ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
EXPERIMENT NO: 03
THE DETERMINATION OF THE INITIAL AND FINAL SETTING
TIME OF THE CEMENT BY VICAT NEEDLE APPARATUS.
ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
INTRODUCTION:
Setting time of cement: When cement is mixed with water, it hydrates and makes cement
paste. This paste can be molded into any desired shape due to its plasticity. Within this time
cement continues with reacting water and slowly cement starts losing its plasticity and set
harden. This complete cycle is called Setting time of cement.
Initial Setting time of Cement: The time at which cement starts hardens and completely loses
its plasticity is called Initial setting time of cement.
Final setting time of Cement: The time at which cement completely loses its plasticity and
became hard is a final setting time of cement.
USE OF SETTING TIME OF CEMENT:
Initial setting time of cement is important, to know when the cement is starting to lose its
plasticity. It is helpful in determining the time needed for the concreting process, i.e.
transportation, placing and compaction of concrete.
Final setting time of cement is important to know when the cement would be set. This testing
of cement is helpful to determine safe removal time of side of form (not vertical support) or
scaffolding of concrete.
SCOPE & SIGNIFICANCE:
This test method is used to determine the time of setting of the hydraulic cement by VICAT
needle apparatus.
The knowledge of the setting time of the cement is always helpful in deciding the time duration
to mix, transport, place and compact the concrete effectively.
We always prefer a larger initial setting time so that we can mix, transport and place the
concrete easily. According to ASTM specifications, the initial setting time shall not be less
than 45 min but in the field we prefer an initial setting time not less than 90 min.
A smaller value of the final setting time is always preferred in order to avoid large expenditures
on the formwork. According to most of the specifications, the final setting time shall not be
greater than 10hrs and shall not be less than (90 + 1.2 x (initial setting time)) min.
FACTORS THAT AFFECT INITIAL AND FINAL SETTING TIME OF CEMENT: -
The fineness of cement, the presence of salts in sand, atmospheric conditions. For example,
cement requires a temperature of 27°c to complete Hydration, during winters the climate is low
which stops the hydration and takes a longer time to set harden.
ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
APPARATUS
VICAT apparatus
Needle of 1mm2 cross-section and
50mm length (for initial setting time)
Plunger with 1mm smaller needle
and 5mm outer diameter (for final
setting time)
Flat trowel
Graduated cylinders & Enamel tray
Stop watch
Balance
ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
TEST PROCEDURE
Initial Preparation
 Consistency test to be done before starting the test procedure to find out the water
required to give the paste normal consistency (P).
 Take 250 g of cement and prepare a neat cement paste with 0.85P of water by weight
of cement.
 Gauge time is kept between 3 to 5 minutes. Start the stop watch at the instant when the
water is added to the cement.
 Fill the Vicat mould, resting on a glass plate, with the cement paste gauged as above.
Fill the mould completely and smooth off the surface of the paste making it level with
the top of the mould. The cement block thus prepared is called test block.
 The mould may be slightly shaken for remove the air.
Initial Setting Time of Cement
 Place the mould under the rod bearing the needle. (needle for determining the initial
setting time)
 Lower the needle slightly until it comes in contact with the surface of the test block
and quickly release, allowing it to penetrate the test block.
 In the starting, the needle will completely penetrate the test block.
 Repeat this procedure until the needle fails to penetrate the block to the 5 to 7 mm
from the bottom of the mould.
 The period elapsing between the time when water is added to the cement and the
time at which the needle fails to penetrate the test block to the 5 to 7mm from the
bottom of the mould is called the initial setting time.
Final Setting Time of Cement
 To determine the final setting time, the first needle is replaced by the (needle for
determining the final setting time) needle with an annular attachment.
 When applying the needle gently to the surface of the mould, the needle makes an
impression thereon.
 Cement called as final set while the attachment fails to make an impression on the
surface of the test block.
 The period elapsing between the time when water is added to the cement and the
time at which the needle fails to make an impression on the surface of the test block
is called the final setting time.
ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
CALCULATIONS
Initial setting time:
Time when needle fails to penetrate 5 mm to 7 mm from bottom of the mould-Time at which water is first added
to cement.
Final setting time:
Time when the needle makes an impression but the attachment fails to do so - Time at which water is first added
to cement.
OBSERVATION:
Sample brand: Holcim Cement Room temperature :28°c
Normal Consistency: 33%
Weight of cement: 250gms
Water added: 70. 5 ML
Time when water is added to cement 10:35 am
Time at initial setting 12:30 pm
Initial setting time,(min) 115 min.
Time at final setting 2:20 pm
Final setting time,(min) 226 min
RESULTS:
Initial setting time: 115 min.
Final setting time: 226 min
The results of the initial and the final setting time should be reported to the nearest five minutes.
COMMENTS:
After performing the experiment, we have concluded the results that the initial setting time of
cement is 115 min and final setting time of cement paste is 226 min. The minimum initial
setting time is 30 minutes and maximum final setting time is 600min. As the Initial and Final
setting time is coming in between the prescribed range, it means that the experiment is
performed accurately.
SIGNATURE
ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN.
ACCEPTANCE CRITERIA:
Recommended result for various types of cement to their setting time gives by standard
guidelines are as follows:
If test value is not in a rage of the recommended result, there many reasons behind it, such that
some chemical composition may have changed during production (manufacturing defect), fault
in the testing apparatus, error in testing etc. In that case, have to take care of the timing of work
with it. If the initial setting time less than this value, all the process, i.e. mixing, transporting,
placing complete within the time otherwise cement paste/concrete/mortar starts to getting set.
If the final setting time is more than this value, will have to retain scaffolding and the sides of
the form, until the cement paste/concrete/mortar is completely rigid and will have to be careful
to start the curing time.

