Critical Path Method (CPM)
CPM is a network diagramming technique used
to predict total project duration.
CPM is an analysis technique with three main
purposes:
To calculate the project’s finish date
To indentify to what extent each activity in the
schedule can slip(float) without delaying the
project
To identify the activities with highest risk that
cannot slip without changing the project finish
date2
CPM
How does the Critical Path Method calculate the
project’s finish date?
o Forward pass calculation
 calculates Early Start and Early Finish dates
o Backward pass calculation
 calculates Late Start and Late Finish dates
3
Early Start (ES) is the earliest date a task can
start
Early Finish (EF) is the earliest date a task can
be completed
Late Start (LS) is the latest date a task can start
without delaying the project and date
Late Finish (LF) is the latest date a task can
finish without delaying the project end date
4
5
Start
D
5
F
2
C
6
Finish
E
4
B
1
A
2
Forward Pass
0 0
0 1511652
550
1515
1111 13
• Early Start (ES) = Latest related early date of all
immediate predecessors
ES= immediate Predecessors’ ES max
Early finish (EF) = Early Start + Duration
EF= ES + D
6
Activity A
ES EF
ES=3
ES=9
ES=10
D
7
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
Backward Pass
Late Finish (LF) = Earliest related late date of all
immediate successors
LF= immediate Successors’ LF min
Late Start (LS) = Late Finish – Duration
LS= LF-D
8
Activity A
LS LF
LF=3
LF=9
LF=10D
The purpose of backward pass is to find the float.
Float is the amount of time an activity can be
delayed or lengthened. Also called slack.
Total float: the amount of time an activity can be
delayed or extended without extending the overall
project’s completion time
9
What is the total Float for activity A?
10
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
11
Total float = LF-ES-D
A
2
0
108
65
1110
2
B
1
LFLSEFES
10820
A
A
Float
Float
Total Float:
TF= LF - ES – D
TF= LF – (ES+D) = LF-EF
TF= LF-D-ES= LS-ES
12
Activity A
LS LF
ES EF
Free Float: the amount of time an activity can be
delayed without delaying the early start date of its
subsequent tasks
13
Activity A
LS LF
ES EF
What is the FF for activity A?
What would happen if A uses its max float?
(A)EF=LF=10 (B) ES=LS=10
IF the early finish date of activity A =5
the early start date of activity B=5
FF=5-2=3
14
A
2
0
108
65
1110
2
B
1
Free Float: the amount of time an activity can be
delayed without delaying the early start date of its
subsequent tasks
EF= ES(B) – EF(A)
EF= ES(earliest successor)- EF
15
Activity A
LS LF
ES EF
Why floats are important in the critical path
method?
If an activity has a TF=0, what does this mean?
Floats determine thee criticality of an activity
Critical activities have the least amount of Float
Floats determine the critical path
16
The critical path is made of activities that cannot
be delayed without delaying the final date of the
project
If an item is on critical path, it has a zero float
The critical path is the path with longest duration
It is possible to have more than one critical path
17
What is the critical path?
What is the length of the critical path?
18
Start
D
5
F
2
C
6
Finish
E
4
A
2
0
0
0
0
0
108
50
15
15
11
1165
1110
2
550
115
1515
1515
1111 13
B
1
1513
Critical Path Method (CPM)
CPM is a network diagramming technique used
to predict total project duration
A critical path for a project is the series of
activities that determines the earliest time by
which the project can be completed
The critical path is the longest path through the
network diagram and has the least amount of
slack or float
Slack or float is the amount of time an activity
may be delayed without delaying a succeeding
activity or the project finish date
19
Calculating the Critical Path
First develop a good network diagram
Add the duration estimates for all activities on
each path through the network diagram
The longest path is the critical path
If one or more of the activities on the critical path
takes longer than planned, the whole project
schedule will slip unless the project manager
takes corrective action
20

More Related Content

PPTX
Critical Path Method
PDF
Critical path method(cpm)
PPTX
CPM - Critical Path Method
PPTX
Project Management - Critical path method
PDF
Critical Path Method
PPTX
Project Management PERT and CPM
PDF
Lect-6&7: Network Diagrams, PERT and CPM
Critical Path Method
Critical path method(cpm)
CPM - Critical Path Method
Project Management - Critical path method
Critical Path Method
Project Management PERT and CPM
Lect-6&7: Network Diagrams, PERT and CPM

What's hot (20)

