The document discusses how Microsoft Project calculates work for a task by multiplying duration by units. It provides examples showing that when duration is changed but units remain at the default of 100%, work changes proportionally. However, when units are changed to 50% while keeping work fixed, duration must increase to compensate in order to perform the same amount of work over a longer period of time at reduced capacity. In other words, work remains fixed while duration varies inversely with units.