This document discusses the critical path method (CPM) for planning and scheduling construction projects. It provides definitions and explanations of key CPM concepts like the critical path, total float, event time (TE) and late time (TL). The critical path is the longest path through the network that determines the minimum project duration. Activities on the critical path have zero total float and must finish on schedule or the project will be delayed. An example CPM network is given for a small construction project with 5 activities. The critical path and total project duration of 15 days is determined by calculating event times, float, earliest start/finish times and late finish times for each activity in the network.