production Floor Future Data Center & Hand Assembly Areas
  • 3. March 29, 2011 Future Front Entrance Front Office’s Have All Been Framed Break Room Parking Lot Break Room Front Office’s Have All Been Framed
  • 4. March 29, 2011 Production Floor Secure Storage Area/Fulfillment/Machine Shop Fire Alarms – Have Been Installed Production Floor Production Floor Secure Storage Area/Fulfillment/Machine Shop
  • 5. March 29, 2011 Demolition Begins Future Home of Receptionist Office Future Home of Training Room – Front Office Future Home of Prepress Department Front Office Corridor – Seen From Lobby Conference Room – Front Office
  • 6. March 29, 2011 Demolition Continues Future Home of Data Processing & Laser Setup Future Home of Art Department Future Home of Account Management Cubicles Front Lobby Future Home of Art Department
  • 7. April 4, 2011 Future Home of Client Conference Room Production Floor BuildBlocks for Data Center Break Room Hallway leading to Prepress, Art Department, Laser Offices & Production Production Floor – Future home of Heidelberg's
  • 8. April 4, 2011 The new building is hurricane category 3 (CAT 3) certified. Inside of the building, we are using BuildBlock insulating concrete forms to build the data center, which will also be Cat 3 certified. It’s an enclosed structure within the Brian Dairy facility. The cement block walls and ceiling are reinforced by rebar and filled with a special waterproof material. Our state of the art Data Center will be made with
  • 9. April 6, 2011 Future home of Heidelberg's BuildBlocks for Data Center New Heidelberg Offset Press Production Floor Production Floor BuildBlocks for Data Center
  • 10. April 6, 2011 Future Home of Laser Production – 4 HLC Lasers Future Home of Data Processing & Laser Setup Marking The Locations Of The New Heidelberg Presses Future Home of Heidelberg Presses Production Floor Production Floor
  • 11. April 13, 2011 Double Checking The Location Of The Two Heidelberg Presses The Cement Is Going To Be Cut To Put In Steel Rebar Footings To With Stand The Weight Of The Presses
  • 12. April 13, 2011 Beginning To Cut The Cement For The New Presses Wetting The Cement For The Cut! The First Cut Has been Made!
  • 13. April 19, 2011 The Cement Has Been Cut For The Future Home Of Our New Presses
  • 14. April 19, 2011 Data Center Walls Have Arrived Lots Of BuildBlock For The Walls Of The Data Center Unpacking Of The Walls 1 st Five Feet Of Data Center Walls Are Going Up!
  • 15. April 19, 2011 Account Management Cubicles New Heidelberg Press Steel Rebar Is In Place For The Footings Of The Cement For The Heidelberg Press Entrance to Offices From Production Floor
  • 16. April 27, 2011 Future home for 2 Xerox iGen, 4 Xerox HLC printers Steel Rebar Is In Place To Secure The BuildBlocks Used To Build The Walls Of The Data Center Future Home of Data Center Offices The Cement Has Been Poured For The Heidelberg Presses.
