Project Objectives
Solution to design & develop Serious GBL:
- Multi –player capabilities: AR/MR technology
- Implemented over 24 months
Planning and evaluation of entire project
Content
• WBS
• Network Diagram
• Crashing
• Resource Calendar
• What-If Scenario
• Risk Mitigation
WBS
Continue…
Network Diagram
CPM ( Critical Path Method )
CW 5 - ISPM - IS Group Project
Resource Calendar
- reflect real life working times
- public holidays and individual resource scheduling
- keep track of scheduled activities
- allocate tasks to available resources
- benefits save time and money
Working and non-working days
Assigning resources to calendar
ID Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Code
1 AR technologies Work A 100% £26.52/hr £0.00/hr £26.52Start working days
2 Technoeconomic
analysis of the
proposed solution
Work T 100% £11.36/hr £0.00/hr £11.36Prorated working days
3 System Achitecture Work S 100% £22.73/hr £0.00/hr £0.00Prorated working days
4 Avatars Type Work A 100% £4.06/hr £0.00/hr £0.00Prorated working days
5 AR Content Creation Work A 100% £11.36/hr £0.00/hr £0.00Prorated working days
6 Emulated Hazard
Condition in Gaming
Work E 100% £9.94/hr £0.00/hr £0.00Prorated working days
7 Multi-player
Capability
Work M 100% £11.36/hr £0.00/hr £0.00Prorated working days
8 MMORG Analytics Work M 100% £11.36/hr £0.00/hr £0.00Prorated working days
9 User API Work U 100% £11.36/hr £0.00/hr £0.00Prorated working days
10 User Manual Work U 100% £4.06/hr £0.00/hr £0.00Prorated working days
11 Online Help Work O 100% £2.44/hr £0.00/hr £0.00Prorated working days
12 Integrating
Components
Work I 100% £18.94/hr £0.00/hr £0.00Prorated working days
13 Testing & Validation Work T 100% £6.82/hr £0.00/hr £0.00Prorated working days
14 Health Safety Training
Requirement
Work H 100% £5.68/hr £0.00/hr £0.00Prorated working days
15 Learning & Gaming Work L 100% £19.89/hr £0.00/hr £0.00Start working days
16 Aysha Work A 100% £0.00/hr £0.00/hr £0.00Prorated working days
17 Maisha Work M 100% £0.00/hr £0.00/hr £0.00Prorated working days
18 Timothy Work T 100% £0.00/hr £0.00/hr £0.00Prorated working days
19 Lukmon Work L 100% £0.00/hr £0.00/hr £0.00Prorated working days
Assigning team members to tasks
ID Task Mode WBS Code Task Name Duration Start Finish Predecessors Cost Assigned To Activity Label
0 AR/MX- WBS dictionary (AR & Mixed
Reality)
29.77
mons
Mon
02/01/17
Fri
05/07/19
£235,980.80
1 Start -Augmented/Mixed Reality
(AR/MR) Game
0 mons Mon
02/01/17
Mon
02/01/17
£0.00
2 AR/MX-1 Specifying 3 mons Tue 03/01/17Tue 04/04/17 £14,002.56
3 AR/MX-1.1 AR Technologies 66 days Tue 03/01/17Tue 04/04/171 £14,002.56 Timothy A
4 AR/MX-2 Designing 3.18 monsWed 05/04/17Tue 11/07/17 £35,999.04
5 AR/MX-2.1 Technoeconomic analysis of
the proposed solution
66 days Wed
05/04/17
Tue
11/07/17
3 £11,996.16 Lukmon,
Timothy
B
6 AR/MX-2.2 System Architecture 66 days Wed 05/04/17Tue 11/07/173 £24,002.88 Maisha, Aisha C
7 AR/MX-3 Building 15.41 monsWed 12/07/17Mon 29/10/18 £129,976.00
8 AR/MX-3.1 Avatars Type 154 days Wed 12/07/17Fri 16/02/186,5 £10,003.84 Aisha, TimothyD
9 AR/MX-3.2 AR Content Creation 154 days Wed 12/07/17Fri 16/02/186,5 £27,991.04 Aisha, Lukmon E
10 AR/MX-3.3 Emulated Hazard Condition in Gaming176 days Wed 12/07/17Tue 20/03/186,5 £27,991.04 Maisha, LukmonF
11 AR/MX-3.4 Multi-player Capability 154 days Wed 12/07/17Fri 16/02/186,5 £27,991.04 Lukmon, TimothyG
12 AR/MX-3.5 MMORG Analytics 154 days Wed 12/07/17Fri 16/02/186,5 £13,995.52 Lukmon H
13 AR/MX-3.6 User API 154 days Wed 21/03/18Mon 29/10/1811,12,10,9,8 £13,995.52 Timothy I
14 AR/MX-3.7 User Manual 154 days Mon 19/02/18Thu 27/09/1811 £5,001.92 Timothy J
15 AR/MX-3.8 Online Help 154 days Mon 19/02/18Thu 27/09/1811 £3,006.08 Timothy K
16 AR/MX-4 Testing & Implementation 10.36 monsWed 21/03/18Fri 01/02/19 £32,003.84
17 AR/MX-4.1 Integrating Components 132 days Wed 21/03/18Thu 27/09/188,9,10,11,12 £20,000.64 Lukmon L
18 AR/MX-4.2 Testing & Validation 220 days Wed 21/03/18Fri 01/02/1912,11,10,9,8 £12,003.20 Aisha M
19 AR/MX-5 Training 9.14 monsFri 28/09/18Fri 05/07/19 £23,999.36
20 AR/MX-5.1 Health Safety Training Requirement110 days Fri 28/09/18Tue 05/03/1917 £9,996.80 Lukmon, TimothyN
21 AR/MX-5.2 Learning & Gaming 88 days Wed 06/03/19Fri 05/07/1920,13,18,14,15£14,002.56 Aisha O
22 Finish 0 days Fri 05/07/19Fri 05/07/1921 £0.00 P
Avat
AR C
E
Mult
MMO
11/12 26/0
11 October
Levelling Gantt View
Team Schedule
Total cost of project/project investment
What – If Scenario
• Specifying Communication
• Designing – Infrastructural Security Issues/All client requirements are not met
•
• Building - Late Request of features
•
• Testing & Implementation – Random system failures occurring
•
• Training/Skills – Management/Leadership/Communication
Risk Assessment & Mitigation
- Specifying: Lack of knowledge/ Communication
-
- Designing: capital costs/investment/lack of understanding of System Architecture
-
- Building: Hardware failures/user error/natural disasters
-
- Testing & Implementation: System performance failure
-
- Training: Lack of training
Risk Assessment Matrix
Thank you for
listening

