Operations Research
Course Code: IPE 3103
Instructor: Md. Rasel Sarkar
Dept. of IPE, RUET, Rajshahi, Bangladesh
Academic Year: 2020-21
Chapter 10
Dynamic programming
Dynamic Program (DP)
 Dynamic programming is a mathematical technique
dealing with the optimization of multistage decision
process.
 Original decisions problem is divided into small sub-
problem (stages) and stages are optimized rather
than simultaneously.
 In contrast to linear programming, there does not
exist a standard mathematical formulation of “the
dynamic programming problem”.
 Dynamic programming is applicable when the sub-
problems are not independent.
Recursive Nature of Dynamic
Programming
 Computations are then carried out recursively
where the optimum solution of one sub-problem is
used as an input to the next sub-problem.
 The optimum solution for the entire problem is at
hand when the last sub-problem is solved.
 The manner in which the recursive computations
are carried out depends on how the original
problem is decomposed.
Shortest Route Problem
Suppose that we want to select the shortest highway route
between two cities. The network in Figure below provides the
possible routes between the starting city at node 1 and the
destination city at node 7. Where the number on the line
shows distance from one node to another.
First decompose it into stages as delineated by the
vertical dashed lines in Figure. Next, carry out the
computations for each stage separately.
Stage 1
Shortest distance from node 1 to node 2 = 7 miles (from node 1)
Shortest distance from node 1 to node 3 = 8 miles (from node 1)
Shortest distance from node 1 to node 4 = 5 miles (from node 1)
Stage 2 (n=2)
Node 5 can be reached from nodes 2, 3, and 4. Thus –
shortest distance
to node x5
= min
j=2,3,4
{ distance from
node xj to x5
+ shortest distance
to node xj
}
Let,
f*n(xi) be the shortest distance to node xi at stage n
d(xj, xi) as the distance from node xj to node xi.
𝑥𝑗 = all possible routes to node xi.
Now above eqn. can be mathematically expressed as
f*2(x5) = min
j=2,3,4
{d(xj, x5) + (f1(xj)}
Thus,
shortest distance
to node x5
= min
12 + 7 = 19
8 + 8 = 16
7 + 5 = 12
= 12 miles (from node 4)
Node 6 can be reached from nodes 3 and 4. Thus –
shortest distance
to node x6
= min
j=3,4
{ distance from
node xj to x6
+ shortest distance
to node xj
}
= min
9 + 8 = 17
13 + 5 = 18
= 17 miles (from node 3)
Stage 3
The destination node 7 can be reached from either node 5
or 6.
shortest distance
to node x7
= min
j=5,6
distance from
node xj to x7
+ shortest distance
to node xj
= min
9 + 12 = 21
6 + 17 = 23
= 21 miles (from node 5)
Shortest distance from node 1 to node 7 = 21 miles.
Thus, the shortest route is 1 → 4 → 5 → 7.
Recursive equation
The DP recursive equation is defined as –
𝑓0 𝑥1 = 0
𝑓𝑛
∗ 𝑥𝑖 = min 𝑑 𝑥𝑗, 𝑥𝑖 + 𝑓𝑛−1
∗
(𝑥𝑗) , for 𝑛 = 2, 3,…
Principle of optimality
The principle of optimality is the basic principle of
dynamic programming, which was developed by
Richard Bellman that:
“An optimal policy has the property that whatever
the initial conditions and decisions are the remaining
stages constitute an optimal policy regardless of the
policy adopted in all preceding stages”
Capital budgeting problem
Consider the capital budgeting problem where three
existing factories, each being considered for possible
expansion. Factories 1, 2 and 3 have three, four and
two alternative plans for expansion respectively. The
expected additional costs and the corresponding
revenues for jth plan of the nth factory are given by cnj
and Rnj. The objective of the decision problem is to
select a plan j for each factory n which will maximize
the total revenue. The cost of the selected set of
plans should not exceed the total available capital, C.
The data of the problem is tabulated below. All costs
and revenue are scaled by 10-3.
Assume the total capital available is C = 10.
