DOING DEALS AND
AVOIDING SQUEALS
An Australian Perspective
Laina Chan, Barrister Selborne Chambers,
MelbourneTEC Chambers, Director and Secretary
of Society of Construction Law Australia
Introduction
■ Australia is comprised of a
federation of states and territories.
■ The Federal Government budgets
for federal infrastructure projects
on a State andTerritory basis.
■ No guaranteed consistency in the
execution of each infrastructure
project.
ATypical Scenario
■ Common grievances:
– Excessive cost of tendering
– Risk allocation – risk pushed
onto consultants.
■ Contractors are in vulnerable
positions with no bargaining
power.
■ This approach does not lead to
successful delivery of a project.
Changes to systems and
processes
■ The changes to the PPP guidelines and
the new PPPToolbox are intended to:
1. reduce bid costs
2. streamline transaction and approval
processes;
3. promote consistency across NSW PPP
projects
4. promote information sharing across
NSW Government agencies
5. continuous improvement as the
procurement processes evolve
The Sydney Light Rail Project –
A lesson in what not to do
■ A large public transport infrastructure project
■ A cost overrun of over $1 billion with delays of 1 year.
■ Proceedings against the NSW Government for damages for misleading
or deceptive conduct
■ Benefit to cost ratio reduced from 1.4 to less than 1.
The Art of Project
Leadership
■ Only 5% of projects above $1
billion were completed within
their original budget and on
schedule.
■ They are the exception, not
the rule.
■ Average cost overrun was 37%
■ Average schedule overrun was
53%.
Megaprojects are prone to overruns
Root Causes
■ Leadership does must trump the process.
■ Four discrete mindsets
■ Eight practices
– Four relevant to the project setup
phase
– Four relevant to the project delivery
phase
■ Need a clearly defined project scope with
sufficient upfront investment in a detailed
design.
Mindsets
1. Lead as a business, not as a
project.
2. Take full ownership of outcomes.
3. Make your contractor successful.
4. Trust your processes, but know
that leadership is required.
Practices –
The setup phase
■ The four practices that require ‘artful’
application:
1. Define purpose, identity and
culture.
2. Assemble the right team.
3. Carefully allocate risk and align
incentives.
4. Work hard on relationships with
stakeholders.
■ Need to focus on careful allocation
and alignment of risk incentives.
Practices –
The delivery phase
■ The four practices throughout the
delivery phase:
1. Invest in your team,
2. Ensure timely decision making,
3. Adopt forward looking
performance management,
4. Drive desired behaviours
consistently.
A Successful Project –
$16.8 billionWestConnex
■ Involves 33 km of upgraded and new
motorways.
■ A successful example of the art of
leadership in the delivery phase.
■ Project running on budget and on
time.
■ Implements the art of project
leadership.
Advice fromWestConnex
Project Leader
 Aim to provide owner obligations
ahead of time.
 Use influencing and networks
across agencies.
 Mutual trust and joint problem
solving.
 Work as a business partnership
with a mindset of ‘we win
together’.
Advice fromWestConnex
Project Leader
■ Agility is key.
■ Honesty is key.
■ Strong contract
management and
processes are also key.
THE SET UPTO DISPUTE
SYNDROME AND
HOWTO AVOID IT
WaliedAbdeldayem
Managing Director - Intellect Dispute Experts Advisory (IDEA)
16
Claims & Disputes - Overview
17
Claims in Construction Contracts
■ Construction contracts provides for a specific remedy in the event of
breach and grant entitlement in respect of specified events
■ Remedies are sought by following ‘the claims procedure’
■ The claims may be:
– assertion for financial compensation
– assertion for an extension of the time
– and/or other benefits
18
Claims in Construction Contracts
■ Proper planning and risk management could help minimize claims
■ Construction Claims are inevitable - practically impossible to:
– foresee every event that might occur during the construction period
– plan in advance for the consequences of such events
19
Claims vs Disputes
■ Dispute – “any contract question or controversy that must be settled beyond the
jobsite management”
– Diekmann & Girard, 1995
■ Claim – “a request for compensation for damages incurred by any party to a contract”
– Semple, Hartman, & Jergeas, 1994
■ Halki Principle
– A dispute does not exist until a claim has been submitted and rejected; a claim being
a request for compensation for damages incurred by any party to the contract.
