IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 464
EFFECTIVE TECHNIQUES IN COST OPTIMIZATION OF
CONSTRUCTION PROJECT: AN REVIEW
Anuja Rajguru1
, Parag Mahatme2
1
P. G. Scholar, Department of Civil Engineering, PRMCEAM, Badnera, M.S. India
2
Assistant Professor, Department of Civil Engineering, PRMCEAM, Badnera, M.S. India
Abstract
In the construction project, time and cost are the most important factors to be considered in the planning of every project. The aim
of project is to finish the projects on time, within budget and to achieve other project objectives. It is a difficult task undertaken
by project managers in practice, which include constantly measuring progress, evaluation of plans, and corrective actions should
be taken whenever required. Optimization is a systematic effort made to improve profit margins and obtain the best results under
given circumstances. There is a Systematic planning and programming with effective management is necessary for timely
completion of the project. there is availability of various tools and techniques for optimization. Optimizing performance of the
different techniques adopted at one stage of the construction process may not be beneficial if the methods used are not to up the
efficient level. In this approach we have studied various factors which affect the cost of projects. again in this approach we have
studied various techniques and various materials used for cost optimization. Also the need of optimization is discussed.
Keywords: time, cost, optimization.
--------------------------------------------------------------------***-----------------------------------------------------------------
1. INTRODUCTION
India is the developing country and in the economy of
country construction projects and industries play an vital
role. Time and cost are two main concerns in a construction
and they are used for planning a project. This has increased
the importance of time and Cost optimization in
construction projects. is necessary to estimate the cost and
time of each activity through which the whole duration and
total cost of the project are determined to complete the
planning task. Optimization is a systematic effort made to
improve profit margins and obtain the best results under
given circumstances or situations. “Cost Optimization can
be defined as the achievement of real and permanent
reduction in the unit cost of services provided without
damaging their suitability for the in planned use”. There is
availability of various techniques for optimization and
project control software, still many construction projects do
not achieve their cost and time objectives. Optimizing
performance of the different techniques adopted at one stage
of the construction process may not be beneficial if the
methods used are not to up the efficient level. Hence it is
required to follow and implement the techniques in every
stage of the construction process with the analyses of the
information available. The methodology and the type of the
used in a construction is also plays very important role for
the successful completion of a project.
1.1 Need of Optimization
The optimization of time and cost is necessary as it could
minimize both the time and total cost of project. This
optimization in time and cost helps to achieve the greatest
benefit.
2. LITERATURE REVIEW
Shanmugapriya S., Dr. Subramanian K. (October 2013) [1]
Time overruns and Cost overruns has been a major issue in
many Indian construction projects. The objective of this
paper to study significant factors causing Time overruns and
Cost overruns in Indian construction projects. The result
accomplished from the survey revealed that the major cause
for time overruns are contract modification, material market
rate, and high level of quality requirement and the major
cause for cost overruns are , change in material
specification, high transportation cost, and escalation of
materials price.
Salunkhe. A, Patil R (Janeuary2014) [2] Construction delay
is considered to be one of the recurring problems in the
construction industry and it has an adverse effect on project
success in terms of time, cost and quality. The time and cost
for performance of a project are usually important to the
employer and contractor. The authors highlights the types of
construction delays due to which project suffer time and cost
overrun. also give external and internal factors that influence
the construction process and outlines the effect of delay in
large construction projects.
T.Subramani , P S Sruthi, M.Kavitha (June. 2014) [3] The
main objectives of this paper are to identify and analyze the
causes of cost overrun in construction. The results carried
out from survey showed that, poor contract management,
slow decision making, poor schedule management, increase
in material/machine prices poor design/ delay in providing
design, rework due to wrong work, long period between
design and time of bidding/tendering and wrong estimation/
estimation method are the major causes of cost overrun.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 465
Memon A.H, Rahman I.A, Mohd Razaki Abdullah3, Ade
Asmi Abdu Azis, (December 2010) [4] Project cost is one
of the most important criteria of success of project. the
authors are focusing on identification of significant causes
affecting construction cost in MARA large projects. From
the study author found that contractor's poor site
management and supervision, cash flow and financial
difficulties faced by contractors, shortage of site workers,
inadequate contractor experience, incorrect planning and
scheduling by contractors are most severe factors which
affect cost of project. while changes in scope of project and
frequent design changes are least affecting factors on
construction cost.
Benviolent Chigara,Tirivavi Moyo, Fungai Mudzengerere
(2013) [5] they made the research for the cost management
strategies employed by contractor on building projects. Also
made investigation that contractor has to manage project
cost. For data collection they made the survey and
interviews in Zimbabwe. From study they found that
contractor efforts to manage the project cost by
concentrating on the management on the project resources.
Also the cost management process in Zimbabwe compare to
other developing countries is still dominated by prematurely
developed automated system or traditional paper based
systems of managing project cost information. The author
provide a base line information on strategies used for
managing project cost.
Barbole A.N., Yuvraj D. Nalwade, Santosh D. Parakh (
June. 2013) [6] The survival today for any company is how
to manage its service Cost, quality, and performance. Now a
days the customers are continuously demanding high quality
and better performance of services and at the same time they
want the prices to fall. For this author focus on impact of
cost control and cost reduction techniques in present
scenario. An objective of this paper is to understand the
basic concept of Cost, Cost Control, and Cost Reduction and
to study various Tool and Techniques available for Cost
Control and Cost Reduction. The Cost Control and Cost
Reduction techniques used in manufacturing sector like
Value Engineering, Quality Control, and Budgetary Control
are specified by the author also cost, cost reduction, cost
control etc. Various terms are specified by the author.
C.I. Anyanwu (December 2013) [7] author discuss about the
various parameters regarding the cost such as budgeting,
cost monitoring and control systems. he discuss about the
cost control and the cost control parameter in material,
labor, equipments etc .As per the author concept of budget
can be define as the translation of an organizational plan
into concrete form by way of resource allocation in form of
cash. He discuss about the various tools used by the
management and cost supervisors for planning, controlling,
and monitoring of project such as Gantt chart, network
analysis, CPM, PERT. Main focus of author is to study the
manufacturing philosophy and inputs which contributes in
evaluating and maintaining construction cost in order to
reduce the project abandonment which is caused due to cost
overrun.
Akintola Omigbodun (June 2001) [8] as per the author value
engineering can be defined as the ‘‘Engineering is the
conceptualization, design, construction, and administration
of projects and products whatever the field or application,
the engineer solves problems with imagination, creativity
and synthesis of various sources of knowledge.’’ To obtain
the optimal solution for any engineering design 4 methods
has discussed are as follows design for manufacturing and
assembly, concurrent engineering, total quality
management, and value engineering. A summary of other
methods of optimal design methods are compared with
value engineering. Cost minimization in building
construction is discussed with examples on building projects
in West Africa and the Middle East. From study author
concluded that, due to application of value engineering to
building projects management team obtains a solution which
emphasis the functions of project which helps to team to
make final choice and which results in cost effective design
for project. Value engineering is effective because its
procedures give opportunities for raising design issues
associated with the latter group of factors as well as design.