  • 17. April 27, 2011 Entrance To The Data Center Receiving Dock The 1 st Five Feet Of The Data Center Walls Are Stabilized Until The Cement Is Dry Laser
  • 18. April 29, 2011 Old Data Center – Future Storage Inside Of The Data Center, The 2 nd 5 Feet of BuildBlocks Have Been Installed And Are Stabilized Until The Cement Is Dry. Account Management Data Center Offices
  • 19. April 29, 2011 See The Cement IN The Walls Of The Data Center? Data Center Walls Data Processing & Laser Setup Data Center Walls Are Stabilized Until Cement Is Dry Laser Production – location of future HLC Printers
  • 20. May 3, 2011 Data Center Interior 1 st Shift Production Supervisor Office Future Home of Hand Assembly Area USPS & Production Offices Data Center Interior Future Home of Hand Assembly Area
  • 21. May 4, 2011 Heidelberg Slabs waiting for cement pour for wiring
  • 22. May 11, 2011 View Of The Cement Data Center Walls USPS & Production Offices Getting The Ceiling Rods In Place To Finalized The Data Center Data Center
  • 23. May 13, 2011 Account Management Cubicles Future home of Account Management Laser Department Production Looking At Hand Assembly Area Future Home of Training Room Outside of Data Center
  • 24. May 13, 2011 Future Offices of Purchasing and Accounting Roof of Data Center
  • 25. May 16, 2011 Data Production & Laser Setup Wood for Machine Shop Tables Hand Assembly Area Production Area Production Area Hand Assembly & Staging Areas
  • 26. May 16, 2011 Outside of Data Room Next to Account Management Air Conditioning Duct Installation? Future Home of Account Management Data Center Construction Data Center Construction Entrance To Data Center
  • 27. May 16, 2011 From Offices Corridor Flooring Tiles
  • 28. May 17, 2011 Inside of Hand Assembly Area Account Management Hand Assembly Area Outside of Data Room before Hand Assembly Built Outside of Data Room before Hand Assembly Built Data Center Interior w/cuts for the UPC’s
  • 29. May 20, 2011 Building Supplies Going Into Lettershop From Account Managers Area Hand Fulfillment Area Walls & Floor In Process Future Warehouse Area More Building Supplies Heidelberg Press Slab before concrete pour for wiring
  • 30. May 20, 2011 Handroom Old Server Room Being Converted to Storage Data Center Data Center Account Management
  • 31. May 24, 2011 Break Room Training Room Hand Assembly Looking into the training room and IT Installation of New Heidelberg Presses
  • 32. May 24, 2011 Pipe Drain For Presses Data Center Training Room
  • 33. May 27, 2011 Laser Room
  • 34. June 1, 2011 New Heidelberg Press Air Pump For Press Secured Storage Area Wiring For Our House Compressed Air Air Distribution In Room Hallway Looking Into Laser
  • 35. June 3, 2011 Break Room Front Entrance Accounting Office Getting Carpet Account Services Installation Sound Proofing The Ceiling Data Center Account Services
  • 36. June 3, 2011 Voltage converter for new Heidelberg press Production Hand Room Hand Room Air Conditioning Into Data Center High Ceiling In Hand Room
  • 37. June 3, 2011 Creative Services Office Laser Room Pre Press Production Floor Production Floor Data Production
  • 38. June 7, 2011 Visitor Entrance Front Office Hallway Sales Conference Room Board Room Looking Into Visitor Lobby Board Room Data Production
  • 39. June 7, 2011 Data Production Heidelberg Press Ready To Go President’s Office Laser Room Training Room Break Room
  • 40. June 10, 2011 We have power Another security camera We have Internet 1 st Security Camera Has Been Installed
  • 41. June 17, 2011 Data Center Account Management Production – new press Data Center Break Room Main Hall way
  • 42. June 17, 2011 Production Wall Furniture is starting to arrive Press Area Receiving Scissor Lift
  • 43. June 20, 2011 Production Production More furniture Production Production Mark’s new desk
  • 44. June 21, 2011 Forklift charger Data Center Production North wall Production Data Center
  • 45. June 22, 2011 Cubicles Are Going Up In Account Services Production Floor is Taking Shape!
  • 46. June 23, 2011 The Data Center is Coming Along! The patch panels in the data center is installed as well as the Verizon FIOS, Cameras, UPS Unit and security systems….
  • 47. June 24, 2011 Production Floor Cubicles For Account Management Conference Room A Storage Area On Production Floor Shipping Cubicles For Account Management
  • 48. June 26, 2011 The Cubicles In Account Management Are Going Up Furniture Is Being Moved In View from list/IT room looking into bunker/data center door Storage Area
  • 49. June 26, 2011 Al Is Checking Out The Break Room More Stuff For The Data Center I Think She Spots A Tree Can Someone Open The Door Please?
  • 50. June 29, 2011 View From Break Room The President Is Getting Settled In His New Office HVAC Work Is Being Done Cubicles Going Up For List/IT room
  • 51. July 5, 2011 Reception Area Production Floor Heidelberg Is Ready To Go Training Room
  • 52. July 14, 2011 The Perfect Temperature Furniture Is Arriving For The Handroom President’s office at Palmetto office with no furniture! Account Management Cubicles Are Done IT bunker/data center