More Related Content

PPT
Bricks fin
PDF
HƯỚNG DẪN ĐÁNH GIÁ ĐỘ KHÔNG ĐẢM BẢO ĐO TRONG PHÂN TÍCH HOÁ HỌC ĐỊNH LƯỢNG_102...
PPTX
Universal Testing Machine (1007, 1018).pptx
PPTX
Base isolation of structures
PDF
solution manual of mechanics of material by beer johnston
PDF
Structural Analysis - Virtual Work Method
PDF
Tham dinh phuong_phap_9426
PPTX
Various Govt. Schemes for Startups VMT
Bricks fin
HƯỚNG DẪN ĐÁNH GIÁ ĐỘ KHÔNG ĐẢM BẢO ĐO TRONG PHÂN TÍCH HOÁ HỌC ĐỊNH LƯỢNG_102...
Universal Testing Machine (1007, 1018).pptx
Base isolation of structures
solution manual of mechanics of material by beer johnston
Structural Analysis - Virtual Work Method
Tham dinh phuong_phap_9426
Various Govt. Schemes for Startups VMT

What's hot (20)

PDF
Bulk Density & Voids in Aggregate | Jameel Academy
DOCX
Sieve analysis of coarse and fine aggregate - Report
PDF
Sieve Analysis of Fine & Coarse Aggregate | Jameel Academy
PDF
Specific Gravity & Absorption of Aggregate (Coarse & Fine) | Jameel Academy
PDF
Compressive Strength of Hydraulic Cement Mortar | Jameel Academy
PDF
300 solved-problems
PPTX
Tests on cement
DOCX
Unconfined compression test
PDF
Aggregate impact value test experiment
PDF
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
PPTX
Expansive soil
DOCX
Specific gravity of Coarse aggregate
PDF
1-D Consolidation Test
 
PDF
FLOW OVER A SHARP CRESTED WEIR
PPTX
CBR TEST
DOCX
Liquid limit & plastic limit test
PDF
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
DOCX
Standard proctor test
PPTX
Consolidation settlement
Bulk Density & Voids in Aggregate | Jameel Academy
Sieve analysis of coarse and fine aggregate - Report
Sieve Analysis of Fine & Coarse Aggregate | Jameel Academy
Specific Gravity & Absorption of Aggregate (Coarse & Fine) | Jameel Academy
Compressive Strength of Hydraulic Cement Mortar | Jameel Academy
300 solved-problems
Tests on cement
Unconfined compression test
Aggregate impact value test experiment
Setting Time of Hydraulic Cement By Vicat Needle | Jameel Academy
Expansive soil
Specific gravity of Coarse aggregate
1-D Consolidation Test
 
FLOW OVER A SHARP CRESTED WEIR
CBR TEST
Liquid limit & plastic limit test
SPECIFIC GRAVITY TEST ON BITUMINOUS MATERIALS.
Standard proctor test
Consolidation settlement
Ad

Similar to Experiment no 03 setting time of cement. (20)

