4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item Sales percentage
M1 M2 M3 M4 M5 M6
1 5.18%
2 64.08% 30.00% 20.00%
3 30.74% 10.00% 10.00%
100.00% 22.30% 0.00% 0.00% 0.00% 0.00% 15.89%
22.30% 22.30% 22.30% 22.30% 22.30% 38.19%
Months
1 1 22.30% 15.89%
2 3 7.43% 7.43% 7.43% 15.89%
3 9 2.48% 2.48% 2.48% 5.13%
4 7
5 7
6 8
7 5
8 6
9 2
10 6
22.30% 15.89%
1 10.00% 1,214,449.50 865,436.00
7.433% 7.433% 7.433%
2 10.00% 404,816.50 404,816.50 404,816.50
2.48% 2.48% 2.48%
3 15.00% 202,408.25 202,408.25 202,408.25
4 10.00%
5 10.00%
6 10.00%
7 5.00%
8 2.50%
9 2.50%
10 17.50%
11 2.50%
12 2.50%
13 2.50%
100.00% 1,214,449.50 404,816.50 404,816.50 607,224.75 202,408.25 1,067,844.25
1,214,449.50 1,619,266.00 2,024,082.50 2,631,307.25 2,833,715.50 3,901,559.75
2,024,082.50 1,877,477.25
Quarterly Cummulative Cash Inflow 2,024,082.50 3,901,559.75
Quarterly Total Cash Inflow 54,461,770.00
Monthly Total Cash Flow 54,461,770.00
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
1,361,544.25
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
1,361,544.25
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
1,361,544.25
Roadworks 1,361,544.25
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
9,530,809.75
Drainage works 1,361,544.25
Internal &External plastering 5,446,177.00
Sewerage works 2,723,088.50
Roofing, Electrical wiring & plumbing 5,446,177.00
R.C. Framwork 8,169,265.50
Walls, Doors & Window frame 5,446,177.00
Foundation 5,446,177.00
Sales Proceeds
Signing of S&P Agreement (Clause 5) 5,446,177.00
INFRASTRUCTURE WORKS 100.00%
SEWERAGE WORKS 100.00%
DRAINAGE WORKS 100.00%
ROADWORKS 100.00%
WALLS, DOORS & WINDOW FRAME 100.00%
ROOFING, ELEC WIRING & PLUMBING 100.00%
INTERNAL &EXTERNAL PLASTERING 100.00%
EARTHWORKS 100.00%
FOUNDATION 100.00%
R.C. FRAMEWORK 100.00%
% of Cumulative Sales
D/S Terrace 34,901,350.00
D/S Shop/Office 16,740,900.00
Monthly Total 54,461,770.00
Sale Projection
D/S Low Cost 2,819,520.00
Q1 Q2
Description Amount (RM) 2013
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M7 M8 M9 M10 M11 M12
50.0%
20.0% 10.0%
10.0% 10.0%
0.0% 0.0% 18.5% 0.0% 0.0% 9.5%
38.19% 38.19% 56.67% 56.67% 56.67% 66.15%
18.48% 9.48%
18.48% 9.48%
5.13% 5.13% 11.29% 11.29% 11.29% 9.48%
5.46% 5.46% 9.15% 9.15% 9.15% 13.89%
8.10% 8.10% 8.10% 10.47%
7.08% 8.44%
18.48% 9.48%
1,006,412.00 516,422.50
15.89% 18.48%
865,436.00 1,006,412.00
5.13% 5.13% 5.13% 11.29% 11.29% 11.29%
418,767.25 418,767.25 418,767.25 921,973.25 921,973.25 921,973.25
5.46% 5.46% 9.15% 9.15% 9.15%
297,126.50 297,126.50 498,408.90 498,408.90 498,408.90
8.10% 8.10% 8.10%
440,899.64 440,899.64 440,899.64
7.08%
385,787.19
1,284,203.25 715,893.75 1,722,305.75 2,867,693.79 1,861,281.79 2,763,491.48
5,185,763.00 5,901,656.75 7,623,962.50 10,491,656.29 12,352,938.09 15,116,429.57
3,722,402.75 7,492,467.07
7,623,962.50 15,116,429.57
