HV Substation Interface Activities:
Safety/Operational Requirements
Produced By: C Doyle
Contents
• Activity 1: Installation
• Activity 2A: Cable termination HV & LV
• Activity 2B: Unlicensed Commissioning
• Activity 3: Back Energisation
• Activity 4: Commissioning
• Activity 5: Post COD
HV INTERFACE ACTIVITY 1:
INSTALLATION
HV Substation Interface Activities
HV Interface: Activity 1
Installation
• Civil works (cable ducts)
• Cable Support Install
• Scaffolding
• HV Cable Pull
• LV Cable Pull
• Earthing (assume PS Earth is Tested/Complete)
• Install APDF Remote I/O Panel
• NG Unlicensed Relays Installation in M1/M2
HV Interface Activity 1: Installation Safety/Procedural Boundaries
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS, LWC may be
issued
• Point of isolation issued
for work on LV systems/
System Connection Rules
SAFETY:
• APDF work is undertaken
under APDF Local Safety
Instructions/Safety Rules
• Rules submitted to NG
For Review
• RAMS submitted to NG 3
weeks prior to work
taking place for review
by NG
Operational:
• APDF work under a point
of isolation for any LV
work utilising their own
Safety Instructions
APDF Working Party Requires:
NG Persons
NG Competent Persons (key Holder also)
Approved scaffolders for NG Safety Rules
Operational:
• NG Local Instructions
• NG Performs CPO
Notes:
• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate
but will require a key holder under NG rules. This should
be agreed at CDM meeting and also discussed through
TP153 meeting to finalise.
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• Note: If earths are not terminated insulated working must
be carried out under NSI 5,6 &24, RAMS should be based
on this (preferably not done until earths are connected for
safety)
Circuit equipment
on Power station
side
Surge Arrestors
Cable Protected Both Ends
Module M1/M2
Cable Pulled Not
Terminated
CCT 1 & CCT 2 C&P
Module
Esbi Civil Contractor Required
NG Persons
NG Competent Persons (key Holder also)
NG Working Party Requires:
• To work under APDF Permit
• Trained as person and work under APDF competent
person
Actions
• APDF to confirm what qualifications/inductions NG Working Party Requires to
install Protection Relays in M1/M2 and process for submitting RAMS
• APDF to confirm list of personnel undergoing Person/Competent Person training
from AP and DF and that a key holder will also be provided
• APDF to confirm the qualifications of their contractors who will access the
substation for cable pulling HV/LV/I&C, cable support install and terminations
• APDF RAMs to be submitted to NG a minimum of 3 weeks prior to proposed work,
this is to be coordinated through the TP106/153 meetings on site. ESBI remind
APDF of site RAMS review period by OE prior to submission to NG.
• A safety inaugural meeting will be required to take place 6 weeks prior to any
works commencing, APDF to advise when this should be scheduled
• APDF to review programme submitted under APDF/CPL/1187 and advise on
current programme as changes should be coordinated through the TP meetings
with NG
HV INTERFACE ACTIVITY 2A: CABLE
TERMINATION HV & LV
HV Substation Interface Activities
HV Interface: Activity 2A
Cable Termination: HV & LV
• Install GIS Sealing End (ABB Interface)
• HV Cable Testing
• Install HV Cable Termination
• Earth Terminations (cable)
• Scaffolding
• LV Cable Testing and Terminations
HV Interface Activity 2A: HV & LV Cable Terminations
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS, LWC may be
issued
• Point of isolation issued
for work on LV systems/
System Connection Rules
SAFETY:
• APDF work is undertaken
under APDF Local Safety
Instructions/Safety Rules
• Rules submitted to NG
For Review
• Trafo Compound locked
and under NG Safety
Rules
Operational:
• APDF work under a point
of isolation for any LV
work utilising their own
Safety Instructions
APDF Working Party Requires:
NG Persons
NG Competent Persons (key Holder also)
Approved scaffolders for NG Safety Rules
Operational:
• NG Local Instructions
Apply for Isolations
• HVSCC Required to bring
cable and sealing ends in
remote compound
(Trafo) under NG CPO
• NG Performs CPO
Notes:
• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate
but will require a key holder under NG rules. This should
be agreed at CDM meeting and also discussed through
TP153 meeting to finalise.