Based on the case of Halki Shipping Corporation v Sopex Oils Ltd [1998] 1WLR CA.
20
DisputesAvoidance & Resolution - A
Conceptual Model
■ The ‘Must-Have’ Organizational Functions:
– Dispute avoidance: focuses on avoiding disputes by managing claims
in efficient and timely manner
– Dispute resolution: when disputes cannot be avoided, the focus is on
systematic and integrated dispute management mechanism to ensure
the disputes are settled as efficient as possible
21
DisputesAvoidance & Resolution - A
Conceptual Model
22
Poor Project Mission Definition
■ Most owners, while giving attention to project’s symbolic
aspects, overlooking the quality of specification and
realization
– quality of specification concerns proper final and
coordinated design;
– quality of realization covers a realistic timeframe and
budgets.
23
24
Claims and Disputes as a Potential
Risk
25
Owners’Wait & SeeTactic
■ Negative perception of claims - confusing claims for disputes
■ Owners tend to ignore the matter until it is too late
– Leading to less control in addition to losing the opportunity
to have cost efficient and effective resolution
26
Typical Progress Meeting!
27
‘tell them what they want to hear not what they need to
know’ – very damaging, should be avoided
Early and late addressing of claims – Risk
Management Perception
28
• Construction Claims are:  R I S K S!
Claims & Disputes Management against
Project Life-Cycle
29
Impact of lack pr proper Claims & Disputes
Management on the Project’s Economics
30
Prisoners Dilemma
31
Prisoners Dilemma
■ Two suspects got caught for a crime they committed together
– not enough evidence
– at least one has to confess to press charges
■ Suspects were separated and are under interrogation in separate rooms.
– They know they both got caught
■ Suspects Options
– Deny allegations, give no evidence at all
– Snitch, provide evidence against the other suspect
32
Poll Question
■ If you were Suspect 2, which option would you choose? (Remember, you
never know what Suspect 1 will do!)
– Deny (Choose A)
– Snitch (Choose B)
33
Suspect 1 Decision
Snitch
34
The out come of your decision!
Suspect 1 Action
Snitch Deny
Suspect2Action
SnitchDeny
35
The out come of your decision!
Suspect 1 Action
Snitch Deny
Suspect2Action
SnitchDeny
Both walk away
36
The out come of your decision!
Suspect 1 Action
Snitch Deny
Suspect2Action
Snitch
Each gets sentenced for 2 years
Deny
Both walk away
37
The out come of your decision!
Suspect 1 Action
Snitch Deny
Suspect2Action
Snitch
Each gets sentenced for 2 years
Suspect 1 gets 5 years;
Suspect 2 walks away
Deny
Both walk away
38
The out come of your decision!
Suspect 1 Action
Snitch Deny
Suspect2Action
Snitch
Each gets sentenced for 2 years
Suspect 1 gets 5 years;
Suspect 2 walks away
Deny
Suspect 1 walks away;
Suspect 2 gets 5 years.