More Related Content

PDF
Ez labormanager savings_calculator_majors
PDF
Western Equestrian Catalogue
PDF
Rockstars of entrepreneurship
RTF
2 EL EŞYA ALANLAR SATANLAR ESKİCİLER AVCILAR
DOCX
Molly and the three bears
PDF
Healthy and Unhealthy Relationships
PPTX
PDF
Ch14
Ez labormanager savings_calculator_majors
Western Equestrian Catalogue
Rockstars of entrepreneurship
2 EL EŞYA ALANLAR SATANLAR ESKİCİLER AVCILAR
Molly and the three bears
Healthy and Unhealthy Relationships
Ch14

Similar to CW 5 - ISPM - IS Group Project (20)

PDF
Interactive Game Development For Teenagers Proposal PowerPoint Presentation S...
DOCX
Assessment item 2—Group case studyDue date100pm AEST, Friday.docx
PDF
Filament Games: Design & Development
PPTX
From Dream To Reality
PPTX
Five Cliches of Online Game Development
PPTX
Supersize your production pipe enjmin 2013 v1.1 hd
PDF
Explain the mission of the organization
PDF
Game Programming 01 - Introduction
PPT
Games.ppt
PDF
Eight Rules for Making Your First Great Game
PPTX
Car access system
PPTX
Mastery journey timeline
PPTX
Large Scale Software Project
PPT
Skills Week / Paul Mayze and Alan O'Dea / MMOs are a Service not a Game
PPTX
Unit 13 Pecha Kucha
PDF
Lkce12.emergent patternsit ops
PPTX
Maximize Your Production Effort (English)
PPTX
How to Profit from Static Analysis
PPTX
Virtual-Reality-DD-Final02-1
DOC
Resume_Sharvani
Interactive Game Development For Teenagers Proposal PowerPoint Presentation S...
Assessment item 2—Group case studyDue date100pm AEST, Friday.docx
Filament Games: Design & Development
From Dream To Reality
Five Cliches of Online Game Development
Supersize your production pipe enjmin 2013 v1.1 hd
Explain the mission of the organization
Game Programming 01 - Introduction
Games.ppt
Eight Rules for Making Your First Great Game
Car access system
Mastery journey timeline
Large Scale Software Project
Skills Week / Paul Mayze and Alan O'Dea / MMOs are a Service not a Game
Unit 13 Pecha Kucha
Lkce12.emergent patternsit ops
Maximize Your Production Effort (English)
How to Profit from Static Analysis
Virtual-Reality-DD-Final02-1
Resume_Sharvani
Ad

