SlideShare a Scribd company logo
1
GENERATOR
MAINTENANCE
2
GENERATOR CLASSIFICATION
1. INDIRECT HYDROGEN COOLING OF
STATOR AND ROTOR
2. DIRECT GAS COOLING FOR ROTOR AND
DIMINERALISED WATER COOLING OF
STATOR
3. DIRECT GAS COOLING OF ROTOR AND
STATOR
4. AIR COOLED GENERATOR
3
DAILY CHECKS
CLEANLINESS OF THE BEARING INSULATION
CONSUMPTION OF HYDROGEN
GAS SAMPLE IN THE GAS TRAP
CLEAN THE BRUSH GEAR WITH DRY AIR
INSPECT THE SLIPRING CARBON BRUSHES,
PIGTAILS AND SIZE OF THE BRUSHES
REACTIVATION OF GAS DRYERS
CHECK THE LLD COLLECTION FOR OIL / WATER
 CHECK THE VENT LINE OF GAS COOLER FOR ANY
GAS COLLECTION.
4
WEEKLY CHECKS
CHECK THE SPRING TENSION OF THE SLIP RING
BRUSHES USING SPRING BALANCE(150-200gm/cm2)
VIBRATION OF THE BRUSHES
FREE MOVEMENT OF THE CARBON BRUSHES IN
THE HOLDER
START AND RUN THE STAND BY SEAL OIL PUMPS
AND STATOR WATER PUMPS.
CHECK THE FLOW OF SEAL OIL
CHECK THE BEARING VIBRATION USING PORTABLE
VIBRATION INSTRUMENT
5
MONTHLY CHECKS
• CHECK ALL THE BOLTS FOR TIGHTNESS
• CHECK ALL THE PROTECTION AND
INTERLOCKING CIRCUITS
• CHECK THE INSULATION AND SHAFT
VOLTAGE OF THE ROTOR SHAFT
• POLARITY OF SLIPRINGS ARE CHANGED
ONCE IN THREE MONTHS(DONE DURING SHUTDOWN)
• CONDITION OF SILICA GEL IN THE GAS
DRIER.
• MOISTURE CONTENT OF THE
HYDROGEN GAS
6
WHY OVERHAUL IS DONE ?
IT ENSURES NO BREAK DOWNS IN BETWEEN
THE OVERHAULS.
GENERATOR ARE SUBJECTED TO VARIOUS THERMAL,
ELECTRICAL AND MECHANICAL STRESSES.
TO INSPECT AND EXAMINE THE EXTENT OF DAMAGE
IN VARIOUS PARTS
IT IS MANDATORY TO UNDERTAKE CAPITAL
OVERHAUL
7
SCHEDULE OF OVERHAUL
FIRST INSPECTION : 8000 Hours
SECOND INSPECTION : 16,000 Hours
SUBSEQUENT OVERHAUL : AFTER EVERY 24,000 HOURS
TEQUIVALENT = T ACTUAL + Ns x Ts
TEQUIVALENT : EQUIVALENT RUNNING HOURS
T ACTUAL : ACTUAL RUNNING HOURS
Ns : NO OF STARTS
Ts 20 HOURS (ADDITIONAL NUMBER
OF OPERATING HOURS)
8
PRE OVERHAUL ACTIVITIES
1. ENSURE THAT ALL SPARES, CONSUMABLES, SPECIAL TOOLS AND OTHER
MATERIALS ARE AVAILABLE.
2. PREPARE PERT / BARCHART.
3. NOTE DOWN THE VARIOUS PARAMETERS OF THE MACHINE AT FULL LOAD.
4. MW, MVAR, HZ, PF, STATOR VOLTAGE & CURRENT, IRON & COPPER
TEMPERATURE, COLD GAS & HOT GAS TEMPERATURE.
5. STATOR WATER CONDUCTIVITY.
6. SEAL OIL DIFFERENTIAL PRESSURE , SEAL OIL FLOW & SEAL OIL DRAIN
TEMPERATURE.
7. VIBRATION READINGS OF BEARINGS AND SLIPRINGS.
8. BEARING DRAIN OIL TEMPERATURE, AND METAL TEMPERATURE.
9. OIL COLLECTIONS IN LLD,
10. H2 GAS PRESSURE DROP PER DAY.
11. DIFFERENTIAL PRESSURE ACROSS FILTERS AND DIFFERENTIAL
TEMPERATURE ACROSS ALL COOLERS.
12. OIL WATER AND GAS LEAK.
13. CONDITIONS OF ALL VALVES IN THE SYSTEM.
14. IOT, SOT AND ET LEVEL.
15. MODIFICATION WORKS TO BE CARRIED OUT.
9
PERT CHART
EARLIEST START TIME: THE EARLIEST TIME
AT, WHICH THE ACTIVITY CAN START GIVEN
ITS PRECEDENT ACTIVITIES, MUST BE
COMPLETED FIRST
EARLIEST FINISH TIME: EARLIEST FINISH
TIME IS EQUAL TO EARLIEST START TIME
FOR THE ACTIVITY PLUS THE TIME
REQUIRED TO COMPLETE THE ACTIVITY
LATEST STATING TIME: LATEST
FINISHING TIME MINUS THE TIME
REQUIRED TO COMPLETE THE
ACTIVITY
LATEST FINISH TIME: THE LATEST TIME
AT WHICH THE ACTIVITY CAN BE
COMPLETED WITH OUT DELAYING THE
PROJECT
10
SL.N
O
WORKS REQUIRED 1ST inspection after
8000 Hrs
Period after 1st inspection
8000 Hrs 24000 Hrs 48000 Hrs
1 MEASUREMENT OF INSULATION
RESISTANCE OF STATOR WINDING.
X X X X
2 CHECK I.R & CONTINUITY OF RTD’s X X X
3 HYDRAULIC TEST OF STATOR
WINDING.
X X X
4 GAS TIGHTNESS TEST OF
GENERATOR WITH PIPING SYSTEM
X X X X
5 DISMANTLING OF TERMINAL
BUSHING AND CHANGE OF GASKETS
X
6 CHANGE THE GASKETS OF GAS
COOLER
X X
7 DISMANTLING OF END SHIELD &
REPLACEMENT OF GASKETS
X X X
8 CHECKING OF TIGHTNESS OF SLOT
WEDGES
X X X
9 CHECKING THE FIXING OF WINDING
IN SLOT AND OVERHANG
X X X
10 CHECKING CONDITION OF STATOR
CORE
X X X
11 ELCID/CORE LOSS TEST X X
12 CHECKING CONDITION OF TEFLON
TUBE CONNECTION, WATER HEADER
X X X
TIME SCHEDULE
11
SLIPRING MACHING
12
POLISHING OF SLIPRING
HYDROGEN GAS SHOULD BE PURGED OUT
POLISHING OF SLIPRING IS CARRIED OUT BEFORE
SHAFT COMING TO REST AFTER COOLING.
SPECIAL TYPE MINI LATHE SHOULD BE ALIGNED
DEPTH FEED : 0.1 to 0.15 mm FOR CUTTING
0.01 to 0.02 FOR GRINDING
LONGITUDINAL FEED: 0.1 to 0.15 mm/rev FOR CUTTING
0.5 TO 0.6 mm / rev. for GRINDING
FINISH SHOULD BE DELTA 6
13
GROOVE CUTTING OF THE SLIPRING
HELICAL GROOVES ARE PROVIDED FOR BETTER
COOLING
NORMAL GROOVE DEPTH : 6 mm
IF THE GROOVE DEPTH BECOMES LESS THAN 2 mm
GROOVE CUTTING IS NECESSARY
TO BE CARRIED OUT AT LOWER SPEED OF THE
SHAFT
14
GENERATOR
CORE
STATOR
COIL
TERMINAL
BUSHING
COOLER
BEARING &
SEAL RING
GENERATOR OUTLINE
15
GENERATOR ROTOR
BORE
SLIPRING
JOURNAL
RETAINING
RING
ROTOR
WEDGE
JOURNAL
COIL &
INSULATION
16
ROTOR-I
COLLECTOR
RING WEARING
UT & PT
17
ROTOR THREADING IN 1
1. PLACE THE CARD BOARD AND THEN THE METAL PLATE INTO THE STATOR
2. INSTALL THE RAILS AND MOUNT THE LOWER PORTION OF THE OUTER TROLLEY ON THE RAILS
3. CONNECT THE EXTENSION PIPE TO THE HALF COUPLING OF THE ROTOR AND INNER TROLLEY ON THE
SHAFT JOURNAL ON THE TURBINE SIDE.
4. REMOVE THE FAN BLADES
5. ASSEMBLE THE WOODEN BARRELS ON THE ROTOR BARREL WHERE THE
ROTOR MEETS THE LIFTING SLINGS ARE POSITIONED.
6. ASSEMBLE THE TOP PORTION OF THE OUTER TROLLEY.
7. LIFT THE ROTOR BY CRANE.CHECK THE ROTOR IS HORIZONTAL. INSERT THE
ROTOR CAREFULLY INTO THE STATOR TILL THE SLINGS PERMIT.
OUTER TROLLEY
TOP
RAILS
SLING
EXTENSION
PIPE
METAL PLATE
CARD BOARD
INNER
TROLLEY
OUTER
TROLLEY
BOTTOM
18
ROTOR THREADING IN 2
1. BRING THE LOWER PORTION OF THE TROLLEY UNDER
THE TOP TROLLEY AND JOIN THEM BY BOLTS
2. LOWER THE ROTOR AND PLACE ON THE TROLLEYS
3. REMOVE THE SLINGS
4. PLACE THE “ I” BEAM ON THE TURBINE SIDE
I BEAM
19
ROTOR THREADING IN 3
1. PUSH THE ROTOR SLOWLY AND CAREFULLY INTO THE STATOR
(CROWBARS ARE INSERTED INTO THE ROLLERS ON THE OUTER TROLLEY).
2. INSERT THE ROTOR TILL IT OCCUPIES A POSITION WHERE IT IS POSSIBLE TO
PASS THE SLING
UNDER THE PROJECTING PART OF THE EXTENSION PIPE , AND PUT THE SLING
UNDER IT.