Georgekutty C.K, Dr. George Mathew (August - 2012)
[9]the innovation of new technology in the construction
field is not being adopted in project implementation. this
results the growth of construction industry is slow. The real
problem is construction will not complete within the
budgeted cost and time and finally leads to project failure as
end result. Material has a dominating role in construction. If
the material has controlled properly then the total project
cost would be reduced. To achieve this objective, a research
methodology has developed by author to control the
material procurement and carrying cost. The methodology
adopted which adopted has been validated by a computer
program and same is found correct and useful for analysis
and controlling any type of projects.
J Zhou, Ped Love, X Wang, Kl Teo And Z (Irani 2013) [10]
main objective of the paper is to Optimize construction
scheduling. for this author adopted various methods like
Mathematical Method, Heuristic Method, Metaheuristic
Method. As per the author the Methods and algorithms
applied for optimizing construction scheduling efficient and
effective.
Khyomesh V. Patel, Prof. Chetna M. Vyas ( May 2011) [11]
as per the author to manage the productivity and the cost
efficiency material management is more essential. the main
objective of the material management are buying or
purchasing, storing and inventory control, quality assurance.
to achieve these objectives there is need of material
management. Author carried out as survey in Ahmadabad to
check material management. they investigate that material
and equipment contribute 70% that of total cost. hence for
the improvement of product and cost efficiency material
management is important. Also proper tracking, controlling
is required, if there is poor management may lead to delay
of project.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 466
Hisham Said, Khaled El-Rayes, (June 2011) [12]the authors
suggested new model of construction logistics planning to
enable the optimization and integration of critical planning
decisions of material procurement and also of the material
storage on construction site. To check the capability of CLP
model one example was analyzed. After the analysis the
results obtained that material procurement decisions are
affected by the criticality of construction activities
consuming the material, site space available, material
procurement and site layout constrains.
Andrew N Baldwin, Simon A Austin, Chi-Sun Poon, Li-Yin
Shen, Irene Wong (June 2007) [13] the design of high rise
building I different from the different of residential and
other forms of buildings because of the repetition of the
construction and time for the completion of each floor. The
main objective of the authors is to develop the model or
tools and techniques for analyzing the information for the
high rise building. Also, to investigate the difference in the
various models for the private residential buildings. Authors
discuss about the optimization techniques such as design
structural matrix. From study author conclude that there is
need to develop the new tools and techniques which can
help to designer to analyze the information and to make the
improvement in the design management which helps for
optimization.
P. Tiwari, K. Parikh, J. Parikh (September 1999) [14]
authors discussed about the theoretical basic of hope model.
Propose new model of multi criteria optimization technique
for buildings. Also Suggested that multi criteria
optimization model can b developed to solve the problem in
Road, Bridge, and Tunnel construction.
Kale R, Gore G. N, Salunke J. P, (January 2014) [15] Main
objective of this paper is cost optimization of bridge
including the material. As per the authors the optimization is
made for the different grade of steel and concrete. for this
they applied direct design method for analyzing the
structure. The methodology adopted by them is Nonlinear
Programming Problem (NLPP) By Using MATLAB
Software with SUMT (Sequential Unconstrained
minimization technique). Authors found that there is a
significant savings in cost overrun.
C. Sarma, Hoijat Adeli (1998) [16] the objective of this
paper is to optimize cost of concrete structures involves
beams, slabs, columns, bridges, water tanks, frame
structures, tensile members, folded plates, and shear walls,
pipes. One method for Cost Optimization Using Reliability
Theory is explained. From the study the authors concluded
that there is a need to perform research on cost optimization
of realistic three-dimensional structures, especially for the
large structures with number of members where
optimization can result in substantial savings.
Gopal M. Naik , M. Kumar (September 2013) [17] The main
objective of the paper is To increase the productivity and
necessary to forecast the costs arriving from resources so
that the total cost of project can be reduced. The Artificial
Neural Networks have become well established as viable,
multipurpose, robust computational methodologies with
solid theoretic support and with strong potential to be
effective in any discipline, especially in construction. From
survey results comes out that the Neural Networks approach
has optimized the total project cost by 3.91%, and the
duration of the project has been reduced around 5% of the
total duration of the project.
Shrivastava R, Singh S. , Dubey C. G. (2012) [18] Time and
cost are the most important factors to be considered in every
construction project. Ant colony optimization technique was
introduced in the early 1990’s as a novel technique for
solving hard combinational optimization problem. on basis
of that author developed new multi-colony ant algorithm for
the optimization of three objectives time-cost quality with
quantity. The model is also applied to two objectives time –
cost trade off problem. The results which are coming out
compared to those of the existing approaches. As per the
authors Model is capable of compromising between
important aspect of construction projects
Seyed Ali Mousavi Dehmourdi (2014) [19] the Objective of
this paper are to apply the principles of engineering
economics, basic economic concepts , finance and
quantitative techniques to modeling and analysis of civil
engineering projects. Also a practical application of linear
programming in a real life project problem with two
objectives as optimization of transporting cost of equipment
and finding the best solution for reducing the functional
costs of the equipment. Mainly structured linear
programming model is used for optimizing the transporting
cost of equipment. Applications of this approach helps in
determining the need for the replacement and the
maintenance analysis are based on the econometric approach
to the realistic problems and the result shows that
optimization with advanced techniques really helps in
minimization of cost of project.
Daisy X.M. Zheng, S. Thomas Ng , Mohan M.
Kumaraswamy (September 2002) [20] Completing a
construction project with the least time and cost is critical
Factor and usually requires the engagement of additional
labor and plant or the adoption of alternative construction
techniques which add extra cost liabilities to the contractor.
For time-cost optimization several analytical models have
been developed. From those the Genetic Algorithms (GA)
could be used to establish the fitness of solutions by
evaluating the objective function and its constraints. the
objective of paper is to compare the analytical power of the
GA with other techniques proposed for TCO. The results
come out which indicate that the GA techniques could
generate the most optimal outcome for construction Time-
Cost Optimization it is more beneficial when the project is
large and/or complex.
S. Thomas Ng And Yanshuai Zhang (September 2008) [21]
main objective of the paper is to Optimize Construction
Time and Cost of project. For this they adopted the Ant
Colony Method of optimization. Main aspect is Time, Cost
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 467
And Quality Optimization. They made the Comparison with
the other optimization methods. Ant colony method is the
multi objective optimization techinque.
Daisy X.M. Zheng, S. Thomas Ng, Mohan M.
Kumaraswamy (2002) [22] They applied a Genetic
Algorithm to the project for Multi objective optimization.
As per the author Genetic Algorithm is multi objective i.e.
Time, Cost and Quality optimization. Also GA techniques
could generate the most optimal outcome For construction
Time cost Optimization.
A.S. Ali, S.N. Kamaruzzaman (2010) [23] as per the author
for management of construction 4 parameters important are
as follows: scope, cost, time, and quality. the main aim of
the author is to find out the problem or parameters which
contribute for the cost overrun. for this they carried out the
quaternary survey on the live projects. for the data analysis
the method used is quantitative based i.e. descriptive
statistics and ranking analysis is used. from the investigation
they found that factors which contributes to cost overrun
was inaccurate or poor estimation of original cost and factor
which don't affect is mistake in design for this to control the
construction cost method suggested by the author is proper
costing and financing. also they concluded that cost overrun
is most serious problem which may affect the construction
project effectively.