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• Note: If earths are not terminated insulated working must
be carried out under NSI rules, RAMS should be based on
this (preferably not done until earths are connected for
safety)
Circuit equipment
on Power station
side
Module M1/M2
CCT 1 & CCT 2 C&P
Module
No System Connection 3.5m
Safety Distance
HV INTERFACE ACTIVITY 2B:
UNLICENSED COMMISSIONING PHASE 1
HV Substation Interface Activities
HV Interface: Activity 2B
Unlicensed Commissioning: (LV Cable
terminations Complete, Prior to HV Cable)
• Commissioning of signals between PP & SS
(Phase 1)
HV Interface Activity 2B: Unlicensed Relay Commissioning Phase 1
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS, LWC may be
issued
SAFETY:
• NG work in M1/M2
under APDF rules
• Further coordination
required in working
group meetings
Operational:
• Discuss with APDF. How
will this interface be
managed (Phase 1)
NG Working Party Requires:
• To work under APDF Permit
• Trained as person and work under APDF competent
person
Operational:
• NG Local Instructions
Apply for Isolations
• NG Performs CPO
• SRS requires discussion
at TP153 (LV equipment)
Notes:
• SRS requires discussion at TP153 (LV equipment)
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• NG will work under APDF rules in Module M1/M2
Circuit equipment
on Power station
side
Module M1/M2
CCT 1 & CCT 2 C&P
Module
No System Connection 3.5m
Safety Distance
Actions
• NG Unlicensed to confirm power
requirements for relays and APDF to ensure
these are available for programmed dates
• NG unlicensed to provide commissioning plan
for Phase 1 & Phase 2 commissioning
HV INTERFACE ACTIVITY 3A: BACK
ENERGISATION CABLE SOAK
HV Substation Interface Activities
HV Interface: Activity 3
Back Energisation: Cable Soak
• Switch in cable for 24hr soak test
• HVSCC issued and Revert Back to busbar
disconnects for further back energisation
under NG CPS and APDF CPO
HV Interface Activity 3: Back Energisation Cable Soak
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS a RISSP may be
issued
SAFETY:
• APDF work is undertaken
under APDF Local Safety
Instructions/Safety Rules
• Rules submitted to NG
For Review
• Trafo Compound locked
and under NG Safety
Rules
Operational:
• National Grid are CPO
APDF Working Party Requires:
NG Persons
NG Competent Persons (key Holder also)
Operational:
• NG Local Instructions
Apply for Isolations
• HVSCC Required to bring
cable and sealing ends in
remote compound
(Trafo) under NG CPO
• NG Performs CPO
Notes:
• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate
but will require a key holder under NG rules. This should
be agreed at CDM meeting and also discussed through
TP153 meeting to finalise.
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• Immediately after cable soak the control boundary moves
to HV disconnects under a HVSCC, NG relinquish CPO role
and O&M undertake this role under their local
instructions which have been approved by NG
• NG retain the CPS role under contract to Asset
Management
• Partial Discharge monitoring/testing to be discussed at
TP106
Circuit equipment
on Power station
side
Module M1/M2
CCT 1 & CCT 2 C&P
Module
No System Connection 3.5m
Safety Distance
HV INTERFACE ACTIVITY 3: BACK
ENERGISATION
HV Substation Interface Activities
HV Interface: Activity 3
Back Energisation: GSUT Energisation, LV GCB,
6.6kV (as per back energisation procedure)
• Energise GSUT, IPB’s, HV Side of GCB, UT up to
6.6kV Incoming Breakers
HV Interface Activity 3B: Back Energisation: GSUT Energisation, LV GCB, 6.6kV (as per
back energisation procedure)
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION
(O&M
Operational CPO)
POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS a RISSP may be
issued (type of safety
document to be
discussed)
SAFETY:
• APDF work is undertaken
under APDF Local Safety
Instructions/Safety Rules
• RISSP Issued and taken
by O&M CPO, RISSP
integrated into APDF
safety rules
Operational:
• O&M are now CPO
under their operational
procedures/local
instructions
APDF Working Party in Substation Requires:
NG Persons
NG Competent Persons (key Holder also)
APDF liaise with O&M CPO/Requesting Safety officer
Operational:
• HVSCC agreed with SRS
defined as O&M CPO
• Contact persons agreed
in SRS and through
compliance process
between O&M CPO and
NG Control Centre
Notes:
• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate
but will require a key holder under NG rules. This should
be agreed at CDM meeting and also discussed through
TP153 meeting to finalise.