Factory, n n = 1 n = 2 n = 3
Plan, j c1j R1j c2j R2j c3j R3j
1 0 0 0 0 0 0
2 2 5 5 8 1 3
3 4 6 6 9 – –
4 – – 8 12 – –
Recursive equation:
𝑓𝑛
∗ 𝑋 = 𝑚𝑎𝑥
0≤ 𝑐𝑛𝑗≤ 𝑋
{𝑅𝑛𝑗 𝑐𝑛𝑗 + 𝑓𝑛−1
∗
(𝑋 − 𝑐𝑛𝑗)}
Where
X = amounts available for allocation.
𝑓𝑛
∗
𝑋 = the maximum return from allocating X
dollars at nth stage.
𝑐𝑛𝑗 = the decision variable, denote the amount
allocated to jth plan of nth stage.
𝑅𝑛𝑗 𝑐𝑛𝑗 = return from the jth plan on the nth stage.
Stage n = 1 (Factory 1)
𝑓1 𝑋 = 𝑅1𝑗 𝑐1𝑗
j =1
(c11= 0, R11=0)
j = 2
(c12= 2, R12=5)
j = 3
(R13=6, c13= 4)
Optimum Sol.
X 𝑓1 𝑋 𝑓1 𝑋 𝑓1 𝑋 𝑓1
∗
𝑋 j*
0 0 – – 0 1
1 0 – – 0 1
2 0 5 – 5 2
3 0 5 – 5 2
4 0 5 6 6 3
5 0 5 6 6 3
6 0 5 6 6 3
7 0 5 6 6 3
8 0 5 6 6 3
9 0 5 6 6 3
10 0 5 6 6 3
Stage n = 2 (Factory 2)
𝑓2 𝑋 = 𝑅2𝑗 𝑐2𝑗 + 𝑓 ∗1 (𝑋 − 𝑐2𝑗)
j =1
(c21= 0, R21= 0)
j = 2
(c22= 5, R22 = 8)
j = 3
(c23= 6, R23=9)
j = 4
(c24= 8, R23=12)
Optimum
Solution
X 𝑓2 𝑋 𝑓2 𝑋 𝑓2 𝑋 𝑓2 𝑋 𝑓2
∗
𝑋 j*
0 0 + 0 = 0 – – – 0 1
1 0 + 0 = 0 – – – 0 1
2 0 + 5 = 5 – – – 5 1
3 0 + 5 = 5 – – – 5 1
4 0 + 6 = 6 – – – 6 1
5 0 + 6 = 6 8 + 0 = 8 – – 8 2
6 0 + 6 = 6 8 + 0 = 8 9 + 0 = 9 – 9 3
7 0 + 6 = 6 8 + 5 = 13 9 + 0 = 9 – 13 2
8 0 + 6 = 6 8 + 5 = 13 9 + 5 = 14 12 + 0 = 12 14 3
9 0 + 6 = 6 8 + 6 = 14 9 + 5 = 14 12 + 0 = 12 14 2, 3
10 0 + 6 = 6 8 + 6 = 14 9 + 6 = 15 12 + 5 = 17 17 4
Stage n = 3 (Factory 3)
𝑓3 𝑋 = 𝑅3𝑗 𝑐3𝑗 + 𝑓2 (𝑋 − 𝑐3𝑗)*
j =1
(c31 = 0, R31 = 0)
j = 2
(c32= 1, R32 = 3)
Optimum Solution
X 𝑓2 𝑋 𝑓2 𝑋 𝑓3
∗
𝑋 j*
0 0 + 0 = 0 – 0 1
1 0 + 0 = 0 3 + 0 = 3 3 2
2 0 + 5 = 5 3 + 0 = 3 5 1
3 0 + 5 = 5 3 + 5 = 8 8 2
4 0 + 6 = 6 3 + 5 = 8 8 2
5 0 + 8 = 8 3 + 6 = 9 9 2
6 0 + 9 = 9 3 + 8 = 11 11 2
7 0 + 13 = 13 3 + 9 = 12 13 1
8 0 + 14 = 14 3 + 13 = 16 16 2
9 0 + 14 = 14 3 + 14 = 17 17 2
10 0 + 17 = 17 3 + 14 = 17 17 1, 2
Optimal profit = 17
Optimal Policy:
Factory 1 Factory 2 Factory 3
Option 1 2 4 1
Option 2 3 2 2
Option 3 2 3 2
Example
(Liberman)
The owner of a chain of three grocery stores has
purchased five crates of fresh strawberries. The
estimated probability distribution of potential sales
of the strawberries before spoilage differs among the
three stores. Therefore, the owner wants to know
how to allocate five crates to the three stores to
maximize expected profit. For administrative
reasons, the owner does not wish to split crates
between stores. However, he is willing to distribute
no crates to any of his stores.