More from Timothy Adrian Lam (16)

PDF
Amnick Certificate - Timothy Adrian Lam
DOCX
Coursework 5 - IS Project Management Final
PPTX
Smart Cities Timothy Lam
DOCX
PROOFED - Programming Language for Business
PPTX
KAWASAKI STYLE PRESENTATION
DOCX
Business Plan
DOCX
Fresh Tofu Kong Wah Specification Sunnyfield
DOCX
DRAGONFRUIT SPECIFICATION_COOKS
DOCX
DRAGONFRUIT product specification (sunny field)
PDF
UCD Assignment 2 – Final Report – Training Everywhere
DOCX
UCD Usability Evaluation Report
DOCX
Material Database Design
DOCX
Integrated Assignment User Guide
DOCX
Group report
DOCX
FINAL_REPORT_
DOC
The Mind and Body Report
Amnick Certificate - Timothy Adrian Lam
Coursework 5 - IS Project Management Final
Smart Cities Timothy Lam
PROOFED - Programming Language for Business
KAWASAKI STYLE PRESENTATION
Business Plan
Fresh Tofu Kong Wah Specification Sunnyfield
DRAGONFRUIT SPECIFICATION_COOKS
DRAGONFRUIT product specification (sunny field)
UCD Assignment 2 – Final Report – Training Everywhere
UCD Usability Evaluation Report
Material Database Design
Integrated Assignment User Guide
Group report
FINAL_REPORT_
The Mind and Body Report
Ad