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• NG retain the CPS role under contract to Asset
Management
• O&M are CPO
Circuit equipment
on Power station
side
Module M1/M2
CCT 1 & CCT 2 C&P
Module
O&M Personnel:
NG Persons (to access substation)
Competent Persons
Authorised Persons
Requesting Safety Officer (can be the CPO) but must
be trained to level to receive a RISSP
Control/Safety/Maintenance
Ownership Boundaries
X190
X196
X194
X193
CCGT
Equipment
Sub Fence
NG Safety Rules /Maintenance
NG Ownership
NG Operational
APDF Safety rules
O&M Ownership
O&M Operational
HV Safety/Operational Interface
Protocol
Warwick
Substation
Power Station
NG
O&M
APDF
HV Control Person/ CPO
CPOCPS
Implementing
Safety
Coordinator/ SAP
APDF HV Interface
manager
TP106/TP153/Working
Group meetings
Planned Operational Switching/ Outages
Client Review
Planned Outages
Planned Operational Switching
Emergency
Switching
Planned
Switching
Communications
Switching Request/ RISSP
Issue
Emergency
Switching
Planned
Switching
Actions
• O&M Safety Rules/HV Switching/RISSP Process
(including third party involvement) to be finalised
and submitted to NG for review ASAP
• O&M to confirm timelines for training of
Authorised Personnel for HV Control Persons
• Switching should be remote i.e. DCS
• APDF to include a HV Switching Interface protocol
in safety rules to include RISSP process
• CPL/O&M to confirm that HV Busbar Disconnects
are to be switched by NG and not at DCS.
HV INTERFACE ACTIVITY 4:
COMMISSIONING
HV Substation Interface Activities
HV Interface: Activity 4
Commissioning
• Commissioning as Per APDF Programme
• Phase 2 Commissioning of Unlicensed Protection
Relays (load)
• Full Control & Protection Commissioning
• Plant functional tests
• Grid Compliance Tests
• Performance Test
• Reliability Run
• Handover
HV Interface Activity 4: Commissioning
X190
X196
X194
X193
F19A
Cable
bushing
Sub FenceSUBSTATION
(O&M
Operational CPO)
POWERSTATION
SAFETY:
• NG Safety Rules Apply
• NG Performs CPS
• SAP (P.Monaghan, Brian
Sleigh)
• Implementation Safety
Coordinator (P.
Monaghan? TBC)
• Following Review of
RAMS a RISSP may be
issued (type of safety
document to be
discussed)
SAFETY:
• APDF work is undertaken
under APDF Local Safety
Instructions/Safety Rules
• RISSP Issued and taken
by O&M CPO, RISSP
integrated into APDF
safety rules
Operational:
• O&M are now CPO
under their operational
procedures/local
instructions
APDF Working Party in Substation Requires:
NG Persons
NG Competent Persons (key Holder also)
APDF liaise with O&M CPO/Requesting Safety officer
Operational:
• HVSCC agreed with SRS
defined as O&M CPO
• Contact persons agreed
in SRS and through
compliance process
between O&M CPO and
NG Control Centre
Notes:
• Area will be delineated with the EPC Contractor as PC
under the CDM Regs. APDF can access through own gate
but will require a key holder under NG rules. This should
be agreed at CDM meeting and also discussed through
TP153 meeting to finalise.