The following table gives the estimated expected
profit at each store when it is allocated various
numbers of crates:
Use dynamic programming to determine how many
of the five crates should be assigned to each of the
three stores to maximize the total expected profit.
Solution
Let , The decision variables xn (n = 1, 2, 3) are the
number of crates to allocate to stage (store) n.
X = number of crates available for allocation to different
stores.
pn(xn) = be the profit from allocating xn crates to store n.
𝑓𝑛 𝑋 = profit from allocating X crates to store, n
𝑓𝑛
∗
𝑋 = Optimal profit from allocating X crates to store, n
Now get,
𝑓𝑛 𝑋 = 𝑝𝑛 𝑥𝑛 + 𝑓𝑛−1
∗
𝑋 − 𝑥𝑛
Consequently, the recursive relationship is
for n = 1, 2, 3
𝑥𝑛 = 0, 1, 2 … . 𝑋
where 𝑓𝑛
∗ 𝑋 = max 𝑓𝑛
∗ 𝑋 − 𝑥𝑛
𝑓𝑛
∗ 𝑋 = max { 𝑝𝑛 𝑥𝑛 + 𝑓𝑛−1
∗
𝑋 − 𝑥𝑛 }
𝑥𝑛 = 0, 1, 2 … . 𝑋
𝑓1 𝑋 = 𝑝1 𝑥1
X 0 1 2 3 4 5 𝑓1
∗
𝑋 𝑥1
∗
0 0 – – – – – 0 0
1 0 5 – – – – 5 1
2 0 5 9 – – – 9 2
3 0 5 9 14 – – 14 3
4 0 5 9 14 17 – 17 4
5 0 5 9 14 17 21 21 5
Stage, n = 1 (Store 1)
Stage, n = 2 (Store 2)
𝑓2 𝑋 = 𝑝2 𝑥2 + 𝑓1
∗
X − 𝑥2
X 0 1 2 3 4 5 𝑓2
∗
𝑋 𝑥2
∗
0 0 + 0 = 0 – – – – – 0 0
1 0 + 5 = 5 6 + 0 = 6 – – – – 6 1
2 0 + 9 = 9 6 + 5 = 11 11+0= 11 – – – 11 1, 2
3 0+14 = 14 6 + 9= 15 11+5= 16 15+0= 15 – – 16 2
4 0+17= 17 6 + 14= 20 11+9= 20 14+5= 19 19+0= 19 – 20 1, 2
5 0 +21= 21 6 + 17= 23 11+14= 25 14+9= 23 19+5= 24 22+0= 22 25 2
Stage, n = 3 (Store 3)
𝑓3 𝑋 = 𝑝3 𝑥3 + 𝑓2
∗
X − 𝑥3
X 0 1 2 3 4 5 𝑓3
∗
X 𝑥3
∗
0 0+0 = 0 – – – – – 0 0
1 0+6 = 6 4+0 = 4 – – – – 6 0
2 0+11 = 11 4+6 = 10 9+0 = 9 – – – 11 0
3 0+16 = 16 4+11 = 15 9+6 = 15 13+0 = 13 – – 16 0
4 0+20 = 20 4+16 = 20 9+11 = 20 13+6 = 19 18+0 = 18 – 20 0, 1
5 0+25 = 25 4+20 = 24 9+16 = 25 13+11 = 24 18+6 = 24 20+0 = 20 25 0, 2
Optimal Solution
Optimal profit = 25
Optimal Policy:
Store 1 Store 2 Store 3
Option 1 3 2 0
Option 2 1 2 2

More Related Content

PPTX
Linear programming graphical method (feasibility)
PDF
Linear Programming (graphical method)
PPTX
Operations Research - The Big M Method
PPTX
Integration by partial fraction
PPTX
Linear programming - Model formulation, Graphical Method
PPTX
LP special cases and Duality.pptx
PPT
L20 Simplex Method
PDF
Lesson 10: the Product and Quotient Rules
Linear programming graphical method (feasibility)
Linear Programming (graphical method)
Operations Research - The Big M Method
Integration by partial fraction
Linear programming - Model formulation, Graphical Method
LP special cases and Duality.pptx
L20 Simplex Method
Lesson 10: the Product and Quotient Rules

What's hot (20)

PDF
Lesson 17: The Method of Lagrange Multipliers
PPTX
LINEAR PROGRAMMING
PDF
Lesson 7: Limits at Infinity
PPT
Graphical Method
PPTX
Continuous functions
PDF
Unit.3. duality and sensetivity analisis
PPTX
Nonlinear programming 2013
PPSX
Graphical method
PPTX
Uniform Distribution
PDF
Goal programming
PDF
Lecture 04 newton-raphson, secant method etc
PPTX
Linear Programming Quiz Solution
PPTX
Solving Degenaracy in Transportation Problem
PDF
Integer programming
PPTX
Operations Research - Introduction
PPT
Formulation Lpp
PPTX
derivatives math
PPT
Exponential functions
PPT
Goal Programming
PDF
Lesson 17: The Method of Lagrange Multipliers
LINEAR PROGRAMMING
Lesson 7: Limits at Infinity