Ming Li ,Guangdong Wurobust, (2014) [24] the objective of
this paper is to optimization of a time-cost tradeoff problem.
Based on multi objective robust optimization method, a
optimization model for time-cost tradeoff problem is
developed. The results come out that, by means of adjusting
the time and cost robust coefficients, the robust Pareto sets
for time-cost tradeoff can be obtained according to different
acceptable risk level, from which the decision maker could
choose the preferred construction alternative.
Pathak.U.J, Chavan.C.S, Rathode.L.V, Nachare.V.L,
Suryawanshi.A.B, (Apr 2014) [25] Low cost housing
technologies aim to cut down construction cost by using
alternatives to conventional methods and Input. Authors
examined the cost effectiveness of using low cost housing
technologies in comparison with the traditional construction
methods. From Two case studies in India found that about
22 to 26 % of the construction cost including material and
labor cost can be saved by using the low cost housing
technologies in comparison with traditional construction
methods for walling and roofing respectively.
Tam W. Y, (2011) [26] It is necessary to adopt cost
effective, innovative and Eco-friendly housing technologies
for the construction of houses and buildings for enabling the
common people to construct houses at affordable cost.
Methodology used by author is to compares construction
cost for the traditional and low cost housing technologies.
For which Case studies in India are used for the
investigation. Construction methods, Strength and durability
of the structure, stability, safety of various members are
compared during cost reduction. The result found that about
26.11% and 22.68% of the construction cost can be saved by
using low cost housing technologies in comparison with the
traditional construction methods. This proves that using low
cost housing technologies is a cost effective construction
approach for the industry.
Nilanjan Sengupta (January 2008) [27] as per the author the
cost effective construction technologies are useful and
beneficial from both in terms of cost and environment.
Author discuss about the some effective technologies in
India with their features and advantages. Technologies used
in India are
1) Rat trap bond wall: due to this bond cost and material is
saved and strength is more 2) Brick arch: it is given with its
construction. It is beneficial from appearance point of view
3) Filler slab : its slab construction is also discussed. Its
advantageous from economy, appearance, strength, material
usage and reduction, less weight, material saving point of
view.
4) compressed earth block : it is beneficial because it absorb
less water in rainfall.
From the study author concluded that, if we pay attention
towards the terms like sanitization of people, manpower
development, material devolvement, technical guidance’s
then the cost effective techniques will be extensively used in
the light of sustainable development and protection of
environment.
R. Taur, V. Devi (Oct 2009) [28]the main objective of this
paper is to point out the various aspect of prefabricated
building methodology for low housing. For this different
prefabrication techniques with their advantage and
importance are given by authors. In a building the
foundation, walls, doors and windows, floors, roofs are the
most important components which can be analyzed
individually based on the needs. There is need for improving
the speed of construction and reducing the construction cost.
The methods of construction systems suggested by authors
are as follows prefabricated roofing components like precast
RC planks, structural block walls, precast hollow concrete
panels, precast concrete/Ferro cement panels, mortar less
block walls.
3. CONCLUSION
In this paper we have reviewed different techniques for
optimization. To minimize the construction cost and
duration at each phase is important. It is a need to meet the
present day requirements and to complete the project within
the estimated time, cost, and available resources. Mainly
affecting the factor on cost of project is delay in project and
material. Several methods have been developed and applied
to analyze the time-cost problems, but they can optimize
only one parameter. Various low cost material also
suggested for optimizing the cost of project along with
maintaining the quality and strength of the project. Also
various mathematical method and software based models
studied for optimization.
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 468
REFERENCES
[1]. Shanmugapriya S., Dr. Subramanian K.,(October 2013)
“Investigation of Significant Factors Influencing Time And
Cost” International Journal Of Emerging Technology And
Advanced Engineering Volume 3.
[2]. Salunkhe. A, Patil R., (Jan-2014) “Effect of
Construction Delays on Project Time Overrun: Indian
Scenario” Ijret: International Journal of Research in
Engineering and Technology volume: 03
[3]. T.Subramani , P S Sruthi, M.Kavitha, (June. 2014)
“Causes Of Cost Overrun In Construction” Iosr Journal Of
Engineering, vol. 04
[4]. Memon A.H, Rahman I.A, Mohd Razaki Abdullah3,
Ade Asmi Abdu Azis, (December 2010) “Factors Affecting
Construction Cost In Mara Large Construction Project:
Perspective Of Project Management Consultant”
International Journal Of Sustainable Construction
Engineering & Technology Vol 1, No 2.
[5]. Benviolent Chigara,Tirivavi Moyo, Fungai
Mudzengerere (2013) "An Analysis Of Cost Management
Strategies Employed By Building Contractors On Project In
Zimbabwe" International Journal Of Sustainable
Construction Engineering & Technology Vol 4, No 2.
[6]. Barbole A.N., Y. D. Nalwade, S. D. Parakh (June. 2013)
“Impact Of Cost Control And Cost Reduction Techniques
On Manufacturing Sector” Indian Streams Research Journal
Volume 3.
[7]. C.I. Anyanwu (December 2013) "Project Cost Control
in The Nigerian Construction Industry" International Journal
Of Engineering Science Invention Volume 2 Issue 12.
[8]. Akintola Omigbodun (June 2001) "Value Engineering
and Optimal Building Projects" Journal of Architectural
Engineering.
[9]. Georgekutty C.K, Dr.George Mathew (August - 2012)
"Research Methodology For Material Optimization In
Construction Projects” International Journal Of Engineering
Research & Technology (Ijert) Vol. 1.
[10]. J Zhou, Ped Love, X Wang, Kl Teo And Z Irani 2013
A Review Of Methods And Algorithms For Optimizing
Construction Scheduling" Journal Of The Operational
Research Society Vol. 64, No. 8
[11]. Khyomesh V. Patel, Prof. Chetna M. Vyas (13-14 May
2011) "Construction Materials Management On Project
Sites" National Conference On Recent Trends In
Engineering & Technology B.V.M. Engineering College,
V.V.Nagar, Gujarat, India.
[12]. Hisham Said, Khaled El-Rayes, (June 2011)
“Optimizing Material Procurement and Storage on
Construction Sites” Journal of Construction Engineering and
Management
[13]. Andrew N Baldwin, Simon A Austin and Chi-sun
Poon, Li-yin Shen and Irene Wong (June 2007) “Reducing
Waste in High-Rise Residential Buildings by Information
Modeling at the Design Stage” Surveying and Built
Environment Vol 18.
[14]. P. Tiwari, K. Parikh, J. Parikh (September 1999)
“Structural Design Considerations In House Builders’
Model: Optimization Approach" Journal of Infrastructure
Systems.
[15]. Kale R, Gore G. N, Salunke J. P, (January 2014) “Cost
Optimization of R.C.C. T-Beam Girder” International
Journal Of Soft Computing And Engineering, Volume-3.
[16]. K. C. Sarma, Hoijat Adeli (May 1998) “Cost
Optimization Of Concrete Structures” Journal Of Structural
Engineering.
[17]. G. M. Naik , M. Kumar, (September 2013) “Project
Cost And Duration Optimization Using Soft Computing
Techniques” Journal Of Advanced Management Science
Vol. 1, No. 3.