Q3 Q4
2013
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M13 M14 M15 M16 M17 M18 M19 M20
50.0%
20.0%
10.0% 20.0%
0.0% 0.0% 18.5% 0.0% 0.0% 6.1% 0.0% 0.0%
66.15% 66.15% 84.63% 84.63% 84.63% 90.78% 90.78% 90.78%
18.48% 6.15%
18.48% 6.15%
18.48% 6.15%
13.89% 18.48% 6.15%
10.47% 10.47% 28.95% 6.15%
8.44% 8.44% 13.06% 13.06% 13.06% 19.21%
18.16% 18.16%
14.11% 15.33% 15.33% 15.33%
14.11% 14.11% 15.64% 15.64% 15.64%
18.48% 6.15%
1,006,412.00 334,818.00
9.5% 18.48% 6.15%
516,422.50 1,006,412.00 334,818.00
9.48% 18.48% 6.15%
774,633.75 1,509,618.00 502,227.00
13.89% 13.89% 18.48% 6.15%
756,620.15 756,620.15 1,006,412.00 334,818.00
10.47% 10.47% 10.47% 28.95% 6.15%
570,005.27 570,005.27 570,005.27 1,576,417.27 334,818.00
8.44% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21%
459,561.83 459,561.83 459,561.83 711,164.83 711,164.83 711,164.83 1,045,982.83
18.16%
494,395.00
14.11% 15.33% 15.33%
192,047.17 208,788.07 208,788.07
3,077,243.50 1,786,187.25 2,035,979.10 5,810,024.10 711,164.83 1,238,030.00 2,761,451.90 703,183.07
18,193,673.06 19,979,860.31 22,015,839.41 27,825,863.51 28,537,028.34 29,775,058.34 32,536,510.23 33,239,693.30
6,899,409.84 7,759,218.93
22,015,839.41 29,775,058.34
Q1 Q2 Q3
2014
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M21 M22 M23 M24
30.0%
9.2% 0.0% 0.0% 0.0%
100.00% 100.00% 100.00% 100.00%
9.22%
9.22%
9.22%
9.22%
9.22%
9.22%
21.23% 21.23% 21.23%
19.95% 19.95%
50.00% 50.00%
24.86%
9.22% 0.00%
502,227.00 -
9.22%
502,227.00
9.22%
753,340.50
9.22%
502,227.00
9.22%
502,227.00
9.22%
502,227.00
18.16% 21.23% 21.23% 21.23%
494,395.00 578,099.50 578,099.50 578,099.50
15.33% 19.95% 19.95%
208,788.07 271,566.44 271,566.44
50.00%
680,772.13
1,205,410.07 3,611,914.44 849,665.94 1,258,871.63
34,445,103.37 38,057,017.81 38,906,683.75 40,165,555.38
4,670,045.03 5,720,452.01
34,445,103.37 40,165,555.38
Q3 Q4
2014
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M25 M26 M27 M28 M29 M30 M31 M32
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
50.00%
680,772.13
100.00%
9,530,809.75
100.00%
1,361,544.25
10,211,581.88 1,361,544.25 0 0 0 0 0 0
50,377,137.25 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50
11,573,126.13 0
51,738,681.50 51,738,681.50
Q3Q1 Q2
2015
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M33 M34 M35 M36
100.00% 100.00% 100.00% 100.00%
100.00%
1,361,544.25
1,361,544.25 0 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75
1,361,544.25 0
53,100,225.75 53,100,225.75
Q3 Q4
2015
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M37 M38 M39 M40 M41 M42 M43 M44
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
0 0 0 0 0 0 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75
0 0
53,100,225.75 53,100,225.75
Q1
2016
Q2 Q3
4.0 Cash Flow for Project
The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow.