Graphical Method
Continuous functions
Unit.3. duality and sensetivity analisis
Nonlinear programming 2013
Graphical method
Uniform Distribution
Goal programming
Lecture 04 newton-raphson, secant method etc
Linear Programming Quiz Solution
Solving Degenaracy in Transportation Problem
Integer programming
Operations Research - Introduction
Formulation Lpp
derivatives math
Exponential functions
Goal Programming
Ad

Similar to Chapter 12 Dynamic programming.pptx (20)

PPT
PPT
Elak3 need of greedy for design and analysis of algorithms.ppt
PPT
dynamic-programming unit 3 power point presentation
PPTX
Dynamic Programming.pptx
PPTX
Dynamic Programming in design and analysis .pptx
PPTX
unit 5 dynamic programming.pptx
PPTX
Daa:Dynamic Programing
PDF
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
DOCX
Unit 7 dynamic programming
PPT
Dynamic Programming for 4th sem cse students
PPT
Learn about dynamic programming and how to design algorith
PPTX
DynamicProgramming.pptx
PPTX
Dynamic programming (dp) in Algorithm
PPTX
Chapter 5.pptx
PPTX
Dynamic Programming
PDF
Daa chapter 3
PPTX
Design and Analysis of Algorithm-Lecture.pptx
PPTX
8_dynamic_algorithm powerpoint ptesentation.pptx
PPTX
Dynamic Programming
PPT
Lecture11
Elak3 need of greedy for design and analysis of algorithms.ppt
dynamic-programming unit 3 power point presentation
Dynamic Programming.pptx
Dynamic Programming in design and analysis .pptx
unit 5 dynamic programming.pptx
Daa:Dynamic Programing
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Unit 7 dynamic programming
Dynamic Programming for 4th sem cse students
Learn about dynamic programming and how to design algorith
DynamicProgramming.pptx
Dynamic programming (dp) in Algorithm
Chapter 5.pptx
Dynamic Programming
Daa chapter 3
Design and Analysis of Algorithm-Lecture.pptx
8_dynamic_algorithm powerpoint ptesentation.pptx
Dynamic Programming
Lecture11
Ad

Recently uploaded (20)

PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PDF
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
PDF
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Geodesy 1.pptx...............................................
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
PPTX
Current and future trends in Computer Vision.pptx
PDF
Automation-in-Manufacturing-Chapter-Introduction.pdf
PDF
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PDF
PPT on Performance Review to get promotions
PPT
Mechanical Engineering MATERIALS Selection
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PDF
R24 SURVEYING LAB MANUAL for civil enggi
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPTX
Artificial Intelligence
PPTX
additive manufacturing of ss316l using mig welding
PPTX
Foundation to blockchain - A guide to Blockchain Tech
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PREDICTION OF DIABETES FROM ELECTRONIC HEALTH RECORDS
Enhancing Cyber Defense Against Zero-Day Attacks using Ensemble Neural Networks
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Geodesy 1.pptx...............................................
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Infosys Presentation by1.Riyan Bagwan 2.Samadhan Naiknavare 3.Gaurav Shinde 4...
