SOLAR Power Plant 
   pV Module
(Renewable source of  Energy)
With  its  abundance  of  sunlight,  India  has  tremendous 
potential to emerge as one of the leaders in solar power 
generation.  According  to  the  Government  of  India’s 
policy for the solar sector – Jawaharlal Nehru National 
Solar Mission (JNNSM) – a  target  of  20  GW  of  solar 
installations by 2022 has been set. 
Global Scenario
Solar  Energy  demand  globally  has  been  growing  at 
about 30% per annum over the past 15 years. 

In  comparison,  the  hydrocarbon  demand  growth  rate  is    
0‐2% per annum. This high growth rate in solar  energy  is 
due  to  many  reasons  – increasing  cost  of  petroleum 
products  and  the  parallel  decreasing  cost  of  producing 
power  from  solar,  and  a  concern  world  over  on  the 
harmful effects of using fossil fuels 
Solar Energy in India
India  is  one  of  the  few  countries  in  the  world  that 
has  a  dedicated  ministry  for  New  and  Renewable 
energy 

In  India, the  high  GDP  growth  rate  has  created  a  huge 
demand  for  energy,  but  the  supply  is  unable  to  match 
the demand. The total installed capacity of power as of 
January  2012  is  187  GW.  The  per  capita  total 
consumption  is  778  kWh.  The  estimated  shortage  of 
power in India is about 20 GW. 
Plant Commissioned in India 
                             Name of Plant                     DC Peak Power (MW)               Notes
Mithapur Solar Power Plant ‐ Mithapur, Gujarat (Tata Power)            25           Commissioned February 2012
WAA SOLAR POWER PLANT ‐ Surendranagar, Gujarat                        10.22         Commissioned January 2012
Reliance Power Pokaran Solar PV Plant, Rajasthan                       40           Commissioning in March 2012
Adani Bitta Solar Plant, Gujarat                                       40           Completed in January 2012
Mahindra Solar Plant, Jodhpur, Rajasthan                                5           Completed in January 2012
Sivaganga Photovoltaic Plant                                            5           Completed December 2010
Kolar Photovoltaic Plant                                                3           Completed May 2010
Itnal Photovoltaic Plant, Belgaum                                       3           Completed April 2010
Azure Power ‐ Photovoltaic Plant                                        2           Completed 2009 
Chesdin Power ‐ Biomass and Solar Photovoltaic Plants                  4.1          Completes December 2011
Citra and Sepset Power Plants ‐ Solar Photovoltaic Plants                4          Commissioned October 2011
Jamuria Photovoltaic Plant                                               2          Completed 2009 
NDPC Photovoltaic Plant                                                  1          Completed 2010 
Thyagaraj Stadium Plant‐Delhi                                            1          Completed April, 2010
Gandhinagar Solar Plant                                                  1          Completed January 2011
Tata ‐ Mulshi, Maharashtra                                               3          Commissioned April 2011
Azure Power ‐ Sabarkantha, Gujarat (Khadoda village )                  10           Commissioned June 2011. 
Moser Baer ‐ Patan, Gujarat                                            30           Commissioned July 2011
B&G Solar Pvt Ltd ‐ Mayiladuthurai, Tamil Nadu                           1          Commissioned June 2011
REHPL ‐ Sadeipali, (Bolangir) Orissa                                     1          Commissioned July 2011
Tata ‐ Patapur, Orissa                                                   1          Commissioned August 2011
Tata ‐ Osmanabad, Maharastra                                             1          Commissioned 1st Aug 2011
Amruth Solar Power Plant ‐ Kadiri, Andhra Pradesh                        1          Commissioned March 2012
Abengoa ‐ Gwal Pahari, Haryana                                           3          Commissioned September 2011
Chandraleela Power Energy ‐ Narnaul, Haryana                           0.8          Commissioned December 2011
Green Infra Solar Energy Limited ‐ Rajkot, Gujarat                      10          Commissioned November 2011
                                 Total                               182.1
Why In India
 India  is  in  the  sunny  regions  of  the  world  with  most 
  parts of the country receiving 4‐7 kwh (kilowatt‐hour) 
  of  solar  radiation  per  square  meter  per  day,  250‐300 
  sunny  days  in  a  year.  Even  though  Solar  energy 
  constitutes a miniscule part in India’s installed power 
  generation  capacity  (with  grid  connected  solar  PV 
  generation at a mere 6 MW as of March 2010),  in  the 
  medium and long run, it is expected that solar energy, 
  especially solar PV will form a vital component of the 
  country's energy mix. 
India solar power_plant_vpc
Solar Resource Map of India
Different suppliers of Module
   Manufacturer       Country          Model Number   Watts (p)    Life in years/Guarantee
                                                                             given

