PRESENTED BY : R. FRANA PUJA KESUMA
DOCUMENT CONTROL / TECHNICAL ASSISTANT SPECIALIST
 Responsibility
 Procedure
 Protection & Confidentiality
 Storage of Document
 Storage of Electronic Files
 Final Documentation
Document Control & Management System
The Project Control Manager shall be responsible to ensure that this
procedure is implemented for handling of all technical and qualify
system document
1. Master Document Register
2. Submission of Document
3. Receipt of Document
4. Approval Document
5. Distribution
1. The document must storage in the document control
centre
2. The copy machine in the DC shall be operated by DC
personel in order to avoid the contamination of improper
document
3. All project member shall be made aware of the above
limited access right.
1. Upon submission of document to client, the document
shall be stored in project centre
2. File shall be stored out by means of contract
indetification code
3. When final documentation is prepared the latest
version of the document
1. Upon submission of document to client, associated electronic files shall be
corrected from originator
2. Electronic files shall be native format such as word, exce, autocad &
primavera, pdf file may be used
3. File name of electronic file shall be combination of document number and
revision number
4. Old version of the document shall be stored in parallel with teh latest
version
Final documentation shall be compiled in accordance with compan’s
requirement shall develop with reference by company
Document Control Procedure

More Related Content

PPT
Document Control
PPT
Document & Data Control
PPT
Document Control
PPT
Basics of Good Documentation & Document Control System
PPT
Documentation and document control
PPT
Management responsibility
PPTX
ISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence
Document Control
Document & Data Control
Document Control
Basics of Good Documentation & Document Control System
Documentation and document control
Management responsibility
ISO 9001 2015 | Management Reviews | The Five Rules To Business Excellence

What's hot (20)

PPTX
Good Document Control Practices and Procedures: ISO 9001:2015
PPT
Good documentation practices
PPTX
Good documentation practice
PPTX
Document management system
PPT
Good Documentation Practices
PPT
Good documentation practices
PPTX
Good Documentation Practice (GDP)
PPT
1 documents & Requirements
PPTX
Good Documentation Practice
PPTX
Pharmaceutical Data integrity training
PPT
Good documentation practices
PPT
Document Control
PDF
Document management system for Pharmaceutical
PPTX
Data Integrity Issues in Pharmaceutical Companies
PPTX
Data integrity & ALCOA+
PPTX
ENSURING DATA INTEGRTY THROUGH "ALCOA" : BASIC DATA INTEGRITY PRINCIPLES APPL...
PPTX
Good Documentation Practice (GDP)
PPTX
GDP Training NS
PPTX
DATA INTEGRITY GMP COMPLIANCE
PDF
Documents Control Process
Good Document Control Practices and Procedures: ISO 9001:2015
Good documentation practices
Good documentation practice
Document management system
Good Documentation Practices
Good documentation practices
Good Documentation Practice (GDP)
1 documents & Requirements
Good Documentation Practice
Pharmaceutical Data integrity training
Good documentation practices
Document Control
Document management system for Pharmaceutical
Data Integrity Issues in Pharmaceutical Companies
Data integrity & ALCOA+
ENSURING DATA INTEGRTY THROUGH "ALCOA" : BASIC DATA INTEGRITY PRINCIPLES APPL...
Good Documentation Practice (GDP)
GDP Training NS
DATA INTEGRITY GMP COMPLIANCE
Documents Control Process
Ad

Viewers also liked (6)

PDF
Vendom Document Control System User Manual
PPT
Iso 9000 standards
PDF
What is Document Management
PPTX
Iso procedure for document control
PDF
CV - S Atif Masroor - Document Control Manager / Specialist
PDF
2009 ARMA Toronto Symposium - Document Control on Capital Projects - Paper to...
Vendom Document Control System User Manual
Iso 9000 standards
What is Document Management
Iso procedure for document control
CV - S Atif Masroor - Document Control Manager / Specialist
2009 ARMA Toronto Symposium - Document Control on Capital Projects - Paper to...
Ad

Similar to Document Control Procedure (20)

PDF
Adnan CV _ 20161209
DOC
MUSLIM Curriculum Vitea
DOC
Document Controller Resume
DOCX
Mohammad Sohail - Document Controller
DOCX
Curriculum Vitae of Mr. Jerome Basilio Pasion (Document Controller)
DOC
Mohammed Irfan (Sr. Document Controller)
PDF
Manzur c v_document_controller
DOCX
CVargas_CV_2016
PDF
Document Control best practices and definitions
DOC
Dileep-Resume-ADCO
PDF
Resume
PDF
Vijay resume _rev dc.aug. 2015
DOC
Faisal Khan - Documents Controller
PDF
Shoukath-CV
PDF
Shoukath cv
DOCX
CV - Nov - Document Controller - Maria Patricia Vargas Valle
DOC
CV - Hashim
DOCX
Resume - Steve Poulter (Document Control)
PDF
CV- Meeran Sharfudeen
PDF
Bazmi - Document Control Manager
Adnan CV _ 20161209
MUSLIM Curriculum Vitea
Document Controller Resume
Mohammad Sohail - Document Controller
Curriculum Vitae of Mr. Jerome Basilio Pasion (Document Controller)
Mohammed Irfan (Sr. Document Controller)
Manzur c v_document_controller
CVargas_CV_2016
Document Control best practices and definitions
Dileep-Resume-ADCO
Resume
Vijay resume _rev dc.aug. 2015
Faisal Khan - Documents Controller
Shoukath-CV
Shoukath cv
CV - Nov - Document Controller - Maria Patricia Vargas Valle
CV - Hashim
Resume - Steve Poulter (Document Control)
CV- Meeran Sharfudeen
Bazmi - Document Control Manager

Document Control Procedure

  • 1. PRESENTED BY : R. FRANA PUJA KESUMA DOCUMENT CONTROL / TECHNICAL ASSISTANT SPECIALIST
  • 2.  Responsibility  Procedure  Protection & Confidentiality  Storage of Document  Storage of Electronic Files  Final Documentation Document Control & Management System
  • 3. The Project Control Manager shall be responsible to ensure that this procedure is implemented for handling of all technical and qualify system document
  • 4. 1. Master Document Register 2. Submission of Document 3. Receipt of Document 4. Approval Document 5. Distribution
  • 5. 1. The document must storage in the document control centre 2. The copy machine in the DC shall be operated by DC personel in order to avoid the contamination of improper document 3. All project member shall be made aware of the above limited access right.
  • 6. 1. Upon submission of document to client, the document shall be stored in project centre 2. File shall be stored out by means of contract indetification code 3. When final documentation is prepared the latest version of the document
  • 7. 1. Upon submission of document to client, associated electronic files shall be corrected from originator 2. Electronic files shall be native format such as word, exce, autocad & primavera, pdf file may be used 3. File name of electronic file shall be combination of document number and revision number 4. Old version of the document shall be stored in parallel with teh latest version
  • 8. Final documentation shall be compiled in accordance with compan’s requirement shall develop with reference by company