PDF
Cement Test.pdf
PPTX
Properties of Concrete (cement)
PPT
2-150331121223-conversion-gatefdgbv01.ppt
PPTX
Tests of cement in concrete technology
PPTX
Properties of concrete
PPT
2. testing of cement ppt
PPTX
Ppt on test certificate-Amit Payal
PPTX
Tests on cement
PPTX
Is 456 codal provisions
PPTX
Properties of Cement
PDF
3 setting time of cement
PPTX
694176489-Laboratory-Teshdsfsdjhfsjdts.pptx
PDF
Building materials lab_manual lab 01
PDF
Buildingmaterialslabmanuallab01 161125043012
PDF
Buildingmaterialslabmanuallab01 161125043012 (1)
PPTX
presentation_propertiesofcement_1513407631_244125.pptx
PDF
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
PPTX
testsoncement-160131205015.pptx in architecture
PDF
AUTOCLAVE, VICAT, GILLMORE - Material Testing.pdf
PPTX
How to determine Initial and Final Setting Time of Cement?
Cement Test.pdf
Properties of Concrete (cement)
2-150331121223-conversion-gatefdgbv01.ppt
Tests of cement in concrete technology
Properties of concrete
2. testing of cement ppt
Ppt on test certificate-Amit Payal
Tests on cement
Is 456 codal provisions
Properties of Cement
3 setting time of cement
694176489-Laboratory-Teshdsfsdjhfsjdts.pptx
Building materials lab_manual lab 01
Buildingmaterialslabmanuallab01 161125043012
Buildingmaterialslabmanuallab01 161125043012 (1)
presentation_propertiesofcement_1513407631_244125.pptx
EXPERIMENTAL BEHAVIOUR OF SELF COMPACTING CONCRETE USING GGBS WITH PARTIAL RE...
testsoncement-160131205015.pptx in architecture
AUTOCLAVE, VICAT, GILLMORE - Material Testing.pdf
How to determine Initial and Final Setting Time of Cement?
Ad

More from Sayed Sajid H.Zidani (7)

PDF
PENETRATION TEST ON BITUMINOUS MATERIALS.
PDF
Experiment no 03 Determination of the flakiness and the elongation index for ...
PDF
Experiment no 02 crushing value
PDF
Plastic Waste Management In Dhaka City
PPTX
LIGHTNING RELATED CAUSALITIES IN BANGLADESH (1990 TO 2018)
PDF
DETERMINATION OF AGGREGATE IMPACT VALUE.
PDF
Lightning Related Casualties in Bangladesh.
PENETRATION TEST ON BITUMINOUS MATERIALS.
Experiment no 03 Determination of the flakiness and the elongation index for ...
Experiment no 02 crushing value
Plastic Waste Management In Dhaka City
LIGHTNING RELATED CAUSALITIES IN BANGLADESH (1990 TO 2018)
DETERMINATION OF AGGREGATE IMPACT VALUE.
Lightning Related Casualties in Bangladesh.

Recently uploaded (20)

DOCX
573137875-Attendance-Management-System-original
PDF
PPT on Performance Review to get promotions
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PPT
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
PPTX
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPTX
Lecture Notes Electrical Wiring System Components
PPTX
web development for engineering and engineering
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPTX
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
PPTX
Sustainable Sites - Green Building Construction
PPT
Mechanical Engineering MATERIALS Selection
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PDF
Digital Logic Computer Design lecture notes
PDF
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
PDF
composite construction of structures.pdf
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
573137875-Attendance-Management-System-original
PPT on Performance Review to get promotions
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
CRASH COURSE IN ALTERNATIVE PLUMBING CLASS
Recipes for Real Time Voice AI WebRTC, SLMs and Open Source Software.pptx
bas. eng. economics group 4 presentation 1.pptx
Operating System & Kernel Study Guide-1 - converted.pdf
Lecture Notes Electrical Wiring System Components
web development for engineering and engineering
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
CARTOGRAPHY AND GEOINFORMATION VISUALIZATION chapter1 NPTE (2).pptx
Sustainable Sites - Green Building Construction
Mechanical Engineering MATERIALS Selection
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
Embodied AI: Ushering in the Next Era of Intelligent Systems
Digital Logic Computer Design lecture notes
TFEC-4-2020-Design-Guide-for-Timber-Roof-Trusses.pdf
composite construction of structures.pdf
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT

Experiment no 03 setting time of cement.

