Increase your resource capacity without hiring ppt
Session: 9060
Increase resource capacity
without hiring
By: Chris Vandersluis
HMS Software
chris.vandersluis@hms.ca
Introduction
• Founder of HMS Software; publishers of
TimeControl, a project-based timesheet
system
• Over 28 years experience in project and timesheet
systems
• Partner with Primavera since 1997
• Author of the EPMGuidance.com blog
Introduction
• Teaches Advanced Project Management at McGill University
• Writing has appeared in:
• Fortune Magazine
• American Management Association’s Project Management
handbook
• PMI’s PMNetwork
• Microsoft’s TechNet
• Computing Canada, and PM Times magazines.
Introduction
1984 HMS Software founded. First project:
automating the project office at Philips
Information Systems and creating a
project timesheet
1994 HMS releases TimeControl 1.0
1995 TimeControl published with links to
Microsoft Project
1997 HMS becomes a Primavera Technology
Alliance Partner
1997 HMS releases TimeControl 3.0 as a
client/server product
1999 HMS releases first web timesheet
interface for TimeControl
2001 HMS releases TimeControl 4.0, a full
web-based version
2005 HMS becomes a Microsoft Gold
Certified Partner
2007 HMS releases TimeControl Industrial
4.7
2010 HMS becomes Oracle Gold Partner
2010 HMS releases TimeControl 6.0
2011 HMS releases TimeControl Mobile
2012 HMS releases TimeControlOnline –
Hosted TimeControl in the Cloud
Project Constraints
Scope
Solving capacity challenges
• Add capacity hiring/contracting
(In a challenging economy this is unacceptable)
• Reduce the amount of work
(When competition is tough, you must add work.
Reducing work is unacceptable)
• Do the work slower
(In a global economy, working slower is
unacceptable)
The Resource Challenge
No one has an abundance of resources
…nor should they
“Project Management is doing a defined
scope with insufficient resources”
– Ken Mattingly, NASA
Project Mgt is working
• In the last 30 years project management has
advanced as a discipline and it makes a
difference
• Projects are managed more effectively
• Staff are allocated more effectively
• The right projects are often prioritized more
effectively
So problem solved… yes?
• Unfortunately… no
• Resource Capacity Planning remains one of
the most significant organizational issues and
this is regardless of the status of the economy
• When the economy is challenged, staffing is
reduced
• When the economy is booming, skilled
resources are scarce
What organizations try
How do organizations try to solve this?
1. Automate
Purchase an EPM or PPM system in the
hopes that projects will be more effective
2. Implement EPM/PPM processes
Implementing EPM/PPM processes with or
without automation will hopefully improve
project efficiency
3. Push the staff to overtime/more work
The untapped resource
• Project management personnel tend to focus
on improving efficiency within their scope of
influence
• There is often a surprising level of effort being
expended on non-project activities
• How can the Project Management Office
harness some of this time?
Where does the time go?
Some common categories where time is spent
excessively include:
• Bureaucracy
• Maintenance
• Legacy system support
(Particularly in IT)
Ex1: Inter-office transport
Management decisions
1.“Starting immediately all project personnel will
be co-located to the maximum extent
possible”
2.“If many project team members must travel to
a meeting with one executive then that
executive will travel not the entire team”
Charge breakdown
example
Less inter-office travel
M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12
-$640,000
-$480,000
-$360,000
-$320,000
-$280,000
-$200,000
-$183,333
-$175,000
-$167,667
-$150,000
-$133,333
-$120,000
0
$160,000
$280,000
$320,000
$360,000
$440,000
$456,667
$465,000
$473,333
$490,000
$506,667
$520,000
Total savings: for 1 year: $4,471,667
Or the equivalent of hiring 156 people!
Ex2: Reduce bureaucracy
• In a 6000 person staff, 1/3 of the workers were
sub-contractors
• Approving timesheet invoices took 8 weeks and
included:
• Reconciling sub-contractor timesheet information with
internal timekeeping records which arrived in
numerous formats
• Adjusting sub-contractor invoices to match reconciled
timesheet information
• This took key project personnel, supervisors and
finance personnel
Management decisions
• Deploy a single timesheet (in this case
TimeControl) and have all workers use it
including both internal and external staff
• Approve time each week and give the sub-
contractor companies access to the timesheet
data of their own staff