PROJECTED CASH INFLOW FOR 2013-2016
Item
1
2
3
1
2
3
4
5
6
7
8
9
10
1
2
3
4
5
6
7
8
9
10
11
12
13
Quarterly Cummulative Cash Inflow
Quarterly Total Cash Inflow
Monthly Total Cash Flow
Monthly Cummulative Cash Inflow
On the date the Purchaser takes vacant possession of the
said Property as in item 10 and to be held by the
Developer’s solicitor as stakeholder for payment to the
Developer as follows:
(a) two point five per centum (2.5%) at the expiry of the
period of eight (8) months after the date the Purchaser
takes vacant possession of the said Property; and (Clause
5)
(b) two point five per centum (2.5%) at the expiry of the
period of twenty-four (24) months after the date the
Purchaser takes vacant possession of the said Property
(Clause 5)
On the date the Purchaser takes vacant possession of the
said Property as in item 10 where the Developer has
delivered to the Purchaser or the Purchaser’s Solicitor the
original issue document of title to the said Building Lot
registered in the name of the Purchaser. (Clause 5)
Roadworks
On the date the Purchaser takes vacant possession of the
said Property with water and electricity supply ready for
connection. (Clause 5)
Drainage works
Internal &External plastering
Sewerage works
Roofing, Electrical wiring & plumbing
R.C. Framwork
Walls, Doors & Window frame
Foundation
Sales Proceeds
Signing of S&P Agreement (Clause 5)
INFRASTRUCTURE WORKS
SEWERAGE WORKS
DRAINAGE WORKS
ROADWORKS
WALLS, DOORS & WINDOW FRAME
ROOFING, ELEC WIRING & PLUMBING
INTERNAL &EXTERNAL PLASTERING
EARTHWORKS
FOUNDATION
R.C. FRAMEWORK
% of Cumulative Sales
D/S Terrace
D/S Shop/Office
Monthly Total
Sale Projection
D/S Low Cost
Description
M45 M46 M47 M48 M49 M50 M51
100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00%
100.0%
1,361,544.25
0 0 0 0 1,361,544.25 0 0
53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 54,461,770.00 54,461,770.00 54,461,770.00
0 0 1,361,544.25
53,100,225.75 53,100,225.75 54,461,770.00
2016 2017
Q1Q3 Q4

More Related Content

DOCX
De assignment
PDF
Q2 2014 industrial market report
PDF
Assignment - Financial Appraisal
PPTX
Viability Session 2: The role of viability in plan-making and development man...
PDF
JLL Cleveland Industrial Outlook: Q4 2018
PDF
JLL Cleveland Industrial Outlook: Q4 2018
PDF
Q3 2014 industrial market report
PDF
BriteCon 2014 - Keynote
De assignment
Q2 2014 industrial market report
Assignment - Financial Appraisal
Viability Session 2: The role of viability in plan-making and development man...
JLL Cleveland Industrial Outlook: Q4 2018
JLL Cleveland Industrial Outlook: Q4 2018
Q3 2014 industrial market report
BriteCon 2014 - Keynote

Similar to De assignment-finalized-28112017 3 (20)

PDF
JLL Cleveland Industrial Outlook: Q3 2020
PDF
JLL Cleveland Industrial Outlook: Q3 2018
PDF
Second edition epc project rule of credit and progress measurement promo
PDF
JLL Cincinnati Industrial Outlook Q4 2017
PDF
JLL Cleveland Industrial Outlook Q4 2019
PDF
JLL Cleveland Industrial Outlook: Q1 2019
PDF
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
PPTX
viability-presentation-se-98b.pptx
DOCX
2015 Savings Achieved
PDF
JLL Cleveland Industrial Outlook: Q3 2019
PDF
JLL Cleveland Industrial Outlook Q3 2019
PPTX
Skyworks Presentation_Haley Large-Cap Fund
PPTX
Skyworks
PDF
US20140180938
PDF
US20140180938
PDF
Project Management Services
PDF
Item # 8 Sewer Rehab Contract - Ogden
PPTX
Rajgir Sports Complex_Project Kick Off Presentation.pptx
PDF
The ICE conditions of contract seventh edition Brian Eggleston
PDF
The ICE conditions of contract seventh edition Brian Eggleston
JLL Cleveland Industrial Outlook: Q3 2020
JLL Cleveland Industrial Outlook: Q3 2018
Second edition epc project rule of credit and progress measurement promo
JLL Cincinnati Industrial Outlook Q4 2017
JLL Cleveland Industrial Outlook Q4 2019
JLL Cleveland Industrial Outlook: Q1 2019
Raheja Ayana Residences Luxury Independent Floors Sector 79 Gurgaon, Call Now...