Both walk away
39
The Most Logical Choice
Suspect 1 Action
Snitch Deny
Suspect2Action
Snitch
Each gets sentenced for 2 years
Deny
40
■ Consider others’ plays when deciding on your own move
■ Under pressure, a decision maker may willingly take a harming
decision to avoid a potentially more harming situation
■ Construction contracts are generally set for going down a spiral
road of disputes unless:
– Trust is built, proper communication channels are opened, and
(intentional & unintentional) signaling is properly interpreted
41
The Most Logical Choice
42
The Dispute Syndrome
43
The Dispute Syndrome
■ The Client-Agent Problem principle plays a vital role
escalating claims into disputes
■ The Client-Agent Problem is manifested by the fact that each
party has different interest which are often conflicting
44
The Dispute Syndrome
■ The more an organization can align its goals with others’
goals, the less such problem is likely to have a noticeable
impact on the organization’s performance
■ In practice, owners and the contractors tend to participate in
a destructive syndrome that eventually leads to disputes
45
46
Contractor takes
aggressive and
adverse position
Triggering Event
Process of claims
started and
became known to
Owner
Lack of strategic
forward thinking
reflected on
claims
submissions and
Triggering
Event
Lack of trust –
negative
perception of
claims
Owner lacks
objectivity and
unreasonably
dismisses
claims
Owner takes
aggressive and
adverse
position
Contractors’ Syndrome
Owners’ Syndrome
Deadlock – Issues escalated into disputes
Example of aTriggering Event
■ Overriding & manipulating schedules to show what the
scheduler/planner wants it to say
– “I’m a great contractor’s scheduler and I made all owners’ activities
shown as critical”
– “I’m a great owner’s rep and I forced the contractor to remove owner’s
activities from the critical path”
47
The Pitfalls!
■ Losing the opportunity to use schedules to add value to the
project and enhance project delivery
■ Losing trust and ruin relationships
■ Triggering a spiral road towards conflicts & disputes,
sometime over unnecessary issues that may not be relevant
48
Avoiding the syndrome
■ A claim in construction is a contractually agreed upon
mechanism to assert and entitlement, not a declaration of
war, at least not at the start!
■ Negative perception of claims and lack of objectivity are the
main reasons to escalate claims to disputes
49
Avoiding the syndrome
■ Project owners should develop claims and dispute management capabilities
■ Contractor should remain objective in assessing their likely entitlements
■ Consider collaborative planning to meet target programmes and increase
production
– Collaborative working has to be supported by suitable contractual rights and
obligations
– Otherwise, it is a recipe for disputes
50
51
Avoiding the syndrome – Snitch!
At the end – what to take away?
■ Expect and manage claims to avoid (or minimise) escalating issues to disputes
■ Maintain the project schedule (and keep them neutral) to better inform the decision
making process
■ Work to establish trust and communicate effectively, be mindful of the importance of
intentional and unintentional communication signalling
■ Avoid potential triggering events that may cause the spiral dispute syndrome
■ Understand the allocation of risks – work collaboratively but do not assume others’
risks or compromise your contractual position
52

More Related Content

DOCX
2.13 stakeholder management 1
PDF
[Report] Who's protecting your blindside? Construction Management: Protectin...
 
PDF
Crisis Management and Protecting Your Reputation
PPTX
Project Management- Unit II
PDF
Rims Energy Session 2008
PPTX
Edinburgh Trams to Newhaven Project.pptx
PDF
APM Benefits Summit 2017 - From ambition to delivery: Don't just do something...
PPTX
Payment by results - is it right for you?
2.13 stakeholder management 1
[Report] Who's protecting your blindside? Construction Management: Protectin...
 
Crisis Management and Protecting Your Reputation
Project Management- Unit II
Rims Energy Session 2008
Edinburgh Trams to Newhaven Project.pptx
APM Benefits Summit 2017 - From ambition to delivery: Don't just do something...
Payment by results - is it right for you?

Similar to Doing deals and avoiding squeals (20)

PPT
Project managment
PDF
VG - Multi Jurisdictional Litigation - 28.04.2015 -F
PPTX
Chapter 3 Project Identification BnFn.pptx
PPT
Pm risks-and-constraints
PPT
vigilance-ppt.ppt
PPT
PM-Risks-and-Constraints.ppt
PPT
PM-Risks-and-Constraints.ppt
PPT
PM-Risks-and-Constraints.ppt
PPT
PM-Risks-and-Constraints (1).ppt
PDF
Quality, requirements and success webinar, 6 March 2019
PDF
PRCA Expert Briefing - Issues and Crisis Management and the Evolving Media La...
PDF
intro business case for implementation project
PDF
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
PPT
ContractMgmtMPJunejaEx-CTE_300315.ppt
PDF
Negotiation Strategies: Using Game Theory and Decision Tree Analysis to Deter...