Results of one timesheet
• Sub-contractor invoice approvals reduced to less
than 5 days
Company therefore negotiated an early payment
discount of 2% and saved over $2.4 million or the
equivalent of hiring over 60 people
• Company saved 1200 hours per week in more
efficient invoice and timesheet approvals or the
equivalent of hiring more than 30 additional people
Ex3: Excessive
Maintenance
• A US university did an assessment of its
portfolio of IT projects
• It determined that its current and projected
projects for the coming year were the
equivalent of approximately two years of
resource capacity
Overloaded project staff
UnleveledLeveled
Maintenance dominated
Maintenance
Projects
Admin
Maintenance details
Management Decisions
• Reduce supported databases to 3
• Outsource email for free to EDU
(over 15,000 email addresses)
• Reduce legacy applications
• Use Portfolio prioritization to gateway new projects
• Results: increase of project resource by over 50%!
Beforenew
capacity
Afternew
capacity
Ex4: Data-mine the timesheet
• Objective: Which projects had the least staff turnover
and what information in the timesheet could be
correlated
• Change: An increase in internal training resulted in
higher employee satisfaction lower staff turnover and
an increase in the productivity of staff who were more
experienced and did not need to spend time training
new staff.
• Result: An increase in over 10% of resource capacity
Other places to “create” time
• Portfolio Selection through stage gating to
work only on the best projects
• Cancelling bad projects
• Data mining timesheets for
non-productive bureaucracy e.g.:
• Reporting that serves on purpose
• Excessive meetings that are not effective
Cancelling bad projects
• Objective: What has projects end up in
management review?
• Discovery: Projects which would ultimately fail
were identified early and more latitude was
available to cancel them.
• Result: Staff were able to move onto more
successful projects and an increase in
resource capacity of over 10% was realized
Stage Gate Project Review
Project has exceeded
a threshold
Does the project still
meet business
criteria?
Pause project for
rework and
re-assessment
Cancel the project
Make project staff
available for other
projects
Creating a solution
• Key to finding time outside of the existing
project resource availability is to deploy a
single timesheet to be used for both project
and non-project work.
• The timesheet must be able to fulfill the needs
of multiple aspects of the organization…
Time and Attendance
Timesheet solutions
Timesheet system sends
attendance time and types of time
off such as vacation and sick
leave
HR Systems and
Payroll
Timesheets
Timesheet solutions
Time and Billing
Time is summarized by client and
billed with proper rate codes and
overtime when applicable
Finance and
Billing systems
Timesheets
Timesheet solutions
Project Statusing
Timesheet lists time per resource
on each task and updates the
project management system for
budget vs. actual analysis.
Project
Management
Timesheets
Timesheet solutions
Governance
Organizations are required to comply with
government and shareholder compliance rules
such as R&D tax credits, the DCAA, SOX, EEC
work rules and general auditability
Governance
Activity Costing
systems
Timesheets
Multi-purpose timesheet
HR Systems and
Payroll
Finance and
Billing systems
Project
Management
Governance
Activity Costing
systems
Timesheets
Multi-purpose
Timesheet
Timesheet elements
• Browser interface
• Financial controls for
payroll
• Links to the ERP
• Links to Project
Scheduling
• Flexible multi-level
resource definition
• Multi-browser/multi-
device
• Mobile interface
• Coding for tasks at both
the finance/organization
level and the project level
What do we need to deploy in a single timesheet?
Timesheet example
Source: www.timecontrol.com
Why one multi-purpose timesheet?
Oracle Projects Primavera
Multi-purpose
timesheet
Labor Actuals
for OP and
Finance
Timesheet
EBS/Financials/Payroll
Summary
Task data
Including
Dates,
ETC
Conclusions• There is often resource capacity that can be capitalized
on internally
• Start by using a single timesheet for both project and non-
project work
• Look for:
• Big slices of time then drill down for detail
• Excessive bureaucracy
• When you find changes to make, get support from senior
management to make them.
• Make timesheet data review an annual exercise, not
something done only once
Thank you!
For more information:
EPMGuidance Blog: www.epmguidance.com
Chris Vandersluis: chris.vandersluis@hms.ca
TimeControl: www.timecontrol.com

