SlideShare a Scribd company logo
How Commercial Best Practices &
                                       Lessons Learned can Save the Feds
Copyright Green Data Center Alliance
     (http://www.greendca.org)
Agenda



               1                    About the GDCA



               2                    Lessons from the Commercial Sector



               3                   What the Feds Might Want to Consider


               4                    Three Project Examples



   Copyright Green Data Center Alliance
        (http://www.greendca.org)
                                                                          2
About Green Data Center Alliance (GDCA)


GDCA is over 10,000 individual
members from 114 countries
-Awarded Grant from NYSERDA to
design DCEEF
-Evaluated 3 Firms Against Model
-30% Increase in New Members over
2010
-2nd Call For Best Practices issued
-The DCEEF model has been
downloaded by over 2,000 Data Center
Professionals




         Copyright Green Data Center Alliance
              (http://www.greendca.org)         3
GDCA – NYSERDA Program


GDCA has completed a two year work effort under a grant from NYSERDA. The program
had two major goals
         1. Capture best practices at owner operator sites throughout the country
         2. Assess three organizations against the model and where possible provide
             potential projects for increased energy efficiency

What did this exercise teach us?
          - There are a dozens of ways to get to the same end point
          - Viewing the data center holistically works
          - Every data center has an opportunity to increase efficiency
          - Industry leaders actions can save others tremendous effort and cost




         Copyright Green Data Center Alliance
              (http://www.greendca.org)                                               4
Back to the FUTURE…



General Observations:

-   Federal Data Centers are roughly 5 to 10 years behind their commercial
    counterparts
-   Heavy reliance on Equipment Vendors instead of consultants for decision making
    -      Lots of Legacy Sites with Planned Migrations
    -      Most in Early to Mid Stages of Virtualization
    -      Most Employing High % Blade Strategy
-   Shared Federal Data Centers are not prepared for the folks moving into them
-   Most Best Practices for Design, Build & Retrofit are largely ignored
-   Relocation & Impact on Landing Site is also mostly ignored




    Copyright Green Data Center Alliance
         (http://www.greendca.org)                                                   5
What Happened in the Commercial Sector?

Two Data Center Build cycles; 7 to 10 years ago and again 2 to 4
   years ago – What Happened?

   - Virtualization & Blades

   - Fear of too hot, too cold

   - Electrical & Mechanical Capacity projections based on
      Name Plate data

   - Only Commercial Data Centers being built are Collocation
      Cloud Providers

   Copyright Green Data Center Alliance
        (http://www.greendca.org)                                  6
What They Do Now?

New Designs & Builds have basically stopped

Scrutiny of Projects & ROI shortened below 18 months

Went back to facilities and made simple retrofits to extend the life
   and capacity of their facilities

Market Leaders targeted PUE and Industry Data Center “Rules”
       and beat them

Others handed the keys to the collocation providers



   Copyright Green Data Center Alliance
        (http://www.greendca.org)                                      7
What the Federal Data Center Market Should
Consider
Slow Down…..Rushing through these decisions will quicken the
   pace of their impending doom

Look to simple fixes first to extend the life of the data center
   Morgan Stanley               Deutsche Bank
   Google                       Microsoft

Evaluate facilities strategically and compare options with TCO

Find Consultants that went through the commercial cycle

Relocations/Consolidations require tremendous data gathering
    exercises, put it into a DCIM
   Copyright Green Data Center Alliance
        (http://www.greendca.org)                                  8
The Old Way

  Example 1
  -8,000 sqft.
  -Paid Study @ roughly $10 per square foot for analysis (nearly 40 pages)
  -Thousands of points captured
  -Beautifully written, dozens of graphs, charts, tables and live models (40 to be exact)
  -Provided PUE, DCiE and several other industry metrics on power, temp and humidity

  Study SUGGESTED programs and ROI
  -Better align air temperature control to rack inlet air
  -Amend air volume
  -Play with dew point controls
  -Amend airflow to UPS rooms

  Cost of Implementation:                    $460,000
  Anticipated Annual Energy Savings:         $84,000 per year
  ROI                                        5.5 YEARS

