The following data were collected while running a
closed traverse ABCDA. Calculate the missing data.
Control Survey
 The determination of the precise position
of a number of stations, usually spread over
a large area, is referred to as control
surveying
 Control surveys can be horizontal (lat long
or East North) or vertical (height with
respect to mean sea level).
3
Horizontal control
 Traversing,
 Triangulation
 Trilateration
 Triangulateration
 Satellite positioning
4
Triangulation
 A triangulation survey: a network of triangles with one side
length and all the angles are measured, other lengths will be
computed
 The single measured line is the base line of the network
Triangulation surveys are carried out
1. to establish accurate control for plane and geodetic surveys
covering large areas,
2. to establish accurate control for photogrammetric surveys for
large areas,
3. to assist in the determination of the size and shape of the earth,
5
Classification of Triangulation
system
 Based on the accuracy desired for the work,
triangulation system is divided into three
class which are
 First order or primary : country
 Second order or secondary: region
 Third order or tertiary: local
6
Triangulation Figures
i. Simple triangle should be preferably
equilateral,
ii. Braced quadrilateral should be preferably
approximate square,
iii. Centred polygon should be regular.
7
Chain of Triangles
 Rapid and economical when a narrow strip of terrain
is to be surveyed, e.g. highway, river, valley, etc.
8
Braced Quadrilaterals
 An excellent system since the various
combinations of sides and angles can be
used to compute the lengths of the required
sides and checks can be made frequently
9
Centred triangles and Polygons
 It is generally used when vast area in all
directions is required to be covered.
10
Triangulation procedure
 Reconnaissance, select the locations of stations;
 Evaluation of the strength of figures;
 Erection of signals, and in some cases, tower for
elevating the signals and /or instruments;
 Observation of directions or angles;
 Measurement of base lines;
 Astronomic observation at one or more locations,
 Computations including reduction to sea level,
calculation of the lengths of all sides and coordinates for
all stations, and adjustment of the triangulation network
to provide the best estimates of co-ordinates of all points.
11
Trilateration
 When all the sides of a triangulation system are
measured & the technique has been made possible
by the development of EDM (Electronic Distance
Measurement)
 However, the angular measurements define the
shape of the triangulation system better than wholly
linear measurements.
 So a combined triangulation and trilateration
(Triangulateration) system in which all the angles
by theodolite and all the sides are measured by
EDM, represents the strongest network for creating
horizontal control. 12
Location of points by
intersection and resection
 The points located by observing directions from the points
of known locations, are known as the intersected points
 When a point is established by taking observations from the
point (unknown) to the points of known locations, such
points are known as the resected points
13
Location by intersection
 Determine c and ABD
 Azimuth of BC and DC can be calculated
 ABC = ABD - 
 ADC = ADB + 
 Then the coordinates can be
calculated:
 Xc = XB + d.Sin(ABC)
 Yc = YB + d.Cos(ABC)
14
Intersection by the base
solution
15
YC
Intersection when azimuths
are given
 When azimuth of BC and DC known or calculated 16
Resection/satellite station
17
In a triangulation survey, four triangulation stations A, B, C, and D
were tied using a braced quadrilateral ABCD shown in Fig. below. The
length of the diagonal AC was measured and found to be 1116.40 m
long. The measured angles are as below:
α = 44°40′59″ γ = 63°19′28″
β = 67°43′55″ δ = 29°38′50″.
Calculate the length of BD.
Example 1
18
Example 2
19
Determine the coordinates of a point R from the following data:
Coordinates of P = E1200 m, N1200 m
Coordinates of Q = E400 m, N1000 m
Bearing of PR = 62°13′40″
Bearing of QR = 38°46′25″.
Example 3
20
In a triangulation survey, the station C could not be occupied in a
triangle ABC, and a satellite station S was established north of C.
The angles as given in Table below were measured at S using a
theodolite.
Approximate lengths of AC and BC were found by estimation
as 17495 m and 13672 m, respectively, and the angle ACB was
deduced to be 59°44′53″. Calculate the distance of S from C.
21
QUESTIONS?