CW 5 - ISPM - IS Group Project

  • 2. Project Objectives Solution to design & develop Serious GBL: - Multi –player capabilities: AR/MR technology - Implemented over 24 months Planning and evaluation of entire project
  • 3. Content • WBS • Network Diagram • Crashing • Resource Calendar • What-If Scenario • Risk Mitigation
  • 4. WBS
  • 7. CPM ( Critical Path Method )
  • 9. Resource Calendar - reflect real life working times - public holidays and individual resource scheduling - keep track of scheduled activities - allocate tasks to available resources - benefits save time and money
  • 11. Assigning resources to calendar ID Resource Name Type Material Label Initials Group Max. Units Std. Rate Ovt. Rate Cost/Use Accrue At Base Calendar Code 1 AR technologies Work A 100% £26.52/hr £0.00/hr £26.52Start working days 2 Technoeconomic analysis of the proposed solution Work T 100% £11.36/hr £0.00/hr £11.36Prorated working days 3 System Achitecture Work S 100% £22.73/hr £0.00/hr £0.00Prorated working days 4 Avatars Type Work A 100% £4.06/hr £0.00/hr £0.00Prorated working days 5 AR Content Creation Work A 100% £11.36/hr £0.00/hr £0.00Prorated working days 6 Emulated Hazard Condition in Gaming Work E 100% £9.94/hr £0.00/hr £0.00Prorated working days 7 Multi-player Capability Work M 100% £11.36/hr £0.00/hr £0.00Prorated working days 8 MMORG Analytics Work M 100% £11.36/hr £0.00/hr £0.00Prorated working days 9 User API Work U 100% £11.36/hr £0.00/hr £0.00Prorated working days 10 User Manual Work U 100% £4.06/hr £0.00/hr £0.00Prorated working days 11 Online Help Work O 100% £2.44/hr £0.00/hr £0.00Prorated working days 12 Integrating Components Work I 100% £18.94/hr £0.00/hr £0.00Prorated working days 13 Testing & Validation Work T 100% £6.82/hr £0.00/hr £0.00Prorated working days 14 Health Safety Training Requirement Work H 100% £5.68/hr £0.00/hr £0.00Prorated working days 15 Learning & Gaming Work L 100% £19.89/hr £0.00/hr £0.00Start working days 16 Aysha Work A 100% £0.00/hr £0.00/hr £0.00Prorated working days 17 Maisha Work M 100% £0.00/hr £0.00/hr £0.00Prorated working days 18 Timothy Work T 100% £0.00/hr £0.00/hr £0.00Prorated working days 19 Lukmon Work L 100% £0.00/hr £0.00/hr £0.00Prorated working days
  • 12. Assigning team members to tasks ID Task Mode WBS Code Task Name Duration Start Finish Predecessors Cost Assigned To Activity Label 0 AR/MX- WBS dictionary (AR & Mixed Reality) 29.77 mons Mon 02/01/17 Fri 05/07/19 £235,980.80 1 Start -Augmented/Mixed Reality (AR/MR) Game 0 mons Mon 02/01/17 Mon 02/01/17 £0.00 2 AR/MX-1 Specifying 3 mons Tue 03/01/17Tue 04/04/17 £14,002.56 3 AR/MX-1.1 AR Technologies 66 days Tue 03/01/17Tue 04/04/171 £14,002.56 Timothy A 4 AR/MX-2 Designing 3.18 monsWed 05/04/17Tue 11/07/17 £35,999.04 5 AR/MX-2.1 Technoeconomic analysis of the proposed solution 66 days Wed 05/04/17 Tue 11/07/17 3 £11,996.16 Lukmon, Timothy B 6 AR/MX-2.2 System Architecture 66 days Wed 05/04/17Tue 11/07/173 £24,002.88 Maisha, Aisha C 7 AR/MX-3 Building 15.41 monsWed 12/07/17Mon 29/10/18 £129,976.00 8 AR/MX-3.1 Avatars Type 154 days Wed 12/07/17Fri 16/02/186,5 £10,003.84 Aisha, TimothyD 9 AR/MX-3.2 AR Content Creation 154 days Wed 12/07/17Fri 16/02/186,5 £27,991.04 Aisha, Lukmon E 10 AR/MX-3.3 Emulated Hazard Condition in Gaming176 days Wed 12/07/17Tue 20/03/186,5 £27,991.04 Maisha, LukmonF 11 AR/MX-3.4 Multi-player Capability 154 days Wed 12/07/17Fri 16/02/186,5 £27,991.04 Lukmon, TimothyG 12 AR/MX-3.5 MMORG Analytics 154 days Wed 12/07/17Fri 16/02/186,5 £13,995.52 Lukmon H 13 AR/MX-3.6 User API 154 days Wed 21/03/18Mon 29/10/1811,12,10,9,8 £13,995.52 Timothy I 14 AR/MX-3.7 User Manual 154 days Mon 19/02/18Thu 27/09/1811 £5,001.92 Timothy J 15 AR/MX-3.8 Online Help 154 days Mon 19/02/18Thu 27/09/1811 £3,006.08 Timothy K 16 AR/MX-4 Testing & Implementation 10.36 monsWed 21/03/18Fri 01/02/19 £32,003.84 17 AR/MX-4.1 Integrating Components 132 days Wed 21/03/18Thu 27/09/188,9,10,11,12 £20,000.64 Lukmon L 18 AR/MX-4.2 Testing & Validation 220 days Wed 21/03/18Fri 01/02/1912,11,10,9,8 £12,003.20 Aisha M 19 AR/MX-5 Training 9.14 monsFri 28/09/18Fri 05/07/19 £23,999.36 20 AR/MX-5.1 Health Safety Training Requirement110 days Fri 28/09/18Tue 05/03/1917 £9,996.80 Lukmon, TimothyN 21 AR/MX-5.2 Learning & Gaming 88 days Wed 06/03/19Fri 05/07/1920,13,18,14,15£14,002.56 Aisha O 22 Finish 0 days Fri 05/07/19Fri 05/07/1921 £0.00 P Avat AR C E Mult MMO 11/12 26/0 11 October
  • 15. Total cost of project/project investment
  • 16. What – If Scenario • Specifying Communication • Designing – Infrastructural Security Issues/All client requirements are not met • • Building - Late Request of features • • Testing & Implementation – Random system failures occurring • • Training/Skills – Management/Leadership/Communication
  • 17. Risk Assessment & Mitigation - Specifying: Lack of knowledge/ Communication - - Designing: capital costs/investment/lack of understanding of System Architecture - - Building: Hardware failures/user error/natural disasters - - Testing & Implementation: System performance failure - - Training: Lack of training