Bosch               Germany     M 240 3 BB                   240             10 years-90%,
                                                                              25 years-80%
Canadian solar      Canada      CS5A-170                     170                   25 years
Co energy           US          Power Plus 215 P             215             12 years-92%,
                                                                               25years-80%
Del Solar           Taiwan      D6P_E                        120             10 years-90%,
                                                                              25 years-80%
Evergreen solar     US          ES-A series                  200                   25 years
First solar         US          FS Series                     70             10 years-90%,
Mitsubishi          Japan       TD/TE series                 190

JA solar holdings   China       JAS                          165             10 years-90%,
                                                                              25 years-80%
Q cells             Germany     SL 1                          70                   25 years
PLG Solar           India                                                    10 years-90%,
                                                                              25 years-80%
Moser Baer          India                                                    10 years-90%,
                                                                              25 years-80%
Tata BP Solar       India                                                    10 years-90%,
                                                                              25 years-80%
Incentives from Government
Jawaharlal Nehru National Solar 
            Mission
The Jawaharlal Nehru National Solar Mission (also known as the National 
Solar  Mission)  is  a  major  initiative  of  the Government  of  India and  State 
Governments  to  promote  ecologically  sustainable  growth  while  addressing 
India’s energy security challenges. It will also constitute a major contribution 
by India to the global effort to meet the challenges of climate change. Named 
for Jawaharlal Nehru, the Mission is one of the several initiatives that are part 
of  National  Action  Plan  on  Climate  Change. The  program  was  officially 
inaugurated by Prime Minister of India, Manmohan Singh.
Scheme on financing of Off‐Grid and 
    Decentralised Solar Applications
Government  of  India,  Ministry    of  New  and  Renewable  Energy 
(MNRE) has  formulated a scheme on financing of Off‐Grid and 
Decentralised Solar  (Photovoltaic  and Thermal) applications as
part  of  the  Jawaharlal  Nehru  National  Solar  Mission  (JNNSM).  
Under  the  scheme,  banks  may  extend  subsidised  loans  to 
entrepreneurs at interest rates not exceeding five per  cent 
where refinance of two per cent from Government of India 
is available. 
Excise Duty Exemption on Transmission 
              Equipments
Exemption  of  Excise  Duty  on  procurement  of 
Transmission  Equipments  for  initial  setup  of  Solar 
Power  Plant.  The  exemption  would  be  available  on 
transmission  equipments  wherever  the  contractual 
obligation       for      installing       transmission 
lines/equipments up to the point of delivery is c0st on 
the solar power developer. 
Subsidy in installation of Solar 
           Power plant
The  Ministry  of  New  and  Renewable  Energy  (MNRE) 
provides 70 percent subsidy on the installation cost of 
a  solar  photovoltaic  power  plant  in  North‐East  states 
and  30  percentage  subsidy  on  other  regions.  The 
detailed  outlay  of  the  National  Solar  Mission 
highlights  various  targets  set  by  the  government  to 
increase solar energy in the country's energy portfolio.
Major other incentives
In  the  budget  for  2010/11,  the  government  has  announced  an 
allocation  of US  $  220  million  towards  the Jawaharlal  Nehru 
National Solar Mission. 
They  encouraged  private  solar  companies  by  reducing  customs 
duty  on  solar  panels  by  5%  and  exempting  excise  duty on  solar 
photovoltaic panels. 
The  budget  also  proposed  a  coal  tax  of US$1  per  metric  ton on 
domestic and imported coal used for power generation.
The  government  has  initiated  a  Renewable  Energy  Certificate 
(REC) scheme,  which  is  designed  to  drive  investment  in  low‐
carbon energy projects.
Opportunities and Challenges
Land is a scarce resource in India and per capita land availability is low. Dedication 

of  land  area  for  exclusive  installation  of  solar  arrays  might  have  to  compete  with 

other  necessities  that  require  land.  The  amount  of  land  required for  utility‐scale 

solar  power  plants—currently  approximately  1 km2 for  every  20–60 megawatts 

(MW) generated could  pose  a  strain  on  India's  available  land  resource.  The 

architecture  more  suitable  for  most  of  India  would  be  a  highly‐distributed  set  of 

individual  rooftop  power  generation  systems,  all  connected  via  a local 

grid. However,  erecting  such  an  infrastructure,  which  does  not  enjoy  the 

economies  of  scale  possible  in  mass,  utility‐scale,  solar  panel  deployment,  needs 

the market price of solar technology deployment to substantially decline, so that it 

attracts the individual and average family size household consumer. That might be 

possible  in  the  future,  because  PV  is  projected  to  continue  its  current  cost 

reductions for the next decades and be able to compete with fossil fuel.
Solar Power Plant in Gujarat
Incentives from State Government
 Government of Gujarat declared comprehensive Solar 
  Policy 2009, wherein Govt will purchase the power at 
  the following minimum rates.
                    for  first 12 years        for  next 12  years
                               from date of commissioning 