[18]. Shrivastava R, Singh S., Dubey C. G. (2012) “Multi
Objective Optimization Of Time Cost Quality Quantity
Using Multi Colony Ant Algorithm” Int. J. Contemp. Math.
Sciences, Vol. 7.
[19]. Seyed Ali Mousavi Dehmourdi (2014) "Optimization
Of Construction Cost Applying Advanced Techniques"
International Journal Of Structural & Civil Engineering
Research.
[20]. Daisy X.M. Zheng, S. Thomas Ng , M. M.
Kumaraswamy (September 2002) "Applying Genetic
Algorithm Techniques For Time-Cost Optimization" In:
Greenwood, D (Ed.), 18th Annual Arcom Conference,
University Of Northumbria. Association Of Researchers In
Construction Management, Vol. 2
[21]. S. Thomas Ng And Yanshuai Zhang (September 2008)
"Optimizing Construction Time And Cost Using Ant
Colony Optimization Approach" Journal Of Construction
Engineering And Management © ASCE
[22]. Daisy X.M. Zheng, S. Thomas Ng , Mohan M.
Kumaraswamy (APRIL 2004) "Applying a Genetic
Algorithm-Based Multi objective Approach for Time-Cost
Optimization" Journal Of Construction Engineering And
Management © ASCE
[23]. A.S. Ali, S.N. Kamaruzzaman (2010) "Cost
Performance For Building Construction Projects In Klang
Valley " Journal Of Building Performance Issn: 2180-2106
Volume 1.
[24]. Ming Li ,Guangdong Wu (2014) “Robust
Optimization For Time-Cost Tradeoff Problem In
Construction Project” Hindawi Publishing Corporation
Abstract and Applied Analysis Volume 2014.
[25]. Pathak.U.J, Chavan.C.S, Rathode.L.V, Nachare.V.L,
Suryawanshi.A.B, (Apr 2014) “Cost Effective House By
Using Various Construction Techniques And Materials”
Indian Journal Of Applied Research Volume: 4.
[26]. Tam W. Y, (2011) “Cost Effectiveness Of Using Low
Cost Housing Technologies In Construction” Science
Direct.
[27]. Nilanjan Sengupta (January 2008) “Use Of Cost-
Effective Construction Technologies In India To Mitigate
Climate Change” Current Science, Vol. 94
[28]. R. Taur, V. Devi (Oct 2009) “Low Cost Housing”
ACSGE, BITS Pilani, India
IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308
_______________________________________________________________________________________
Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 469
BIOGRAPHIES
Miss. Anuja M. Rajguru received B.E
(Civil Engineering) from SGB Amravati
University in 2013 and pursuing M.E.
(Construction Engineering and
Management) from SGB University. Right
now working as a lecturer in the Dept. of
Civil Engineering at Prof. Ram Meghe College of
Engineering & Management, Badnera –Amravati
Mr. Parag Mahatme received B.E. (Civil
Engineering) & M.Tech. (Environmental
Engineering) from Govt. College of
Engineering Amravati in 2009 & 2011
respectively. He is working as Assistant
Professor in PRMCEAM, Badnera.

More Related Content

PPT
Quality control in construction
PPTX
Underwater construction
PPTX
Construction Equipment Management
PPTX
Safety in construction
PPTX
Construction Project Management.
PDF
Construction Management - New Trends
PPTX
BIM Presentation
PPTX
Tendering
Quality control in construction
Underwater construction
Construction Equipment Management
Safety in construction
Construction Project Management.
Construction Management - New Trends
BIM Presentation
Tendering

What's hot (20)

PDF
Construction Project Management
PDF
Scaffold safe work method statement
PPTX
Contract and Arbitration
PDF
Estimation and Evaluation of G+3 Residential Building
PPTX
Construction Cost Control
PPTX
Safety management for construction machines & equipments
PPTX
Stakeholder management In Construction Industry
PDF
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
PPTX
Construction Project Management
PDF
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
PPTX
Construction safety management
PPTX
Burj Khalifa Tower Project
PDF
Standards of Cruise Terminal
PDF
Project management in construction
DOCX
Pre qualification stages and tender selection
DOC
Method statement for repair of concrete surface
PDF
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
PPT
Safety in Excavations
PPTX
Terminal 4, Changi airport Singapore
PPTX
Construction Project Management
Construction Project Management
Scaffold safe work method statement
Contract and Arbitration
Estimation and Evaluation of G+3 Residential Building
Construction Cost Control
Safety management for construction machines & equipments
Stakeholder management In Construction Industry
QUALITY CONTROL AND SAFETY DURING CONSTRUCTIONIjmet 08 03_012
Construction Project Management
Module-1:Introduction to Construction Management by Dr. Vinay Kumar B M
Construction safety management
Burj Khalifa Tower Project
Standards of Cruise Terminal
Project management in construction
Pre qualification stages and tender selection
Method statement for repair of concrete surface
Module 3 - Construction quality and safety by Dr.Vinay Kumar B M
Safety in Excavations
Terminal 4, Changi airport Singapore
Construction Project Management
Ad

Viewers also liked (9)

PPTX
Cost Effective Construction Techniques By Okey Fabian Eze
PPTX
Cost Effective Construction Techniques By Stephen Rayment
PPTX
Cost effective construction tech PPT
PPTX
Cost Effective and Alternate construction techniques
PPTX
Cost effective construction techniques
PDF
Cost effective construction materials
PPT
Queuing Theory by Dr. B. J. Mohite
PPT
QUEUING THEORY
Cost Effective Construction Techniques By Okey Fabian Eze
Cost Effective Construction Techniques By Stephen Rayment
Cost effective construction tech PPT
Cost Effective and Alternate construction techniques
Cost effective construction techniques
Cost effective construction materials
Queuing Theory by Dr. B. J. Mohite
QUEUING THEORY
Ad

Similar to Effective techniques in cost optimization of construction project an review (20)

PDF
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
PDF
B1303020508
PDF
The role of time, cost and quality in project management
PDF
Construction Project Scheduling of MK Apartment using MS Project 2013
PDF
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
PDF
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
PDF
Assesing the various problems facing in arranging appropirate labour and qual...
PDF
IRJET- To Study the Causes and Effects of Delays in Construction Project
PDF
Evaluate the effective resource management through pert analysis
PDF
Review Application of value engineering in construction project.
PDF
IRJET-Influence of Material Management on Construction Project
PDF
Efficient Planning Scheduling and Delay Analysis of Residential Project
PDF
Role of PMC in Construction of Collector Well Project, a Case Study
PDF
Element of Cost overrun and Delay in Construction: A Review
PDF
Application of Value Engineering in Commercial Building Projects
PDF
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
PDF
Ijciet 10 01_075
PDF
Application of Value Engineering in Construction Projects
PDF
IRJET- Study on Economic Sustainability of Industrial Buildings
PDF
Project Planning: Advanced Techniques and Process Waste Removals – A Review
IRJET- Planning and Scheduling Multi- Storeyed Residential Building using Mic...
B1303020508
The role of time, cost and quality in project management
Construction Project Scheduling of MK Apartment using MS Project 2013
IRJET- Implementing Time and Cost Optimization in Commercial Building using P...
IRJET- Controlling and Monitoring the Construction Projects by using Earned V...