  **** Does not include cost of study

  Copyright Green Data Center Alliance
       (http://www.greendca.org)                                                            9
Types of Actions:
Inexpensive (ROI < 24 Months)
  Example 2
  -One of 8 data center cells: 1,500 sqft cell for POC
  -Half a day to walk site, capture air speed and spot temps.
  -Half day to compile report into 2 page report/Scope
          - 4 (30) Ton Units Delivering 50,000 CFM or 500 kW IT load
          - Actual IT load 108 kW
          - Client had deployed 4 ft. Cold Aisle with 56% flow tiles
                - Over pressurized, lots of by pass air and recirculation

  Project & ROI
  -Better align air temperature control to rack inlet air by changing floor tiles
  -Amend air volume and rebalance floor after implementation

  Cost of Implementation:                      $15,000
  Anticipated Annual Energy Savings:           $25,000 per year
  ROI                                          7.5 MONTHS




   Copyright Green Data Center Alliance
        (http://www.greendca.org)                                                   10
The Best (ROI < 10 Months)

  Example 3 – Google “Point of Presence” Rooms equivalent to small data center
  -Optimized air flow through blanking, sealing gaps targeting trouble spots by changing floor
  tile configuration
  -Deploy cold aisle containment with curtains
  -Raise height of CRAC air return by 4 feet for more uniform return air temp
  -Increase temperature from 71 F to 81 F
  -Increase humidity range to accept 20 to 80% relative humidity
  -Able to reduce # of CRACs from 4 to 2
        -    Their cold aisle was actually cooler with the thermostat turned up and half the CRACs running

  Project & ROI
  Cost of Implementation:                       $25,000
  Anticipated Annual Energy Savings:            $67,000 per year
  ROI                                           2.7 MONTHS

  PUE dropped from 2.4 to 1.5 in 5 rooms



  Copyright Green Data Center Alliance
       (http://www.greendca.org)                                                                             11
The Best (ROI < 10 Months)

  Example 3 – Google “Point of Presence” Rooms equivalent to small data center
  -Optimized air flow through blanking, sealing gaps targeting trouble spots by changing floor
  tile configuration
  -Deploy cold aisle containment with curtains
  -Raise height of CRAC air return by 4 feet for more uniform return air temp
  -Increase temperature from 71 F to 81 F
  -Increase humidity range to accept 20 to 80% relative humidity
  -Able to reduce # of CRACs from 4 to 2
        -    Their cold aisle was actually cooler with the thermostat turned up and half the CRACs running

  Project & ROI
  Cost of Implementation:                       $25,000
  Anticipated Annual Energy Savings:            $67,000 per year
  ROI                                           2.7 MONTHS

  PUE dropped from 2.4 to 1.5 in 5 rooms



  Copyright Green Data Center Alliance
       (http://www.greendca.org)                                                                             12
Questions?




   Copyright Green Data Center Alliance
        (http://www.greendca.org)         13

More Related Content

PPT
Oracle and the Green Data Center
PDF
Grow a Greener Data Center
PDF
Green it at university of bahrain
PDF
Can the Cloud Be Green?
PPTX
American Institute of Architects Committee on the Envrinment
PDF
Air Flow Presentation Pdf
PPTX
Cold-Climate Research Round-Up
PPT
The next wave of GreenIT
Oracle and the Green Data Center
Grow a Greener Data Center
Green it at university of bahrain
Can the Cloud Be Green?
American Institute of Architects Committee on the Envrinment
Air Flow Presentation Pdf
Cold-Climate Research Round-Up
The next wave of GreenIT

What's hot (20)

PPTX
Consolidate, Virtualize, Energize
DOCX
Dr Callum Rae - A New Approach to Energy Centre Design
PDF
Energy Saving by Migrating Virtual Machine to Green Cloud Computing
PDF
GREEN CLOUD COMPUTING-A Data Center Approach
PPT
It Presentation 2011 Santa Clara1
PDF
Improved performance through carbon aware green cloud policy
PDF
Proof of Concept for Hadoop: storage and analytics of electrical time-series
PDF
Air Flow Presentation 0218
PPTX
Green cloud computing India
PDF
Meet the Data Processing Workflow Challenges of Oil and Gas Exploration with ...
PPTX
Green Data Centre for banks
PDF
High-Performance Storage for the Evolving Computational Requirements of Energ...
PPTX
Strategic Air Planning: Is the Time for a PAL Here?
PDF
Dr. Dan Arvizu
KEY
Green IT Concept
PDF
11.need of green computing measures for indian it industry
PDF
Need of green computing measures for indian it industry
PPT
Green cloud computing
PPTX
Project GreenLight
PPTX
GREEN CLOUD COMPUTING BY SAIKIRAN PANJALA
Consolidate, Virtualize, Energize
Dr Callum Rae - A New Approach to Energy Centre Design
Energy Saving by Migrating Virtual Machine to Green Cloud Computing
GREEN CLOUD COMPUTING-A Data Center Approach
It Presentation 2011 Santa Clara1
Improved performance through carbon aware green cloud policy
Proof of Concept for Hadoop: storage and analytics of electrical time-series
Air Flow Presentation 0218
Green cloud computing India
Meet the Data Processing Workflow Challenges of Oil and Gas Exploration with ...
Green Data Centre for banks
High-Performance Storage for the Evolving Computational Requirements of Energ...
Strategic Air Planning: Is the Time for a PAL Here?
Dr. Dan Arvizu
Green IT Concept
11.need of green computing measures for indian it industry
Need of green computing measures for indian it industry
Green cloud computing
Project GreenLight
GREEN CLOUD COMPUTING BY SAIKIRAN PANJALA
Ad

