Basic Principles of
   Project Management
               RLDC 1
            Barry Cordero
             SHPE National VP
Principal Project Engineer, Medtronic Inc.
    Master Black Belt: Lean Six Sigma
“It takes as much energy to wish as it
does to plan”

Eleanor Roosevelt
Project Management


• Goals/Obj           Execute             • Control Plan
• Tasks/Owners                            • Schedule
                 • Manage Critical Path
• Resources
                 • Solve Problems
• Deadlines
                 • Adjust Plan
                 • Phase Reviews

         Plan                                   Control
Importance of Planning
The Project Planning Cycle
                            Background




         Plan of                                Current
         Action                                  State




                   Future
                                         Goal
                    State
Other Project Cycles
              Define                       Plan

Control                    Measure
             Lean
          Six - Sigma                Act    TPS    Do


    Improve            Analyze             Check
Essential Components of Planning
   Goal                                  Background

   Objectives
     SMART            Plan of                                Current
                      Action                                  State
   Tasks
     Specific items
     Owners
     Deadlines                  Future
                                                      Goal
                                 State
     Resources
DEFINING THE PROBLEM
(BACKGROUND AND CURRENT
STATE)
PM Role
Is the role of the PM to describe your ideas and
plan in order…
      -- to convince?
      -- or to engage?
Convince means to “sell” or “get buy in”


Engage means to “become part of”
    -- to invite to take part in the thinking
    -- and the experiment based on it

                                                   9
What is our natural tendency?



    Perception     BLACK
       of a        HOLE      The
     Problem               SOLUTION

   Impressions &
                   FACTS
    Assumptions             Theory
How can we be more effective?
   Ask questions to help ourselves see:
     What is Actually Happening?
     What do I actually know?

                    FACTS
    The Real        FACTS
     or Main                          A
    Problem         FACTS          SOLUTION
                    FACTS
   Impressions &
    Assumptions                     Theory
                                              11
3 Common Mistakes in Problem Solving
   1. Assuming you know what the problem is
      without seeing what is actually happening.

   2. Assuming you know how to fix a problem
      without finding out what is causing it.

   3. Assuming you know what is causing the
      problem without confirming it.

   In other words - Not Grasping the Situation.
   (And where do we grasp the situation?
      At the gemba!)                               12
Maintain a Questioning Mind
• What do you actually know?
         How do you know it?

• What do you need to know?
        How can you learn it?

• Avoid acting on assumptions or
jumping to conclusions.
                                   13
Keys to a good problem statement
   Purely a problem
   Explains why problem is relevant to
   business/chapter
   Does not include a solution
     Avoid “lack of” statements
   Avoids assumptions
   Can be visual
Example Bad Problem Statements
   “lack of professional development opportunities
   causes low member retention”
   “Company x minority representation is poor.”
   “process z yield is low due to inattention to detail
   by process inspectors”
Example Good Problem Statements
   “member retention is very low, minimizing the
   strength of networking and the ability to develop
   chapter leaders”
   “technical Hispanics at company x stay for an
   average of 3 years. This attributes to low
   Hispanic representation at all levels in the
   company.”
   “process z yield has dropped from 98% to 92%
   over the past year, resulting in increased cost of
   goods and additional labor”
CLASS EXAMPLE
EXERCISE: WRITE A PROBLEM
STATEMENT
Writing your A3: Background
   Why are you solving
   this problem?

   Why is this problem
   important? How is it
   contributing to the
   company’s need?

   Keep it simple
DESCRIBING CURRENT STATE
Describe your Current State/Gap
   Be visual
   Show process map
   Show graphs
   Show charts
“A Problem Clearly Defined Is Half Solved”
    What do we mean by “clearly defined”?
  • Gap between what is actually happening
    (current condition) and what should/needs to be
    happening described in performance terms.
  • Gap broken down to concrete, observable
    conditions (smaller problems in the gap or in the
    related work processes) that are contributing to
    the Gap & can be investigated first hand?
                                                        22
A GAP: 2 types of Gaps




                         Created
                           GAP




                         Caused
                          GAP




                                   23
SWOT Analysis
  Provides clarity as a board
  Provides opportunity to reach out to
  your stakeholders
  Drives your strategic plan
  Provides platform for goal making
SWOT Analysis
                                      Strengths                                 Weaknesses
                      -   Strong relationships with…..             -   Small Budget
                      -   Large membership base                    -   Unknown Academic….
   Internal Factors