PPTX
Robust collateral management: What is it? Why is it important? How to get there!
PPTX
Building relationships within the oil & gas sector may 2013
PDF
Grievance Redressal Mechanism - Training Slides .pdf
PPTX
Introduction to project management framework v2
PPT
Feasibility Study.ppt
Project managment
VG - Multi Jurisdictional Litigation - 28.04.2015 -F
Chapter 3 Project Identification BnFn.pptx
Pm risks-and-constraints
vigilance-ppt.ppt
PM-Risks-and-Constraints.ppt
PM-Risks-and-Constraints.ppt
PM-Risks-and-Constraints.ppt
PM-Risks-and-Constraints (1).ppt
Quality, requirements and success webinar, 6 March 2019
PRCA Expert Briefing - Issues and Crisis Management and the Evolving Media La...
intro business case for implementation project
RPN 2022 Manila: Session 4.5 Lindsey Scannell US CLDP.pdf
ContractMgmtMPJunejaEx-CTE_300315.ppt
Negotiation Strategies: Using Game Theory and Decision Tree Analysis to Deter...
Robust collateral management: What is it? Why is it important? How to get there!
Building relationships within the oil & gas sector may 2013
Grievance Redressal Mechanism - Training Slides .pdf
Introduction to project management framework v2
Feasibility Study.ppt
Ad

More from Laina Chan (12)

PDF
Construction Law Intensive - UNSW Edge
PDF
Handout pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021
PPTX
Mediation, Adjudication and Arbitration - What gets the job done?
PPTX
Powerpoint for Legalwise Annual Property Seminar March 2016
PPTX
The Law of Penalties - ANZ v Andrews and beyond
PPTX
Powerpoint for New York State Bar Lecture
PPTX
Rob Harper SC & Laina Chan How to brief counsel and Why
PPTX
Power Point for Contract Damages
PPT
Insuring Risk in Construction Projects
PPT
Security for Performance
PPT
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
PPTX
Ethics Presentation
Construction Law Intensive - UNSW Edge
Handout pillar 1 regulatory reforms - laina chan bar cpd 9 march 2021
Mediation, Adjudication and Arbitration - What gets the job done?
Powerpoint for Legalwise Annual Property Seminar March 2016
The Law of Penalties - ANZ v Andrews and beyond
Powerpoint for New York State Bar Lecture
Rob Harper SC & Laina Chan How to brief counsel and Why
Power Point for Contract Damages
Insuring Risk in Construction Projects
Security for Performance
When Conveyances Go Wrong - Purchaser’s Remedies for Vendor Breaches
Ethics Presentation
Ad

Recently uploaded (20)

PPTX
Court PROCESS Notes_Law Clinic Notes.pptx
PPT
Gender sensitivity and fair language implementation
PDF
Palghar-286Nilemore-VoterList-Aug25-1.pdf
PPT
Understanding the Impact of the Cyber Act
PPTX
Behavioural_Approach_Public_Administration_Zambia_USA.pptx
PDF
APPELLANT'S AMENDED BRIEF – DPW ENTERPRISES LLC & MOUNTAIN PRIME 2018 LLC v. ...
PPTX
ART OF LEGAL WRITING IN THE CBD [Autosaved].pptx
PPTX
prenuptial agreement ppt my by a phd scholar
PPTX
POSH Awareness and policy ppt with all design covering .