• Programme of work to be managed through TP106 and
specific working groups. APDF must submit detailed
activity programme.
• NG retain the CPS role under contract to Asset
Management
• O&M are CPO
• O&M are working in APDF working parties for power
station commissioning and are trained under APDF Safety
Rules
Circuit equipment
on Power station
side
Module M1/M2
CCT 1 & CCT 2 C&P
Module
O&M Personnel:
NG Persons (to access substation)
Competent Persons
Authorised Persons
Requesting Safety Officer (can be the CPO) but must
be trained to level to receive a RISSP
HV Interface: Activity 5
Post COD
• Normal Operation
Control/Safety/Maintenance
Ownership Boundaries
X190
X196
X194
X193
CCGT
Equipment
Sub Fence
NG Safety Rules /Maintenance
NG Ownership
NG Operational
O&M Ownership
O&M Operational
O&M Safety Rules /Maintenance
HV Safety/Operational Interface
Protocol
Warwick
Substation
Power Station
NG
O&M
HV Control Person/ CPO
CPOCPS
Implementing
Safety
Coordinator/ SAP
Planned Outages
Planned Operational Switching
Emergency
Switching
Planned
Switching
Communications/
TOGA
Switching Request/ RISSP
Issue

More Related Content

PDF
Responsibility Matrix RM
DOC
PPTX
AgileSwitch SiC Product Overview
PPTX
60 GHz mixed signal active load pull for millimeter wave devices characteriza...
PPTX
Apec 2014 Presentation by Albert Charpentier
PPSX
Intertest
PPTX
First GREP Project
PDF
Duotech's F-16 Briefing During the 2015 F-16 TCG WWR
Responsibility Matrix RM
AgileSwitch SiC Product Overview
60 GHz mixed signal active load pull for millimeter wave devices characteriza...
Apec 2014 Presentation by Albert Charpentier
Intertest
First GREP Project
Duotech's F-16 Briefing During the 2015 F-16 TCG WWR

What's hot (14)

PDF
Special Seismic Certification OSHPD
PDF
Seismic Considerations Seminar | Portland, Oregon
PPTX
Three d company-AAI Presentation
DOC
Preventive Maintenance Report - Dubai
PDF
06 CIP-002-5.1 Additional Consideration - 10 13 15
PDF
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
PDF
PROJECT STORYBOARD: Call One Router Installation Process Improvement Project
PDF
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
PDF
Inspection & Test Plan -Electrical - Hazardous Area Installation - Q1447-CS-P...
PDF
132901 draft-001-001
PPT
Huawei wcdma-rno-single-site-verificationV1
PDF
HC24.29.625-IA-23-Wide-Ruhl-Intel_2012_NTV_iA
PDF
RTStand LV 124 - fully-automated testing system for LV 124
PPS
Mechanical Completions
Special Seismic Certification OSHPD
Seismic Considerations Seminar | Portland, Oregon
Three d company-AAI Presentation
Preventive Maintenance Report - Dubai
06 CIP-002-5.1 Additional Consideration - 10 13 15
Inspection & Test Plan - Electrical - Telecommunications & Security Systems -...
PROJECT STORYBOARD: Call One Router Installation Process Improvement Project
Inspection & Test Plan - Electrical Power Distribution System - Q1447-CS-PCP-...
Inspection & Test Plan -Electrical - Hazardous Area Installation - Q1447-CS-P...
132901 draft-001-001
Huawei wcdma-rno-single-site-verificationV1
HC24.29.625-IA-23-Wide-Ruhl-Intel_2012_NTV_iA
RTStand LV 124 - fully-automated testing system for LV 124
Mechanical Completions
Ad

Viewers also liked (20)

PDF
Third Year Design Briefs
PDF
PPTX
Звіт про роботу за напрямками гри "Добрик 2015"
PPTX
інструкція 01.11.15
PPTX
Apresentação Completa Programa All Star Club oficial. 2016
PDF
Métricas em Mídias Sociais - MBA Gestão Estratégica de Mídias Sociais (aula 01)
PDF
Plano de negócio sci
PDF
Minerworld - Gran Presentación de Nuevos Negocios
PPTX
Портфоліо Глушко М.І.