                      -   Tradition of….                           -   Programs are inconsistent
                      -   Only engineering society for Latinos




                                    Opportunities                                  Threats
                      -   Neighboring town X has high Hispanic     -   Current sponsorships teetering
                          population                               -   Economic environment
   External Factors




                      -   Company X,Y,Z has shown interest in      -   Programs are inconsistent
                          chapter programs
                      -   Partnership interest from NSBE chapter
                          locally
                      -
Example
SHOW EXAMPLE
EXERCISE: DEFINE YOUR OWN
CURRENT STATE
Writing your A3: Current Conditions
   Describe the current situation vs the
   desired situation and quantify the gap
SETTING MEASUREABLE
GOALS
Write your Goal/Target
 Consider SMART
   Specific
                                                         Goals/Targets



   Measurable
                                                            What specific outcomes are required to close the gap?
                                                            What is the target condition?
    • Numbers oriented, can tell if you achieved it         Is your goal S.M.A.R.T?


   Attainable
    • Within you or your team’s scope of influence

   Relevant
    • Related to the problem statement or gap

   Timely
    • If you are ready, assign a date to it (by when?)

Avoid words like “Create, Implement, Develop”
Goal/Target

           IS                        Is NOT
SMART                        Restating your solution
Addresses a problem in       “Workers will oil the
performance                  machine daily”
“Will prevent the bearing
from wearing out too         A statement of a possible
frequently”                  countermeasure
Stated as SMART as           “Implement standard work”
possible                     “Implement Robust Design”
“Increase performance from
50 hours to 300 hours
without wear 100% of the
time”
EXERCISE: WRITE A GOAL
STATEMENT
ANALYZE THE PROBLEM
34
Choosing the right Analysis Tool
   What tool might     Consider:
   you choose for:
     Quality issue?      – SPC, Pareto, Six Sigma
                           project guide

     Delivery Issue?     – VSM, Process Map, Flow
                           Chart, PFM, SOE, Lean
                           Project Guide
     Productivity        – Balance chart, pareto
     Issue?
                         – Pie chart, fishbone, swim
     Cost Issue?           lane
Analyze
   Technical Problems
     Perform hypothesis testing
     Do experiments
     Collect data
     Determine root cause
   Business Problems
     Root cause analysis
     Share with stakeholders
COUNTERMEASURES
Problems and Solutions and Countermeasures
    The Solution?
      To solve = to find the answer…..the One correct answer


    A Countermeasure?
      To resolve = to find and try out an action that seems
      likely to reduce the problem condition (the GAP)
        • A temporary measure “fixes” a problem by blocking or working
          around its impact
        • A permanent countermeasure eliminates a problem by removing
          its cause

                                                                    38
What to look for in Recommendations for Countermeasures
  1. Do I see the link between your proposed
     countermeasures and the causes they are
     intended to address?
  2. Do I feel you have considered all the options for
     addressing the causes?
  3. Do your recommended countermeasures make
     sense as the way to address the causes and
     resolve the problem?
  4. Am I confident these countermeasures will
     accomplish your goals and achieve your purpose
     for addressing the problem?                         39
Countermeasure Evaluation
COUNTERMEASURES TO
PROJECT PLANS
Drive backward: Networking Diagram
   Each completed countermeasure as a
   milestone
   Use mind mapping to determine
   predecessors to completed milestones
   Build dependencies
   Add in dates and task owners
Networking Diagram: Example

                                        Survey Members on
                                              needs

                     Develop Program

    Professional                            Place Bids
   Development
 Workshops Monthly

                                        Survey members for
                     Acquire Location
                                           free locations
Convert to Project Plan
   Use MS Project if you want
   Or use Excel
Excel Example
                  Dates: June 1-7 June 8-17 June 15-21 June 22-28 Jun29-Jul5 Jul 6-13
DEFINE
Agree on charter
Gather more VOC
Define Phase Review
Enter project in QTRAK

MEASURE
Develop Project Strategy
MSA
Baseline Capability
Process Map / VSM
Fishbone (C&E Diagram)
C&E Matrix
XIA
Data Collection Plan
Collect data
Update Charter, if needed
Optional M Phase Rev.

ANALYZE
Analysis plan
Verify Key X's
Finalize Charter
Analyze Phase Rev.

IMPROVE
Define Improvements
Optimize Improvements
The Plan In Place
   Half of work should be done

   Now it’s time to manage
Thank You
  Questions?