Assesing the various problems facing in arranging appropirate labour and qual...
IRJET- To Study the Causes and Effects of Delays in Construction Project
Evaluate the effective resource management through pert analysis
Review Application of value engineering in construction project.
IRJET-Influence of Material Management on Construction Project
Efficient Planning Scheduling and Delay Analysis of Residential Project
Role of PMC in Construction of Collector Well Project, a Case Study
Element of Cost overrun and Delay in Construction: A Review
Application of Value Engineering in Commercial Building Projects
USING LEAN TECHNIQUES TO REDUCE WASTE AND IMPROVE PERFORMANCE IN MUNICIPAL CO...
Ijciet 10 01_075
Application of Value Engineering in Construction Projects
IRJET- Study on Economic Sustainability of Industrial Buildings
Project Planning: Advanced Techniques and Process Waste Removals – A Review

More from eSAT Journals (20)

PDF
Mechanical properties of hybrid fiber reinforced concrete for pavements
PDF
Material management in construction – a case study
PDF
Managing drought short term strategies in semi arid regions a case study
PDF
Life cycle cost analysis of overlay for an urban road in bangalore
PDF
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
PDF
Laboratory investigation of expansive soil stabilized with natural inorganic ...
PDF
Influence of reinforcement on the behavior of hollow concrete block masonry p...
PDF
Influence of compaction energy on soil stabilized with chemical stabilizer
PDF
Geographical information system (gis) for water resources management
PDF
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
PDF
Factors influencing compressive strength of geopolymer concrete
PDF
Experimental investigation on circular hollow steel columns in filled with li...
PDF
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
PDF
Evaluation of punching shear in flat slabs
PDF
Evaluation of performance of intake tower dam for recent earthquake in india
PDF
Evaluation of operational efficiency of urban road network using travel time ...
PDF
Estimation of surface runoff in nallur amanikere watershed using scs cn method
PDF
Estimation of morphometric parameters and runoff using rs & gis techniques
PDF
Effect of variation of plastic hinge length on the results of non linear anal...
PDF
Effect of use of recycled materials on indirect tensile strength of asphalt c...
Mechanical properties of hybrid fiber reinforced concrete for pavements
Material management in construction – a case study
Managing drought short term strategies in semi arid regions a case study
Life cycle cost analysis of overlay for an urban road in bangalore
Laboratory studies of dense bituminous mixes ii with reclaimed asphalt materials
Laboratory investigation of expansive soil stabilized with natural inorganic ...
Influence of reinforcement on the behavior of hollow concrete block masonry p...
Influence of compaction energy on soil stabilized with chemical stabilizer
Geographical information system (gis) for water resources management
Forest type mapping of bidar forest division, karnataka using geoinformatics ...
Factors influencing compressive strength of geopolymer concrete
Experimental investigation on circular hollow steel columns in filled with li...
Experimental behavior of circular hsscfrc filled steel tubular columns under ...
Evaluation of punching shear in flat slabs
Evaluation of performance of intake tower dam for recent earthquake in india
Evaluation of operational efficiency of urban road network using travel time ...
Estimation of surface runoff in nallur amanikere watershed using scs cn method
Estimation of morphometric parameters and runoff using rs & gis techniques
Effect of variation of plastic hinge length on the results of non linear anal...
Effect of use of recycled materials on indirect tensile strength of asphalt c...

Recently uploaded (20)

PPTX
Geodesy 1.pptx...............................................
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Categorization of Factors Affecting Classification Algorithms Selection
PPT
Total quality management ppt for engineering students
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPTX
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
PDF
Well-logging-methods_new................
PPTX
Safety Seminar civil to be ensured for safe working.
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
DOCX
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
PPTX
Fundamentals of safety and accident prevention -final (1).pptx
PPTX
Internet of Things (IOT) - A guide to understanding
PDF
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
Artificial Intelligence
PDF
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
PPTX
Fundamentals of Mechanical Engineering.pptx
PDF
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
PPT
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
DOCX
573137875-Attendance-Management-System-original
Geodesy 1.pptx...............................................
Embodied AI: Ushering in the Next Era of Intelligent Systems
Categorization of Factors Affecting Classification Algorithms Selection
Total quality management ppt for engineering students
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
6ME3A-Unit-II-Sensors and Actuators_Handouts.pptx
Well-logging-methods_new................
Safety Seminar civil to be ensured for safe working.
UNIT-1 - COAL BASED THERMAL POWER PLANTS
ASol_English-Language-Literature-Set-1-27-02-2023-converted.docx
Fundamentals of safety and accident prevention -final (1).pptx
Internet of Things (IOT) - A guide to understanding
A SYSTEMATIC REVIEW OF APPLICATIONS IN FRAUD DETECTION
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Artificial Intelligence
BIO-INSPIRED HORMONAL MODULATION AND ADAPTIVE ORCHESTRATION IN S-AI-GPT
Fundamentals of Mechanical Engineering.pptx
null (2) bgfbg bfgb bfgb fbfg bfbgf b.pdf
Introduction, IoT Design Methodology, Case Study on IoT System for Weather Mo...
573137875-Attendance-Management-System-original

Effective techniques in cost optimization of construction project an review

  • 1. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 464 EFFECTIVE TECHNIQUES IN COST OPTIMIZATION OF CONSTRUCTION PROJECT: AN REVIEW Anuja Rajguru1 , Parag Mahatme2 1 P. G. Scholar, Department of Civil Engineering, PRMCEAM, Badnera, M.S. India 2 Assistant Professor, Department of Civil Engineering, PRMCEAM, Badnera, M.S. India Abstract In the construction project, time and cost are the most important factors to be considered in the planning of every project. The aim of project is to finish the projects on time, within budget and to achieve other project objectives. It is a difficult task undertaken by project managers in practice, which include constantly measuring progress, evaluation of plans, and corrective actions should be taken whenever required. Optimization is a systematic effort made to improve profit margins and obtain the best results under given circumstances. There is a Systematic planning and programming with effective management is necessary for timely completion of the project. there is availability of various tools and techniques for optimization. Optimizing performance of the different techniques adopted at one stage of the construction process may not be beneficial if the methods used are not to up the efficient level. In this approach we have studied various factors which affect the cost of projects. again in this approach we have studied various techniques and various materials used for cost optimization. Also the need of optimization is discussed. Keywords: time, cost, optimization. --------------------------------------------------------------------***----------------------------------------------------------------- 1. INTRODUCTION India is the developing country and in the economy of country construction projects and industries play an vital role. Time and cost are two main concerns in a construction and they are used for planning a project. This has increased the importance of time and Cost optimization in construction projects. is necessary to estimate the cost and time of each activity through which the whole duration and total cost of the project are determined to complete the planning task. Optimization is a systematic effort made to improve profit margins and obtain the best results under given circumstances or situations. “Cost Optimization can be defined as the achievement of real and permanent reduction in the unit cost of services provided without damaging their suitability for the in planned use”. There is availability of various techniques for optimization and project control software, still many construction projects do not achieve their cost and time objectives. Optimizing performance of the different techniques adopted at one stage of the construction process may not be beneficial if the methods used are not to up the efficient level. Hence it is required to follow and implement the techniques in every stage of the construction process with the analyses of the information available. The methodology and the type of the used in a construction is also plays very important role for the successful completion of a project. 1.1 Need of Optimization The optimization of time and cost is necessary as it could minimize both the time and total cost of project. This optimization in time and cost helps to achieve the greatest benefit. 2. LITERATURE REVIEW Shanmugapriya S., Dr. Subramanian K. (October 2013) [1] Time overruns and Cost overruns has been a major issue in many Indian construction projects. The objective of this paper to study significant factors causing Time overruns and Cost overruns in Indian construction projects. The result accomplished from the survey revealed that the major cause for time overruns are contract modification, material market rate, and high level of quality requirement and the major cause for cost overruns are , change in material specification, high transportation cost, and escalation of materials price. Salunkhe. A, Patil R (Janeuary2014) [2] Construction delay is considered to be one of the recurring problems in the construction industry and it has an adverse effect on project success in terms of time, cost and quality. The time and cost for performance of a project are usually important to the employer and contractor. The authors highlights the types of construction delays due to which project suffer time and cost overrun. also give external and internal factors that influence the construction process and outlines the effect of delay in large construction projects. T.Subramani , P S Sruthi, M.Kavitha (June. 2014) [3] The main objectives of this paper are to identify and analyze the causes of cost overrun in construction. The results carried out from survey showed that, poor contract management, slow decision making, poor schedule management, increase in material/machine prices poor design/ delay in providing design, rework due to wrong work, long period between design and time of bidding/tendering and wrong estimation/ estimation method are the major causes of cost overrun.