  • 1. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. EXPERIMENT NO: 03 THE DETERMINATION OF THE INITIAL AND FINAL SETTING TIME OF THE CEMENT BY VICAT NEEDLE APPARATUS.
  • 2. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. INTRODUCTION: Setting time of cement: When cement is mixed with water, it hydrates and makes cement paste. This paste can be molded into any desired shape due to its plasticity. Within this time cement continues with reacting water and slowly cement starts losing its plasticity and set harden. This complete cycle is called Setting time of cement. Initial Setting time of Cement: The time at which cement starts hardens and completely loses its plasticity is called Initial setting time of cement. Final setting time of Cement: The time at which cement completely loses its plasticity and became hard is a final setting time of cement. USE OF SETTING TIME OF CEMENT: Initial setting time of cement is important, to know when the cement is starting to lose its plasticity. It is helpful in determining the time needed for the concreting process, i.e. transportation, placing and compaction of concrete. Final setting time of cement is important to know when the cement would be set. This testing of cement is helpful to determine safe removal time of side of form (not vertical support) or scaffolding of concrete. SCOPE & SIGNIFICANCE: This test method is used to determine the time of setting of the hydraulic cement by VICAT needle apparatus. The knowledge of the setting time of the cement is always helpful in deciding the time duration to mix, transport, place and compact the concrete effectively. We always prefer a larger initial setting time so that we can mix, transport and place the concrete easily. According to ASTM specifications, the initial setting time shall not be less than 45 min but in the field we prefer an initial setting time not less than 90 min. A smaller value of the final setting time is always preferred in order to avoid large expenditures on the formwork. According to most of the specifications, the final setting time shall not be greater than 10hrs and shall not be less than (90 + 1.2 x (initial setting time)) min. FACTORS THAT AFFECT INITIAL AND FINAL SETTING TIME OF CEMENT: - The fineness of cement, the presence of salts in sand, atmospheric conditions. For example, cement requires a temperature of 27°c to complete Hydration, during winters the climate is low which stops the hydration and takes a longer time to set harden.
  • 3. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. APPARATUS VICAT apparatus Needle of 1mm2 cross-section and 50mm length (for initial setting time) Plunger with 1mm smaller needle and 5mm outer diameter (for final setting time) Flat trowel Graduated cylinders & Enamel tray Stop watch Balance
  • 4. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. TEST PROCEDURE Initial Preparation  Consistency test to be done before starting the test procedure to find out the water required to give the paste normal consistency (P).  Take 250 g of cement and prepare a neat cement paste with 0.85P of water by weight of cement.  Gauge time is kept between 3 to 5 minutes. Start the stop watch at the instant when the water is added to the cement.  Fill the Vicat mould, resting on a glass plate, with the cement paste gauged as above. Fill the mould completely and smooth off the surface of the paste making it level with the top of the mould. The cement block thus prepared is called test block.  The mould may be slightly shaken for remove the air. Initial Setting Time of Cement  Place the mould under the rod bearing the needle. (needle for determining the initial setting time)  Lower the needle slightly until it comes in contact with the surface of the test block and quickly release, allowing it to penetrate the test block.  In the starting, the needle will completely penetrate the test block.  Repeat this procedure until the needle fails to penetrate the block to the 5 to 7 mm from the bottom of the mould.  The period elapsing between the time when water is added to the cement and the time at which the needle fails to penetrate the test block to the 5 to 7mm from the bottom of the mould is called the initial setting time. Final Setting Time of Cement  To determine the final setting time, the first needle is replaced by the (needle for determining the final setting time) needle with an annular attachment.  When applying the needle gently to the surface of the mould, the needle makes an impression thereon.  Cement called as final set while the attachment fails to make an impression on the surface of the test block.  The period elapsing between the time when water is added to the cement and the time at which the needle fails to make an impression on the surface of the test block is called the final setting time.
  • 5. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. CALCULATIONS Initial setting time: Time when needle fails to penetrate 5 mm to 7 mm from bottom of the mould-Time at which water is first added to cement. Final setting time: Time when the needle makes an impression but the attachment fails to do so - Time at which water is first added to cement. OBSERVATION: Sample brand: Holcim Cement Room temperature :28°c Normal Consistency: 33% Weight of cement: 250gms Water added: 70. 5 ML Time when water is added to cement 10:35 am Time at initial setting 12:30 pm Initial setting time,(min) 115 min. Time at final setting 2:20 pm Final setting time,(min) 226 min RESULTS: Initial setting time: 115 min. Final setting time: 226 min The results of the initial and the final setting time should be reported to the nearest five minutes. COMMENTS: After performing the experiment, we have concluded the results that the initial setting time of cement is 115 min and final setting time of cement paste is 226 min. The minimum initial setting time is 30 minutes and maximum final setting time is 600min. As the Initial and Final setting time is coming in between the prescribed range, it means that the experiment is performed accurately. SIGNATURE
  • 6. ENGINEERING MATERIALS LABORATORY ENGR.SAYED SHAJEDUL HASAN. ACCEPTANCE CRITERIA: Recommended result for various types of cement to their setting time gives by standard guidelines are as follows: If test value is not in a rage of the recommended result, there many reasons behind it, such that some chemical composition may have changed during production (manufacturing defect), fault in the testing apparatus, error in testing etc. In that case, have to take care of the timing of work with it. If the initial setting time less than this value, all the process, i.e. mixing, transporting, placing complete within the time otherwise cement paste/concrete/mortar starts to getting set. If the final setting time is more than this value, will have to retain scaffolding and the sides of the form, until the cement paste/concrete/mortar is completely rigid and will have to be careful to start the curing time.