SLING
3. LIFT THE ROTOR BY CRANE TILL THERE IS NO CONTACT ON THE INNER TROLLEY WITH THE SHEET
20
ROTOR THREADING IN 4
1. BRING THE ROTOR TO THE POSITION AS SHOWN IN THE FIGURE
2. MAKE THE ROTOR REST ON THE BEAM TAKING CARE SO THAT IT DOES NOT REST ON
THE STATOR
3. DISCONNECT THE EXTENSION PIPE
4. PASS THE SLING UNDER THE HALF COUPLING
5. LIFT THE END OF THE ROTOR
6. MOVE THE ROTOR TO A POSITION WHERE IT IS CONVENIENT TO REMOVE THE INNER
TROLLEY
7. REMOVE THE INNER TROLLEY
21
ROTOR THREADING IN 5
1. BY MEANS OF CROWBAR AND CRANE TAKE THE ROTOR TO THE POSITION WHERE HALF
COUPLING OF TURBINE AND GENERATOR MEET
2. MOUNT THE LOWER HALF OF THE BEARING ON THE TURBINE SIDE
3. LOWER THE ROTOR ON THE BEARING
4. REMOVE THE I BEAM
LP TURBINE
LOWER HALF OF THE
TE BEARING
22
ROTOR THREADING IN 6
1. PLACE THE” I” BEAM ON THE EXCITER SIDE
2. REMOVE THE LOWER PART OF THE OUTER TROLLEY BY LIFTING THE ROTOR WITH CRANE
3. MAKE THE ROTOR REST ON THE “ I “ BEAM
4. REMOVE THE OUTER TROLLEY BOTH (TOP AND LOWER)
5. REMOVE THE RAILS
6. MOUNT THE EXCITER END BEARING PEDESTAL AND MOUNT THE LOWER HALF OF
THE BEARING
7. LIFT THE END OF THE ROTOR BY CRANE
8. REMOVE THE “ I” BEAM
9. MAKE THE ROTOR REST ON THE BOTTOM HALF OF THE BEARING
I BEAM
23
GENERATOR PARTS
FAN
SHIELD
FAN
BLADE
H2 SIDE
DRAIN AIR SIDE DRAIN
SEAL
RING
LABRINYTH STRIP
SEAL
OIL
INLET
SEALING
COVER
OIL DEFLECTOR PLATE
SEAL BODY
H2 SIDE OIL CATCHER
SEALING
CORD
AIR SIDE
OIL
CATCHER
END SHIELD
24
SEAL RING & OIL CATCHER
POSITION NOMINAL
VALUE IN mm
TOP 0.3. – 0.6
1 SIDE 0.17 – 0.35
BOTTOM 0.04 – 0.10
TOP 0.3. – 0.6
2 SIDE 0.17 – 0.35
BOTTOM 0.05 – 0.10
TOP 0.3. – 0.6
3 SIDE 0.17 – 0.35
BOTTOM 0.05 – 0.10
TOP 0.3. – 0.6
5 RADIAL 0.13-0.15
AXIAL CLEARANCE OF THE SLIP RING : 0.17 - 0.22 mm
RADIAL CLEARAQNCES : 0.26 - 0.30 mm
NOMINAL CLEARANCES
OIL DEFLECTING
RING
END SHIELD
H2 SIDE
OIL
CATCHER
AIR SIDE
OIL
CATCHER
SEALING
COVER
SEAL
BODY
25
6TH BEARING CLEARANCES
BEARING YOKE
0.04 TO 0.17
BEARING
OIL DEFLECTING RING OF BEARING
OUTER
BEARING OUTER
OIL CATCHER
U
L
S
U S
L
0.35 TO 0.45 0.25 TO 0.35 0.15 TO 0.25
INNER ODR
OUTER ODR
BEARING
OUTER OIL CATCHER
0.4 TO 0.5 0.3 TO 0.45 0.15 TO 0.25
0.7 TO 0.9 0.35 TO 0.45 0
0.2 TO 0.4 0.15 TO 0.30 0.10 TO 0.20
26
WINDING ON TE
27
SEAL BODY
28
SEALBODY AND SEALRING
29
RUBBER GROMMETS
30
OUTLET
HEADER
INLET
HEADER
TEFLON
TUBE
SW HEADER I/L & O/L
31
GENERATOR ALIGNMENT
H1 H2
L1
L2
r
a FOR AXIAL ALIGNMENT
H1/a = L1/r ∴ H1=(L1/r ) X a
H2/a = L2/r ∴ H2=(L2/r ) X a
FOR RADIAL ADJUSTMENT
CORRECTION=ERROR/2
FOR AXIAL ADJUSTMENT
TURBINE
SHAFT AXIS
TURBINE END
BEARING EXCITER END BEARING
RADIAL
AXIAL
32
COUPLING RUN OUT AND NATURAL RUN OUT
RUNOUT CHECK OF
GENERATOR ROTOR
RADIAL RUNOUT SHOULD NOT EXCEED 0.03MM
END FACE RUNOUT SHOULD NOT EXCEED 0.03MM
LP TURBINE
HALF COUPLING
5TH BEARING SHAFT
JOURNAL
6TH BEARING SHAFT
JOURNAL
SLIPRINGS
33
GENERATOR AIR GAP
AIR GAP : 70  2.5% ( 1.75MM)
CENTERING OF STATOR WITH RESPECT TO ROTOR SHOULD
NOT DIFFER BY 0.5MM IN ALL FOUR DIRECTIONS
475
MM
DIA
475
MM
DIA
34
MAGNETIC OFF CENTRE
CENTERING OF STATOR FRAME WITH RESPECT TO ROTOR SHOULD NOT DIFFER BY 0.5MM IN ALL FOUR
DIRECTIONS
EXCITER ENDTURBINE END
OFFSET OF STATOR AND ROTOR AXIX(VERTICAL) = 18MM IS ONLY FOR REFERENCE
35
FAN BLADE CLEARANCES
(EE)A > 40mm (EE) A < 10mm(TE)
B = 2 mm to 2.98mm
A
B
C D
THE DIFFERENCE BETWEEN “A” AND “ B” AND “C” AND “D” SHOULD NOT EXCEED 0.7MM
FAN BLADE
FAN SHIELD
ROTOR
36
INSPECTION OF THE STATOR
INSPECT THE WINDING FOR ANY BLOCK SPOT AND
PRESENCE OF ANY OIL, CARBON DISCHARGES
INSPECT THE CORE FOR ANY LOOSENESS, VENTILATION
CANALS, AND HOTSPOT AND FUSION MARKS
CHECK THE TEFLON TUBE FOR ANY DECOLORATION,
CONDITIONS OF RUBBER GROMETS
INSPECT THE OVERHANG WINDING SUPPORTS,
SPACERS, CORE PRESS RINGS, CORE BOLTS AND ALL
THE BOLTS AND NUTS OF THE SUPPORTS
CHECK THE TERMINAL BUSHINGS, STATORWATER
BUSHINGS AND GASKETS.
37
DRYING OF STATOR WINDING
BEFORE ANY ELECTRICAL TESTING WINDING SHOULD BE DRY. THE
WINDING IS CONSIDERED TO BE DRY IF THE IR, PI VALUES ARE
NORMAL
THE STAGNATED WATER IF PUFFED OUT BY PASSING COMPLETELY
DRY AND PURE AIR.
THE OTHER METHODS IN AN EXTREME CASES ARE
BY PASSING HOT AIR OR STEAM
WINDAGE LOSS METHOD BY RUNNING THE MACHINE AT NO
LOAD WITH AIR
CORE LOSS METHOD BY MAGNETIC FLUX CREATED BY
MAGNETISING THE COIL WOUND THROUGH STATOR BORE
BY THREE PHASE SHORT CIRCUIT
BY PASSING DC CURRENT
IN TS-II / NLC WINDING IS DRIED COMPLETELY BY PASSING
DEHUMIDIFIED HOT AIR AND THE RESULTS IS FAST AND
EXCELLENT.
38
INSULATION RESISTANCE OF STATOR
PRECAUTIONS
1. WINDING SHOULD BE COMPLETELY DRY
2. NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND
EACH WINDING SHOULD BE SEPARATE
3. WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD
BE GROUNDED.
ABSORPTION COEFFICIENT = R60 / R15 > 1.3
POLARISATION INDEX (PI) = R600 / R60 > 2
NOTE: THE RATIO IS BEING TAKEN TO AS MEANS FOR TEMPERATURE CORRECTION
39
CURRENT COMPONENTS
Ic- CAPACITANCE CURRENT
5KVDC
Ic IpIr
Ip – POLARISATION CURRENT
DECAY WITH TIME
Ir - LEAKAGE CURRENT
CONSTANT AND MAINLY DEPENDS
UPON THE DRYNESS OF THE WINDING
THREE COMPONENTS OF CURRENT WHILE MEGGERING
40
DC WINDING RESISTANCE
V
THE VALUES ARE COMPARED WITH FACTORY VALUE
AFTER THE TEMPERATURE CORRECTION OF THE
READING.
THE VARIATION WITHIN 2% IS CONSIDERED AS NORMAL.
V
I I
CONSTANT CURRENT GENERATOR
WINDING
41
HIGH VOLTAGE TEST
PRECAUTIONS:
1. WINDING SHOULD BE COMPLETELY DRY. IR VALUE OF THE WINDING
SHOULD BE SATISFACTORY.
2. NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND EACH
WINDING SHOULD BE SEPARATE
3. WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD BE
GROUNDED.
4. PERSONS SHOULD NOT BE ALLOWED NEAR THE WINDING
TEST:
1. 2 TIMES THE RATED VOLTAGE +1 KV FOR FIRST TIME
2. 80% OF THE PREVIOUS VALUE FOR THE SECOND TIME
3. 80% OF THE PREVIOUS VALUE FOR THE SUBSEQUENT TIMES
FOR OLD GENERATOR STATOR .
1. NOT USUALLY CARRIED BECAUSE OF DESTRUCTIVE
NATURE OF THE TEST.
2. ONLY CARRIED OUT IN CASE OF ANY WORK IS CARRIED
OUT IN THE GENERATOR STATOR.