  • 2. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 465 Memon A.H, Rahman I.A, Mohd Razaki Abdullah3, Ade Asmi Abdu Azis, (December 2010) [4] Project cost is one of the most important criteria of success of project. the authors are focusing on identification of significant causes affecting construction cost in MARA large projects. From the study author found that contractor's poor site management and supervision, cash flow and financial difficulties faced by contractors, shortage of site workers, inadequate contractor experience, incorrect planning and scheduling by contractors are most severe factors which affect cost of project. while changes in scope of project and frequent design changes are least affecting factors on construction cost. Benviolent Chigara,Tirivavi Moyo, Fungai Mudzengerere (2013) [5] they made the research for the cost management strategies employed by contractor on building projects. Also made investigation that contractor has to manage project cost. For data collection they made the survey and interviews in Zimbabwe. From study they found that contractor efforts to manage the project cost by concentrating on the management on the project resources. Also the cost management process in Zimbabwe compare to other developing countries is still dominated by prematurely developed automated system or traditional paper based systems of managing project cost information. The author provide a base line information on strategies used for managing project cost. Barbole A.N., Yuvraj D. Nalwade, Santosh D. Parakh ( June. 2013) [6] The survival today for any company is how to manage its service Cost, quality, and performance. Now a days the customers are continuously demanding high quality and better performance of services and at the same time they want the prices to fall. For this author focus on impact of cost control and cost reduction techniques in present scenario. An objective of this paper is to understand the basic concept of Cost, Cost Control, and Cost Reduction and to study various Tool and Techniques available for Cost Control and Cost Reduction. The Cost Control and Cost Reduction techniques used in manufacturing sector like Value Engineering, Quality Control, and Budgetary Control are specified by the author also cost, cost reduction, cost control etc. Various terms are specified by the author. C.I. Anyanwu (December 2013) [7] author discuss about the various parameters regarding the cost such as budgeting, cost monitoring and control systems. he discuss about the cost control and the cost control parameter in material, labor, equipments etc .As per the author concept of budget can be define as the translation of an organizational plan into concrete form by way of resource allocation in form of cash. He discuss about the various tools used by the management and cost supervisors for planning, controlling, and monitoring of project such as Gantt chart, network analysis, CPM, PERT. Main focus of author is to study the manufacturing philosophy and inputs which contributes in evaluating and maintaining construction cost in order to reduce the project abandonment which is caused due to cost overrun. Akintola Omigbodun (June 2001) [8] as per the author value engineering can be defined as the ‘‘Engineering is the conceptualization, design, construction, and administration of projects and products whatever the field or application, the engineer solves problems with imagination, creativity and synthesis of various sources of knowledge.’’ To obtain the optimal solution for any engineering design 4 methods has discussed are as follows design for manufacturing and assembly, concurrent engineering, total quality management, and value engineering. A summary of other methods of optimal design methods are compared with value engineering. Cost minimization in building construction is discussed with examples on building projects in West Africa and the Middle East. From study author concluded that, due to application of value engineering to building projects management team obtains a solution which emphasis the functions of project which helps to team to make final choice and which results in cost effective design for project. Value engineering is effective because its procedures give opportunities for raising design issues associated with the latter group of factors as well as design. Georgekutty C.K, Dr. George Mathew (August - 2012) [9]the innovation of new technology in the construction field is not being adopted in project implementation. this results the growth of construction industry is slow. The real problem is construction will not complete within the budgeted cost and time and finally leads to project failure as end result. Material has a dominating role in construction. If the material has controlled properly then the total project cost would be reduced. To achieve this objective, a research methodology has developed by author to control the material procurement and carrying cost. The methodology adopted which adopted has been validated by a computer program and same is found correct and useful for analysis and controlling any type of projects. J Zhou, Ped Love, X Wang, Kl Teo And Z (Irani 2013) [10] main objective of the paper is to Optimize construction scheduling. for this author adopted various methods like Mathematical Method, Heuristic Method, Metaheuristic Method. As per the author the Methods and algorithms applied for optimizing construction scheduling efficient and effective. Khyomesh V. Patel, Prof. Chetna M. Vyas ( May 2011) [11] as per the author to manage the productivity and the cost efficiency material management is more essential. the main objective of the material management are buying or purchasing, storing and inventory control, quality assurance. to achieve these objectives there is need of material management. Author carried out as survey in Ahmadabad to check material management. they investigate that material and equipment contribute 70% that of total cost. hence for the improvement of product and cost efficiency material management is important. Also proper tracking, controlling is required, if there is poor management may lead to delay of project.