ODP
Critical path method
PPTX
Project monitoring and control & planning for monitoring
PPTX
Work breakdown structure in project management ppt by kiran j
PPTX
Pert and CPM
PPT
Module :-5 project scheduling and resource levelling
PPTX
PROJECT SCHEDULE
PPTX
Work breakdown structure ppt
PPTX
Construction Project Management
PPTX
project management
PPTX
6.5 Resource Leveling and Resource Smoothing
PPTX
MS Project Presentation
PPS
An Introduction To Project Management
PPT
Project Management: NETWORK ANALYSIS - CPM and PERT
PPT
Project Scope Management -
PPTX
PROJECT CONTROL PROCESS
PPTX
Pert & cpm project management
PDF
PERT AND CPM PROJECT MANAGEMENT
PPT
09. Project Cost Management
PPT
Project Management Techniques
ODP
Project life cycle
Critical path method
Project monitoring and control & planning for monitoring
Work breakdown structure in project management ppt by kiran j
Pert and CPM
Module :-5 project scheduling and resource levelling
PROJECT SCHEDULE
Work breakdown structure ppt
Construction Project Management
project management
6.5 Resource Leveling and Resource Smoothing
MS Project Presentation
An Introduction To Project Management
Project Management: NETWORK ANALYSIS - CPM and PERT
Project Scope Management -
PROJECT CONTROL PROCESS
Pert & cpm project management
PERT AND CPM PROJECT MANAGEMENT
09. Project Cost Management
Project Management Techniques
Project life cycle
Ad

Similar to Critical path method (cpm) (20)

PDF
criticalpathmethod-151022164503-lva1-app6892.pdf
PPTX
CPM AND PERT(critical path method) .pptx
PPTX
CPM, Network Analysis A-O-A, A-O-N, Resource management
PPTX
Critical path method (CPM).pptx
PPTX
Project Evaluation and Review Technique "
PPTX
Chapter 5 - PERT-CPM
PPTX
Methods for critical path method and numerical
PPT
Critical Path Method
PPT
Cpm (critical path method)
PPTX
PROJECT TIME MANAGEMENT_LECTURE SIX.pptx
PDF
Pmp time chapter 6
PPT
chapter 6.ppt
PPTX
CPM.pptx
PPTX
CPM By Junaid.pptx
PPTX
6.5 The Forward and Backward Pass (Critical Path)
PPTX
Critical path lecture by EDP.pptxbdhshsjjdj
PPTX
CPM_CRITICAL_PATH_METHOD_PROJECT_MANAGEMENT.pptx
PPTX
Project Management Techniques ( CPM & PERT Techniques )
PDF
CPM AND PERT
PDF
Unit.6. network analysis with cpm and pert
criticalpathmethod-151022164503-lva1-app6892.pdf
CPM AND PERT(critical path method) .pptx
CPM, Network Analysis A-O-A, A-O-N, Resource management
Critical path method (CPM).pptx
Project Evaluation and Review Technique "
Chapter 5 - PERT-CPM
Methods for critical path method and numerical
Critical Path Method
Cpm (critical path method)
PROJECT TIME MANAGEMENT_LECTURE SIX.pptx
Pmp time chapter 6
chapter 6.ppt
CPM.pptx
CPM By Junaid.pptx
6.5 The Forward and Backward Pass (Critical Path)
Critical path lecture by EDP.pptxbdhshsjjdj
CPM_CRITICAL_PATH_METHOD_PROJECT_MANAGEMENT.pptx
Project Management Techniques ( CPM & PERT Techniques )
CPM AND PERT
Unit.6. network analysis with cpm and pert
Ad

Recently uploaded (20)

PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Internet of Things (IOT) - A guide to understanding
DOCX
573137875-Attendance-Management-System-original
PPTX
Sustainable Sites - Green Building Construction
PPTX
Foundation to blockchain - A guide to Blockchain Tech
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
additive manufacturing of ss316l using mig welding
PDF
composite construction of structures.pdf
PDF
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
PPTX
Welding lecture in detail for understanding
PDF
Arduino robotics embedded978-1-4302-3184-4.pdf
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PDF
Digital Logic Computer Design lecture notes
PPTX
OOP with Java - Java Introduction (Basics)
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Mechanical Engineering MATERIALS Selection
Internet of Things (IOT) - A guide to understanding
573137875-Attendance-Management-System-original
Sustainable Sites - Green Building Construction
Foundation to blockchain - A guide to Blockchain Tech
Embodied AI: Ushering in the Next Era of Intelligent Systems
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
CH1 Production IntroductoryConcepts.pptx
additive manufacturing of ss316l using mig welding
composite construction of structures.pdf
Evaluating the Democratization of the Turkish Armed Forces from a Normative P...
Welding lecture in detail for understanding
Arduino robotics embedded978-1-4302-3184-4.pdf
Model Code of Practice - Construction Work - 21102022 .pdf
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Digital Logic Computer Design lecture notes
OOP with Java - Java Introduction (Basics)