More Related Content

PPT
Управление ресурсами проекта: опыт Северной Америки. Making time. Creating R...
PPT
Spm chapter 8
PPT
Hyperion - IBANK
PPT
Enterprise Project Management Webinar (2010)
Управление ресурсами проекта: опыт Северной Америки. Making time. Creating R...
Spm chapter 8
Hyperion - IBANK
Enterprise Project Management Webinar (2010)

What's hot (20)

PDF
Galorath - IT Data Collection, Analysis and Benchmarking: From Processes and...
PPTX
Project Schedule Management - Sequence Activities - PMP Workgroup
PPTX
CSOHIMSS_Fall2016 - Premier Health ePMO Journey
PDF
The Agile Process Owner an ITSM Academy Webinar
PPTX
PPTX
Becoming Lean
PPTX
ITIL Transformation - 9 Traps to Avoid
PPT
Improving Performance Improvement (Market Requirements Document - MRD)
PPTX
PM685 - Shin
PPTX
Project Scheduling
PPTX
Challenges in deploying AX 2012: A recipe for success!
PPTX
Lean applied in Project Management
PDF
SUCCESS STORY: Improving the Purchasing Process for Supplies
PPTX
rules of formulating network planning model .
PDF
Effective software project planning and scheduling
PDF
Leveraging NetPoint & Excel for Template-Based Project Planning
PDF
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
PPT
Galorath - IT Data Collection, Analysis and Benchmarking: From Processes and...
Project Schedule Management - Sequence Activities - PMP Workgroup
CSOHIMSS_Fall2016 - Premier Health ePMO Journey
The Agile Process Owner an ITSM Academy Webinar
Becoming Lean
ITIL Transformation - 9 Traps to Avoid
Improving Performance Improvement (Market Requirements Document - MRD)
PM685 - Shin
Project Scheduling
Challenges in deploying AX 2012: A recipe for success!
Lean applied in Project Management
SUCCESS STORY: Improving the Purchasing Process for Supplies
rules of formulating network planning model .
Effective software project planning and scheduling
Leveraging NetPoint & Excel for Template-Based Project Planning
4.3.2013 Tool Demo - Traditional Development RTC Planning In Context Collabor...
Ad

Viewers also liked (12)

PPTX
Strategic Workforce Planning_25 July 2013
PPT
(CAPACITY PLANNIG)
PPTX
Capacity Management
PDF
Resource mgmt capacity to planning to reporting actuals - Oracle Primavera Co...
PDF
Ikea operational startegies
PDF
What Makes Great Infographics
PDF
Masters of SlideShare
PDF
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
PDF
You Suck At PowerPoint!
PDF
10 Ways to Win at SlideShare SEO & Presentation Optimization
PDF
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
PDF
How to Make Awesome SlideShares: Tips & Tricks
Strategic Workforce Planning_25 July 2013
(CAPACITY PLANNIG)
Capacity Management
Resource mgmt capacity to planning to reporting actuals - Oracle Primavera Co...
Ikea operational startegies
What Makes Great Infographics
Masters of SlideShare
STOP! VIEW THIS! 10-Step Checklist When Uploading to Slideshare
You Suck At PowerPoint!
10 Ways to Win at SlideShare SEO & Presentation Optimization
How To Get More From SlideShare - Super-Simple Tips For Content Marketing
How to Make Awesome SlideShares: Tips & Tricks
Ad

Similar to Increase your resource capacity without hiring ppt (20)