  • 3. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 466 Hisham Said, Khaled El-Rayes, (June 2011) [12]the authors suggested new model of construction logistics planning to enable the optimization and integration of critical planning decisions of material procurement and also of the material storage on construction site. To check the capability of CLP model one example was analyzed. After the analysis the results obtained that material procurement decisions are affected by the criticality of construction activities consuming the material, site space available, material procurement and site layout constrains. Andrew N Baldwin, Simon A Austin, Chi-Sun Poon, Li-Yin Shen, Irene Wong (June 2007) [13] the design of high rise building I different from the different of residential and other forms of buildings because of the repetition of the construction and time for the completion of each floor. The main objective of the authors is to develop the model or tools and techniques for analyzing the information for the high rise building. Also, to investigate the difference in the various models for the private residential buildings. Authors discuss about the optimization techniques such as design structural matrix. From study author conclude that there is need to develop the new tools and techniques which can help to designer to analyze the information and to make the improvement in the design management which helps for optimization. P. Tiwari, K. Parikh, J. Parikh (September 1999) [14] authors discussed about the theoretical basic of hope model. Propose new model of multi criteria optimization technique for buildings. Also Suggested that multi criteria optimization model can b developed to solve the problem in Road, Bridge, and Tunnel construction. Kale R, Gore G. N, Salunke J. P, (January 2014) [15] Main objective of this paper is cost optimization of bridge including the material. As per the authors the optimization is made for the different grade of steel and concrete. for this they applied direct design method for analyzing the structure. The methodology adopted by them is Nonlinear Programming Problem (NLPP) By Using MATLAB Software with SUMT (Sequential Unconstrained minimization technique). Authors found that there is a significant savings in cost overrun. C. Sarma, Hoijat Adeli (1998) [16] the objective of this paper is to optimize cost of concrete structures involves beams, slabs, columns, bridges, water tanks, frame structures, tensile members, folded plates, and shear walls, pipes. One method for Cost Optimization Using Reliability Theory is explained. From the study the authors concluded that there is a need to perform research on cost optimization of realistic three-dimensional structures, especially for the large structures with number of members where optimization can result in substantial savings. Gopal M. Naik , M. Kumar (September 2013) [17] The main objective of the paper is To increase the productivity and necessary to forecast the costs arriving from resources so that the total cost of project can be reduced. The Artificial Neural Networks have become well established as viable, multipurpose, robust computational methodologies with solid theoretic support and with strong potential to be effective in any discipline, especially in construction. From survey results comes out that the Neural Networks approach has optimized the total project cost by 3.91%, and the duration of the project has been reduced around 5% of the total duration of the project. Shrivastava R, Singh S. , Dubey C. G. (2012) [18] Time and cost are the most important factors to be considered in every construction project. Ant colony optimization technique was introduced in the early 1990’s as a novel technique for solving hard combinational optimization problem. on basis of that author developed new multi-colony ant algorithm for the optimization of three objectives time-cost quality with quantity. The model is also applied to two objectives time – cost trade off problem. The results which are coming out compared to those of the existing approaches. As per the authors Model is capable of compromising between important aspect of construction projects Seyed Ali Mousavi Dehmourdi (2014) [19] the Objective of this paper are to apply the principles of engineering economics, basic economic concepts , finance and quantitative techniques to modeling and analysis of civil engineering projects. Also a practical application of linear programming in a real life project problem with two objectives as optimization of transporting cost of equipment and finding the best solution for reducing the functional costs of the equipment. Mainly structured linear programming model is used for optimizing the transporting cost of equipment. Applications of this approach helps in determining the need for the replacement and the maintenance analysis are based on the econometric approach to the realistic problems and the result shows that optimization with advanced techniques really helps in minimization of cost of project. Daisy X.M. Zheng, S. Thomas Ng , Mohan M. Kumaraswamy (September 2002) [20] Completing a construction project with the least time and cost is critical Factor and usually requires the engagement of additional labor and plant or the adoption of alternative construction techniques which add extra cost liabilities to the contractor. For time-cost optimization several analytical models have been developed. From those the Genetic Algorithms (GA) could be used to establish the fitness of solutions by evaluating the objective function and its constraints. the objective of paper is to compare the analytical power of the GA with other techniques proposed for TCO. The results come out which indicate that the GA techniques could generate the most optimal outcome for construction Time- Cost Optimization it is more beneficial when the project is large and/or complex. S. Thomas Ng And Yanshuai Zhang (September 2008) [21] main objective of the paper is to Optimize Construction Time and Cost of project. For this they adopted the Ant Colony Method of optimization. Main aspect is Time, Cost
  • 4. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 467 And Quality Optimization. They made the Comparison with the other optimization methods. Ant colony method is the multi objective optimization techinque. Daisy X.M. Zheng, S. Thomas Ng, Mohan M. Kumaraswamy (2002) [22] They applied a Genetic Algorithm to the project for Multi objective optimization. As per the author Genetic Algorithm is multi objective i.e. Time, Cost and Quality optimization. Also GA techniques could generate the most optimal outcome For construction Time cost Optimization. A.S. Ali, S.N. Kamaruzzaman (2010) [23] as per the author for management of construction 4 parameters important are as follows: scope, cost, time, and quality. the main aim of the author is to find out the problem or parameters which contribute for the cost overrun. for this they carried out the quaternary survey on the live projects. for the data analysis the method used is quantitative based i.e. descriptive statistics and ranking analysis is used. from the investigation they found that factors which contributes to cost overrun was inaccurate or poor estimation of original cost and factor which don't affect is mistake in design for this to control the construction cost method suggested by the author is proper costing and financing. also they concluded that cost overrun is most serious problem which may affect the construction project effectively. Ming Li ,Guangdong Wurobust, (2014) [24] the objective of this paper is to optimization of a time-cost tradeoff problem. Based on multi objective robust optimization method, a optimization model for time-cost tradeoff problem is developed. The results come out that, by means of adjusting the time and cost robust coefficients, the robust Pareto sets for time-cost tradeoff can be obtained according to different acceptable risk level, from which the decision maker could choose the preferred construction alternative. Pathak.U.J, Chavan.C.S, Rathode.L.V, Nachare.V.L, Suryawanshi.A.B, (Apr 2014) [25] Low cost housing technologies aim to cut down construction cost by using alternatives to conventional methods and Input. Authors examined the cost effectiveness of using low cost housing technologies in comparison with the traditional construction methods. From Two case studies in India found that about 22 to 26 % of the construction cost including material and labor cost can be saved by using the low cost housing technologies in comparison with traditional construction methods for walling and roofing respectively. Tam W. Y, (2011) [26] It is necessary to adopt cost effective, innovative and Eco-friendly housing technologies for the construction of houses and buildings for enabling the common people to construct houses at affordable cost. Methodology used by author is to compares construction cost for the traditional and low cost housing technologies. For which Case studies in India are used for the investigation. Construction methods, Strength and durability of the structure, stability, safety of various members are compared during cost reduction. The result found that about 26.11% and 22.68% of the construction cost can be saved by using low cost housing technologies in comparison with the traditional construction methods. This proves that using low cost housing technologies is a cost effective construction approach for the industry. Nilanjan Sengupta (January 2008) [27] as per the author the cost effective construction technologies are useful and beneficial from both in terms of cost and environment. Author discuss about the some effective technologies in India with their features and advantages. Technologies used in India are 1) Rat trap bond wall: due to this bond cost and material is saved and strength is more 2) Brick arch: it is given with its construction. It is beneficial from appearance point of view 3) Filler slab : its slab construction is also discussed. Its advantageous from economy, appearance, strength, material usage and reduction, less weight, material saving point of view. 4) compressed earth block : it is beneficial because it absorb less water in rainfall. From the study author concluded that, if we pay attention towards the terms like sanitization of people, manpower development, material devolvement, technical guidance’s then the cost effective techniques will be extensively used in the light of sustainable development and protection of environment. R. Taur, V. Devi (Oct 2009) [28]the main objective of this paper is to point out the various aspect of prefabricated building methodology for low housing. For this different prefabrication techniques with their advantage and importance are given by authors. In a building the foundation, walls, doors and windows, floors, roofs are the most important components which can be analyzed individually based on the needs. There is need for improving the speed of construction and reducing the construction cost. The methods of construction systems suggested by authors are as follows prefabricated roofing components like precast RC planks, structural block walls, precast hollow concrete panels, precast concrete/Ferro cement panels, mortar less block walls. 3. CONCLUSION In this paper we have reviewed different techniques for optimization. To minimize the construction cost and duration at each phase is important. It is a need to meet the present day requirements and to complete the project within the estimated time, cost, and available resources. Mainly affecting the factor on cost of project is delay in project and material. Several methods have been developed and applied to analyze the time-cost problems, but they can optimize only one parameter. Various low cost material also suggested for optimizing the cost of project along with maintaining the quality and strength of the project. Also various mathematical method and software based models studied for optimization.