Critical path method (cpm)

  • 2. CPM is a network diagramming technique used to predict total project duration. CPM is an analysis technique with three main purposes: To calculate the project’s finish date To indentify to what extent each activity in the schedule can slip(float) without delaying the project To identify the activities with highest risk that cannot slip without changing the project finish date2
  • 3. CPM How does the Critical Path Method calculate the project’s finish date? o Forward pass calculation  calculates Early Start and Early Finish dates o Backward pass calculation  calculates Late Start and Late Finish dates 3
  • 4. Early Start (ES) is the earliest date a task can start Early Finish (EF) is the earliest date a task can be completed Late Start (LS) is the latest date a task can start without delaying the project and date Late Finish (LF) is the latest date a task can finish without delaying the project end date 4
  • 6. • Early Start (ES) = Latest related early date of all immediate predecessors ES= immediate Predecessors’ ES max Early finish (EF) = Early Start + Duration EF= ES + D 6 Activity A ES EF ES=3 ES=9 ES=10 D
  • 8. Late Finish (LF) = Earliest related late date of all immediate successors LF= immediate Successors’ LF min Late Start (LS) = Late Finish – Duration LS= LF-D 8 Activity A LS LF LF=3 LF=9 LF=10D
  • 9. The purpose of backward pass is to find the float. Float is the amount of time an activity can be delayed or lengthened. Also called slack. Total float: the amount of time an activity can be delayed or extended without extending the overall project’s completion time 9
  • 10. What is the total Float for activity A? 10 Start D 5 F 2 C 6 Finish E 4 A 2 0 0 0 0 0 108 50 15 15 11 1165 1110 2 550 115 1515 1515 1111 13 B 1 1513
  • 11. 11 Total float = LF-ES-D A 2 0 108 65 1110 2 B 1 LFLSEFES 10820 A A Float Float
  • 12. Total Float: TF= LF - ES – D TF= LF – (ES+D) = LF-EF TF= LF-D-ES= LS-ES 12 Activity A LS LF ES EF
  • 13. Free Float: the amount of time an activity can be delayed without delaying the early start date of its subsequent tasks 13 Activity A LS LF ES EF
  • 14. What is the FF for activity A? What would happen if A uses its max float? (A)EF=LF=10 (B) ES=LS=10 IF the early finish date of activity A =5 the early start date of activity B=5 FF=5-2=3 14 A 2 0 108 65 1110 2 B 1
  • 15. Free Float: the amount of time an activity can be delayed without delaying the early start date of its subsequent tasks EF= ES(B) – EF(A) EF= ES(earliest successor)- EF 15 Activity A LS LF ES EF
  • 16. Why floats are important in the critical path method? If an activity has a TF=0, what does this mean? Floats determine thee criticality of an activity Critical activities have the least amount of Float Floats determine the critical path 16
  • 17. The critical path is made of activities that cannot be delayed without delaying the final date of the project If an item is on critical path, it has a zero float The critical path is the path with longest duration It is possible to have more than one critical path 17
  • 18. What is the critical path? What is the length of the critical path? 18 Start D 5 F 2 C 6 Finish E 4 A 2 0 0 0 0 0 108 50 15 15 11 1165 1110 2 550 115 1515 1515 1111 13 B 1 1513
  • 19. Critical Path Method (CPM) CPM is a network diagramming technique used to predict total project duration A critical path for a project is the series of activities that determines the earliest time by which the project can be completed The critical path is the longest path through the network diagram and has the least amount of slack or float Slack or float is the amount of time an activity may be delayed without delaying a succeeding activity or the project finish date 19
  • 20. Calculating the Critical Path First develop a good network diagram Add the duration estimates for all activities on each path through the network diagram The longest path is the critical path If one or more of the activities on the critical path takes longer than planned, the whole project schedule will slip unless the project manager takes corrective action 20