PPT
некрасов «тройка»
PPTX
история написания мастера и маргариты
PPTX
мифология
PDF
Box Office Best Practices [Webinar]
PPTX
124 nova drama
PPTX
михаил булгаков Microsoft office power point
PDF
StratetgicRetailingRedesignGroupProject (1)
PDF
HR Solutions saksham universal
PPTX
франц кафка
PDF
Jig 2016 A Revolução Será Monitorada?
PDF
Social Recruiting - Google+ for Recruiting Update - 10 richtungsweisende Neue...
Third Year Design Briefs
Звіт про роботу за напрямками гри "Добрик 2015"
інструкція 01.11.15
Apresentação Completa Programa All Star Club oficial. 2016
Métricas em Mídias Sociais - MBA Gestão Estratégica de Mídias Sociais (aula 01)
Plano de negócio sci
Minerworld - Gran Presentación de Nuevos Negocios
Портфоліо Глушко М.І.
некрасов «тройка»
история написания мастера и маргариты
мифология
Box Office Best Practices [Webinar]
124 nova drama
михаил булгаков Microsoft office power point
StratetgicRetailingRedesignGroupProject (1)
HR Solutions saksham universal
франц кафка
Jig 2016 A Revolução Será Monitorada?
Social Recruiting - Google+ for Recruiting Update - 10 richtungsweisende Neue...
Ad

Similar to HV Interface Presentation (1) (20)

DOC
ELECTRICAL TECHNICIAN
DOC
ELECTRICAL TECHNICIAN
PPTX
EIT_Presentation
DOCX
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
PPTX
Permit menjalankan kerja untuk SME Training
PPTX
EIT_Presentation
DOC
Electrical Inspector CV
PPTX
Safety Campaign - RSP Final.pptx for construction industry
PDF
Sungrow commissioning meeting Parque Fotovoltaico
DOC
Commissioning Engineer
PPTX
Singapore Power
PPTX
A year with Larsen & Toubro
PDF
4 david schepers certification process safety relay modules for machinery app...
PPTX
TIme Sync & Remote Access of protection relays.pptx
DOCX
Sop 6.6 kv switchboard
PPT
R1_Project - QC Safety System
DOC
Khaled elhag cv
PDF
Satham Mohamed.A-CV..
DOC
Sr.Electrical Engineer
PDF
Commission resume
ELECTRICAL TECHNICIAN
ELECTRICAL TECHNICIAN
EIT_Presentation
Ohl transmission lines opgw instalation procedure for fiber optic cables rev.00
Permit menjalankan kerja untuk SME Training
EIT_Presentation
Electrical Inspector CV
Safety Campaign - RSP Final.pptx for construction industry
Sungrow commissioning meeting Parque Fotovoltaico
Commissioning Engineer
Singapore Power
A year with Larsen & Toubro
4 david schepers certification process safety relay modules for machinery app...
TIme Sync & Remote Access of protection relays.pptx
Sop 6.6 kv switchboard
R1_Project - QC Safety System
Khaled elhag cv
Satham Mohamed.A-CV..