3. THE VOLTAGE LEVEL FOR THE TEST DEPENDS ON THE AGE
OF THE MACHINE.
42
TAN  MEASUREMENT
IC
CP
IR
RP
E


IR
IC
IT
VOLTAGE
E-TEST VOLTAGE IN STEPS OF 2 KV UPTO 10 KV
IT- TOTAL CURRENT
IR- RESISTANCE CURRENT
CP- EQUIVALENT PARALLEL CAPACITANCE
RP- EQUIVALENT PARALLEL RESISTANCE
IT
43
PARTIAL DISCHARGE TEST-1
PRINCIPLES
• PARTIAL DISCHARGES ARE ELECTRICAL SPARKS WHICH OCCURS IN GAS
VOIDS WITHIN THE INSULATION
• DISCHARGES ARE PARTIAL AS SOME MORE INSULATION IS REMAINING TO
PREVENT COMPLETE BREAK DOWN
• IF PD CAUSE THE PD CHANNELS TO PROPOGATE WHICH RESULTS IN
COMPLETE BREAK DOWN OF INSULATION
• ELECTROMAGNETIC PROBES (PROXIMITY DETECTOR ) THAT IS SENSITIVE
TO RADIO FREQUENCY SIGNALS PRODUCED BY PARTIAL DISCHARGES
LOCATE SPECIFIC SITES OF DETERIORATION WITHIN THE WINDING
TEST PROCEDURE
• MACHINE SHOULD BE DISASSEMBLED
• WITH NORMAL GROUND TO LINE VOLTAGE THE WINDING IS ENERGIZED.
• ONE PHASE IS ENERGIZED WHILE THE OTHER TWO PHASES ARE
GROUNDED.
• THE PROBE IS POSITIONED NEAR STATOR COIL WEDGE AND SLOT EXIT
ABOUT 100MM FROM THE WEDGE.
• READING ARE TAKEN WITH PEAK PULSE METER.
44
PARTIAL DISCHARGE TEST-2
PARTIAL DISCHARGE ARE HIGH FREQUENCY
ELECTRICAL PULSE DUE TO DISCHARGE IN VOIDS IN THE
INSULATION
CORE
CONDUCTOR
VOIDS NEAR COPPER- NEGATIVE DISCHARGE
VOIDS INSIDE THE INSULATION – BOTH
POSITIVE AND NEGATIVE DISCHARGES
VOIDS NEAR THE CORE – POSITIVE DISCHARGE
IT PARTIALLY BRIDGES THE GAP BETWEEN THE
INSULATION AND THE GROUND
RATED VOLTAGE IS APPLIED IN THE WINDING AND WAVE
FORMS ARE RECORDED.
CRACKS / CONTAMINATIONS ON THE SURFACE OF THE INSULATION CAUSES PD
45
ABOUT STATOR CORE
• THE GENERATOR STATOR CORE IS BUILT FROM
THOUSANDS OF THIN SHEET STEEL LAMINATION.(0.5mm)
• THESE LAMINATIONS ARE COATED WITH A THIN LAYER
OF VARNISH FOR PREVENTION OF CIRCULATING
INDUCED CURRENTS ALSO KNOWN AS EDDY CURRENTS.
• ANY DEFECT IN THE INTER LAMINAR INSULATION
CAUSES FAULT CURRENT TO FLOW LOCALLY IN THE
CORE.
• THESE CIRCULATING CURRENT CAN THUS CAUSE
LOCALISED OVER HEATING AND HOT SPOTS IN THE
DAMAGED AREAS AND THIS MAY FURTHER DAMAGE THE
CORE.
• HENCE IT CALLS FOR TESTING THE INTERLAMINAR
INSULATION
46
CORE LOOP TEST
A
V
AC VOLTAGE
SOURCE
FLUX DENSITY :14000/10000GAUSS
VOLTAGE/CURRENT IN MAGNETISING WINDING 475V/970A
1.STATOR SHOULD BE SOLIDLY EARTHED.2.NO BODY SHOULD ENTER UNLESS SUPPLY IS SWITCHED
OFF 3. CABLE SHOULD NOT BE IN DAMAGED CONDITION 4. THERE SHOULD NOT BE ANY MAGNETIC
/METAL OBJECTS NEAR THE CASING 5. TEMPERATURE MONITORING SYSTEM SHOULD BE READY.
STATOR
STATOR
47
DRAWBACKS OF RING LOOP TEST
• IT IS A DESTRUCTIVE TEST
• INVOLVES HEAVY POWER LOSS
48
ELCID TEST-NEED
• THE DIGITAL ELCID TEST USES 4% OF THE
RATED FLUX LEVEL TO GENERATE FAULT
LEVEL WITH IN THE CORE BODY.
49
PRINCIPLE OF ELCID TEST
• THE CIRCUMFERENTIAL MAGNETIC FIELD OF THE CORE
IS DUE TO THE EXCITATION PLUS THAT DUE TO ANY
FAULT CURRENTS PRESENT.
• THE EFFECT OF THE MAGNETIC FIELDS IS TO PRODUCE
MAGNETIC POTENTIAL GRADIENT ON THE CORE
SURFACE.
• THIS MAGNETIC POTENTIAL GRADIENT IS DETECTED BY
SPECIALLY WOUND COIL KNOWN AS CHATTOCK COIL
• THIS COIL PROVIDES AN OUTPUT PROPORTIONAL TO
THE DIFFERENCE IN THE MAGNETIC POTENTIAL
BETWEEN ITS TWO ENDS.
• A SENSING HEAD (CHATTOCK COIL) IS PASSED OVER
THE SURFACE OF THE CORE TO DETECT MAGNETICALLY
THE PRESENCE OF FAULT
50
ELCID TEST
51
ELCID TEST –HOW RECORDED
THE SIGNAL PROCESSOR IS CALIBRATED TO
GIVE A DIRECT READING OF THE VALUE OF
1. DISTANCE INFORMATION ON THE X AXIS
2. THE FAULT CURRENT ALONG Y AXIS.
52
ELCID WAVE FORM
53
ELCID TEST CALCULATION
Vt = (.04 X Vp-p )/ (2 x √3 x k x TP)
Vt = TEST VOLTAGE MEASURED IN THE TRACE WINDING
Vp-p = RATED PHASE TO PHASE VOLTAGE
K = PITCH FACTOR (0.92 FOR ALL GENERATORS)
TP = TURNS IN SERIES /PHASE
54
STATOR SLOT
STATOR SLOT
SLOT WEDGE
SLOT RIPPLE SPRING
GLASS TEXTOLITE
SPACERS
SOILID CONDUCTOR
HOLLOW CONDUCTOR
TOP BAR
INSULATING PACKING
BOTTOM BAR
THERMOREACTIVE
INSULATION
BOTTOM PACKING
55
STATOR WEDGE DEFLECTION
THE WINDINGS ARE SUBJECTED TO EXPANSION, CONTRACTION
AND VIBRATIONS WHICH LEAD TO LOOSENING OF WEDGE
THE TIGHTNESS OF THE WEDGES IS CHECKED BY
KNOCKING WITH A SMALL HAMMER. FROM THE KNOCKING
SOUND THE LOOSENESS OF THE WEDGE IS JUDGED.
IF TOP RIPPLE SPRINGS ARE PROVIDED, THEN KNOCKING METHOD
CAN NOT BE USED.
DEFLECTION OF WEDGE IS MEASURED BY APPLYING CALCULATED
PRESSURE USING “WEDGE DEFLECTION CHECKING KIT”
TOP RIPPLE SPRINGS ARE NOT PROVIDED IN THE END WEDGES
AND WHERE RTDs ARE PROVIDED.
DEFLECTION OF LESS THAN 0.9 mm IS ALLOWED FOR 60% OF THE
WEDGES AND A DEFLECTION OF LESS THAN 1.1 mm IS ALLOWED
FOR 40% OF THE WEDGES.
THE PRESSURE APPLIED IS CALCULATED USING THE FORMULA
REQUIRED MANOMETER PR. = ((10 X PF ) / FK ) X LN X BN BAR
SPECIFIC TEST PRESSURE FOR THE WEDGES (PF ) = 1.8 N / mm2
LN = SLOT WEDGE LENGTH IN cm BN = SLOT WIDTH IN cm
PF= SPECIFIC TEST Pr. IN N/mm2 FK= PISTON SURFACE AREA IN cm2
56
WEDGE DEFLECTION LIMITS
1. IF THE WEDGE MOVEMENT OF MORE THAN 1.1MM IS MEASURED
IN ANY SLOT, THE NUMBER OF MEASURING POINTS IN THIS
SLOT IS DOUBLED AND IF THE VALUE IS EXCEEDED IN 2 POINTS.
2. ALL THE WEDGES IN THIS SLOT SHOULD BE CHECKED TO
KNOW THAT NOT MORE THAN 2 POINTS ARE HAVING
MOVEMENT MORE THAN THE SPECIFIED VALUE.
3. IF THE VALUE IS EXCEEDED, CORRECT PACKER ARE INSERTED
AND TIGHTENED.
4. AFTER ALL SUCH WEDGES ARE TIGHTENED, THE WEDGE
TIGHTNESS CHECKING WILL BE CARRIED OUT AGAIN.
5. AFTER TIGHTENING SLOT WEDGES,
DEFLECTION SHOULD BE: BETWEEN 0.1mm to 0.3 mm FOR 75%
: NOT MORE THAN 0.45 mm FOR 25%
57
INSPECTION OF ROTOR
INSPECT THE JOURNAL FOR ANY PITTING AND SCRATCHES
INSPECT FOR ANY DUST OR ANY UNDESIRABLE
MATERIALS LYING IN VENTILATION HOLES AND
VENTILATION CANALS OF RETAINING RING
CHECK THE LOCKING OF BALANCE WEIGHTS
CHECK THE TIGHTNESS OF WEDGES AND PACKERS
UNDER RETAINING RING
DP TEST OF FAN BLADES AND RETAINING RING
DO NOT REST THE ROTOR ON RETAINING RING,SLIPRINGS,HALF
COUPLING AND ROTOR WEDGES
PRESERVE AGAINST RUSTING OF JOURNAL, SLIP RING
AND HALF COUPLING WHEN THE ROTOR IS OUT.
58
TESTS ON ROTOR
INSULATION RESISTANCE VALUE USING 500 V MEGGER.
IT SHOULD BE MORE THAN 1. 3 MEGA OHMS
DC RESISTANCE VALUE IS MEASURED. AFTER TEMPERATURE
CORRECTION, IT IS COMPARED WITH FACTORY VALUE.
VARIATION WITH IN 2 % IS CONSIDERED AS NORMAL
AC IMPEDANCE VALUE IS MEASURED AT VARIOUS
SPEED OF THE ROTOR.
HV TEST: AT 2.5 KV, FOR ONE MINUTE FOR A NEW
ROTOR AT SITE. VALUE MAY BE REDUCED FOR OLD
ROTOR. GENERALLY CARRIED OUT ONLY WHEN ANY
REPAIR IS DONE ON THE ROTOR WINDING.
59
RETAINING RING
60
RECURRENT SURGE OSCILLOSCOPE TEST ON ROTOR
A D.C STEP BETWEEN ONE END OF THE ROTOR WINDING AND THE ROTOR BODY.
THE TRANSMITTED WAVE AND THE REFLECTED WAVE AT THE INPUT END OF THE
WINDING IS MONITORED USING TWO OSCILLOSCOPE CHANNELS
IF THE VOLTAGE STEP IS APPLIED FROM EACH END OF THE ROTOR WINDING
THEN ALTERNATIVELY THEN TWO OSCILLOSCOPE TRACES WILL BE OBTAINED
WHICH MAY BE SUPERIMPOSED ON THE OSCILLOSCOPE SCREEN
A HEALTHY ROTOR WILL HAVE TWO INDENTICAL TRACES
A ROTOR WILL A FAULT WILL HAVE DIFFERING TRACES
THE POSITION OF THE FAULT MAY BE DEDUCED BY SCALING THE TIME DOMAIN
61
RSO TEST CIRCUIT CONNECTION
Pulse
Generator
oscilloscope
chanell 1
62
ROTOR GAS TIGHTNESS TEST
GENERATOR STATOR
FAN BLADE
INNER
CURRENT
CARRYING
BOLT
CORE
BAR
ROTOR RETAINING
RINGHALF
COUPLING
OUTER CURRENT
CARRYING BOLT
SLIP RING
NITROGEN CYLINDER
GAS TIGHTNESS OF ROTOR
PRESSURE
REGULATOR
63
ROTOR SLOT
SLOT WEDGE
TOP LINER
ROTOR
SHAFT
SLOT BACK
BOTTOM
LINER
64
PURGE TEST -2
65
PURGE TEST-3
66
STATIC PRESSURE AND VELOCITY PRESSURE
STATIC PRESSURE:THE RISE IN STATIC PRESSURE AT A POINT MINUS THE
REFERENCE ATMOSPHERIC PRESSURE.
VELOCITY PRESSURE: THE RISE IN STATIC PRESSURE WHICH OCCURS WHEN
AIR MOVING WITH SPECIFIED VELOCITY AT A POINT IS BROUGHT TO REST
WITH OUT LOSS OF MECHANICAL ENERGY
67
PURGE TEST
1 PRESSURE OF 3. 0 ± 0.1KG/cm2 GAUGE SHOULD BE APPLIED AT THE
VENTILATING CANALS OF SLOT THROUGH THE ADOPTER.
2. WHILE CARRYING OUT TEST ON OVERHANG, A STATIC PRESSURE
OF 50 mm OF WATER COLUMN SHOULD BE MAINTAINED UNDER
RETAINING RING.
3. THE AVERAGE VELOCITY PRESSURE IN THE CANALS OF SLOT
PORTION SHOULD NOT BE LESS THAN 15 mm OF WATER COLUMN
FOR EACH ZONE AND 21 mm OF WATER COLUMN FOR EACH SLOT.
4. THE MINIMUM VALUE OF STATIC PRESSURE IN INDIVIDUAL
CANALS OF OVER HANG PORTION SHOULD NOT BE LESS THAN
15mm OF WATER COLUMN.
5. FULLY CLOSED CANALS ARE NOT ALLOWED IN THE OVER HANG
PORTION OF ROTOR WINDING.
6. ENSURE THAT ALL THE VENTILATION CANALS/ DUCTS ARE
PROPERLY SEALED AFTER THE PURGE TEST.
68
HYDRO TEST OF STATOR WINDING
HYDRAULIC TEST FOR THE STATOR WINDING IS
CONDUCTED AT 5 KG/ cm2 FOR 24 HOURS USING
FILTERED DM WATER.
NO DROP IS ALLOWED.
PROBABLE LEAK POINTS ARE
TEFLON HOSES AT THE TURBINE END
THE CONNECTING PIPES OF THE TERMINAL
BUSHINGS
THE CONNECTING PIPES AT THE EXCITER
END
69
EPOXY GLUE INJECTION OF STATOR OVERHANG
WINDING & VARNISHING OF STATOR
THE STATOR OVERHANG WINDING ARE SUBJECTED TO MORE
STRESS DURING ANY ELECTRICAL FAULT
TO GIVE ADDITIONAL STRENGTH TO THE OVERHANG WINDING
SUPPORTS, EPOXY GLUE IS PUMPED & SPRAYED OVER IT AFTER
CLEANING AND DRYING BY EXTERNAL HEATING, USING
ELECTRICAL BULBS.
RESIN CY 205 : ( 4250 GRAMS)
DILUENT – C : (750 GRAMS)
HARDENER- HY 840 : (2000 GRAMS)
THE CORE IS GIVEN A COATING OF VARNISH AFTER CLEANING
AND DRYING.
70
AIR TIGHTNESS TEST OF GENERATOR
So – LEAKAGE OF GAS ( AT ATM. PRESSURE AND AT 20 OC IN %)
P1 & P2 - ABS. PR. AT BEGINNING AND END OF THE TEST IN mm of HG.
T1 & T2 ABS. TEMP AT BEGINNING AND END OF THE TEST IN DEGREE
KELVIN.
t – DURATION OF TIME.
AFTER COMPLETING THE ASSEMBLY & COMMISSIONING OF SEAL OIL
SYSTEM, AIR LEAK IS CONDUCTED WITH DRY AIR, AT A PRESSURE OF 4 KSC
FOR 24 HOURS
%
925
:
2
2
1
1











T
P
T
P
t
So
Vo = So X V V – GAS VOLUME OF STATOR IN M3 ( 56 M3 )
Vo – ABSOLUTE IN LEAKAGE IN M3100
71
AIR TIGHTNESS TEST -2
VOLUME IS INVERSELY PROPORTIONAL TO SQUARE OF DENSITIES.
3.20.1138/1.18
AirV
HydrogenV
o
o

GAS LEAK SHOULD BE WITHIN 1 % OF THE VOLUME
72
BRUSHGEAR CLEARANCES
I1
I2
I1 & I2 = 0.1 TO 0.3
S = 2 TO 2.5
S
t1
t2
t4
t3
t1, t2 , t3, t4 = 3.4 to 4.1
BRUSHGEAR
BRUSH HOLDER
SLIPRING
ALIGNMENT OF BRUSHGEAR BRUSH HOLDER AND
BRUSHES
BRUSH
BRUSH
HOLDER
73
STAGGERING OF BRUSHES
A
D
BC
A 0
D 50 TO 54
B 16- 20
C 32 TO 36
74
THANK YOU

More Related Content

PPT
Generators
PDF
Generator Set Operation and Maintenance Training .pdf
PDF
Wide area monitoring, protection and control in future smart grid
PDF
ChatGPT PPT
PDF
8 Steps To Success In Maintenance Planning And Scheduling
PDF
Plan de calidad ejemplo
PDF
236407565 gas-turbine-notes
PPT
660 mw supercritical boiler
Generators
Generator Set Operation and Maintenance Training .pdf
Wide area monitoring, protection and control in future smart grid
ChatGPT PPT
8 Steps To Success In Maintenance Planning And Scheduling
Plan de calidad ejemplo
236407565 gas-turbine-notes
660 mw supercritical boiler

What's hot (20)

PPTX
Testing of transformer
PPT
Installation Operation & Maintenance of 33kV & 11kV Switchgear
PDF
Motor Protection
PPSX
Excitation system for alternator
PPTX
Transformer maintenance
PPT
Steam turbine introduction & maintenance ppt
PDF
DIESEL GENERATOR DETAILS
PPTX
Brushless excitation
PDF
Power transformer protection
PPTX
Generator Protection
PPTX
Electrohydraulic governing system
PPTX
Different types of Transformers used in Generating Station
PPTX
Ppt turbo generator
PPTX
INTRODUCTION TO GOVERNING
PDF
Synchronous generators
PPTX
Power Transformer Protection
PPTX
Current Transformer.pptx
PDF
STEAM TURBINES Governing System & TROUBLE SHOOTING
PPTX
Turbine safety protection
PPTX
A presentation on turbogenerator and excitor
Testing of transformer
Installation Operation & Maintenance of 33kV & 11kV Switchgear
Motor Protection
Excitation system for alternator
Transformer maintenance
Steam turbine introduction & maintenance ppt
DIESEL GENERATOR DETAILS
Brushless excitation
Power transformer protection
Generator Protection
Electrohydraulic governing system
Different types of Transformers used in Generating Station
Ppt turbo generator
INTRODUCTION TO GOVERNING
Synchronous generators
Power Transformer Protection
Current Transformer.pptx
STEAM TURBINES Governing System & TROUBLE SHOOTING
Turbine safety protection
A presentation on turbogenerator and excitor
Ad

Similar to Generator maintenance (20)

PDF
Bladd maint
PPTX
Rail cum Road Bridge across the Ganga near Munger
PPT
dry seal gas in centrifugal compressors.ppt
PDF
Hyster c019 (h16.00 xl europe) forklift service repair manual
PDF
ZELS1206B Portable Water Velocity Meter Data
PPTX
Pump_IOM_N1.pptx
PDF
2 cylinderservicemanual
PDF
Triumph service bulletin 1964
PDF
Yale b974 glp20 lx lift truck service repair manual
PDF
YALE B974 GLP25LX LIFT TRUCK Service Repair Manual
PDF
Yale b974 gdp20 lx lift truck service repair manual
PDF
YALE B974 GDP25LX LIFT TRUCK Service Repair Manual
PDF
Yale b974 glp25 lx lift truck service repair manual
PDF
YALE B974 GDP20LX LIFT TRUCK Service Repair Manual
PDF
YALE B974 GLP20LX LIFT TRUCK Service Repair Manual
PDF
Yale b974 gdp25 lx lift truck service repair manual
PDF
YALE B974 GDP25LX LIFT TRUCK Service Repair Manual
PDF
YALE B974 GLP25LX LIFT TRUCK Service Repair Manual
PDF
00 elbarougy turbine Course Hapy
PPT
Pre commissioning steam turbines load trial
Bladd maint
Rail cum Road Bridge across the Ganga near Munger
dry seal gas in centrifugal compressors.ppt
Hyster c019 (h16.00 xl europe) forklift service repair manual
ZELS1206B Portable Water Velocity Meter Data
Pump_IOM_N1.pptx
2 cylinderservicemanual
Triumph service bulletin 1964
Yale b974 glp20 lx lift truck service repair manual
YALE B974 GLP25LX LIFT TRUCK Service Repair Manual
Yale b974 gdp20 lx lift truck service repair manual
YALE B974 GDP25LX LIFT TRUCK Service Repair Manual
Yale b974 glp25 lx lift truck service repair manual
YALE B974 GDP20LX LIFT TRUCK Service Repair Manual
YALE B974 GLP20LX LIFT TRUCK Service Repair Manual
Yale b974 gdp25 lx lift truck service repair manual
YALE B974 GDP25LX LIFT TRUCK Service Repair Manual
YALE B974 GLP25LX LIFT TRUCK Service Repair Manual
00 elbarougy turbine Course Hapy
Pre commissioning steam turbines load trial
Ad

Recently uploaded (20)

PPTX
UNIT 4 Total Quality Management .pptx
PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PDF
PPT on Performance Review to get promotions
PPTX
Geodesy 1.pptx...............................................
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PDF
Digital Logic Computer Design lecture notes
PPTX
Lesson 3_Tessellation.pptx finite Mathematics
PPTX
Strings in CPP - Strings in C++ are sequences of characters used to store and...
PPTX
CYBER-CRIMES AND SECURITY A guide to understanding
PPTX
UNIT-1 - COAL BASED THERMAL POWER PLANTS
PPTX
Sustainable Sites - Green Building Construction
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPT
Project quality management in manufacturing
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PDF
Model Code of Practice - Construction Work - 21102022 .pdf
PDF
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
PPTX
Lecture Notes Electrical Wiring System Components
PDF
Operating System & Kernel Study Guide-1 - converted.pdf
PPT
Mechanical Engineering MATERIALS Selection
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
UNIT 4 Total Quality Management .pptx
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPT on Performance Review to get promotions
Geodesy 1.pptx...............................................
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Digital Logic Computer Design lecture notes
Lesson 3_Tessellation.pptx finite Mathematics
Strings in CPP - Strings in C++ are sequences of characters used to store and...
CYBER-CRIMES AND SECURITY A guide to understanding
UNIT-1 - COAL BASED THERMAL POWER PLANTS
Sustainable Sites - Green Building Construction
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
Project quality management in manufacturing
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
Model Code of Practice - Construction Work - 21102022 .pdf
Mohammad Mahdi Farshadian CV - Prospective PhD Student 2026
Lecture Notes Electrical Wiring System Components
Operating System & Kernel Study Guide-1 - converted.pdf
Mechanical Engineering MATERIALS Selection
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd

Generator maintenance

  • 2. 2 GENERATOR CLASSIFICATION 1. INDIRECT HYDROGEN COOLING OF STATOR AND ROTOR 2. DIRECT GAS COOLING FOR ROTOR AND DIMINERALISED WATER COOLING OF STATOR 3. DIRECT GAS COOLING OF ROTOR AND STATOR 4. AIR COOLED GENERATOR
  • 3. 3 DAILY CHECKS CLEANLINESS OF THE BEARING INSULATION CONSUMPTION OF HYDROGEN GAS SAMPLE IN THE GAS TRAP CLEAN THE BRUSH GEAR WITH DRY AIR INSPECT THE SLIPRING CARBON BRUSHES, PIGTAILS AND SIZE OF THE BRUSHES REACTIVATION OF GAS DRYERS CHECK THE LLD COLLECTION FOR OIL / WATER  CHECK THE VENT LINE OF GAS COOLER FOR ANY GAS COLLECTION.
  • 4. 4 WEEKLY CHECKS CHECK THE SPRING TENSION OF THE SLIP RING BRUSHES USING SPRING BALANCE(150-200gm/cm2) VIBRATION OF THE BRUSHES FREE MOVEMENT OF THE CARBON BRUSHES IN THE HOLDER START AND RUN THE STAND BY SEAL OIL PUMPS AND STATOR WATER PUMPS. CHECK THE FLOW OF SEAL OIL CHECK THE BEARING VIBRATION USING PORTABLE VIBRATION INSTRUMENT
  • 5. 5 MONTHLY CHECKS • CHECK ALL THE BOLTS FOR TIGHTNESS • CHECK ALL THE PROTECTION AND INTERLOCKING CIRCUITS • CHECK THE INSULATION AND SHAFT VOLTAGE OF THE ROTOR SHAFT • POLARITY OF SLIPRINGS ARE CHANGED ONCE IN THREE MONTHS(DONE DURING SHUTDOWN) • CONDITION OF SILICA GEL IN THE GAS DRIER. • MOISTURE CONTENT OF THE HYDROGEN GAS
  • 6. 6 WHY OVERHAUL IS DONE ? IT ENSURES NO BREAK DOWNS IN BETWEEN THE OVERHAULS. GENERATOR ARE SUBJECTED TO VARIOUS THERMAL, ELECTRICAL AND MECHANICAL STRESSES. TO INSPECT AND EXAMINE THE EXTENT OF DAMAGE IN VARIOUS PARTS IT IS MANDATORY TO UNDERTAKE CAPITAL OVERHAUL
  • 7. 7 SCHEDULE OF OVERHAUL FIRST INSPECTION : 8000 Hours SECOND INSPECTION : 16,000 Hours SUBSEQUENT OVERHAUL : AFTER EVERY 24,000 HOURS TEQUIVALENT = T ACTUAL + Ns x Ts TEQUIVALENT : EQUIVALENT RUNNING HOURS T ACTUAL : ACTUAL RUNNING HOURS Ns : NO OF STARTS Ts 20 HOURS (ADDITIONAL NUMBER OF OPERATING HOURS)
  • 8. 8 PRE OVERHAUL ACTIVITIES 1. ENSURE THAT ALL SPARES, CONSUMABLES, SPECIAL TOOLS AND OTHER MATERIALS ARE AVAILABLE. 2. PREPARE PERT / BARCHART. 3. NOTE DOWN THE VARIOUS PARAMETERS OF THE MACHINE AT FULL LOAD. 4. MW, MVAR, HZ, PF, STATOR VOLTAGE & CURRENT, IRON & COPPER TEMPERATURE, COLD GAS & HOT GAS TEMPERATURE. 5. STATOR WATER CONDUCTIVITY. 6. SEAL OIL DIFFERENTIAL PRESSURE , SEAL OIL FLOW & SEAL OIL DRAIN TEMPERATURE. 7. VIBRATION READINGS OF BEARINGS AND SLIPRINGS. 8. BEARING DRAIN OIL TEMPERATURE, AND METAL TEMPERATURE. 9. OIL COLLECTIONS IN LLD, 10. H2 GAS PRESSURE DROP PER DAY. 11. DIFFERENTIAL PRESSURE ACROSS FILTERS AND DIFFERENTIAL TEMPERATURE ACROSS ALL COOLERS. 12. OIL WATER AND GAS LEAK. 13. CONDITIONS OF ALL VALVES IN THE SYSTEM. 14. IOT, SOT AND ET LEVEL. 15. MODIFICATION WORKS TO BE CARRIED OUT.
  • 9. 9 PERT CHART EARLIEST START TIME: THE EARLIEST TIME AT, WHICH THE ACTIVITY CAN START GIVEN ITS PRECEDENT ACTIVITIES, MUST BE COMPLETED FIRST EARLIEST FINISH TIME: EARLIEST FINISH TIME IS EQUAL TO EARLIEST START TIME FOR THE ACTIVITY PLUS THE TIME REQUIRED TO COMPLETE THE ACTIVITY LATEST STATING TIME: LATEST FINISHING TIME MINUS THE TIME REQUIRED TO COMPLETE THE ACTIVITY LATEST FINISH TIME: THE LATEST TIME AT WHICH THE ACTIVITY CAN BE COMPLETED WITH OUT DELAYING THE PROJECT
  • 10. 10 SL.N O WORKS REQUIRED 1ST inspection after 8000 Hrs Period after 1st inspection 8000 Hrs 24000 Hrs 48000 Hrs 1 MEASUREMENT OF INSULATION RESISTANCE OF STATOR WINDING. X X X X 2 CHECK I.R & CONTINUITY OF RTD’s X X X 3 HYDRAULIC TEST OF STATOR WINDING. X X X 4 GAS TIGHTNESS TEST OF GENERATOR WITH PIPING SYSTEM X X X X 5 DISMANTLING OF TERMINAL BUSHING AND CHANGE OF GASKETS X 6 CHANGE THE GASKETS OF GAS COOLER X X 7 DISMANTLING OF END SHIELD & REPLACEMENT OF GASKETS X X X 8 CHECKING OF TIGHTNESS OF SLOT WEDGES X X X 9 CHECKING THE FIXING OF WINDING IN SLOT AND OVERHANG X X X 10 CHECKING CONDITION OF STATOR CORE X X X 11 ELCID/CORE LOSS TEST X X 12 CHECKING CONDITION OF TEFLON TUBE CONNECTION, WATER HEADER X X X TIME SCHEDULE
  • 12. 12 POLISHING OF SLIPRING HYDROGEN GAS SHOULD BE PURGED OUT POLISHING OF SLIPRING IS CARRIED OUT BEFORE SHAFT COMING TO REST AFTER COOLING. SPECIAL TYPE MINI LATHE SHOULD BE ALIGNED DEPTH FEED : 0.1 to 0.15 mm FOR CUTTING 0.01 to 0.02 FOR GRINDING LONGITUDINAL FEED: 0.1 to 0.15 mm/rev FOR CUTTING 0.5 TO 0.6 mm / rev. for GRINDING FINISH SHOULD BE DELTA 6
  • 13. 13 GROOVE CUTTING OF THE SLIPRING HELICAL GROOVES ARE PROVIDED FOR BETTER COOLING NORMAL GROOVE DEPTH : 6 mm IF THE GROOVE DEPTH BECOMES LESS THAN 2 mm GROOVE CUTTING IS NECESSARY TO BE CARRIED OUT AT LOWER SPEED OF THE SHAFT
  • 17. 17 ROTOR THREADING IN 1 1. PLACE THE CARD BOARD AND THEN THE METAL PLATE INTO THE STATOR 2. INSTALL THE RAILS AND MOUNT THE LOWER PORTION OF THE OUTER TROLLEY ON THE RAILS 3. CONNECT THE EXTENSION PIPE TO THE HALF COUPLING OF THE ROTOR AND INNER TROLLEY ON THE SHAFT JOURNAL ON THE TURBINE SIDE. 4. REMOVE THE FAN BLADES 5. ASSEMBLE THE WOODEN BARRELS ON THE ROTOR BARREL WHERE THE ROTOR MEETS THE LIFTING SLINGS ARE POSITIONED. 6. ASSEMBLE THE TOP PORTION OF THE OUTER TROLLEY. 7. LIFT THE ROTOR BY CRANE.CHECK THE ROTOR IS HORIZONTAL. INSERT THE ROTOR CAREFULLY INTO THE STATOR TILL THE SLINGS PERMIT. OUTER TROLLEY TOP RAILS SLING EXTENSION PIPE METAL PLATE CARD BOARD INNER TROLLEY OUTER TROLLEY BOTTOM
  • 18. 18 ROTOR THREADING IN 2 1. BRING THE LOWER PORTION OF THE TROLLEY UNDER THE TOP TROLLEY AND JOIN THEM BY BOLTS 2. LOWER THE ROTOR AND PLACE ON THE TROLLEYS 3. REMOVE THE SLINGS 4. PLACE THE “ I” BEAM ON THE TURBINE SIDE I BEAM
  • 19. 19 ROTOR THREADING IN 3 1. PUSH THE ROTOR SLOWLY AND CAREFULLY INTO THE STATOR (CROWBARS ARE INSERTED INTO THE ROLLERS ON THE OUTER TROLLEY). 2. INSERT THE ROTOR TILL IT OCCUPIES A POSITION WHERE IT IS POSSIBLE TO PASS THE SLING UNDER THE PROJECTING PART OF THE EXTENSION PIPE , AND PUT THE SLING UNDER IT. SLING 3. LIFT THE ROTOR BY CRANE TILL THERE IS NO CONTACT ON THE INNER TROLLEY WITH THE SHEET
  • 20. 20 ROTOR THREADING IN 4 1. BRING THE ROTOR TO THE POSITION AS SHOWN IN THE FIGURE 2. MAKE THE ROTOR REST ON THE BEAM TAKING CARE SO THAT IT DOES NOT REST ON THE STATOR 3. DISCONNECT THE EXTENSION PIPE 4. PASS THE SLING UNDER THE HALF COUPLING 5. LIFT THE END OF THE ROTOR 6. MOVE THE ROTOR TO A POSITION WHERE IT IS CONVENIENT TO REMOVE THE INNER TROLLEY 7. REMOVE THE INNER TROLLEY
  • 21. 21 ROTOR THREADING IN 5 1. BY MEANS OF CROWBAR AND CRANE TAKE THE ROTOR TO THE POSITION WHERE HALF COUPLING OF TURBINE AND GENERATOR MEET 2. MOUNT THE LOWER HALF OF THE BEARING ON THE TURBINE SIDE 3. LOWER THE ROTOR ON THE BEARING 4. REMOVE THE I BEAM LP TURBINE LOWER HALF OF THE TE BEARING
  • 22. 22 ROTOR THREADING IN 6 1. PLACE THE” I” BEAM ON THE EXCITER SIDE 2. REMOVE THE LOWER PART OF THE OUTER TROLLEY BY LIFTING THE ROTOR WITH CRANE 3. MAKE THE ROTOR REST ON THE “ I “ BEAM 4. REMOVE THE OUTER TROLLEY BOTH (TOP AND LOWER) 5. REMOVE THE RAILS 6. MOUNT THE EXCITER END BEARING PEDESTAL AND MOUNT THE LOWER HALF OF THE BEARING 7. LIFT THE END OF THE ROTOR BY CRANE 8. REMOVE THE “ I” BEAM 9. MAKE THE ROTOR REST ON THE BOTTOM HALF OF THE BEARING I BEAM
  • 23. 23 GENERATOR PARTS FAN SHIELD FAN BLADE H2 SIDE DRAIN AIR SIDE DRAIN SEAL RING LABRINYTH STRIP SEAL OIL INLET SEALING COVER OIL DEFLECTOR PLATE SEAL BODY H2 SIDE OIL CATCHER SEALING CORD AIR SIDE OIL CATCHER END SHIELD
  • 24. 24 SEAL RING & OIL CATCHER POSITION NOMINAL VALUE IN mm TOP 0.3. – 0.6 1 SIDE 0.17 – 0.35 BOTTOM 0.04 – 0.10 TOP 0.3. – 0.6 2 SIDE 0.17 – 0.35 BOTTOM 0.05 – 0.10 TOP 0.3. – 0.6 3 SIDE 0.17 – 0.35 BOTTOM 0.05 – 0.10 TOP 0.3. – 0.6 5 RADIAL 0.13-0.15 AXIAL CLEARANCE OF THE SLIP RING : 0.17 - 0.22 mm RADIAL CLEARAQNCES : 0.26 - 0.30 mm NOMINAL CLEARANCES OIL DEFLECTING RING END SHIELD H2 SIDE OIL CATCHER AIR SIDE OIL CATCHER SEALING COVER SEAL BODY
  • 25. 25 6TH BEARING CLEARANCES BEARING YOKE 0.04 TO 0.17 BEARING OIL DEFLECTING RING OF BEARING OUTER BEARING OUTER OIL CATCHER U L S U S L 0.35 TO 0.45 0.25 TO 0.35 0.15 TO 0.25 INNER ODR OUTER ODR BEARING OUTER OIL CATCHER 0.4 TO 0.5 0.3 TO 0.45 0.15 TO 0.25 0.7 TO 0.9 0.35 TO 0.45 0 0.2 TO 0.4 0.15 TO 0.30 0.10 TO 0.20
  • 31. 31 GENERATOR ALIGNMENT H1 H2 L1 L2 r a FOR AXIAL ALIGNMENT H1/a = L1/r ∴ H1=(L1/r ) X a H2/a = L2/r ∴ H2=(L2/r ) X a FOR RADIAL ADJUSTMENT CORRECTION=ERROR/2 FOR AXIAL ADJUSTMENT TURBINE SHAFT AXIS TURBINE END BEARING EXCITER END BEARING RADIAL AXIAL
  • 32. 32 COUPLING RUN OUT AND NATURAL RUN OUT RUNOUT CHECK OF GENERATOR ROTOR RADIAL RUNOUT SHOULD NOT EXCEED 0.03MM END FACE RUNOUT SHOULD NOT EXCEED 0.03MM LP TURBINE HALF COUPLING 5TH BEARING SHAFT JOURNAL 6TH BEARING SHAFT JOURNAL SLIPRINGS
  • 33. 33 GENERATOR AIR GAP AIR GAP : 70  2.5% ( 1.75MM) CENTERING OF STATOR WITH RESPECT TO ROTOR SHOULD NOT DIFFER BY 0.5MM IN ALL FOUR DIRECTIONS 475 MM DIA 475 MM DIA
  • 34. 34 MAGNETIC OFF CENTRE CENTERING OF STATOR FRAME WITH RESPECT TO ROTOR SHOULD NOT DIFFER BY 0.5MM IN ALL FOUR DIRECTIONS EXCITER ENDTURBINE END OFFSET OF STATOR AND ROTOR AXIX(VERTICAL) = 18MM IS ONLY FOR REFERENCE
  • 35. 35 FAN BLADE CLEARANCES (EE)A > 40mm (EE) A < 10mm(TE) B = 2 mm to 2.98mm A B C D THE DIFFERENCE BETWEEN “A” AND “ B” AND “C” AND “D” SHOULD NOT EXCEED 0.7MM FAN BLADE FAN SHIELD ROTOR
  • 36. 36 INSPECTION OF THE STATOR INSPECT THE WINDING FOR ANY BLOCK SPOT AND PRESENCE OF ANY OIL, CARBON DISCHARGES INSPECT THE CORE FOR ANY LOOSENESS, VENTILATION CANALS, AND HOTSPOT AND FUSION MARKS CHECK THE TEFLON TUBE FOR ANY DECOLORATION, CONDITIONS OF RUBBER GROMETS INSPECT THE OVERHANG WINDING SUPPORTS, SPACERS, CORE PRESS RINGS, CORE BOLTS AND ALL THE BOLTS AND NUTS OF THE SUPPORTS CHECK THE TERMINAL BUSHINGS, STATORWATER BUSHINGS AND GASKETS.
  • 37. 37 DRYING OF STATOR WINDING BEFORE ANY ELECTRICAL TESTING WINDING SHOULD BE DRY. THE WINDING IS CONSIDERED TO BE DRY IF THE IR, PI VALUES ARE NORMAL THE STAGNATED WATER IF PUFFED OUT BY PASSING COMPLETELY DRY AND PURE AIR. THE OTHER METHODS IN AN EXTREME CASES ARE BY PASSING HOT AIR OR STEAM WINDAGE LOSS METHOD BY RUNNING THE MACHINE AT NO LOAD WITH AIR CORE LOSS METHOD BY MAGNETIC FLUX CREATED BY MAGNETISING THE COIL WOUND THROUGH STATOR BORE BY THREE PHASE SHORT CIRCUIT BY PASSING DC CURRENT IN TS-II / NLC WINDING IS DRIED COMPLETELY BY PASSING DEHUMIDIFIED HOT AIR AND THE RESULTS IS FAST AND EXCELLENT.
  • 38. 38 INSULATION RESISTANCE OF STATOR PRECAUTIONS 1. WINDING SHOULD BE COMPLETELY DRY 2. NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND EACH WINDING SHOULD BE SEPARATE 3. WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD BE GROUNDED. ABSORPTION COEFFICIENT = R60 / R15 > 1.3 POLARISATION INDEX (PI) = R600 / R60 > 2 NOTE: THE RATIO IS BEING TAKEN TO AS MEANS FOR TEMPERATURE CORRECTION
  • 39. 39 CURRENT COMPONENTS Ic- CAPACITANCE CURRENT 5KVDC Ic IpIr Ip – POLARISATION CURRENT DECAY WITH TIME Ir - LEAKAGE CURRENT CONSTANT AND MAINLY DEPENDS UPON THE DRYNESS OF THE WINDING THREE COMPONENTS OF CURRENT WHILE MEGGERING
  • 40. 40 DC WINDING RESISTANCE V THE VALUES ARE COMPARED WITH FACTORY VALUE AFTER THE TEMPERATURE CORRECTION OF THE READING. THE VARIATION WITHIN 2% IS CONSIDERED AS NORMAL. V I I CONSTANT CURRENT GENERATOR WINDING
  • 41. 41 HIGH VOLTAGE TEST PRECAUTIONS: 1. WINDING SHOULD BE COMPLETELY DRY. IR VALUE OF THE WINDING SHOULD BE SATISFACTORY. 2. NEUTRAL AND PHASE POINT SHOULD BE DISCONNECTED AND EACH WINDING SHOULD BE SEPARATE 3. WHILE MEGGERING ONE PHASE OTHER TWO PHASE SHOULD BE GROUNDED. 4. PERSONS SHOULD NOT BE ALLOWED NEAR THE WINDING TEST: 1. 2 TIMES THE RATED VOLTAGE +1 KV FOR FIRST TIME 2. 80% OF THE PREVIOUS VALUE FOR THE SECOND TIME 3. 80% OF THE PREVIOUS VALUE FOR THE SUBSEQUENT TIMES FOR OLD GENERATOR STATOR . 1. NOT USUALLY CARRIED BECAUSE OF DESTRUCTIVE NATURE OF THE TEST. 2. ONLY CARRIED OUT IN CASE OF ANY WORK IS CARRIED OUT IN THE GENERATOR STATOR. 3. THE VOLTAGE LEVEL FOR THE TEST DEPENDS ON THE AGE OF THE MACHINE.
  • 42. 42 TAN  MEASUREMENT IC CP IR RP E   IR IC IT VOLTAGE E-TEST VOLTAGE IN STEPS OF 2 KV UPTO 10 KV IT- TOTAL CURRENT IR- RESISTANCE CURRENT CP- EQUIVALENT PARALLEL CAPACITANCE RP- EQUIVALENT PARALLEL RESISTANCE IT
  • 43. 43 PARTIAL DISCHARGE TEST-1 PRINCIPLES • PARTIAL DISCHARGES ARE ELECTRICAL SPARKS WHICH OCCURS IN GAS VOIDS WITHIN THE INSULATION • DISCHARGES ARE PARTIAL AS SOME MORE INSULATION IS REMAINING TO PREVENT COMPLETE BREAK DOWN • IF PD CAUSE THE PD CHANNELS TO PROPOGATE WHICH RESULTS IN COMPLETE BREAK DOWN OF INSULATION • ELECTROMAGNETIC PROBES (PROXIMITY DETECTOR ) THAT IS SENSITIVE TO RADIO FREQUENCY SIGNALS PRODUCED BY PARTIAL DISCHARGES LOCATE SPECIFIC SITES OF DETERIORATION WITHIN THE WINDING TEST PROCEDURE • MACHINE SHOULD BE DISASSEMBLED • WITH NORMAL GROUND TO LINE VOLTAGE THE WINDING IS ENERGIZED. • ONE PHASE IS ENERGIZED WHILE THE OTHER TWO PHASES ARE GROUNDED. • THE PROBE IS POSITIONED NEAR STATOR COIL WEDGE AND SLOT EXIT ABOUT 100MM FROM THE WEDGE. • READING ARE TAKEN WITH PEAK PULSE METER.
  • 44. 44 PARTIAL DISCHARGE TEST-2 PARTIAL DISCHARGE ARE HIGH FREQUENCY ELECTRICAL PULSE DUE TO DISCHARGE IN VOIDS IN THE INSULATION CORE CONDUCTOR VOIDS NEAR COPPER- NEGATIVE DISCHARGE VOIDS INSIDE THE INSULATION – BOTH POSITIVE AND NEGATIVE DISCHARGES VOIDS NEAR THE CORE – POSITIVE DISCHARGE IT PARTIALLY BRIDGES THE GAP BETWEEN THE INSULATION AND THE GROUND RATED VOLTAGE IS APPLIED IN THE WINDING AND WAVE FORMS ARE RECORDED. CRACKS / CONTAMINATIONS ON THE SURFACE OF THE INSULATION CAUSES PD
  • 45. 45 ABOUT STATOR CORE • THE GENERATOR STATOR CORE IS BUILT FROM THOUSANDS OF THIN SHEET STEEL LAMINATION.(0.5mm) • THESE LAMINATIONS ARE COATED WITH A THIN LAYER OF VARNISH FOR PREVENTION OF CIRCULATING INDUCED CURRENTS ALSO KNOWN AS EDDY CURRENTS. • ANY DEFECT IN THE INTER LAMINAR INSULATION CAUSES FAULT CURRENT TO FLOW LOCALLY IN THE CORE. • THESE CIRCULATING CURRENT CAN THUS CAUSE LOCALISED OVER HEATING AND HOT SPOTS IN THE DAMAGED AREAS AND THIS MAY FURTHER DAMAGE THE CORE. • HENCE IT CALLS FOR TESTING THE INTERLAMINAR INSULATION
  • 46. 46 CORE LOOP TEST A V AC VOLTAGE SOURCE FLUX DENSITY :14000/10000GAUSS VOLTAGE/CURRENT IN MAGNETISING WINDING 475V/970A 1.STATOR SHOULD BE SOLIDLY EARTHED.2.NO BODY SHOULD ENTER UNLESS SUPPLY IS SWITCHED OFF 3. CABLE SHOULD NOT BE IN DAMAGED CONDITION 4. THERE SHOULD NOT BE ANY MAGNETIC /METAL OBJECTS NEAR THE CASING 5. TEMPERATURE MONITORING SYSTEM SHOULD BE READY. STATOR STATOR
  • 47. 47 DRAWBACKS OF RING LOOP TEST • IT IS A DESTRUCTIVE TEST • INVOLVES HEAVY POWER LOSS
  • 48. 48 ELCID TEST-NEED • THE DIGITAL ELCID TEST USES 4% OF THE RATED FLUX LEVEL TO GENERATE FAULT LEVEL WITH IN THE CORE BODY.
  • 49. 49 PRINCIPLE OF ELCID TEST • THE CIRCUMFERENTIAL MAGNETIC FIELD OF THE CORE IS DUE TO THE EXCITATION PLUS THAT DUE TO ANY FAULT CURRENTS PRESENT. • THE EFFECT OF THE MAGNETIC FIELDS IS TO PRODUCE MAGNETIC POTENTIAL GRADIENT ON THE CORE SURFACE. • THIS MAGNETIC POTENTIAL GRADIENT IS DETECTED BY SPECIALLY WOUND COIL KNOWN AS CHATTOCK COIL • THIS COIL PROVIDES AN OUTPUT PROPORTIONAL TO THE DIFFERENCE IN THE MAGNETIC POTENTIAL BETWEEN ITS TWO ENDS. • A SENSING HEAD (CHATTOCK COIL) IS PASSED OVER THE SURFACE OF THE CORE TO DETECT MAGNETICALLY THE PRESENCE OF FAULT
  • 51. 51 ELCID TEST –HOW RECORDED THE SIGNAL PROCESSOR IS CALIBRATED TO GIVE A DIRECT READING OF THE VALUE OF 1. DISTANCE INFORMATION ON THE X AXIS 2. THE FAULT CURRENT ALONG Y AXIS.
  • 53. 53 ELCID TEST CALCULATION Vt = (.04 X Vp-p )/ (2 x √3 x k x TP) Vt = TEST VOLTAGE MEASURED IN THE TRACE WINDING Vp-p = RATED PHASE TO PHASE VOLTAGE K = PITCH FACTOR (0.92 FOR ALL GENERATORS) TP = TURNS IN SERIES /PHASE
  • 54. 54 STATOR SLOT STATOR SLOT SLOT WEDGE SLOT RIPPLE SPRING GLASS TEXTOLITE SPACERS SOILID CONDUCTOR HOLLOW CONDUCTOR TOP BAR INSULATING PACKING BOTTOM BAR THERMOREACTIVE INSULATION BOTTOM PACKING
  • 55. 55 STATOR WEDGE DEFLECTION THE WINDINGS ARE SUBJECTED TO EXPANSION, CONTRACTION AND VIBRATIONS WHICH LEAD TO LOOSENING OF WEDGE THE TIGHTNESS OF THE WEDGES IS CHECKED BY KNOCKING WITH A SMALL HAMMER. FROM THE KNOCKING SOUND THE LOOSENESS OF THE WEDGE IS JUDGED. IF TOP RIPPLE SPRINGS ARE PROVIDED, THEN KNOCKING METHOD CAN NOT BE USED. DEFLECTION OF WEDGE IS MEASURED BY APPLYING CALCULATED PRESSURE USING “WEDGE DEFLECTION CHECKING KIT” TOP RIPPLE SPRINGS ARE NOT PROVIDED IN THE END WEDGES AND WHERE RTDs ARE PROVIDED. DEFLECTION OF LESS THAN 0.9 mm IS ALLOWED FOR 60% OF THE WEDGES AND A DEFLECTION OF LESS THAN 1.1 mm IS ALLOWED FOR 40% OF THE WEDGES. THE PRESSURE APPLIED IS CALCULATED USING THE FORMULA REQUIRED MANOMETER PR. = ((10 X PF ) / FK ) X LN X BN BAR SPECIFIC TEST PRESSURE FOR THE WEDGES (PF ) = 1.8 N / mm2 LN = SLOT WEDGE LENGTH IN cm BN = SLOT WIDTH IN cm PF= SPECIFIC TEST Pr. IN N/mm2 FK= PISTON SURFACE AREA IN cm2
  • 56. 56 WEDGE DEFLECTION LIMITS 1. IF THE WEDGE MOVEMENT OF MORE THAN 1.1MM IS MEASURED IN ANY SLOT, THE NUMBER OF MEASURING POINTS IN THIS SLOT IS DOUBLED AND IF THE VALUE IS EXCEEDED IN 2 POINTS. 2. ALL THE WEDGES IN THIS SLOT SHOULD BE CHECKED TO KNOW THAT NOT MORE THAN 2 POINTS ARE HAVING MOVEMENT MORE THAN THE SPECIFIED VALUE. 3. IF THE VALUE IS EXCEEDED, CORRECT PACKER ARE INSERTED AND TIGHTENED. 4. AFTER ALL SUCH WEDGES ARE TIGHTENED, THE WEDGE TIGHTNESS CHECKING WILL BE CARRIED OUT AGAIN. 5. AFTER TIGHTENING SLOT WEDGES, DEFLECTION SHOULD BE: BETWEEN 0.1mm to 0.3 mm FOR 75% : NOT MORE THAN 0.45 mm FOR 25%
  • 57. 57 INSPECTION OF ROTOR INSPECT THE JOURNAL FOR ANY PITTING AND SCRATCHES INSPECT FOR ANY DUST OR ANY UNDESIRABLE MATERIALS LYING IN VENTILATION HOLES AND VENTILATION CANALS OF RETAINING RING CHECK THE LOCKING OF BALANCE WEIGHTS CHECK THE TIGHTNESS OF WEDGES AND PACKERS UNDER RETAINING RING DP TEST OF FAN BLADES AND RETAINING RING DO NOT REST THE ROTOR ON RETAINING RING,SLIPRINGS,HALF COUPLING AND ROTOR WEDGES PRESERVE AGAINST RUSTING OF JOURNAL, SLIP RING AND HALF COUPLING WHEN THE ROTOR IS OUT.
  • 58. 58 TESTS ON ROTOR INSULATION RESISTANCE VALUE USING 500 V MEGGER. IT SHOULD BE MORE THAN 1. 3 MEGA OHMS DC RESISTANCE VALUE IS MEASURED. AFTER TEMPERATURE CORRECTION, IT IS COMPARED WITH FACTORY VALUE. VARIATION WITH IN 2 % IS CONSIDERED AS NORMAL AC IMPEDANCE VALUE IS MEASURED AT VARIOUS SPEED OF THE ROTOR. HV TEST: AT 2.5 KV, FOR ONE MINUTE FOR A NEW ROTOR AT SITE. VALUE MAY BE REDUCED FOR OLD ROTOR. GENERALLY CARRIED OUT ONLY WHEN ANY REPAIR IS DONE ON THE ROTOR WINDING.
  • 60. 60 RECURRENT SURGE OSCILLOSCOPE TEST ON ROTOR A D.C STEP BETWEEN ONE END OF THE ROTOR WINDING AND THE ROTOR BODY. THE TRANSMITTED WAVE AND THE REFLECTED WAVE AT THE INPUT END OF THE WINDING IS MONITORED USING TWO OSCILLOSCOPE CHANNELS IF THE VOLTAGE STEP IS APPLIED FROM EACH END OF THE ROTOR WINDING THEN ALTERNATIVELY THEN TWO OSCILLOSCOPE TRACES WILL BE OBTAINED WHICH MAY BE SUPERIMPOSED ON THE OSCILLOSCOPE SCREEN A HEALTHY ROTOR WILL HAVE TWO INDENTICAL TRACES A ROTOR WILL A FAULT WILL HAVE DIFFERING TRACES THE POSITION OF THE FAULT MAY BE DEDUCED BY SCALING THE TIME DOMAIN
  • 61. 61 RSO TEST CIRCUIT CONNECTION Pulse Generator oscilloscope chanell 1
  • 62. 62 ROTOR GAS TIGHTNESS TEST GENERATOR STATOR FAN BLADE INNER CURRENT CARRYING BOLT CORE BAR ROTOR RETAINING RINGHALF COUPLING OUTER CURRENT CARRYING BOLT SLIP RING NITROGEN CYLINDER GAS TIGHTNESS OF ROTOR PRESSURE REGULATOR
  • 63. 63 ROTOR SLOT SLOT WEDGE TOP LINER ROTOR SHAFT SLOT BACK BOTTOM LINER
  • 66. 66 STATIC PRESSURE AND VELOCITY PRESSURE STATIC PRESSURE:THE RISE IN STATIC PRESSURE AT A POINT MINUS THE REFERENCE ATMOSPHERIC PRESSURE. VELOCITY PRESSURE: THE RISE IN STATIC PRESSURE WHICH OCCURS WHEN AIR MOVING WITH SPECIFIED VELOCITY AT A POINT IS BROUGHT TO REST WITH OUT LOSS OF MECHANICAL ENERGY
  • 67. 67 PURGE TEST 1 PRESSURE OF 3. 0 ± 0.1KG/cm2 GAUGE SHOULD BE APPLIED AT THE VENTILATING CANALS OF SLOT THROUGH THE ADOPTER. 2. WHILE CARRYING OUT TEST ON OVERHANG, A STATIC PRESSURE OF 50 mm OF WATER COLUMN SHOULD BE MAINTAINED UNDER RETAINING RING. 3. THE AVERAGE VELOCITY PRESSURE IN THE CANALS OF SLOT PORTION SHOULD NOT BE LESS THAN 15 mm OF WATER COLUMN FOR EACH ZONE AND 21 mm OF WATER COLUMN FOR EACH SLOT. 4. THE MINIMUM VALUE OF STATIC PRESSURE IN INDIVIDUAL CANALS OF OVER HANG PORTION SHOULD NOT BE LESS THAN 15mm OF WATER COLUMN. 5. FULLY CLOSED CANALS ARE NOT ALLOWED IN THE OVER HANG PORTION OF ROTOR WINDING. 6. ENSURE THAT ALL THE VENTILATION CANALS/ DUCTS ARE PROPERLY SEALED AFTER THE PURGE TEST.
  • 68. 68 HYDRO TEST OF STATOR WINDING HYDRAULIC TEST FOR THE STATOR WINDING IS CONDUCTED AT 5 KG/ cm2 FOR 24 HOURS USING FILTERED DM WATER. NO DROP IS ALLOWED. PROBABLE LEAK POINTS ARE TEFLON HOSES AT THE TURBINE END THE CONNECTING PIPES OF THE TERMINAL BUSHINGS THE CONNECTING PIPES AT THE EXCITER END
  • 69. 69 EPOXY GLUE INJECTION OF STATOR OVERHANG WINDING & VARNISHING OF STATOR THE STATOR OVERHANG WINDING ARE SUBJECTED TO MORE STRESS DURING ANY ELECTRICAL FAULT TO GIVE ADDITIONAL STRENGTH TO THE OVERHANG WINDING SUPPORTS, EPOXY GLUE IS PUMPED & SPRAYED OVER IT AFTER CLEANING AND DRYING BY EXTERNAL HEATING, USING ELECTRICAL BULBS. RESIN CY 205 : ( 4250 GRAMS) DILUENT – C : (750 GRAMS) HARDENER- HY 840 : (2000 GRAMS) THE CORE IS GIVEN A COATING OF VARNISH AFTER CLEANING AND DRYING.
  • 70. 70 AIR TIGHTNESS TEST OF GENERATOR So – LEAKAGE OF GAS ( AT ATM. PRESSURE AND AT 20 OC IN %) P1 & P2 - ABS. PR. AT BEGINNING AND END OF THE TEST IN mm of HG. T1 & T2 ABS. TEMP AT BEGINNING AND END OF THE TEST IN DEGREE KELVIN. t – DURATION OF TIME. AFTER COMPLETING THE ASSEMBLY & COMMISSIONING OF SEAL OIL SYSTEM, AIR LEAK IS CONDUCTED WITH DRY AIR, AT A PRESSURE OF 4 KSC FOR 24 HOURS % 925 : 2 2 1 1            T P T P t So Vo = So X V V – GAS VOLUME OF STATOR IN M3 ( 56 M3 ) Vo – ABSOLUTE IN LEAKAGE IN M3100
  • 71. 71 AIR TIGHTNESS TEST -2 VOLUME IS INVERSELY PROPORTIONAL TO SQUARE OF DENSITIES. 3.20.1138/1.18 AirV HydrogenV o o  GAS LEAK SHOULD BE WITHIN 1 % OF THE VOLUME
  • 72. 72 BRUSHGEAR CLEARANCES I1 I2 I1 & I2 = 0.1 TO 0.3 S = 2 TO 2.5 S t1 t2 t4 t3 t1, t2 , t3, t4 = 3.4 to 4.1 BRUSHGEAR BRUSH HOLDER SLIPRING ALIGNMENT OF BRUSHGEAR BRUSH HOLDER AND BRUSHES BRUSH BRUSH HOLDER
  • 73. 73 STAGGERING OF BRUSHES A D BC A 0 D 50 TO 54 B 16- 20 C 32 TO 36