Current and future trends in Computer Vision.pptx
Automation-in-Manufacturing-Chapter-Introduction.pdf
BMEC211 - INTRODUCTION TO MECHATRONICS-1.pdf
PPT on Performance Review to get promotions
Mechanical Engineering MATERIALS Selection
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
R24 SURVEYING LAB MANUAL for civil enggi
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
Artificial Intelligence
additive manufacturing of ss316l using mig welding
Foundation to blockchain - A guide to Blockchain Tech

Chapter 12 Dynamic programming.pptx

  • 1. Operations Research Course Code: IPE 3103 Instructor: Md. Rasel Sarkar Dept. of IPE, RUET, Rajshahi, Bangladesh Academic Year: 2020-21 Chapter 10 Dynamic programming
  • 2. Dynamic Program (DP)  Dynamic programming is a mathematical technique dealing with the optimization of multistage decision process.  Original decisions problem is divided into small sub- problem (stages) and stages are optimized rather than simultaneously.  In contrast to linear programming, there does not exist a standard mathematical formulation of “the dynamic programming problem”.  Dynamic programming is applicable when the sub- problems are not independent.
  • 3. Recursive Nature of Dynamic Programming  Computations are then carried out recursively where the optimum solution of one sub-problem is used as an input to the next sub-problem.  The optimum solution for the entire problem is at hand when the last sub-problem is solved.  The manner in which the recursive computations are carried out depends on how the original problem is decomposed.
  • 4. Shortest Route Problem Suppose that we want to select the shortest highway route between two cities. The network in Figure below provides the possible routes between the starting city at node 1 and the destination city at node 7. Where the number on the line shows distance from one node to another.
  • 5. First decompose it into stages as delineated by the vertical dashed lines in Figure. Next, carry out the computations for each stage separately.
  • 6. Stage 1 Shortest distance from node 1 to node 2 = 7 miles (from node 1) Shortest distance from node 1 to node 3 = 8 miles (from node 1) Shortest distance from node 1 to node 4 = 5 miles (from node 1)
  • 7. Stage 2 (n=2) Node 5 can be reached from nodes 2, 3, and 4. Thus – shortest distance to node x5 = min j=2,3,4 { distance from node xj to x5 + shortest distance to node xj } Let, f*n(xi) be the shortest distance to node xi at stage n d(xj, xi) as the distance from node xj to node xi. 𝑥𝑗 = all possible routes to node xi. Now above eqn. can be mathematically expressed as f*2(x5) = min j=2,3,4 {d(xj, x5) + (f1(xj)}
  • 8. Thus, shortest distance to node x5 = min 12 + 7 = 19 8 + 8 = 16 7 + 5 = 12 = 12 miles (from node 4) Node 6 can be reached from nodes 3 and 4. Thus – shortest distance to node x6 = min j=3,4 { distance from node xj to x6 + shortest distance to node xj } = min 9 + 8 = 17 13 + 5 = 18 = 17 miles (from node 3)
  • 9. Stage 3 The destination node 7 can be reached from either node 5 or 6. shortest distance to node x7 = min j=5,6 distance from node xj to x7 + shortest distance to node xj = min 9 + 12 = 21 6 + 17 = 23 = 21 miles (from node 5) Shortest distance from node 1 to node 7 = 21 miles. Thus, the shortest route is 1 → 4 → 5 → 7.
  • 10. Recursive equation The DP recursive equation is defined as – 𝑓0 𝑥1 = 0 𝑓𝑛 ∗ 𝑥𝑖 = min 𝑑 𝑥𝑗, 𝑥𝑖 + 𝑓𝑛−1 ∗ (𝑥𝑗) , for 𝑛 = 2, 3,…
  • 11. Principle of optimality The principle of optimality is the basic principle of dynamic programming, which was developed by Richard Bellman that: “An optimal policy has the property that whatever the initial conditions and decisions are the remaining stages constitute an optimal policy regardless of the policy adopted in all preceding stages”
  • 12. Capital budgeting problem Consider the capital budgeting problem where three existing factories, each being considered for possible expansion. Factories 1, 2 and 3 have three, four and two alternative plans for expansion respectively. The expected additional costs and the corresponding revenues for jth plan of the nth factory are given by cnj and Rnj. The objective of the decision problem is to select a plan j for each factory n which will maximize the total revenue. The cost of the selected set of plans should not exceed the total available capital, C.