Solar  PV         Rs. 12/‐ kWh               Rs. 3/‐ kWh 
Solar Thermal     Rs. 9/‐ kWh                Rs. 3/‐ kWh 
Transmission charges & transmission 
               losses
 At  66kV  :  Transmission  charges  and  transmission 
  losses applicable to normal Open Access Consumer.
 Below  66  kV  :  Transmission  charges,  applicable  to 
  normal  open  access  consumer  and  transmission  and 
  wheeling  losses  @  10%  of  the  energy  fed  to  the  grid, 
  for Solar power Plant of capacity more than 5MW.
 For  Solar  power  Plants  of  capacity  less  than  5  MW, 
  Transmission  charges,  applicable  to  normal  open 
  access  consumer    and  transmission  and  wheeling 
  losses @ 7% of the energy fed to the grid.
India solar power_plant_vpc
Policy related to Land Acquisition for 
              Solar Plant
 At  66kV  :  Transmission  charges  and  transmission 
  losses applicable to normal Open Access Consumer.
 Below  66  kV  :  Transmission  charges,  applicable  to 
  normal  open  access  consumer  and  transmission  and 
  wheeling  losses  @  10%  of  the  energy  fed  to  the  grid, 
  for Solar power Plant of capacity more than 5MW.
 For  Solar  power  Plants  of  capacity  less  than  5  MW, 
  Transmission  charges,  applicable  to  normal  open 
  access  consumer    and  transmission  and  wheeling 
  losses @ 7% of the energy fed to the grid.
Govt.’s Initiative
    The Government of Gujarat is promoting Solar Power Parks in the Sate. 

    Rolled Out  Special Policy in 2009. 

    Already few Plants are operational in the State. 
    The  development  of  solar  parks  will  streamline  the  project  development 
    timeline  by  letting  government  agencies  undertake  land  acquisition  and 
    necessary  permits,  and  provide  dedicated  common  infrastructure  for  setting 
    up solar power generation plants largely in the private sector. 

    The  State  Government  is  taking  initiative  in  providing  the  common 
     infrastructure/ facilities like site preparation and leveling, power evacuation, 
     availability  of  water,  access  roads,  security  and  services.  In  parallel  with  the 
     central government's initiative.
.
Contd.
 The  Gujarat  Electricity  Regulatory  Commission  has  announced 
 feed‐in‐tariff  to  mainstream  solar  power  generation  which  will 
 be applied for solar power generation plants in the solar park. 

 Gujarat  Power  Corporation  Limited  is  the  responsible  agency 
 for  developing  the  solar  park  of  500  megawatts  and  will  lease 
 the lands to the project developers to generate solar power. 

 Gujarat  Energy  Transmission  Corporation  Limited  will  develop
 the transmission evacuation from the identified interconnection 
 points with the solar developer. This project is being supported, 
 in part, by the Asian Development Bank
Exclusive mandate for Land in 
           Gujarat
Land area         : About 1200 acre (485 hec.)

Location          : 60 km from Ahmedabad (Capital of Gujarat)
                   20 km from Sanand (Plant of Tata Nano Car).

Expected Price    : $ 12,000/‐ per acre

Primary Use       : Solar Power Plant

Secondary Use     : Storage/ Warehousing 
Location : INDIA
Location : Gujarat
Location : Bagodra
Location :     Bagodra to proposed site
Location  : Proposed site
Expected Production 
       1200 acre @ 10 MW /100 acre X 0.80
                           = 96 MW




Assuming efficiency 80% 
Cost of the Project ($ m)
 Land Cost :                                    1.4
 Cost of Approvals/Coversion/Devlopment         0.28
  (20% of land cost)
 PV Power Panels @ 4m                         480.00

• Thus total initial investment for 120 Mw :   48168
•                                      Say     500.00
• Less Subsidy 30%                             150.00
• Net Investment                               350.00
Expected revenue
 Expected Revenue from the Selling of Electricity  @  
  Rs. 12/‐ per kWh for first 12 years:
  = 2,102,400,000/‐ or USD $ 42 mn/ year 




 Assuming the plant will for 5 hours a day with efficiency of 80%
Return of Investment
 Payback period of 8 years includes land also

 With that other benefits like Carbon Credits and 

 other subsidies, moreover appreciation in the land 

 value. 
Secondary benefits
 Can be used as Storage purpose if constructed as Roof 
  top Solar power plant,  to store the items which is not 
  effected by UV rays and other harmful rays.
India solar power_plant_vpc