  Barry.Cordero@shpe.org
References
   Lean Enterprise Institute
     “Managing to Learn” John Shook
   Project Management Book of
   Knowledge (loosely)

More Related Content

PDF
Institute small-business-payroll-report
PDF
Offenberg.joel
PDF
T4 case analysis_workbook_may_2011
PPT
Mulenburg.jerry
PPTX
Type/MBTI and Project Management
PPTX
Tools and Techniques for Project Management
PDF
Intro To Consulting Prework 1
PDF
Becoming Effective Problem Solvers
Institute small-business-payroll-report
Offenberg.joel
T4 case analysis_workbook_may_2011
Mulenburg.jerry
Type/MBTI and Project Management
Tools and Techniques for Project Management
Intro To Consulting Prework 1
Becoming Effective Problem Solvers

What's hot (20)

PPTX
House.cindy
PPTX
Style matters in project management
PDF
Agile in the Bathtub
PDF
GRA - Scenario Planning: Addressing a Capability Gap Affecting Industry Compe...
PPTX
An Overview of Scenario Planning - Introduction, Overview and Examples
PPTX
Risky Business: Super Charging Strategic Plans with New Risk Management Tools
PPTX
P6 Advantages Final 20100715 Raj
PPT
Scenario Planning Linking Scenarios to Strategy
PDF
Kremer Executive
PDF
Rosenberg.i.blackwood.g
PPTX
Crash Course in Scenario Planning
PPT
Strategic planning gsw
PDF
Project Management | Why do projects fail?
PDF
JETPACK Scenario Planning Module
PDF
Scenario Planning PowerPoint Presentation Slides
PPTX
Strategic planning that works
PDF
Problem Solving
PDF
Flevy.com - Six Sigma Basics
PPTX
Agile Adoption and Initiation
PPTX
John marinaro pm_process
House.cindy
Style matters in project management
Agile in the Bathtub
GRA - Scenario Planning: Addressing a Capability Gap Affecting Industry Compe...
An Overview of Scenario Planning - Introduction, Overview and Examples
Risky Business: Super Charging Strategic Plans with New Risk Management Tools
P6 Advantages Final 20100715 Raj
Scenario Planning Linking Scenarios to Strategy
Kremer Executive
Rosenberg.i.blackwood.g
Crash Course in Scenario Planning
Strategic planning gsw
Project Management | Why do projects fail?
JETPACK Scenario Planning Module
Scenario Planning PowerPoint Presentation Slides
Strategic planning that works
Problem Solving
Flevy.com - Six Sigma Basics
Agile Adoption and Initiation
John marinaro pm_process
Ad

Viewers also liked (10)

PPT
PPT
Chap 6 Developing A Project Plan
PPTX
CRTA Network Project Summer 2011
PDF
Microsoft Project Network Diagram
PPTX
The Project Network - Service Offering
PPT
Project Plan Development - A FlackVentures Training Example
PPT
PM Session 5
PPT
Demand forecasting 12
PPTX
Practical Project Management - full course
PPSX
Project network scheduling and S-curve
Chap 6 Developing A Project Plan
CRTA Network Project Summer 2011
Microsoft Project Network Diagram
The Project Network - Service Offering
Project Plan Development - A FlackVentures Training Example
PM Session 5
Demand forecasting 12
Practical Project Management - full course
Project network scheduling and S-curve
Ad

Similar to Developing a Project Plan (20)

PPTX
Building a problem solving organization
PPT
Decision making & problem solving
PPTX
developing problem solving skills
PPTX
In Chuck Norris we trust - A3 thinking intro
PPTX
Problems, Opportunities and Decisions
PPT
Unit a
PPT
Cusersibrahimdesktopproblemsolvinganddecisionmaking 090321143622 Phpapp01
PPT
Problem Solving and Decision Making
PPTX
Problem Management - Systematic Approach
PPTX
Problem Solving & Decision Making Training.pptx
PPT
PPT
Problem Solving PowerPoint PPT Content Modern Sample
PPTX
Career Development In a Box GDC Online 2011
PDF
Problem Solving & Critical Thinking
PDF
Flevy.com - Structured Problem Solving & Hypothesis Generation
PPTX
Change management
PPTX
Koios - Collective Intelligence and Crowd sourcing for public good
PDF
Strategic planning.natyogachandra,oct,11, 2008
Building a problem solving organization
Decision making & problem solving
developing problem solving skills
In Chuck Norris we trust - A3 thinking intro
Problems, Opportunities and Decisions
Unit a
Cusersibrahimdesktopproblemsolvinganddecisionmaking 090321143622 Phpapp01
Problem Solving and Decision Making
Problem Management - Systematic Approach
Problem Solving & Decision Making Training.pptx
Problem Solving PowerPoint PPT Content Modern Sample
Career Development In a Box GDC Online 2011
Problem Solving & Critical Thinking
Flevy.com - Structured Problem Solving & Hypothesis Generation
Change management
Koios - Collective Intelligence and Crowd sourcing for public good
Strategic planning.natyogachandra,oct,11, 2008