viability-presentation-se-98b.pptx
2015 Savings Achieved
JLL Cleveland Industrial Outlook: Q3 2019
JLL Cleveland Industrial Outlook Q3 2019
Skyworks Presentation_Haley Large-Cap Fund
Skyworks
US20140180938
US20140180938
Project Management Services
Item # 8 Sewer Rehab Contract - Ogden
Rajgir Sports Complex_Project Kick Off Presentation.pptx
The ICE conditions of contract seventh edition Brian Eggleston
The ICE conditions of contract seventh edition Brian Eggleston
Ad

More from Arthur Wilson (20)

PDF
Pm group-compileddd
DOCX
Activity id
DOCX
Pm project-control-compiled
PDF
Final 2
PPTX
Law relating-to-payment
DOCX
Cl report final
PDF
Vm assignment - presentation slide (1)
PDF
Vm compiled-edited (print)
PDF
De assignment-finalized-28112017
PDF
De assignment-finalized-28112017 6
PDF
De assignment-finalized-28112017 5
PDF
De assignment-finalized-28112017 4
PDF
De assignment-finalized-28112017 2
DOCX
Research proposal draft v3
PDF
Chapter 2 draft v1
DOCX
Fm assignment-final-updated v2.0
PDF
De & be final workshop submission
DOCX
Community service
PDF
Excavation
PPTX
Elemental cost analysis
Pm group-compileddd
Activity id
Pm project-control-compiled
Final 2
Law relating-to-payment
Cl report final
Vm assignment - presentation slide (1)
Vm compiled-edited (print)
De assignment-finalized-28112017
De assignment-finalized-28112017 6
De assignment-finalized-28112017 5
De assignment-finalized-28112017 4
De assignment-finalized-28112017 2
Research proposal draft v3
Chapter 2 draft v1
Fm assignment-final-updated v2.0
De & be final workshop submission
Community service
Excavation
Elemental cost analysis
Ad

Recently uploaded (20)

PPTX
Art Appreciation-Lesson-1-1.pptx College
PPTX
current by laws xxxxxxxxxxxxxxxxxxxxxxxxxxx
PDF
Love & Romance in Every Sparkle_ Discover the Magic of Diamond Painting.pdf
PPTX
QA PROCESS FLOW CHART (1).pptxaaaaaaaaaaaa
PPTX
This is about the usage of color in universities design
PDF
630895715-Romanesque-Architecture-ppt.pdf
PPTX
DIMAYUGA ANDEA MAE P. BSED ENG 3-2 (CHAPTER 7).pptx
PPTX
Neoclassical and Mystery Plays Entertain
PPTX
Callie Slide Show Slide Show Slide Show S
PPTX
SlideEgg_21518-Company Presentation.pptx
PPTX
Review1_Bollywood_Project analysis of bolywood trends from 1950s to 2025
PPTX
Copy of liver-cancer-case-study.pptx.pptx
PPTX
CPAR_QR1_WEEK1_INTRODUCTION TO CPAR.pptx
PPTX
Military history & Evolution of Armed Forces of the Philippines
PPTX
Visual-Arts.pptx power point elements of art the line, shape, form
PPTX
Green and Orange Illustration Understanding Climate Change Presentation.pptx
PPTX
Cloud Computing ppt.ppt1QU4FFIWEKWEIFRRGx
PPTX
65bc3704-6ed1-4724-977d-a70f145d40da.pptx
PPTX
573393963-choose-your-own-adventure(2).pptx
PPTX
philippine contemporary artscot ppt.pptx
Art Appreciation-Lesson-1-1.pptx College
current by laws xxxxxxxxxxxxxxxxxxxxxxxxxxx
Love & Romance in Every Sparkle_ Discover the Magic of Diamond Painting.pdf