Sr.Electrical Engineer
Commission resume

HV Interface Presentation (1)

  • 1. HV Substation Interface Activities: Safety/Operational Requirements Produced By: C Doyle
  • 2. Contents • Activity 1: Installation • Activity 2A: Cable termination HV & LV • Activity 2B: Unlicensed Commissioning • Activity 3: Back Energisation • Activity 4: Commissioning • Activity 5: Post COD
  • 3. HV INTERFACE ACTIVITY 1: INSTALLATION HV Substation Interface Activities
  • 4. HV Interface: Activity 1 Installation • Civil works (cable ducts) • Cable Support Install • Scaffolding • HV Cable Pull • LV Cable Pull • Earthing (assume PS Earth is Tested/Complete) • Install APDF Remote I/O Panel • NG Unlicensed Relays Installation in M1/M2
  • 5. HV Interface Activity 1: Installation Safety/Procedural Boundaries X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS, LWC may be issued • Point of isolation issued for work on LV systems/ System Connection Rules SAFETY: • APDF work is undertaken under APDF Local Safety Instructions/Safety Rules • Rules submitted to NG For Review • RAMS submitted to NG 3 weeks prior to work taking place for review by NG Operational: • APDF work under a point of isolation for any LV work utilising their own Safety Instructions APDF Working Party Requires: NG Persons NG Competent Persons (key Holder also) Approved scaffolders for NG Safety Rules Operational: • NG Local Instructions • NG Performs CPO Notes: • Area will be delineated with the EPC Contractor as PC under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise. • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • Note: If earths are not terminated insulated working must be carried out under NSI 5,6 &24, RAMS should be based on this (preferably not done until earths are connected for safety) Circuit equipment on Power station side Surge Arrestors Cable Protected Both Ends Module M1/M2 Cable Pulled Not Terminated CCT 1 & CCT 2 C&P Module Esbi Civil Contractor Required NG Persons NG Competent Persons (key Holder also) NG Working Party Requires: • To work under APDF Permit • Trained as person and work under APDF competent person
  • 6. Actions • APDF to confirm what qualifications/inductions NG Working Party Requires to install Protection Relays in M1/M2 and process for submitting RAMS • APDF to confirm list of personnel undergoing Person/Competent Person training from AP and DF and that a key holder will also be provided • APDF to confirm the qualifications of their contractors who will access the substation for cable pulling HV/LV/I&C, cable support install and terminations • APDF RAMs to be submitted to NG a minimum of 3 weeks prior to proposed work, this is to be coordinated through the TP106/153 meetings on site. ESBI remind APDF of site RAMS review period by OE prior to submission to NG. • A safety inaugural meeting will be required to take place 6 weeks prior to any works commencing, APDF to advise when this should be scheduled • APDF to review programme submitted under APDF/CPL/1187 and advise on current programme as changes should be coordinated through the TP meetings with NG
  • 7. HV INTERFACE ACTIVITY 2A: CABLE TERMINATION HV & LV HV Substation Interface Activities
  • 8. HV Interface: Activity 2A Cable Termination: HV & LV • Install GIS Sealing End (ABB Interface) • HV Cable Testing • Install HV Cable Termination • Earth Terminations (cable) • Scaffolding • LV Cable Testing and Terminations
  • 9. HV Interface Activity 2A: HV & LV Cable Terminations X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS, LWC may be issued • Point of isolation issued for work on LV systems/ System Connection Rules SAFETY: • APDF work is undertaken under APDF Local Safety Instructions/Safety Rules • Rules submitted to NG For Review • Trafo Compound locked and under NG Safety Rules Operational: • APDF work under a point of isolation for any LV work utilising their own Safety Instructions APDF Working Party Requires: NG Persons NG Competent Persons (key Holder also) Approved scaffolders for NG Safety Rules Operational: • NG Local Instructions Apply for Isolations • HVSCC Required to bring cable and sealing ends in remote compound (Trafo) under NG CPO • NG Performs CPO Notes: • Area will be delineated with the EPC Contractor as PC under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise. • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • Note: If earths are not terminated insulated working must be carried out under NSI rules, RAMS should be based on this (preferably not done until earths are connected for safety) Circuit equipment on Power station side Module M1/M2 CCT 1 & CCT 2 C&P Module No System Connection 3.5m Safety Distance