More Related Content

PDF
Survey i book
PPTX
Surveying Complete Notes of Unit 1.pptx
PPTX
PPTX
PLANE TABLE SURVEYING
PDF
traversing of survey
PPT
PLANE TABLE SURVEY
PPTX
Aerial photogrammetry ppt 1
PPTX
PROJECTS ON SURVEYING
Survey i book
Surveying Complete Notes of Unit 1.pptx
PLANE TABLE SURVEYING
traversing of survey
PLANE TABLE SURVEY
Aerial photogrammetry ppt 1
PROJECTS ON SURVEYING

What's hot (20)

PDF
Chain survey_Surveying, Civil Engineering
PDF
Geodesy - Definition, Types, Uses and Applications
PPTX
Modern surveying methods and instruments
PDF
Lec. 11 setting out simple circular curve
PDF
TOTAL STATION: THEORY, USES AND APPLICATIONS.
PPTX
Introduction of Surveying
PDF
Lecture note triangulation_and_trilatera2016
PPTX
Hydrographic survey
PDF
Total station
PPT
Total station, digital self leveling levels,
PPTX
Modern surveying techniques
PPTX
Total station Surveying
PPT
Basics Of Surveying
PDF
Levelling in Surveying
PDF
Total station surveying and its application
PDF
Modern Surveying & Mapping
PDF
Surveying
PPTX
Geophysical studies
PPTX
Module 2,plane table surveying (kannur university)
Chain survey_Surveying, Civil Engineering
Geodesy - Definition, Types, Uses and Applications
Modern surveying methods and instruments
Lec. 11 setting out simple circular curve
TOTAL STATION: THEORY, USES AND APPLICATIONS.
Introduction of Surveying
Lecture note triangulation_and_trilatera2016
Hydrographic survey
Total station
Total station, digital self leveling levels,
Modern surveying techniques
Total station Surveying
Basics Of Surveying
Levelling in Surveying
Total station surveying and its application
Modern Surveying & Mapping
Surveying
Geophysical studies
Module 2,plane table surveying (kannur university)
Ad

Similar to Chapter 1 - Triangulation and Trilateration.pdf (20)

PDF
S2 5 traverses
PPTX
Triangulation is the process of tracing and measurement
PPTX
se_312_ch_3_-triangulation_survey.pptx
PPTX
se_312_ch_3_-triangulation_survey.pptx
PPTX
surveying 2 lecture 5 Curves, types of curves.pptx
PPT
Introduction to surveying
PPTX
8-0-triangulation-and-trilteration-notes.pptx
PPTX
triangulation.pptx
PDF
Chapter4_ Trilateration.pdf...............................
PDF
Advanced surveying LecXEDWture_2 (2).pdf
PDF
Engineering surveying-ii
PPT
30838893 chain-survey
PPTX
TRIANGULATION SURVEY is the study of survey
PDF
Surveying - Module I - Introduction to surveying
PDF
Surveying 2
PPTX
ADVANCED SURVEYING TRIANGULATIONADVANCED SURVEYING TRIANGULATION
PPTX
ADVANCED SURVEYING TRIANGULATION ADVANCED SURVEYING TRIANGULATION
DOCX
Project 2- traversing
DOCX
Project 2- traversing
S2 5 traverses
Triangulation is the process of tracing and measurement
se_312_ch_3_-triangulation_survey.pptx
se_312_ch_3_-triangulation_survey.pptx
surveying 2 lecture 5 Curves, types of curves.pptx
Introduction to surveying
8-0-triangulation-and-trilteration-notes.pptx
triangulation.pptx
Chapter4_ Trilateration.pdf...............................
Advanced surveying LecXEDWture_2 (2).pdf
Engineering surveying-ii
30838893 chain-survey
TRIANGULATION SURVEY is the study of survey
Surveying - Module I - Introduction to surveying
Surveying 2
ADVANCED SURVEYING TRIANGULATIONADVANCED SURVEYING TRIANGULATION
ADVANCED SURVEYING TRIANGULATION ADVANCED SURVEYING TRIANGULATION
Project 2- traversing
Project 2- traversing
Ad

Recently uploaded (20)

PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Construction Project Organization Group 2.pptx
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Current and future trends in Computer Vision.pptx
PDF
III.4.1.2_The_Space_Environment.p pdffdf
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PDF
Well-logging-methods_new................
PPTX
Safety Seminar civil to be ensured for safe working.
PPT
Project quality management in manufacturing
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PPTX
CH1 Production IntroductoryConcepts.pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPT
Mechanical Engineering MATERIALS Selection
Embodied AI: Ushering in the Next Era of Intelligent Systems
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
Operating System & Kernel Study Guide-1 - converted.pdf
Construction Project Organization Group 2.pptx
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Current and future trends in Computer Vision.pptx
III.4.1.2_The_Space_Environment.p pdffdf
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Well-logging-methods_new................
Safety Seminar civil to be ensured for safe working.
Project quality management in manufacturing
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Unit I ESSENTIAL OF DIGITAL MARKETING.pdf
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Automation-in-Manufacturing-Chapter-Introduction.pdf
CH1 Production IntroductoryConcepts.pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
Mechanical Engineering MATERIALS Selection