  • 5. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 468 REFERENCES [1]. Shanmugapriya S., Dr. Subramanian K.,(October 2013) “Investigation of Significant Factors Influencing Time And Cost” International Journal Of Emerging Technology And Advanced Engineering Volume 3. [2]. Salunkhe. A, Patil R., (Jan-2014) “Effect of Construction Delays on Project Time Overrun: Indian Scenario” Ijret: International Journal of Research in Engineering and Technology volume: 03 [3]. T.Subramani , P S Sruthi, M.Kavitha, (June. 2014) “Causes Of Cost Overrun In Construction” Iosr Journal Of Engineering, vol. 04 [4]. Memon A.H, Rahman I.A, Mohd Razaki Abdullah3, Ade Asmi Abdu Azis, (December 2010) “Factors Affecting Construction Cost In Mara Large Construction Project: Perspective Of Project Management Consultant” International Journal Of Sustainable Construction Engineering & Technology Vol 1, No 2. [5]. Benviolent Chigara,Tirivavi Moyo, Fungai Mudzengerere (2013) "An Analysis Of Cost Management Strategies Employed By Building Contractors On Project In Zimbabwe" International Journal Of Sustainable Construction Engineering & Technology Vol 4, No 2. [6]. Barbole A.N., Y. D. Nalwade, S. D. Parakh (June. 2013) “Impact Of Cost Control And Cost Reduction Techniques On Manufacturing Sector” Indian Streams Research Journal Volume 3. [7]. C.I. Anyanwu (December 2013) "Project Cost Control in The Nigerian Construction Industry" International Journal Of Engineering Science Invention Volume 2 Issue 12. [8]. Akintola Omigbodun (June 2001) "Value Engineering and Optimal Building Projects" Journal of Architectural Engineering. [9]. Georgekutty C.K, Dr.George Mathew (August - 2012) "Research Methodology For Material Optimization In Construction Projects” International Journal Of Engineering Research & Technology (Ijert) Vol. 1. [10]. J Zhou, Ped Love, X Wang, Kl Teo And Z Irani 2013 A Review Of Methods And Algorithms For Optimizing Construction Scheduling" Journal Of The Operational Research Society Vol. 64, No. 8 [11]. Khyomesh V. Patel, Prof. Chetna M. Vyas (13-14 May 2011) "Construction Materials Management On Project Sites" National Conference On Recent Trends In Engineering & Technology B.V.M. Engineering College, V.V.Nagar, Gujarat, India. [12]. Hisham Said, Khaled El-Rayes, (June 2011) “Optimizing Material Procurement and Storage on Construction Sites” Journal of Construction Engineering and Management [13]. Andrew N Baldwin, Simon A Austin and Chi-sun Poon, Li-yin Shen and Irene Wong (June 2007) “Reducing Waste in High-Rise Residential Buildings by Information Modeling at the Design Stage” Surveying and Built Environment Vol 18. [14]. P. Tiwari, K. Parikh, J. Parikh (September 1999) “Structural Design Considerations In House Builders’ Model: Optimization Approach" Journal of Infrastructure Systems. [15]. Kale R, Gore G. N, Salunke J. P, (January 2014) “Cost Optimization of R.C.C. T-Beam Girder” International Journal Of Soft Computing And Engineering, Volume-3. [16]. K. C. Sarma, Hoijat Adeli (May 1998) “Cost Optimization Of Concrete Structures” Journal Of Structural Engineering. [17]. G. M. Naik , M. Kumar, (September 2013) “Project Cost And Duration Optimization Using Soft Computing Techniques” Journal Of Advanced Management Science Vol. 1, No. 3. [18]. Shrivastava R, Singh S., Dubey C. G. (2012) “Multi Objective Optimization Of Time Cost Quality Quantity Using Multi Colony Ant Algorithm” Int. J. Contemp. Math. Sciences, Vol. 7. [19]. Seyed Ali Mousavi Dehmourdi (2014) "Optimization Of Construction Cost Applying Advanced Techniques" International Journal Of Structural & Civil Engineering Research. [20]. Daisy X.M. Zheng, S. Thomas Ng , M. M. Kumaraswamy (September 2002) "Applying Genetic Algorithm Techniques For Time-Cost Optimization" In: Greenwood, D (Ed.), 18th Annual Arcom Conference, University Of Northumbria. Association Of Researchers In Construction Management, Vol. 2 [21]. S. Thomas Ng And Yanshuai Zhang (September 2008) "Optimizing Construction Time And Cost Using Ant Colony Optimization Approach" Journal Of Construction Engineering And Management © ASCE [22]. Daisy X.M. Zheng, S. Thomas Ng , Mohan M. Kumaraswamy (APRIL 2004) "Applying a Genetic Algorithm-Based Multi objective Approach for Time-Cost Optimization" Journal Of Construction Engineering And Management © ASCE [23]. A.S. Ali, S.N. Kamaruzzaman (2010) "Cost Performance For Building Construction Projects In Klang Valley " Journal Of Building Performance Issn: 2180-2106 Volume 1. [24]. Ming Li ,Guangdong Wu (2014) “Robust Optimization For Time-Cost Tradeoff Problem In Construction Project” Hindawi Publishing Corporation Abstract and Applied Analysis Volume 2014. [25]. Pathak.U.J, Chavan.C.S, Rathode.L.V, Nachare.V.L, Suryawanshi.A.B, (Apr 2014) “Cost Effective House By Using Various Construction Techniques And Materials” Indian Journal Of Applied Research Volume: 4. [26]. Tam W. Y, (2011) “Cost Effectiveness Of Using Low Cost Housing Technologies In Construction” Science Direct. [27]. Nilanjan Sengupta (January 2008) “Use Of Cost- Effective Construction Technologies In India To Mitigate Climate Change” Current Science, Vol. 94 [28]. R. Taur, V. Devi (Oct 2009) “Low Cost Housing” ACSGE, BITS Pilani, India
  • 6. IJRET: International Journal of Research in Engineering and Technology eISSN: 2319-1163 | pISSN: 2321-7308 _______________________________________________________________________________________ Volume: 04 Issue: 03 | Mar-2015, Available @ http://www.ijret.org 469 BIOGRAPHIES Miss. Anuja M. Rajguru received B.E (Civil Engineering) from SGB Amravati University in 2013 and pursuing M.E. (Construction Engineering and Management) from SGB University. Right now working as a lecturer in the Dept. of Civil Engineering at Prof. Ram Meghe College of Engineering & Management, Badnera –Amravati Mr. Parag Mahatme received B.E. (Civil Engineering) & M.Tech. (Environmental Engineering) from Govt. College of Engineering Amravati in 2009 & 2011 respectively. He is working as Assistant Professor in PRMCEAM, Badnera.