Viewers also liked (18)

PPT
Pbj[1]
PPTX
Mark Mac Auley Data Center Marketplace Event
PPTX
Nuvalo Nephophobia Seattle 2011
PPTX
Future Of The Data Center Sept 29 Preso Final
PPTX
Patrick Costello Green Guide Presentation Final 032112
PPTX
Siemon Carrie Higbie
PPTX
Dcm Program
PPTX
Iron Mountain Presentation How Well Do You Know Your Data Seattle 2011
PPTX
Schneider Alex Kretschmer Presentation Deck Facility Modules Nyc Sept 2011
PPTX
Schneider Alex Kretschmer Presentation Deck Facility Modules Nyc Sept 2011
PPTX
Vigilent Jeffrey Hecht Presentation Deck
PPT
Raritan Data Center Marketplace Pue
PPT
Powerpoint voor bijspijkerles
PPTX
Schneider Presentation Seattle 2011
PPTX
Creative cv
PPTX
Sustainability reporting updated
PPSX
Placa Mãe
PDF
Empathy In The Workplace
Pbj[1]
Mark Mac Auley Data Center Marketplace Event
Nuvalo Nephophobia Seattle 2011
Future Of The Data Center Sept 29 Preso Final
Patrick Costello Green Guide Presentation Final 032112
Siemon Carrie Higbie
Dcm Program
Iron Mountain Presentation How Well Do You Know Your Data Seattle 2011
Schneider Alex Kretschmer Presentation Deck Facility Modules Nyc Sept 2011
Schneider Alex Kretschmer Presentation Deck Facility Modules Nyc Sept 2011
Vigilent Jeffrey Hecht Presentation Deck
Raritan Data Center Marketplace Pue
Powerpoint voor bijspijkerles
Schneider Presentation Seattle 2011
Creative cv
Sustainability reporting updated
Placa Mãe
Empathy In The Workplace
Ad

Similar to Derek Schwartz Fed Lessons Learned.Final (20)

PDF
Embracing Change with Green IT
PPT
Building a Sustainable Data Center
PPTX
Retrofit, build, or go cloud/colo? Choosing your best direction
PPTX
Retrofit, build, or go cloud/colo? Choosing your best direction
PPTX
Green Cloud Computing
PPT
IBM and GREEN IT; Green IT – How to Make IT Work and Save Money
PPTX
Google ppt. mis
PDF
Improvements in Data Center Management
PDF
Austin Data Center Project Feasibility Study TACC SECO Final Feasibility Repo...
PPT
Green data center_rahul ppt
PPTX
Supermicro and The Green Grid (TGG)
PPT
Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...
PPTX
Green bond fund opportunities for NRENs and universities 2016
PPTX
Unlock Your Buildings Hidden Energy Data - Corenet Seattle
PPT
Environmental Sustainability - Green IT
PPTX
Greencomputing
PDF
Harel Kodesh, Vice President, Predix and CTO, GE Digital
PPTX
Energy Efficiency in Data Centers
PPT
GREEN_CLOUD_COMPUTING.ppt
Embracing Change with Green IT
Building a Sustainable Data Center
Retrofit, build, or go cloud/colo? Choosing your best direction
Retrofit, build, or go cloud/colo? Choosing your best direction
Green Cloud Computing
IBM and GREEN IT; Green IT – How to Make IT Work and Save Money
Google ppt. mis
Improvements in Data Center Management
Austin Data Center Project Feasibility Study TACC SECO Final Feasibility Repo...
Green data center_rahul ppt
Supermicro and The Green Grid (TGG)
Green & Beyond: Data Center Actions to Increase Business Responsiveness and R...
Green bond fund opportunities for NRENs and universities 2016
Unlock Your Buildings Hidden Energy Data - Corenet Seattle
Environmental Sustainability - Green IT
Greencomputing
Harel Kodesh, Vice President, Predix and CTO, GE Digital
Energy Efficiency in Data Centers
GREEN_CLOUD_COMPUTING.ppt