Chapter 1 - Triangulation and Trilateration.pdf

  • 1. Surveying II CENG 2092 SCHOOL OF CIVIL AND ENVIROMENTAL ENGINEERING Chapter 1 Triangulation and Trilateration Tamru T. 2012EC (2019/20GC) 2nd Sem
  • 2. To refresh Surveying I The following data were collected while running a closed traverse ABCDA. Calculate the missing data.
  • 3. Control Survey  The determination of the precise position of a number of stations, usually spread over a large area, is referred to as control surveying  Control surveys can be horizontal (lat long or East North) or vertical (height with respect to mean sea level). 3
  • 4. Horizontal control  Traversing,  Triangulation  Trilateration  Triangulateration  Satellite positioning 4
  • 5. Triangulation  A triangulation survey: a network of triangles with one side length and all the angles are measured, other lengths will be computed  The single measured line is the base line of the network Triangulation surveys are carried out 1. to establish accurate control for plane and geodetic surveys covering large areas, 2. to establish accurate control for photogrammetric surveys for large areas, 3. to assist in the determination of the size and shape of the earth, 5
  • 6. Classification of Triangulation system  Based on the accuracy desired for the work, triangulation system is divided into three class which are  First order or primary : country  Second order or secondary: region  Third order or tertiary: local 6
  • 7. Triangulation Figures i. Simple triangle should be preferably equilateral, ii. Braced quadrilateral should be preferably approximate square, iii. Centred polygon should be regular. 7
  • 8. Chain of Triangles  Rapid and economical when a narrow strip of terrain is to be surveyed, e.g. highway, river, valley, etc. 8
  • 9. Braced Quadrilaterals  An excellent system since the various combinations of sides and angles can be used to compute the lengths of the required sides and checks can be made frequently 9
  • 10. Centred triangles and Polygons  It is generally used when vast area in all directions is required to be covered. 10
  • 11. Triangulation procedure  Reconnaissance, select the locations of stations;  Evaluation of the strength of figures;  Erection of signals, and in some cases, tower for elevating the signals and /or instruments;  Observation of directions or angles;  Measurement of base lines;  Astronomic observation at one or more locations,  Computations including reduction to sea level, calculation of the lengths of all sides and coordinates for all stations, and adjustment of the triangulation network to provide the best estimates of co-ordinates of all points. 11
  • 12. Trilateration  When all the sides of a triangulation system are measured & the technique has been made possible by the development of EDM (Electronic Distance Measurement)  However, the angular measurements define the shape of the triangulation system better than wholly linear measurements.  So a combined triangulation and trilateration (Triangulateration) system in which all the angles by theodolite and all the sides are measured by EDM, represents the strongest network for creating horizontal control. 12
  • 13. Location of points by intersection and resection  The points located by observing directions from the points of known locations, are known as the intersected points  When a point is established by taking observations from the point (unknown) to the points of known locations, such points are known as the resected points 13
  • 14. Location by intersection  Determine c and ABD  Azimuth of BC and DC can be calculated  ABC = ABD -   ADC = ADB +   Then the coordinates can be calculated:  Xc = XB + d.Sin(ABC)  Yc = YB + d.Cos(ABC) 14
  • 15. Intersection by the base solution 15 YC
  • 16. Intersection when azimuths are given  When azimuth of BC and DC known or calculated 16
  • 18. In a triangulation survey, four triangulation stations A, B, C, and D were tied using a braced quadrilateral ABCD shown in Fig. below. The length of the diagonal AC was measured and found to be 1116.40 m long. The measured angles are as below: α = 44°40′59″ γ = 63°19′28″ β = 67°43′55″ δ = 29°38′50″. Calculate the length of BD. Example 1 18
  • 19. Example 2 19 Determine the coordinates of a point R from the following data: Coordinates of P = E1200 m, N1200 m Coordinates of Q = E400 m, N1000 m Bearing of PR = 62°13′40″ Bearing of QR = 38°46′25″.
  • 20. Example 3 20 In a triangulation survey, the station C could not be occupied in a triangle ABC, and a satellite station S was established north of C. The angles as given in Table below were measured at S using a theodolite. Approximate lengths of AC and BC were found by estimation as 17495 m and 13672 m, respectively, and the angle ACB was deduced to be 59°44′53″. Calculate the distance of S from C.