PDF
250811-FINAL-Bihar_Voter_Deletion_Analysis_Presentation.pdf
PDF
8-14-25 Examiner Report from NJ Bankruptcy (Heller)
PDF
AI in Modern Warfare and Business Ethics Ortynska Law Ventures Cafe.pdf
PDF
Insolvency and Bankruptcy Amendment Bill 2025
PPTX
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
PDF
OBLICON (Civil Law of the Philippines) Obligations and Contracts
PPTX
R.A. NO. 76 10 OR THE CHILD ABUSE LAW.pptx
PPTX
Punjab Fertilizers Control Act 2025.pptx
PDF
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
PDF
Companies Act (1).pdf in details anlysis
PDF
SUMMARY CASES-42-47.pdf tax -1 257++/ hsknsnd
Court PROCESS Notes_Law Clinic Notes.pptx
Gender sensitivity and fair language implementation
Palghar-286Nilemore-VoterList-Aug25-1.pdf
Understanding the Impact of the Cyber Act
Behavioural_Approach_Public_Administration_Zambia_USA.pptx
APPELLANT'S AMENDED BRIEF – DPW ENTERPRISES LLC & MOUNTAIN PRIME 2018 LLC v. ...
ART OF LEGAL WRITING IN THE CBD [Autosaved].pptx
prenuptial agreement ppt my by a phd scholar
POSH Awareness and policy ppt with all design covering .
250811-FINAL-Bihar_Voter_Deletion_Analysis_Presentation.pdf
8-14-25 Examiner Report from NJ Bankruptcy (Heller)
AI in Modern Warfare and Business Ethics Ortynska Law Ventures Cafe.pdf
Insolvency and Bankruptcy Amendment Bill 2025
FFFFFFFFFFFFFFFFFFFFFFTA_012425_PPT.pptx
OBLICON (Civil Law of the Philippines) Obligations and Contracts
R.A. NO. 76 10 OR THE CHILD ABUSE LAW.pptx
Punjab Fertilizers Control Act 2025.pptx
The AI & LegalTech Surge Reshaping the Indian Legal Landscape
Companies Act (1).pdf in details anlysis
SUMMARY CASES-42-47.pdf tax -1 257++/ hsknsnd

Doing deals and avoiding squeals

  • 1. Track A1 Doing Deals & Avoiding Squeals; andThe Set UpTo Dispute Syndrome & HowTo Avoid It
  • 2. DOING DEALS AND AVOIDING SQUEALS An Australian Perspective Laina Chan, Barrister Selborne Chambers, MelbourneTEC Chambers, Director and Secretary of Society of Construction Law Australia
  • 3. Introduction ■ Australia is comprised of a federation of states and territories. ■ The Federal Government budgets for federal infrastructure projects on a State andTerritory basis. ■ No guaranteed consistency in the execution of each infrastructure project.
  • 4. ATypical Scenario ■ Common grievances: – Excessive cost of tendering – Risk allocation – risk pushed onto consultants. ■ Contractors are in vulnerable positions with no bargaining power. ■ This approach does not lead to successful delivery of a project.
  • 5. Changes to systems and processes ■ The changes to the PPP guidelines and the new PPPToolbox are intended to: 1. reduce bid costs 2. streamline transaction and approval processes; 3. promote consistency across NSW PPP projects 4. promote information sharing across NSW Government agencies 5. continuous improvement as the procurement processes evolve
  • 6. The Sydney Light Rail Project – A lesson in what not to do ■ A large public transport infrastructure project ■ A cost overrun of over $1 billion with delays of 1 year. ■ Proceedings against the NSW Government for damages for misleading or deceptive conduct ■ Benefit to cost ratio reduced from 1.4 to less than 1.
  • 7. The Art of Project Leadership ■ Only 5% of projects above $1 billion were completed within their original budget and on schedule. ■ They are the exception, not the rule. ■ Average cost overrun was 37% ■ Average schedule overrun was 53%.
  • 9. Root Causes ■ Leadership does must trump the process. ■ Four discrete mindsets ■ Eight practices – Four relevant to the project setup phase – Four relevant to the project delivery phase ■ Need a clearly defined project scope with sufficient upfront investment in a detailed design.
  • 10. Mindsets 1. Lead as a business, not as a project. 2. Take full ownership of outcomes. 3. Make your contractor successful. 4. Trust your processes, but know that leadership is required.
  • 11. Practices – The setup phase ■ The four practices that require ‘artful’ application: 1. Define purpose, identity and culture. 2. Assemble the right team. 3. Carefully allocate risk and align incentives. 4. Work hard on relationships with stakeholders. ■ Need to focus on careful allocation and alignment of risk incentives.