PDF
Successful Project Estimation: How to Get Your Weekends Back
PPTX
IHR Presentation
PDF
Deploying Resource Management with MS Project Online
PDF
Deploying Resource Management with MS Project Online_Projility
PPTX
Figures for solution
PPT
How PMOs Save Money
PDF
Benefits of EPM
PPTX
Achieving Business Value Through PPM and Resource Planning
PPTX
112012eddymoleoverview
PDF
5 Pillars of Project Success
PDF
People Planner Plus Brochure 3.0[1]
PDF
DELTEK Maconomy People planner
PDF
Resource scheduling & capacity planning for project online webinar 25 oct18
PDF
Time and Resource Management: Why Is It Crucial Today?
PDF
Toc in a nutshell
PDF
Ictc hr guide_module_i
PDF
The Business Case for Workforce Management Solutions - White Paper
PDF
Google-ize My CRM
PPTX
Manage up Workload Planning Application
PPTX
Develop a Resource Management Strategy for the New Reality
Successful Project Estimation: How to Get Your Weekends Back
IHR Presentation
Deploying Resource Management with MS Project Online
Deploying Resource Management with MS Project Online_Projility
Figures for solution
How PMOs Save Money
Benefits of EPM
Achieving Business Value Through PPM and Resource Planning
112012eddymoleoverview
5 Pillars of Project Success
People Planner Plus Brochure 3.0[1]
DELTEK Maconomy People planner
Resource scheduling & capacity planning for project online webinar 25 oct18
Time and Resource Management: Why Is It Crucial Today?
Toc in a nutshell
Ictc hr guide_module_i
The Business Case for Workforce Management Solutions - White Paper
Google-ize My CRM
Manage up Workload Planning Application
Develop a Resource Management Strategy for the New Reality

More from p6academy (20)

PDF
Oracle OpenWorld 2015
PDF
Plan and Execute the Right Projects— Easily and Affordably
PDF
What's New In Primavera P6 EPPM 17.1
PDF
Oracle Primavera Unifier What's New in Release 16.2
PDF
Oracle What's New In Primavera P6 16.2
PDF
What's New in Primavera Prime 16.1
PDF
What's New in Primavera Gateway 16.1
PDF
What's New In Primavera Analytics 16.1
PDF
What's New in Unifier 16.1
PDF
20160405 How to Install Primavera P6 16.1 Professional desktop
PDF
Oracle Primavera P6 16.1 Announced
PDF
Oracle Primavera Unifier 16.1
PDF
P6 Release 8 Application Considerations Overview
PDF
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
PDF
P6 Release 8 Installation Orientation
PDF
Oracle Primavera P6 R8 Release Value Proposition
PDF
Oracle Primavera P6 v7 Release Value Proposition
PDF
Oracle Primavera P6 Release Content Document (RCD)
PDF
Oracle Support Accreditation – Level 1 Study Guide
PDF
Oracle Primavera Support Accreditation Study Guide
Oracle OpenWorld 2015
Plan and Execute the Right Projects— Easily and Affordably
What's New In Primavera P6 EPPM 17.1
Oracle Primavera Unifier What's New in Release 16.2
Oracle What's New In Primavera P6 16.2
What's New in Primavera Prime 16.1
What's New in Primavera Gateway 16.1
What's New In Primavera Analytics 16.1
What's New in Unifier 16.1
20160405 How to Install Primavera P6 16.1 Professional desktop
Oracle Primavera P6 16.1 Announced
Oracle Primavera Unifier 16.1
P6 Release 8 Application Considerations Overview
Administering Users, Access and Views in P6 EPPM (Web) Release 8 and later
P6 Release 8 Installation Orientation
Oracle Primavera P6 R8 Release Value Proposition
Oracle Primavera P6 v7 Release Value Proposition
Oracle Primavera P6 Release Content Document (RCD)
Oracle Support Accreditation – Level 1 Study Guide
Oracle Primavera Support Accreditation Study Guide