  • 13. The data of the problem is tabulated below. All costs and revenue are scaled by 10-3. Assume the total capital available is C = 10. Factory, n n = 1 n = 2 n = 3 Plan, j c1j R1j c2j R2j c3j R3j 1 0 0 0 0 0 0 2 2 5 5 8 1 3 3 4 6 6 9 – – 4 – – 8 12 – –
  • 14. Recursive equation: 𝑓𝑛 ∗ 𝑋 = 𝑚𝑎𝑥 0≤ 𝑐𝑛𝑗≤ 𝑋 {𝑅𝑛𝑗 𝑐𝑛𝑗 + 𝑓𝑛−1 ∗ (𝑋 − 𝑐𝑛𝑗)} Where X = amounts available for allocation. 𝑓𝑛 ∗ 𝑋 = the maximum return from allocating X dollars at nth stage. 𝑐𝑛𝑗 = the decision variable, denote the amount allocated to jth plan of nth stage. 𝑅𝑛𝑗 𝑐𝑛𝑗 = return from the jth plan on the nth stage.
  • 15. Stage n = 1 (Factory 1) 𝑓1 𝑋 = 𝑅1𝑗 𝑐1𝑗 j =1 (c11= 0, R11=0) j = 2 (c12= 2, R12=5) j = 3 (R13=6, c13= 4) Optimum Sol. X 𝑓1 𝑋 𝑓1 𝑋 𝑓1 𝑋 𝑓1 ∗ 𝑋 j* 0 0 – – 0 1 1 0 – – 0 1 2 0 5 – 5 2 3 0 5 – 5 2 4 0 5 6 6 3 5 0 5 6 6 3 6 0 5 6 6 3 7 0 5 6 6 3 8 0 5 6 6 3 9 0 5 6 6 3 10 0 5 6 6 3
  • 16. Stage n = 2 (Factory 2) 𝑓2 𝑋 = 𝑅2𝑗 𝑐2𝑗 + 𝑓 ∗1 (𝑋 − 𝑐2𝑗) j =1 (c21= 0, R21= 0) j = 2 (c22= 5, R22 = 8) j = 3 (c23= 6, R23=9) j = 4 (c24= 8, R23=12) Optimum Solution X 𝑓2 𝑋 𝑓2 𝑋 𝑓2 𝑋 𝑓2 𝑋 𝑓2 ∗ 𝑋 j* 0 0 + 0 = 0 – – – 0 1 1 0 + 0 = 0 – – – 0 1 2 0 + 5 = 5 – – – 5 1 3 0 + 5 = 5 – – – 5 1 4 0 + 6 = 6 – – – 6 1 5 0 + 6 = 6 8 + 0 = 8 – – 8 2 6 0 + 6 = 6 8 + 0 = 8 9 + 0 = 9 – 9 3 7 0 + 6 = 6 8 + 5 = 13 9 + 0 = 9 – 13 2 8 0 + 6 = 6 8 + 5 = 13 9 + 5 = 14 12 + 0 = 12 14 3 9 0 + 6 = 6 8 + 6 = 14 9 + 5 = 14 12 + 0 = 12 14 2, 3 10 0 + 6 = 6 8 + 6 = 14 9 + 6 = 15 12 + 5 = 17 17 4
  • 17. Stage n = 3 (Factory 3) 𝑓3 𝑋 = 𝑅3𝑗 𝑐3𝑗 + 𝑓2 (𝑋 − 𝑐3𝑗)* j =1 (c31 = 0, R31 = 0) j = 2 (c32= 1, R32 = 3) Optimum Solution X 𝑓2 𝑋 𝑓2 𝑋 𝑓3 ∗ 𝑋 j* 0 0 + 0 = 0 – 0 1 1 0 + 0 = 0 3 + 0 = 3 3 2 2 0 + 5 = 5 3 + 0 = 3 5 1 3 0 + 5 = 5 3 + 5 = 8 8 2 4 0 + 6 = 6 3 + 5 = 8 8 2 5 0 + 8 = 8 3 + 6 = 9 9 2 6 0 + 9 = 9 3 + 8 = 11 11 2 7 0 + 13 = 13 3 + 9 = 12 13 1 8 0 + 14 = 14 3 + 13 = 16 16 2 9 0 + 14 = 14 3 + 14 = 17 17 2 10 0 + 17 = 17 3 + 14 = 17 17 1, 2
  • 18. Optimal profit = 17 Optimal Policy: Factory 1 Factory 2 Factory 3 Option 1 2 4 1 Option 2 3 2 2 Option 3 2 3 2
  • 19. Example (Liberman) The owner of a chain of three grocery stores has purchased five crates of fresh strawberries. The estimated probability distribution of potential sales of the strawberries before spoilage differs among the three stores. Therefore, the owner wants to know how to allocate five crates to the three stores to maximize expected profit. For administrative reasons, the owner does not wish to split crates between stores. However, he is willing to distribute no crates to any of his stores.