  • 12. Practices – The delivery phase ■ The four practices throughout the delivery phase: 1. Invest in your team, 2. Ensure timely decision making, 3. Adopt forward looking performance management, 4. Drive desired behaviours consistently.
  • 13. A Successful Project – $16.8 billionWestConnex ■ Involves 33 km of upgraded and new motorways. ■ A successful example of the art of leadership in the delivery phase. ■ Project running on budget and on time. ■ Implements the art of project leadership.
  • 14. Advice fromWestConnex Project Leader  Aim to provide owner obligations ahead of time.  Use influencing and networks across agencies.  Mutual trust and joint problem solving.  Work as a business partnership with a mindset of ‘we win together’.
  • 15. Advice fromWestConnex Project Leader ■ Agility is key. ■ Honesty is key. ■ Strong contract management and processes are also key.
  • 16. THE SET UPTO DISPUTE SYNDROME AND HOWTO AVOID IT WaliedAbdeldayem Managing Director - Intellect Dispute Experts Advisory (IDEA) 16
  • 17. Claims & Disputes - Overview 17
  • 18. Claims in Construction Contracts ■ Construction contracts provides for a specific remedy in the event of breach and grant entitlement in respect of specified events ■ Remedies are sought by following ‘the claims procedure’ ■ The claims may be: – assertion for financial compensation – assertion for an extension of the time – and/or other benefits 18
  • 19. Claims in Construction Contracts ■ Proper planning and risk management could help minimize claims ■ Construction Claims are inevitable - practically impossible to: – foresee every event that might occur during the construction period – plan in advance for the consequences of such events 19
  • 20. Claims vs Disputes ■ Dispute – “any contract question or controversy that must be settled beyond the jobsite management” – Diekmann & Girard, 1995 ■ Claim – “a request for compensation for damages incurred by any party to a contract” – Semple, Hartman, & Jergeas, 1994 ■ Halki Principle – A dispute does not exist until a claim has been submitted and rejected; a claim being a request for compensation for damages incurred by any party to the contract. Based on the case of Halki Shipping Corporation v Sopex Oils Ltd [1998] 1WLR CA. 20
  • 21. DisputesAvoidance & Resolution - A Conceptual Model ■ The ‘Must-Have’ Organizational Functions: – Dispute avoidance: focuses on avoiding disputes by managing claims in efficient and timely manner – Dispute resolution: when disputes cannot be avoided, the focus is on systematic and integrated dispute management mechanism to ensure the disputes are settled as efficient as possible 21
  • 22. DisputesAvoidance & Resolution - A Conceptual Model 22
  • 23. Poor Project Mission Definition ■ Most owners, while giving attention to project’s symbolic aspects, overlooking the quality of specification and realization – quality of specification concerns proper final and coordinated design; – quality of realization covers a realistic timeframe and budgets. 23
  • 24. 24
  • 25. Claims and Disputes as a Potential Risk 25
  • 26. Owners’Wait & SeeTactic ■ Negative perception of claims - confusing claims for disputes ■ Owners tend to ignore the matter until it is too late – Leading to less control in addition to losing the opportunity to have cost efficient and effective resolution 26
  • 27. Typical Progress Meeting! 27 ‘tell them what they want to hear not what they need to know’ – very damaging, should be avoided
  • 28. Early and late addressing of claims – Risk Management Perception 28 • Construction Claims are:  R I S K S!