QA PROCESS FLOW CHART (1).pptxaaaaaaaaaaaa
This is about the usage of color in universities design
630895715-Romanesque-Architecture-ppt.pdf
DIMAYUGA ANDEA MAE P. BSED ENG 3-2 (CHAPTER 7).pptx
Neoclassical and Mystery Plays Entertain
Callie Slide Show Slide Show Slide Show S
SlideEgg_21518-Company Presentation.pptx
Review1_Bollywood_Project analysis of bolywood trends from 1950s to 2025
Copy of liver-cancer-case-study.pptx.pptx
CPAR_QR1_WEEK1_INTRODUCTION TO CPAR.pptx
Military history & Evolution of Armed Forces of the Philippines
Visual-Arts.pptx power point elements of art the line, shape, form
Green and Orange Illustration Understanding Climate Change Presentation.pptx
Cloud Computing ppt.ppt1QU4FFIWEKWEIFRRGx
65bc3704-6ed1-4724-977d-a70f145d40da.pptx
573393963-choose-your-own-adventure(2).pptx
philippine contemporary artscot ppt.pptx

De assignment-finalized-28112017 3

  • 1. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item Sales percentage M1 M2 M3 M4 M5 M6 1 5.18% 2 64.08% 30.00% 20.00% 3 30.74% 10.00% 10.00% 100.00% 22.30% 0.00% 0.00% 0.00% 0.00% 15.89% 22.30% 22.30% 22.30% 22.30% 22.30% 38.19% Months 1 1 22.30% 15.89% 2 3 7.43% 7.43% 7.43% 15.89% 3 9 2.48% 2.48% 2.48% 5.13% 4 7 5 7 6 8 7 5 8 6 9 2 10 6 22.30% 15.89% 1 10.00% 1,214,449.50 865,436.00 7.433% 7.433% 7.433% 2 10.00% 404,816.50 404,816.50 404,816.50 2.48% 2.48% 2.48% 3 15.00% 202,408.25 202,408.25 202,408.25 4 10.00% 5 10.00% 6 10.00% 7 5.00% 8 2.50% 9 2.50% 10 17.50% 11 2.50% 12 2.50% 13 2.50% 100.00% 1,214,449.50 404,816.50 404,816.50 607,224.75 202,408.25 1,067,844.25 1,214,449.50 1,619,266.00 2,024,082.50 2,631,307.25 2,833,715.50 3,901,559.75 2,024,082.50 1,877,477.25 Quarterly Cummulative Cash Inflow 2,024,082.50 3,901,559.75 Quarterly Total Cash Inflow 54,461,770.00 Monthly Total Cash Flow 54,461,770.00 Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) 1,361,544.25 (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) 1,361,544.25 On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) 1,361,544.25 Roadworks 1,361,544.25 On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) 9,530,809.75 Drainage works 1,361,544.25 Internal &External plastering 5,446,177.00 Sewerage works 2,723,088.50 Roofing, Electrical wiring & plumbing 5,446,177.00 R.C. Framwork 8,169,265.50 Walls, Doors & Window frame 5,446,177.00 Foundation 5,446,177.00 Sales Proceeds Signing of S&P Agreement (Clause 5) 5,446,177.00 INFRASTRUCTURE WORKS 100.00% SEWERAGE WORKS 100.00% DRAINAGE WORKS 100.00% ROADWORKS 100.00% WALLS, DOORS & WINDOW FRAME 100.00% ROOFING, ELEC WIRING & PLUMBING 100.00% INTERNAL &EXTERNAL PLASTERING 100.00% EARTHWORKS 100.00% FOUNDATION 100.00% R.C. FRAMEWORK 100.00% % of Cumulative Sales D/S Terrace 34,901,350.00 D/S Shop/Office 16,740,900.00 Monthly Total 54,461,770.00 Sale Projection D/S Low Cost 2,819,520.00 Q1 Q2 Description Amount (RM) 2013
  • 2. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M7 M8 M9 M10 M11 M12 50.0% 20.0% 10.0% 10.0% 10.0% 0.0% 0.0% 18.5% 0.0% 0.0% 9.5% 38.19% 38.19% 56.67% 56.67% 56.67% 66.15% 18.48% 9.48% 18.48% 9.48% 5.13% 5.13% 11.29% 11.29% 11.29% 9.48% 5.46% 5.46% 9.15% 9.15% 9.15% 13.89% 8.10% 8.10% 8.10% 10.47% 7.08% 8.44% 18.48% 9.48% 1,006,412.00 516,422.50 15.89% 18.48% 865,436.00 1,006,412.00 5.13% 5.13% 5.13% 11.29% 11.29% 11.29% 418,767.25 418,767.25 418,767.25 921,973.25 921,973.25 921,973.25 5.46% 5.46% 9.15% 9.15% 9.15% 297,126.50 297,126.50 498,408.90 498,408.90 498,408.90 8.10% 8.10% 8.10% 440,899.64 440,899.64 440,899.64 7.08% 385,787.19 1,284,203.25 715,893.75 1,722,305.75 2,867,693.79 1,861,281.79 2,763,491.48 5,185,763.00 5,901,656.75 7,623,962.50 10,491,656.29 12,352,938.09 15,116,429.57 3,722,402.75 7,492,467.07 7,623,962.50 15,116,429.57 Q3 Q4 2013
  • 3. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M13 M14 M15 M16 M17 M18 M19 M20 50.0% 20.0% 10.0% 20.0% 0.0% 0.0% 18.5% 0.0% 0.0% 6.1% 0.0% 0.0% 66.15% 66.15% 84.63% 84.63% 84.63% 90.78% 90.78% 90.78% 18.48% 6.15% 18.48% 6.15% 18.48% 6.15% 13.89% 18.48% 6.15% 10.47% 10.47% 28.95% 6.15% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21% 18.16% 18.16% 14.11% 15.33% 15.33% 15.33% 14.11% 14.11% 15.64% 15.64% 15.64% 18.48% 6.15% 1,006,412.00 334,818.00 9.5% 18.48% 6.15% 516,422.50 1,006,412.00 334,818.00 9.48% 18.48% 6.15% 774,633.75 1,509,618.00 502,227.00 13.89% 13.89% 18.48% 6.15% 756,620.15 756,620.15 1,006,412.00 334,818.00 10.47% 10.47% 10.47% 28.95% 6.15% 570,005.27 570,005.27 570,005.27 1,576,417.27 334,818.00 8.44% 8.44% 8.44% 13.06% 13.06% 13.06% 19.21% 459,561.83 459,561.83 459,561.83 711,164.83 711,164.83 711,164.83 1,045,982.83 18.16% 494,395.00 14.11% 15.33% 15.33% 192,047.17 208,788.07 208,788.07 3,077,243.50 1,786,187.25 2,035,979.10 5,810,024.10 711,164.83 1,238,030.00 2,761,451.90 703,183.07 18,193,673.06 19,979,860.31 22,015,839.41 27,825,863.51 28,537,028.34 29,775,058.34 32,536,510.23 33,239,693.30 6,899,409.84 7,759,218.93 22,015,839.41 29,775,058.34 Q1 Q2 Q3 2014
  • 4. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M21 M22 M23 M24 30.0% 9.2% 0.0% 0.0% 0.0% 100.00% 100.00% 100.00% 100.00% 9.22% 9.22% 9.22% 9.22% 9.22% 9.22% 21.23% 21.23% 21.23% 19.95% 19.95% 50.00% 50.00% 24.86% 9.22% 0.00% 502,227.00 - 9.22% 502,227.00 9.22% 753,340.50 9.22% 502,227.00 9.22% 502,227.00 9.22% 502,227.00 18.16% 21.23% 21.23% 21.23% 494,395.00 578,099.50 578,099.50 578,099.50 15.33% 19.95% 19.95% 208,788.07 271,566.44 271,566.44 50.00% 680,772.13 1,205,410.07 3,611,914.44 849,665.94 1,258,871.63 34,445,103.37 38,057,017.81 38,906,683.75 40,165,555.38 4,670,045.03 5,720,452.01 34,445,103.37 40,165,555.38 Q3 Q4 2014
  • 5. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M25 M26 M27 M28 M29 M30 M31 M32 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 50.00% 680,772.13 100.00% 9,530,809.75 100.00% 1,361,544.25 10,211,581.88 1,361,544.25 0 0 0 0 0 0 50,377,137.25 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 51,738,681.50 11,573,126.13 0 51,738,681.50 51,738,681.50 Q3Q1 Q2 2015
  • 6. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M33 M34 M35 M36 100.00% 100.00% 100.00% 100.00% 100.00% 1,361,544.25 1,361,544.25 0 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 1,361,544.25 0 53,100,225.75 53,100,225.75 Q3 Q4 2015
  • 7. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M37 M38 M39 M40 M41 M42 M43 M44 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 0 0 0 0 0 0 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 0 0 53,100,225.75 53,100,225.75 Q1 2016 Q2 Q3
  • 8. 4.0 Cash Flow for Project The cash flow for this project is based on ‘Sell-then-Build’ concept. The analysis is divided into three sections, which are cash inflow, cash outflow and quarter-yearly cashflow. PROJECTED CASH INFLOW FOR 2013-2016 Item 1 2 3 1 2 3 4 5 6 7 8 9 10 1 2 3 4 5 6 7 8 9 10 11 12 13 Quarterly Cummulative Cash Inflow Quarterly Total Cash Inflow Monthly Total Cash Flow Monthly Cummulative Cash Inflow On the date the Purchaser takes vacant possession of the said Property as in item 10 and to be held by the Developer’s solicitor as stakeholder for payment to the Developer as follows: (a) two point five per centum (2.5%) at the expiry of the period of eight (8) months after the date the Purchaser takes vacant possession of the said Property; and (Clause 5) (b) two point five per centum (2.5%) at the expiry of the period of twenty-four (24) months after the date the Purchaser takes vacant possession of the said Property (Clause 5) On the date the Purchaser takes vacant possession of the said Property as in item 10 where the Developer has delivered to the Purchaser or the Purchaser’s Solicitor the original issue document of title to the said Building Lot registered in the name of the Purchaser. (Clause 5) Roadworks On the date the Purchaser takes vacant possession of the said Property with water and electricity supply ready for connection. (Clause 5) Drainage works Internal &External plastering Sewerage works Roofing, Electrical wiring & plumbing R.C. Framwork Walls, Doors & Window frame Foundation Sales Proceeds Signing of S&P Agreement (Clause 5) INFRASTRUCTURE WORKS SEWERAGE WORKS DRAINAGE WORKS ROADWORKS WALLS, DOORS & WINDOW FRAME ROOFING, ELEC WIRING & PLUMBING INTERNAL &EXTERNAL PLASTERING EARTHWORKS FOUNDATION R.C. FRAMEWORK % of Cumulative Sales D/S Terrace D/S Shop/Office Monthly Total Sale Projection D/S Low Cost Description M45 M46 M47 M48 M49 M50 M51 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.00% 100.0% 1,361,544.25 0 0 0 0 1,361,544.25 0 0 53,100,225.75 53,100,225.75 53,100,225.75 53,100,225.75 54,461,770.00 54,461,770.00 54,461,770.00 0 0 1,361,544.25 53,100,225.75 53,100,225.75 54,461,770.00 2016 2017 Q1Q3 Q4