Derek Schwartz Fed Lessons Learned.Final

  • 1. How Commercial Best Practices & Lessons Learned can Save the Feds Copyright Green Data Center Alliance (http://www.greendca.org)
  • 2. Agenda 1 About the GDCA 2 Lessons from the Commercial Sector 3 What the Feds Might Want to Consider 4 Three Project Examples Copyright Green Data Center Alliance (http://www.greendca.org) 2
  • 3. About Green Data Center Alliance (GDCA) GDCA is over 10,000 individual members from 114 countries -Awarded Grant from NYSERDA to design DCEEF -Evaluated 3 Firms Against Model -30% Increase in New Members over 2010 -2nd Call For Best Practices issued -The DCEEF model has been downloaded by over 2,000 Data Center Professionals Copyright Green Data Center Alliance (http://www.greendca.org) 3
  • 4. GDCA – NYSERDA Program GDCA has completed a two year work effort under a grant from NYSERDA. The program had two major goals 1. Capture best practices at owner operator sites throughout the country 2. Assess three organizations against the model and where possible provide potential projects for increased energy efficiency What did this exercise teach us? - There are a dozens of ways to get to the same end point - Viewing the data center holistically works - Every data center has an opportunity to increase efficiency - Industry leaders actions can save others tremendous effort and cost Copyright Green Data Center Alliance (http://www.greendca.org) 4
  • 5. Back to the FUTURE… General Observations: - Federal Data Centers are roughly 5 to 10 years behind their commercial counterparts - Heavy reliance on Equipment Vendors instead of consultants for decision making - Lots of Legacy Sites with Planned Migrations - Most in Early to Mid Stages of Virtualization - Most Employing High % Blade Strategy - Shared Federal Data Centers are not prepared for the folks moving into them - Most Best Practices for Design, Build & Retrofit are largely ignored - Relocation & Impact on Landing Site is also mostly ignored Copyright Green Data Center Alliance (http://www.greendca.org) 5
  • 6. What Happened in the Commercial Sector? Two Data Center Build cycles; 7 to 10 years ago and again 2 to 4 years ago – What Happened? - Virtualization & Blades - Fear of too hot, too cold - Electrical & Mechanical Capacity projections based on Name Plate data - Only Commercial Data Centers being built are Collocation Cloud Providers Copyright Green Data Center Alliance (http://www.greendca.org) 6
  • 7. What They Do Now? New Designs & Builds have basically stopped Scrutiny of Projects & ROI shortened below 18 months Went back to facilities and made simple retrofits to extend the life and capacity of their facilities Market Leaders targeted PUE and Industry Data Center “Rules” and beat them Others handed the keys to the collocation providers Copyright Green Data Center Alliance (http://www.greendca.org) 7
  • 8. What the Federal Data Center Market Should Consider Slow Down…..Rushing through these decisions will quicken the pace of their impending doom Look to simple fixes first to extend the life of the data center Morgan Stanley Deutsche Bank Google Microsoft Evaluate facilities strategically and compare options with TCO Find Consultants that went through the commercial cycle Relocations/Consolidations require tremendous data gathering exercises, put it into a DCIM Copyright Green Data Center Alliance (http://www.greendca.org) 8
  • 9. The Old Way Example 1 -8,000 sqft. -Paid Study @ roughly $10 per square foot for analysis (nearly 40 pages) -Thousands of points captured -Beautifully written, dozens of graphs, charts, tables and live models (40 to be exact) -Provided PUE, DCiE and several other industry metrics on power, temp and humidity Study SUGGESTED programs and ROI -Better align air temperature control to rack inlet air -Amend air volume -Play with dew point controls -Amend airflow to UPS rooms Cost of Implementation: $460,000 Anticipated Annual Energy Savings: $84,000 per year ROI 5.5 YEARS **** Does not include cost of study Copyright Green Data Center Alliance (http://www.greendca.org) 9
  • 10. Types of Actions: Inexpensive (ROI < 24 Months) Example 2 -One of 8 data center cells: 1,500 sqft cell for POC -Half a day to walk site, capture air speed and spot temps. -Half day to compile report into 2 page report/Scope - 4 (30) Ton Units Delivering 50,000 CFM or 500 kW IT load - Actual IT load 108 kW - Client had deployed 4 ft. Cold Aisle with 56% flow tiles - Over pressurized, lots of by pass air and recirculation Project & ROI -Better align air temperature control to rack inlet air by changing floor tiles -Amend air volume and rebalance floor after implementation Cost of Implementation: $15,000 Anticipated Annual Energy Savings: $25,000 per year ROI 7.5 MONTHS Copyright Green Data Center Alliance (http://www.greendca.org) 10
  • 11. The Best (ROI < 10 Months) Example 3 – Google “Point of Presence” Rooms equivalent to small data center -Optimized air flow through blanking, sealing gaps targeting trouble spots by changing floor tile configuration -Deploy cold aisle containment with curtains -Raise height of CRAC air return by 4 feet for more uniform return air temp -Increase temperature from 71 F to 81 F -Increase humidity range to accept 20 to 80% relative humidity -Able to reduce # of CRACs from 4 to 2 - Their cold aisle was actually cooler with the thermostat turned up and half the CRACs running Project & ROI Cost of Implementation: $25,000 Anticipated Annual Energy Savings: $67,000 per year ROI 2.7 MONTHS PUE dropped from 2.4 to 1.5 in 5 rooms Copyright Green Data Center Alliance (http://www.greendca.org) 11
  • 12. The Best (ROI < 10 Months) Example 3 – Google “Point of Presence” Rooms equivalent to small data center -Optimized air flow through blanking, sealing gaps targeting trouble spots by changing floor tile configuration -Deploy cold aisle containment with curtains -Raise height of CRAC air return by 4 feet for more uniform return air temp -Increase temperature from 71 F to 81 F -Increase humidity range to accept 20 to 80% relative humidity -Able to reduce # of CRACs from 4 to 2 - Their cold aisle was actually cooler with the thermostat turned up and half the CRACs running Project & ROI Cost of Implementation: $25,000 Anticipated Annual Energy Savings: $67,000 per year ROI 2.7 MONTHS PUE dropped from 2.4 to 1.5 in 5 rooms Copyright Green Data Center Alliance (http://www.greendca.org) 12
  • 13. Questions? Copyright Green Data Center Alliance (http://www.greendca.org) 13