  • 29. Claims & Disputes Management against Project Life-Cycle 29
  • 30. Impact of lack pr proper Claims & Disputes Management on the Project’s Economics 30
  • 32. Prisoners Dilemma ■ Two suspects got caught for a crime they committed together – not enough evidence – at least one has to confess to press charges ■ Suspects were separated and are under interrogation in separate rooms. – They know they both got caught ■ Suspects Options – Deny allegations, give no evidence at all – Snitch, provide evidence against the other suspect 32
  • 33. Poll Question ■ If you were Suspect 2, which option would you choose? (Remember, you never know what Suspect 1 will do!) – Deny (Choose A) – Snitch (Choose B) 33
  • 35. The out come of your decision! Suspect 1 Action Snitch Deny Suspect2Action SnitchDeny 35
  • 36. The out come of your decision! Suspect 1 Action Snitch Deny Suspect2Action SnitchDeny Both walk away 36
  • 37. The out come of your decision! Suspect 1 Action Snitch Deny Suspect2Action Snitch Each gets sentenced for 2 years Deny Both walk away 37
  • 38. The out come of your decision! Suspect 1 Action Snitch Deny Suspect2Action Snitch Each gets sentenced for 2 years Suspect 1 gets 5 years; Suspect 2 walks away Deny Both walk away 38
  • 39. The out come of your decision! Suspect 1 Action Snitch Deny Suspect2Action Snitch Each gets sentenced for 2 years Suspect 1 gets 5 years; Suspect 2 walks away Deny Suspect 1 walks away; Suspect 2 gets 5 years. Both walk away 39
  • 40. The Most Logical Choice Suspect 1 Action Snitch Deny Suspect2Action Snitch Each gets sentenced for 2 years Deny 40
  • 41. ■ Consider others’ plays when deciding on your own move ■ Under pressure, a decision maker may willingly take a harming decision to avoid a potentially more harming situation ■ Construction contracts are generally set for going down a spiral road of disputes unless: – Trust is built, proper communication channels are opened, and (intentional & unintentional) signaling is properly interpreted 41 The Most Logical Choice
  • 42. 42
  • 44. The Dispute Syndrome ■ The Client-Agent Problem principle plays a vital role escalating claims into disputes ■ The Client-Agent Problem is manifested by the fact that each party has different interest which are often conflicting 44
  • 45. The Dispute Syndrome ■ The more an organization can align its goals with others’ goals, the less such problem is likely to have a noticeable impact on the organization’s performance ■ In practice, owners and the contractors tend to participate in a destructive syndrome that eventually leads to disputes 45
  • 46. 46 Contractor takes aggressive and adverse position Triggering Event Process of claims started and became known to Owner Lack of strategic forward thinking reflected on claims submissions and Triggering Event Lack of trust – negative perception of claims Owner lacks objectivity and unreasonably dismisses claims Owner takes aggressive and adverse position Contractors’ Syndrome Owners’ Syndrome Deadlock – Issues escalated into disputes
  • 47. Example of aTriggering Event ■ Overriding & manipulating schedules to show what the scheduler/planner wants it to say – “I’m a great contractor’s scheduler and I made all owners’ activities shown as critical” – “I’m a great owner’s rep and I forced the contractor to remove owner’s activities from the critical path” 47
  • 48. The Pitfalls! ■ Losing the opportunity to use schedules to add value to the project and enhance project delivery ■ Losing trust and ruin relationships ■ Triggering a spiral road towards conflicts & disputes, sometime over unnecessary issues that may not be relevant 48
  • 49. Avoiding the syndrome ■ A claim in construction is a contractually agreed upon mechanism to assert and entitlement, not a declaration of war, at least not at the start! ■ Negative perception of claims and lack of objectivity are the main reasons to escalate claims to disputes 49
  • 50. Avoiding the syndrome ■ Project owners should develop claims and dispute management capabilities ■ Contractor should remain objective in assessing their likely entitlements ■ Consider collaborative planning to meet target programmes and increase production – Collaborative working has to be supported by suitable contractual rights and obligations – Otherwise, it is a recipe for disputes 50
  • 52. At the end – what to take away? ■ Expect and manage claims to avoid (or minimise) escalating issues to disputes ■ Maintain the project schedule (and keep them neutral) to better inform the decision making process ■ Work to establish trust and communicate effectively, be mindful of the importance of intentional and unintentional communication signalling ■ Avoid potential triggering events that may cause the spiral dispute syndrome ■ Understand the allocation of risks – work collaboratively but do not assume others’ risks or compromise your contractual position 52