More from barrycordero (8)

PPT
Waking Giants: US Latino's growing opportunity in philanthropy
PPT
Personal strategic planning March 2015
PPT
Business Case for Diversity: Diversity and Global Competitiveness
PPT
SHPE NILA Speech 2012
PPTX
SHPE Time Management
PPT
Strategic Planning Workshop 08.07.10
PPSX
SHPE 2010 Professional Development Presentation
PPT
Shpe Presentation To Medtronic 9.16.09
Waking Giants: US Latino's growing opportunity in philanthropy
Personal strategic planning March 2015
Business Case for Diversity: Diversity and Global Competitiveness
SHPE NILA Speech 2012
SHPE Time Management
Strategic Planning Workshop 08.07.10
SHPE 2010 Professional Development Presentation
Shpe Presentation To Medtronic 9.16.09

Developing a Project Plan

  • 1. Basic Principles of Project Management RLDC 1 Barry Cordero SHPE National VP Principal Project Engineer, Medtronic Inc. Master Black Belt: Lean Six Sigma
  • 2. “It takes as much energy to wish as it does to plan” Eleanor Roosevelt
  • 3. Project Management • Goals/Obj Execute • Control Plan • Tasks/Owners • Schedule • Manage Critical Path • Resources • Solve Problems • Deadlines • Adjust Plan • Phase Reviews Plan Control
  • 5. The Project Planning Cycle Background Plan of Current Action State Future Goal State
  • 6. Other Project Cycles Define Plan Control Measure Lean Six - Sigma Act TPS Do Improve Analyze Check
  • 7. Essential Components of Planning Goal Background Objectives SMART Plan of Current Action State Tasks Specific items Owners Deadlines Future Goal State Resources
  • 8. DEFINING THE PROBLEM (BACKGROUND AND CURRENT STATE)
  • 9. PM Role Is the role of the PM to describe your ideas and plan in order… -- to convince? -- or to engage? Convince means to “sell” or “get buy in” Engage means to “become part of” -- to invite to take part in the thinking -- and the experiment based on it 9
  • 10. What is our natural tendency? Perception BLACK of a HOLE The Problem SOLUTION Impressions & FACTS Assumptions Theory
  • 11. How can we be more effective? Ask questions to help ourselves see: What is Actually Happening? What do I actually know? FACTS The Real FACTS or Main A Problem FACTS SOLUTION FACTS Impressions & Assumptions Theory 11
  • 12. 3 Common Mistakes in Problem Solving 1. Assuming you know what the problem is without seeing what is actually happening. 2. Assuming you know how to fix a problem without finding out what is causing it. 3. Assuming you know what is causing the problem without confirming it. In other words - Not Grasping the Situation. (And where do we grasp the situation? At the gemba!) 12
  • 13. Maintain a Questioning Mind • What do you actually know?  How do you know it? • What do you need to know? How can you learn it? • Avoid acting on assumptions or jumping to conclusions. 13
  • 14. Keys to a good problem statement Purely a problem Explains why problem is relevant to business/chapter Does not include a solution Avoid “lack of” statements Avoids assumptions Can be visual
  • 15. Example Bad Problem Statements “lack of professional development opportunities causes low member retention” “Company x minority representation is poor.” “process z yield is low due to inattention to detail by process inspectors”
  • 16. Example Good Problem Statements “member retention is very low, minimizing the strength of networking and the ability to develop chapter leaders” “technical Hispanics at company x stay for an average of 3 years. This attributes to low Hispanic representation at all levels in the company.” “process z yield has dropped from 98% to 92% over the past year, resulting in increased cost of goods and additional labor”
  • 18. EXERCISE: WRITE A PROBLEM STATEMENT
  • 19. Writing your A3: Background Why are you solving this problem? Why is this problem important? How is it contributing to the company’s need? Keep it simple
  • 21. Describe your Current State/Gap Be visual Show process map Show graphs Show charts
  • 22. “A Problem Clearly Defined Is Half Solved” What do we mean by “clearly defined”? • Gap between what is actually happening (current condition) and what should/needs to be happening described in performance terms. • Gap broken down to concrete, observable conditions (smaller problems in the gap or in the related work processes) that are contributing to the Gap & can be investigated first hand? 22