  • 10. HV INTERFACE ACTIVITY 2B: UNLICENSED COMMISSIONING PHASE 1 HV Substation Interface Activities
  • 11. HV Interface: Activity 2B Unlicensed Commissioning: (LV Cable terminations Complete, Prior to HV Cable) • Commissioning of signals between PP & SS (Phase 1)
  • 12. HV Interface Activity 2B: Unlicensed Relay Commissioning Phase 1 X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS, LWC may be issued SAFETY: • NG work in M1/M2 under APDF rules • Further coordination required in working group meetings Operational: • Discuss with APDF. How will this interface be managed (Phase 1) NG Working Party Requires: • To work under APDF Permit • Trained as person and work under APDF competent person Operational: • NG Local Instructions Apply for Isolations • NG Performs CPO • SRS requires discussion at TP153 (LV equipment) Notes: • SRS requires discussion at TP153 (LV equipment) • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • NG will work under APDF rules in Module M1/M2 Circuit equipment on Power station side Module M1/M2 CCT 1 & CCT 2 C&P Module No System Connection 3.5m Safety Distance
  • 13. Actions • NG Unlicensed to confirm power requirements for relays and APDF to ensure these are available for programmed dates • NG unlicensed to provide commissioning plan for Phase 1 & Phase 2 commissioning
  • 14. HV INTERFACE ACTIVITY 3A: BACK ENERGISATION CABLE SOAK HV Substation Interface Activities
  • 15. HV Interface: Activity 3 Back Energisation: Cable Soak • Switch in cable for 24hr soak test • HVSCC issued and Revert Back to busbar disconnects for further back energisation under NG CPS and APDF CPO
  • 16. HV Interface Activity 3: Back Energisation Cable Soak X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS a RISSP may be issued SAFETY: • APDF work is undertaken under APDF Local Safety Instructions/Safety Rules • Rules submitted to NG For Review • Trafo Compound locked and under NG Safety Rules Operational: • National Grid are CPO APDF Working Party Requires: NG Persons NG Competent Persons (key Holder also) Operational: • NG Local Instructions Apply for Isolations • HVSCC Required to bring cable and sealing ends in remote compound (Trafo) under NG CPO • NG Performs CPO Notes: • Area will be delineated with the EPC Contractor as PC under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise. • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • Immediately after cable soak the control boundary moves to HV disconnects under a HVSCC, NG relinquish CPO role and O&M undertake this role under their local instructions which have been approved by NG • NG retain the CPS role under contract to Asset Management • Partial Discharge monitoring/testing to be discussed at TP106 Circuit equipment on Power station side Module M1/M2 CCT 1 & CCT 2 C&P Module No System Connection 3.5m Safety Distance
  • 17. HV INTERFACE ACTIVITY 3: BACK ENERGISATION HV Substation Interface Activities
  • 18. HV Interface: Activity 3 Back Energisation: GSUT Energisation, LV GCB, 6.6kV (as per back energisation procedure) • Energise GSUT, IPB’s, HV Side of GCB, UT up to 6.6kV Incoming Breakers
  • 19. HV Interface Activity 3B: Back Energisation: GSUT Energisation, LV GCB, 6.6kV (as per back energisation procedure) X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION (O&M Operational CPO) POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS a RISSP may be issued (type of safety document to be discussed) SAFETY: • APDF work is undertaken under APDF Local Safety Instructions/Safety Rules • RISSP Issued and taken by O&M CPO, RISSP integrated into APDF safety rules Operational: • O&M are now CPO under their operational procedures/local instructions APDF Working Party in Substation Requires: NG Persons NG Competent Persons (key Holder also) APDF liaise with O&M CPO/Requesting Safety officer Operational: • HVSCC agreed with SRS defined as O&M CPO • Contact persons agreed in SRS and through compliance process between O&M CPO and NG Control Centre Notes: • Area will be delineated with the EPC Contractor as PC under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise. • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • NG retain the CPS role under contract to Asset Management • O&M are CPO Circuit equipment on Power station side Module M1/M2 CCT 1 & CCT 2 C&P Module O&M Personnel: NG Persons (to access substation) Competent Persons Authorised Persons Requesting Safety Officer (can be the CPO) but must be trained to level to receive a RISSP