  • 20. The following table gives the estimated expected profit at each store when it is allocated various numbers of crates: Use dynamic programming to determine how many of the five crates should be assigned to each of the three stores to maximize the total expected profit.
  • 21. Solution Let , The decision variables xn (n = 1, 2, 3) are the number of crates to allocate to stage (store) n. X = number of crates available for allocation to different stores. pn(xn) = be the profit from allocating xn crates to store n. 𝑓𝑛 𝑋 = profit from allocating X crates to store, n 𝑓𝑛 ∗ 𝑋 = Optimal profit from allocating X crates to store, n
  • 22. Now get, 𝑓𝑛 𝑋 = 𝑝𝑛 𝑥𝑛 + 𝑓𝑛−1 ∗ 𝑋 − 𝑥𝑛 Consequently, the recursive relationship is for n = 1, 2, 3 𝑥𝑛 = 0, 1, 2 … . 𝑋 where 𝑓𝑛 ∗ 𝑋 = max 𝑓𝑛 ∗ 𝑋 − 𝑥𝑛 𝑓𝑛 ∗ 𝑋 = max { 𝑝𝑛 𝑥𝑛 + 𝑓𝑛−1 ∗ 𝑋 − 𝑥𝑛 } 𝑥𝑛 = 0, 1, 2 … . 𝑋
  • 23. 𝑓1 𝑋 = 𝑝1 𝑥1 X 0 1 2 3 4 5 𝑓1 ∗ 𝑋 𝑥1 ∗ 0 0 – – – – – 0 0 1 0 5 – – – – 5 1 2 0 5 9 – – – 9 2 3 0 5 9 14 – – 14 3 4 0 5 9 14 17 – 17 4 5 0 5 9 14 17 21 21 5 Stage, n = 1 (Store 1)
  • 24. Stage, n = 2 (Store 2) 𝑓2 𝑋 = 𝑝2 𝑥2 + 𝑓1 ∗ X − 𝑥2 X 0 1 2 3 4 5 𝑓2 ∗ 𝑋 𝑥2 ∗ 0 0 + 0 = 0 – – – – – 0 0 1 0 + 5 = 5 6 + 0 = 6 – – – – 6 1 2 0 + 9 = 9 6 + 5 = 11 11+0= 11 – – – 11 1, 2 3 0+14 = 14 6 + 9= 15 11+5= 16 15+0= 15 – – 16 2 4 0+17= 17 6 + 14= 20 11+9= 20 14+5= 19 19+0= 19 – 20 1, 2 5 0 +21= 21 6 + 17= 23 11+14= 25 14+9= 23 19+5= 24 22+0= 22 25 2
  • 25. Stage, n = 3 (Store 3) 𝑓3 𝑋 = 𝑝3 𝑥3 + 𝑓2 ∗ X − 𝑥3 X 0 1 2 3 4 5 𝑓3 ∗ X 𝑥3 ∗ 0 0+0 = 0 – – – – – 0 0 1 0+6 = 6 4+0 = 4 – – – – 6 0 2 0+11 = 11 4+6 = 10 9+0 = 9 – – – 11 0 3 0+16 = 16 4+11 = 15 9+6 = 15 13+0 = 13 – – 16 0 4 0+20 = 20 4+16 = 20 9+11 = 20 13+6 = 19 18+0 = 18 – 20 0, 1 5 0+25 = 25 4+20 = 24 9+16 = 25 13+11 = 24 18+6 = 24 20+0 = 20 25 0, 2
  • 26. Optimal Solution Optimal profit = 25 Optimal Policy: Store 1 Store 2 Store 3 Option 1 3 2 0 Option 2 1 2 2