  • 23. A GAP: 2 types of Gaps Created GAP Caused GAP 23
  • 24. SWOT Analysis Provides clarity as a board Provides opportunity to reach out to your stakeholders Drives your strategic plan Provides platform for goal making
  • 25. SWOT Analysis Strengths Weaknesses - Strong relationships with….. - Small Budget - Large membership base - Unknown Academic…. Internal Factors - Tradition of…. - Programs are inconsistent - Only engineering society for Latinos Opportunities Threats - Neighboring town X has high Hispanic - Current sponsorships teetering population - Economic environment External Factors - Company X,Y,Z has shown interest in - Programs are inconsistent chapter programs - Partnership interest from NSBE chapter locally -
  • 27. SHOW EXAMPLE EXERCISE: DEFINE YOUR OWN CURRENT STATE
  • 28. Writing your A3: Current Conditions Describe the current situation vs the desired situation and quantify the gap
  • 30. Write your Goal/Target Consider SMART Specific Goals/Targets Measurable What specific outcomes are required to close the gap? What is the target condition? • Numbers oriented, can tell if you achieved it Is your goal S.M.A.R.T? Attainable • Within you or your team’s scope of influence Relevant • Related to the problem statement or gap Timely • If you are ready, assign a date to it (by when?) Avoid words like “Create, Implement, Develop”
  • 31. Goal/Target IS Is NOT SMART Restating your solution Addresses a problem in “Workers will oil the performance machine daily” “Will prevent the bearing from wearing out too A statement of a possible frequently” countermeasure Stated as SMART as “Implement standard work” possible “Implement Robust Design” “Increase performance from 50 hours to 300 hours without wear 100% of the time”
  • 32. EXERCISE: WRITE A GOAL STATEMENT
  • 34. 34
  • 35. Choosing the right Analysis Tool What tool might Consider: you choose for: Quality issue? – SPC, Pareto, Six Sigma project guide Delivery Issue? – VSM, Process Map, Flow Chart, PFM, SOE, Lean Project Guide Productivity – Balance chart, pareto Issue? – Pie chart, fishbone, swim Cost Issue? lane
  • 36. Analyze Technical Problems Perform hypothesis testing Do experiments Collect data Determine root cause Business Problems Root cause analysis Share with stakeholders
  • 38. Problems and Solutions and Countermeasures The Solution? To solve = to find the answer…..the One correct answer A Countermeasure? To resolve = to find and try out an action that seems likely to reduce the problem condition (the GAP) • A temporary measure “fixes” a problem by blocking or working around its impact • A permanent countermeasure eliminates a problem by removing its cause 38
  • 39. What to look for in Recommendations for Countermeasures 1. Do I see the link between your proposed countermeasures and the causes they are intended to address? 2. Do I feel you have considered all the options for addressing the causes? 3. Do your recommended countermeasures make sense as the way to address the causes and resolve the problem? 4. Am I confident these countermeasures will accomplish your goals and achieve your purpose for addressing the problem? 39
  • 42. Drive backward: Networking Diagram Each completed countermeasure as a milestone Use mind mapping to determine predecessors to completed milestones Build dependencies Add in dates and task owners
  • 43. Networking Diagram: Example Survey Members on needs Develop Program Professional Place Bids Development Workshops Monthly Survey members for Acquire Location free locations
  • 44. Convert to Project Plan Use MS Project if you want Or use Excel
  • 45. Excel Example Dates: June 1-7 June 8-17 June 15-21 June 22-28 Jun29-Jul5 Jul 6-13 DEFINE Agree on charter Gather more VOC Define Phase Review Enter project in QTRAK MEASURE Develop Project Strategy MSA Baseline Capability Process Map / VSM Fishbone (C&E Diagram) C&E Matrix XIA Data Collection Plan Collect data Update Charter, if needed Optional M Phase Rev. ANALYZE Analysis plan Verify Key X's Finalize Charter Analyze Phase Rev. IMPROVE Define Improvements Optimize Improvements
  • 46. The Plan In Place Half of work should be done Now it’s time to manage
  • 47. Thank You Questions? Barry.Cordero@shpe.org
  • 48. References Lean Enterprise Institute “Managing to Learn” John Shook Project Management Book of Knowledge (loosely)