  • 20. Control/Safety/Maintenance Ownership Boundaries X190 X196 X194 X193 CCGT Equipment Sub Fence NG Safety Rules /Maintenance NG Ownership NG Operational APDF Safety rules O&M Ownership O&M Operational
  • 21. HV Safety/Operational Interface Protocol Warwick Substation Power Station NG O&M APDF HV Control Person/ CPO CPOCPS Implementing Safety Coordinator/ SAP APDF HV Interface manager TP106/TP153/Working Group meetings Planned Operational Switching/ Outages Client Review Planned Outages Planned Operational Switching Emergency Switching Planned Switching Communications Switching Request/ RISSP Issue Emergency Switching Planned Switching
  • 22. Actions • O&M Safety Rules/HV Switching/RISSP Process (including third party involvement) to be finalised and submitted to NG for review ASAP • O&M to confirm timelines for training of Authorised Personnel for HV Control Persons • Switching should be remote i.e. DCS • APDF to include a HV Switching Interface protocol in safety rules to include RISSP process • CPL/O&M to confirm that HV Busbar Disconnects are to be switched by NG and not at DCS.
  • 23. HV INTERFACE ACTIVITY 4: COMMISSIONING HV Substation Interface Activities
  • 24. HV Interface: Activity 4 Commissioning • Commissioning as Per APDF Programme • Phase 2 Commissioning of Unlicensed Protection Relays (load) • Full Control & Protection Commissioning • Plant functional tests • Grid Compliance Tests • Performance Test • Reliability Run • Handover
  • 25. HV Interface Activity 4: Commissioning X190 X196 X194 X193 F19A Cable bushing Sub FenceSUBSTATION (O&M Operational CPO) POWERSTATION SAFETY: • NG Safety Rules Apply • NG Performs CPS • SAP (P.Monaghan, Brian Sleigh) • Implementation Safety Coordinator (P. Monaghan? TBC) • Following Review of RAMS a RISSP may be issued (type of safety document to be discussed) SAFETY: • APDF work is undertaken under APDF Local Safety Instructions/Safety Rules • RISSP Issued and taken by O&M CPO, RISSP integrated into APDF safety rules Operational: • O&M are now CPO under their operational procedures/local instructions APDF Working Party in Substation Requires: NG Persons NG Competent Persons (key Holder also) APDF liaise with O&M CPO/Requesting Safety officer Operational: • HVSCC agreed with SRS defined as O&M CPO • Contact persons agreed in SRS and through compliance process between O&M CPO and NG Control Centre Notes: • Area will be delineated with the EPC Contractor as PC under the CDM Regs. APDF can access through own gate but will require a key holder under NG rules. This should be agreed at CDM meeting and also discussed through TP153 meeting to finalise. • Programme of work to be managed through TP106 and specific working groups. APDF must submit detailed activity programme. • NG retain the CPS role under contract to Asset Management • O&M are CPO • O&M are working in APDF working parties for power station commissioning and are trained under APDF Safety Rules Circuit equipment on Power station side Module M1/M2 CCT 1 & CCT 2 C&P Module O&M Personnel: NG Persons (to access substation) Competent Persons Authorised Persons Requesting Safety Officer (can be the CPO) but must be trained to level to receive a RISSP
  • 26. HV Interface: Activity 5 Post COD • Normal Operation
  • 27. Control/Safety/Maintenance Ownership Boundaries X190 X196 X194 X193 CCGT Equipment Sub Fence NG Safety Rules /Maintenance NG Ownership NG Operational O&M Ownership O&M Operational O&M Safety Rules /Maintenance
  • 28. HV Safety/Operational Interface Protocol Warwick Substation Power Station NG O&M HV Control Person/ CPO CPOCPS Implementing Safety Coordinator/ SAP Planned Outages Planned Operational Switching Emergency Switching Planned Switching Communications/ TOGA Switching Request/ RISSP Issue