Editor's Notes

  • #4: The Green Data Center Alliance started in accumulating members in June of 2008 and has steadily grown over the last three years. The award of an Innovation grant from NYSERDA helped us remain current and helped us gain access to hundreds of data center professionals. This engagement also included 3 evaluations against the model, and while not all participants chose to augment their space we learned a great deal about how organizations approach the space from all angles. We average 50 new individuals a week so interest in this topic does not seem to be waning and we hope to be part of the discussion for years to come. We are currently collecting our second round of best practices from end users and vendors and look forward to releasing the second revision by Fall of 2012.
  • #5: The Green Data Center Alliance started in accumulating members in June of 2008 and has steadily grown over the last three years. The award of an Innovation grant from NYSERDA helped us remain current and helped us gain access to hundreds of data center professionals. This engagement also included 3 evaluations against the model, and while not all participants chose to augment their space we learned a great deal about how organizations approach the space from all angles. We average 50 new individuals a week so interest in this topic does not seem to be waning and we hope to be part of the discussion for years to come. We are currently collecting our second round of best practices from end users and vendors and look forward to releasing the second revision by Fall of 2012.
  • #6: The Green Data Center Alliance started in accumulating members in June of 2008 and has steadily grown over the last three years. The award of an Innovation grant from NYSERDA helped us remain current and helped us gain access to hundreds of data center professionals. This engagement also included 3 evaluations against the model, and while not all participants chose to augment their space we learned a great deal about how organizations approach the space from all angles. We average 50 new individuals a week so interest in this topic does not seem to be waning and we hope to be part of the discussion for years to come. We are currently collecting our second round of best practices from end users and vendors and look forward to releasing the second revision by Fall of 2012.
  • #14: We have learned that entering the organization in one of the 5 silos forces several things: