Module Plan 
DOC NO.:TSFO034 
REVISION NO.:00 
(Administrator/Instructor Guide) 
STP No: 
AIRCRAFT 
STRUCTURE 
WORKSHOP 
PART 1 
Location: 
IR.IRAN CATC 
Date : 
November 2014 
Completed by : 
CDU 
Page 1 
Module Title: 
A/C GROUND HANDLING 
Function No: 
Task No(s): 1` Sub-Task No(s): 
End-of-Module Objective: 
Conditions: GIVEN ALL NECESSARY TOOLS, TWO MAIN JACK, A TAIL JACK, AN 
AIRCRAFT, WHEEL CHOCKS, JACK PADS, TOW BAR, A/C M.M 
Performance: PERFORM GROUND HANDLING PROCEDURES 
Standard: ACCORDING TO A/C M.M, part 66 modules 7.1, 7.2, 7.17 & F28 M.M. 
Intermediate Objectives: 
1. Explain: 
a. Aspect Of Safe Working Practices & Precautions In Hanger Area & 
When Involving Aircraft Maintenance Tasks Also Remedial Action 
b. Care Of Tools, Control Of Tools, Use Of Workshop Materials. 
2. Prepare A/C M.M & Teach Trainees A/C Publications Types & Its Usage 
3. Determine A/C Dimensions & Zones (Locations ) 
4. Explain Towing /Taxing and associated safety precautions. 
5. Explain Mooring 
6. EXPLAIN Jacking, Chocking, Securing And Associated Safety Precautions. 
7. Perform Jacking 
8. Explain Levelling The A/C / perform levelling. 
General Notes for the Instructor: 
• Encourage Trainees To Discuss Safety & Its Importance, Show Them 
Various Sections Of Workshop, Hanger Area & Target Aircraft. 
• Make Sure That All Necessary Tools & Equipment Are Available 
• Prepare Adequate Tool Box & A/C M.M 
• During Each Phase Of Performing Intermediate Objectives Supervise 
Trainees. 
• Inform Trainees About Right Use Of Tools.
DOC NO.:TSFO034 Module Plan 
REVISION NO.:00 (Administrator/Instructor Guide) 
STP No: 
AIRCRAFT STRUCTURE WORKSHOP PART ( I ) 
Page 2 
Module Title: A/C GROUND HANDLING Module No: 
Time Main Units/Steps/Aids Contents:-Summary of activities, points to be emphasized, 
etc 
10” 
INTRODUCTION 
MODULE 
OBJECTIVE 
OUTLINE 
MODULE 
CONTENT 
- Inform Importance Of Ground Handling, 
Accomplishment According To M.M. 
- Emphasise On Safety & Tool Using. 
- Present Module Objective And Point Out That 
The Mastery Test Matches Objective 
- Inform Trainees There Will Be Grope Practical 
Test 
- Present All Steps To Be Covered In Ground 
Handling 
20” 
SAFETY 
PRECAUTION 
-Point Out Aspect Of Safe Working Practices To 
Component In Workshop Area And Hangar Also 
When Involving Maintenance Tasks. 
- USE M.M, TTS MODUL 7(7.1, 7.2 ) 
45” 
AIRCRAFT 
PUBLICATIONS 
BOOKS: 
Forms: 
SERVICE BULETENS 
CHECKLISTS 
-Inform Trainees That All Maintenance Tasks & 
Procedures In Airlines Are Accomplished According 
To A/C Publications. 
-Explain Briefly Publications As Follow Below: 
M.M, F.M, T.M, S.R.M, T.S.M, O.H, R.M, O.M, 
T.S.M, .( ANY TYPE OF A/C LIKE A300, A310, F28 
-Explain S.B (Optional S.B, Mandatory S.B, ,. . . ) 
-Explain (Hourly, Daily, Weekly, Monthly, 
Calendared,.) Checklists. 
- Show Trainees F28 Checklists, (A310, . . . . . )
30” 
DIMENSION 
& 
ZONES 
(LOCATIONS) 
Explain A/C Dimensions And Zones, Go Through M.M 
- Emphasize Due To Varity Of System And Component 
And The Location, Along The Fuselage Or Wings It Is 
Important To Have Full View Of Whole A/C. 
- Also Sections & Divisions,( Longitudinally, Literally, 
Vertically). 
- Use F28 M.M (A300, A310, . . .) Discuss Subject. 
30” 
TOWING 
& 
TAXING 
-Explain Taxing During Ground Maundering (Taxi 
Way, Runway, Park Area ) 
-Show Trainees Tow Bar, Tell About “Tow Man” In 
The Past And “Tow Truck”, Using M.M For Detail. 
Illustrate Danger Areas (M.M). 
- Walk Around F28 A/C And Show Tow Attachment 
Point, . . . 
30” 
MOORING 
a. Internal mooring 
Parking brake 
b. External mooring 
gust lock, chocks, 
feather, covering jet 
engine intake 
Explain mooring, refer to M.M, explain types of mooring 
Show trainees mooring "lock & cable" 
Explain Mooring Inside Cockpit, Show Positioning 
Moor Elements. 
Explain Mooring Outside Cockpit, Show Positioning 
Moor elements. 
90” 
JACKING 
& 
CHOCKING 
Jacking points 
Jack pads 
CHOCKS 
PRACTICAL 
EXERCISE 
Hands Out Each Trainee M.M Explain Types Of 
Jacks. 
Show Trainees Jacking Point Trough M.M, Also 
Walk Around A/C & Locate Jacking Points.(F28 
M.M ) 
Explain Jack Pad & Method Of Installation 
Show Trainees Chocks & The Method Of 
Installation. 
Divide Trainees Into Two Groups 
Prepare A/C Jacks, Jack Pads, Necessary Tools & 
A/C M.M Ask Them To Perform Jacking & Chocking
STP No: 
A/C STRUCTURE WORKSHOP PART 1 
Page 4 
Module Title: A/C GROUND HANDLING 
Module No: 
Time Main Units/Steps/Aids Contents:-Summary of activities, points to be emphasized, 
etc 
60” 
LEVELING 
PRACTICAL 
EXERCISE 
Notify Levelling Purposes & Importance, Referring 
To M.M And Walk Around The A/C. 
Divide Trainees Into Two Groups 
Prepare A/C M.M Ask Them To Perform Levelling. 
15” 
Completion of 
Practical training 
log 
Carefully Record & Sign Each Trainee P.T.LOG 
15” 
Mastery test 
Hand Out Copies Of Mastery Test ( MT G H.1 ) & 
( A Sheet G H.1 )Ask Trainees Perform Test 
Individually In 15”( Minutes ). 
Test May Be Multiple Choice Or Oral Questions.
ground handling (2)

More Related Content

PPT
Take Off And Landing Performance
PPTX
Marketing yang bisa menjadi overkilled produk atau jasa
PPTX
Semakin tersebar kebohongankebangkitantuhanyesus
RTF
Company profile
PPTX
Kelemahan dan kekuatan uberpool
PPTX
Apakah saudara sudah tahu 34 yesuspaulus
PPTX
Apakah saudara sudah tahu 70 pestamirasalkitab
PPTX
Ajaran yang sama
Take Off And Landing Performance
Marketing yang bisa menjadi overkilled produk atau jasa
Semakin tersebar kebohongankebangkitantuhanyesus
Company profile
Kelemahan dan kekuatan uberpool
Apakah saudara sudah tahu 34 yesuspaulus
Apakah saudara sudah tahu 70 pestamirasalkitab
Ajaran yang sama

Viewers also liked (12)

PPTX
Apakah saudara sudah tahu jawabansayapenulisblogislam2
PPTX
Konsistenkarakter
PPTX
Apakah saudara sudah tahu menjawabpertanyaanlagi
PPTX
Tempe setengah jadi imantnpperbuatan
PPTX
Alquranmendukungalkitab
PPTX
Apakah saudara sudah tahu kemacetanituharusteratur
DOCX
LauraBradway_resume
DOCX
Latest resume rkp 4th oct.
PPTX
Don’t give up nick vujicic
PPTX
Once in a lifetime
PPTX
Apakah saudara sudah tahu 84 justcurious x
PPTX
Apakah saudara sudah tahu alkitabalquran
Apakah saudara sudah tahu jawabansayapenulisblogislam2
Konsistenkarakter
Apakah saudara sudah tahu menjawabpertanyaanlagi
Tempe setengah jadi imantnpperbuatan
Alquranmendukungalkitab
Apakah saudara sudah tahu kemacetanituharusteratur
LauraBradway_resume
Latest resume rkp 4th oct.
Don’t give up nick vujicic
Once in a lifetime
Apakah saudara sudah tahu 84 justcurious x
Apakah saudara sudah tahu alkitabalquran
Ad

Similar to ground handling (2) (8)

PPT
ET-A08 - aircraft handling.ppt
PPT
EASA module 7.17 Aircraft handling and storage.ppt
PDF
01 GENERAL.pdf
PDF
07 JACKING.pdf
PPTX
DISASSEMBLY and re assembly of aircraft component
PDF
PPT
Aircraft inspection and_repair
PPT
Unit III Maintenance of Safety
ET-A08 - aircraft handling.ppt
EASA module 7.17 Aircraft handling and storage.ppt
01 GENERAL.pdf
07 JACKING.pdf
DISASSEMBLY and re assembly of aircraft component
Aircraft inspection and_repair
Unit III Maintenance of Safety
Ad

ground handling (2)

  • 1. Module Plan DOC NO.:TSFO034 REVISION NO.:00 (Administrator/Instructor Guide) STP No: AIRCRAFT STRUCTURE WORKSHOP PART 1 Location: IR.IRAN CATC Date : November 2014 Completed by : CDU Page 1 Module Title: A/C GROUND HANDLING Function No: Task No(s): 1` Sub-Task No(s): End-of-Module Objective: Conditions: GIVEN ALL NECESSARY TOOLS, TWO MAIN JACK, A TAIL JACK, AN AIRCRAFT, WHEEL CHOCKS, JACK PADS, TOW BAR, A/C M.M Performance: PERFORM GROUND HANDLING PROCEDURES Standard: ACCORDING TO A/C M.M, part 66 modules 7.1, 7.2, 7.17 & F28 M.M. Intermediate Objectives: 1. Explain: a. Aspect Of Safe Working Practices & Precautions In Hanger Area & When Involving Aircraft Maintenance Tasks Also Remedial Action b. Care Of Tools, Control Of Tools, Use Of Workshop Materials. 2. Prepare A/C M.M & Teach Trainees A/C Publications Types & Its Usage 3. Determine A/C Dimensions & Zones (Locations ) 4. Explain Towing /Taxing and associated safety precautions. 5. Explain Mooring 6. EXPLAIN Jacking, Chocking, Securing And Associated Safety Precautions. 7. Perform Jacking 8. Explain Levelling The A/C / perform levelling. General Notes for the Instructor: • Encourage Trainees To Discuss Safety & Its Importance, Show Them Various Sections Of Workshop, Hanger Area & Target Aircraft. • Make Sure That All Necessary Tools & Equipment Are Available • Prepare Adequate Tool Box & A/C M.M • During Each Phase Of Performing Intermediate Objectives Supervise Trainees. • Inform Trainees About Right Use Of Tools.
  • 2. DOC NO.:TSFO034 Module Plan REVISION NO.:00 (Administrator/Instructor Guide) STP No: AIRCRAFT STRUCTURE WORKSHOP PART ( I ) Page 2 Module Title: A/C GROUND HANDLING Module No: Time Main Units/Steps/Aids Contents:-Summary of activities, points to be emphasized, etc 10” INTRODUCTION MODULE OBJECTIVE OUTLINE MODULE CONTENT - Inform Importance Of Ground Handling, Accomplishment According To M.M. - Emphasise On Safety & Tool Using. - Present Module Objective And Point Out That The Mastery Test Matches Objective - Inform Trainees There Will Be Grope Practical Test - Present All Steps To Be Covered In Ground Handling 20” SAFETY PRECAUTION -Point Out Aspect Of Safe Working Practices To Component In Workshop Area And Hangar Also When Involving Maintenance Tasks. - USE M.M, TTS MODUL 7(7.1, 7.2 ) 45” AIRCRAFT PUBLICATIONS BOOKS: Forms: SERVICE BULETENS CHECKLISTS -Inform Trainees That All Maintenance Tasks & Procedures In Airlines Are Accomplished According To A/C Publications. -Explain Briefly Publications As Follow Below: M.M, F.M, T.M, S.R.M, T.S.M, O.H, R.M, O.M, T.S.M, .( ANY TYPE OF A/C LIKE A300, A310, F28 -Explain S.B (Optional S.B, Mandatory S.B, ,. . . ) -Explain (Hourly, Daily, Weekly, Monthly, Calendared,.) Checklists. - Show Trainees F28 Checklists, (A310, . . . . . )
  • 3. 30” DIMENSION & ZONES (LOCATIONS) Explain A/C Dimensions And Zones, Go Through M.M - Emphasize Due To Varity Of System And Component And The Location, Along The Fuselage Or Wings It Is Important To Have Full View Of Whole A/C. - Also Sections & Divisions,( Longitudinally, Literally, Vertically). - Use F28 M.M (A300, A310, . . .) Discuss Subject. 30” TOWING & TAXING -Explain Taxing During Ground Maundering (Taxi Way, Runway, Park Area ) -Show Trainees Tow Bar, Tell About “Tow Man” In The Past And “Tow Truck”, Using M.M For Detail. Illustrate Danger Areas (M.M). - Walk Around F28 A/C And Show Tow Attachment Point, . . . 30” MOORING a. Internal mooring Parking brake b. External mooring gust lock, chocks, feather, covering jet engine intake Explain mooring, refer to M.M, explain types of mooring Show trainees mooring "lock & cable" Explain Mooring Inside Cockpit, Show Positioning Moor Elements. Explain Mooring Outside Cockpit, Show Positioning Moor elements. 90” JACKING & CHOCKING Jacking points Jack pads CHOCKS PRACTICAL EXERCISE Hands Out Each Trainee M.M Explain Types Of Jacks. Show Trainees Jacking Point Trough M.M, Also Walk Around A/C & Locate Jacking Points.(F28 M.M ) Explain Jack Pad & Method Of Installation Show Trainees Chocks & The Method Of Installation. Divide Trainees Into Two Groups Prepare A/C Jacks, Jack Pads, Necessary Tools & A/C M.M Ask Them To Perform Jacking & Chocking
  • 4. STP No: A/C STRUCTURE WORKSHOP PART 1 Page 4 Module Title: A/C GROUND HANDLING Module No: Time Main Units/Steps/Aids Contents:-Summary of activities, points to be emphasized, etc 60” LEVELING PRACTICAL EXERCISE Notify Levelling Purposes & Importance, Referring To M.M And Walk Around The A/C. Divide Trainees Into Two Groups Prepare A/C M.M Ask Them To Perform Levelling. 15” Completion of Practical training log Carefully Record & Sign Each Trainee P.T.LOG 15” Mastery test Hand Out Copies Of Mastery Test ( MT G H.1 ) & ( A Sheet G H.1 )Ask Trainees Perform Test Individually In 15”( Minutes ). Test May Be Multiple Choice Or Oral Questions.