Increase your resource capacity without hiring ppt

  • 2. Session: 9060 Increase resource capacity without hiring By: Chris Vandersluis HMS Software chris.vandersluis@hms.ca
  • 3. Introduction • Founder of HMS Software; publishers of TimeControl, a project-based timesheet system • Over 28 years experience in project and timesheet systems • Partner with Primavera since 1997 • Author of the EPMGuidance.com blog
  • 4. Introduction • Teaches Advanced Project Management at McGill University • Writing has appeared in: • Fortune Magazine • American Management Association’s Project Management handbook • PMI’s PMNetwork • Microsoft’s TechNet • Computing Canada, and PM Times magazines.
  • 5. Introduction 1984 HMS Software founded. First project: automating the project office at Philips Information Systems and creating a project timesheet 1994 HMS releases TimeControl 1.0 1995 TimeControl published with links to Microsoft Project 1997 HMS becomes a Primavera Technology Alliance Partner 1997 HMS releases TimeControl 3.0 as a client/server product 1999 HMS releases first web timesheet interface for TimeControl 2001 HMS releases TimeControl 4.0, a full web-based version 2005 HMS becomes a Microsoft Gold Certified Partner 2007 HMS releases TimeControl Industrial 4.7 2010 HMS becomes Oracle Gold Partner 2010 HMS releases TimeControl 6.0 2011 HMS releases TimeControl Mobile 2012 HMS releases TimeControlOnline – Hosted TimeControl in the Cloud
  • 7. Solving capacity challenges • Add capacity hiring/contracting (In a challenging economy this is unacceptable) • Reduce the amount of work (When competition is tough, you must add work. Reducing work is unacceptable) • Do the work slower (In a global economy, working slower is unacceptable)
  • 8. The Resource Challenge No one has an abundance of resources …nor should they “Project Management is doing a defined scope with insufficient resources” – Ken Mattingly, NASA
  • 9. Project Mgt is working • In the last 30 years project management has advanced as a discipline and it makes a difference • Projects are managed more effectively • Staff are allocated more effectively • The right projects are often prioritized more effectively
  • 10. So problem solved… yes? • Unfortunately… no • Resource Capacity Planning remains one of the most significant organizational issues and this is regardless of the status of the economy • When the economy is challenged, staffing is reduced • When the economy is booming, skilled resources are scarce
  • 11. What organizations try How do organizations try to solve this? 1. Automate Purchase an EPM or PPM system in the hopes that projects will be more effective 2. Implement EPM/PPM processes Implementing EPM/PPM processes with or without automation will hopefully improve project efficiency 3. Push the staff to overtime/more work
  • 12. The untapped resource • Project management personnel tend to focus on improving efficiency within their scope of influence • There is often a surprising level of effort being expended on non-project activities • How can the Project Management Office harness some of this time?
  • 13. Where does the time go? Some common categories where time is spent excessively include: • Bureaucracy • Maintenance • Legacy system support (Particularly in IT)
  • 15. Management decisions 1.“Starting immediately all project personnel will be co-located to the maximum extent possible” 2.“If many project team members must travel to a meeting with one executive then that executive will travel not the entire team”
  • 17. Less inter-office travel M1 M2 M3 M4 M5 M6 M7 M8 M9 M10 M11 M12 -$640,000 -$480,000 -$360,000 -$320,000 -$280,000 -$200,000 -$183,333 -$175,000 -$167,667 -$150,000 -$133,333 -$120,000 0 $160,000 $280,000 $320,000 $360,000 $440,000 $456,667 $465,000 $473,333 $490,000 $506,667 $520,000 Total savings: for 1 year: $4,471,667 Or the equivalent of hiring 156 people!
  • 18. Ex2: Reduce bureaucracy • In a 6000 person staff, 1/3 of the workers were sub-contractors • Approving timesheet invoices took 8 weeks and included: • Reconciling sub-contractor timesheet information with internal timekeeping records which arrived in numerous formats • Adjusting sub-contractor invoices to match reconciled timesheet information • This took key project personnel, supervisors and finance personnel
  • 19. Management decisions • Deploy a single timesheet (in this case TimeControl) and have all workers use it including both internal and external staff • Approve time each week and give the sub- contractor companies access to the timesheet data of their own staff
  • 20. Results of one timesheet • Sub-contractor invoice approvals reduced to less than 5 days Company therefore negotiated an early payment discount of 2% and saved over $2.4 million or the equivalent of hiring over 60 people • Company saved 1200 hours per week in more efficient invoice and timesheet approvals or the equivalent of hiring more than 30 additional people
  • 21. Ex3: Excessive Maintenance • A US university did an assessment of its portfolio of IT projects • It determined that its current and projected projects for the coming year were the equivalent of approximately two years of resource capacity
  • 26. Management Decisions • Reduce supported databases to 3 • Outsource email for free to EDU (over 15,000 email addresses) • Reduce legacy applications • Use Portfolio prioritization to gateway new projects • Results: increase of project resource by over 50%!
  • 28. Ex4: Data-mine the timesheet • Objective: Which projects had the least staff turnover and what information in the timesheet could be correlated • Change: An increase in internal training resulted in higher employee satisfaction lower staff turnover and an increase in the productivity of staff who were more experienced and did not need to spend time training new staff. • Result: An increase in over 10% of resource capacity
  • 29. Other places to “create” time • Portfolio Selection through stage gating to work only on the best projects • Cancelling bad projects • Data mining timesheets for non-productive bureaucracy e.g.: • Reporting that serves on purpose • Excessive meetings that are not effective
  • 30. Cancelling bad projects • Objective: What has projects end up in management review? • Discovery: Projects which would ultimately fail were identified early and more latitude was available to cancel them. • Result: Staff were able to move onto more successful projects and an increase in resource capacity of over 10% was realized
  • 31. Stage Gate Project Review Project has exceeded a threshold Does the project still meet business criteria? Pause project for rework and re-assessment Cancel the project Make project staff available for other projects
  • 32. Creating a solution • Key to finding time outside of the existing project resource availability is to deploy a single timesheet to be used for both project and non-project work. • The timesheet must be able to fulfill the needs of multiple aspects of the organization…
  • 33. Time and Attendance Timesheet solutions Timesheet system sends attendance time and types of time off such as vacation and sick leave HR Systems and Payroll Timesheets
  • 34. Timesheet solutions Time and Billing Time is summarized by client and billed with proper rate codes and overtime when applicable Finance and Billing systems Timesheets
  • 35. Timesheet solutions Project Statusing Timesheet lists time per resource on each task and updates the project management system for budget vs. actual analysis. Project Management Timesheets
  • 36. Timesheet solutions Governance Organizations are required to comply with government and shareholder compliance rules such as R&D tax credits, the DCAA, SOX, EEC work rules and general auditability Governance Activity Costing systems Timesheets
  • 37. Multi-purpose timesheet HR Systems and Payroll Finance and Billing systems Project Management Governance Activity Costing systems Timesheets Multi-purpose Timesheet
  • 38. Timesheet elements • Browser interface • Financial controls for payroll • Links to the ERP • Links to Project Scheduling • Flexible multi-level resource definition • Multi-browser/multi- device • Mobile interface • Coding for tasks at both the finance/organization level and the project level What do we need to deploy in a single timesheet?
  • 40. Why one multi-purpose timesheet? Oracle Projects Primavera Multi-purpose timesheet Labor Actuals for OP and Finance Timesheet EBS/Financials/Payroll Summary Task data Including Dates, ETC
  • 41. Conclusions• There is often resource capacity that can be capitalized on internally • Start by using a single timesheet for both project and non- project work • Look for: • Big slices of time then drill down for detail • Excessive bureaucracy • When you find changes to make, get support from senior management to make them. • Make timesheet data review an annual exercise, not something done only once
  • 42. Thank you! For more information: EPMGuidance Blog: www.epmguidance.com Chris Vandersluis: chris.vandersluis@hms.ca TimeControl: www.timecontrol.com