More Related Content

PDF
Solar PV Sector in India: Challenges & Way Ahead
PPTX
Introduction to Off Grid Solar Power system
PPT
Solar off grid
PPT
Solar Photovoltaic Power Plant
PDF
Concentrated solar power in India - an evaluation
PPT
Nuclearbattery
PPTX
Solar to energy presentation geofrey yator
PPT
IETE Institute Solar PPT
Solar PV Sector in India: Challenges & Way Ahead
Introduction to Off Grid Solar Power system
Solar off grid
Solar Photovoltaic Power Plant
Concentrated solar power in India - an evaluation
Nuclearbattery
Solar to energy presentation geofrey yator
IETE Institute Solar PPT

What's hot (20)

PPTX
photovoltaics cell pv cell solar cell
PPTX
Solar rooftop presentation
PPT
Solar energy
PPTX
Solar street light
PPTX
Solar energy(Renewable source)
PPTX
PDF
Photovoltaic Training - Session 4 - Plant Maintenance
PPTX
Solar power plants for generation of electricity
PDF
BESS - Battery Energy Storage System.pdf
PDF
Solar PV-D.G. Hybrid Plant
PPT
Solar power system
PPTX
On Grid Solar System to Create your own Electricity
PPT
Photovoltaic Systems
PDF
Rooftop Solar Systems
PDF
Solar Policy in India (Article)
PPTX
Solar on grid application ppt
PPTX
Solar photo voltaics
PPTX
Supercapacitors
ODP
Pump storage Hydroelectricity
PDF
Floating Solar
photovoltaics cell pv cell solar cell
Solar rooftop presentation
Solar energy
Solar street light
Solar energy(Renewable source)
Photovoltaic Training - Session 4 - Plant Maintenance
Solar power plants for generation of electricity
BESS - Battery Energy Storage System.pdf
Solar PV-D.G. Hybrid Plant
Solar power system
On Grid Solar System to Create your own Electricity
Photovoltaic Systems
Rooftop Solar Systems
Solar Policy in India (Article)
Solar on grid application ppt
Solar photo voltaics
Supercapacitors
Pump storage Hydroelectricity
Floating Solar
Ad

Viewers also liked (20)

PPTX
solar power plant
PPTX
Solarpowerplant
PPTX
Solar power.ppt
PPTX
1. Solar Power Plant Technologies
PPT
Solar energy ppt
PPT
Solar energy power point presentation
PPTX
Solar plant ppt by ritesh kumawat
PPTX
Solar Energy
PPT
Pusad solar power plant presentation (rev 7)
PPTX
Project on Solar Energy
PPT
Solar Energy Presentation
PPTX
Solar Power Generation
PPTX
solar power generation
PPTX
Solar power plant
PPT
Solar energy
PPTX
Project Proposal on 10 MW Solar PV Power Plant
PPSX
Advance Electrical system Design and solar power plant design courses
DOCX
Financial Feasibility of Solar Power Plant in India
PPT
Solar photovoltaic systems
PPTX
Solar panel Technology ppt
solar power plant
Solarpowerplant
Solar power.ppt
1. Solar Power Plant Technologies
Solar energy ppt
Solar energy power point presentation
Solar plant ppt by ritesh kumawat
Solar Energy
Pusad solar power plant presentation (rev 7)
Project on Solar Energy
Solar Energy Presentation
Solar Power Generation
solar power generation
Solar power plant
Solar energy
Project Proposal on 10 MW Solar PV Power Plant
Advance Electrical system Design and solar power plant design courses
Financial Feasibility of Solar Power Plant in India
Solar photovoltaic systems
Solar panel Technology ppt
Ad

Similar to India solar power_plant_vpc (20)

PPT
Solar Power Technology in India by S Kumar
PPTX
installation of grid solar panel of electrical department
PPTX
Welcome to the presentation
PPT
A n srivastava
PDF
IRJET-A Standalone Solar System
PPTX
Solar System
PDF
A CASE STUDY ON PLANNING OF REWA ULTRA MEGA SOLAR POWER PROJECT
PDF
Report June 22.pdf
PPTX
Sanjunit
PDF
Solar allotment webnote
PDF
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
PDF
Performance report of solar projects under NSM
PPTX
Solar_companies_of_india_Copy.pptx
PPTX
217332 renewable energy
PDF
Market Research India - Solar Energy Market in India 2009
PDF
PPTX
History of Solar Energy
DOCX
Report ntpc
PDF
Rbsa Research Report rise of solar power in India
PDF
Indian Solar Project Jan2010
Solar Power Technology in India by S Kumar
installation of grid solar panel of electrical department
Welcome to the presentation
A n srivastava
IRJET-A Standalone Solar System
Solar System
A CASE STUDY ON PLANNING OF REWA ULTRA MEGA SOLAR POWER PROJECT
Report June 22.pdf
Sanjunit
Solar allotment webnote
Solar Energy Corporation of India (SECI) Subsidy for Rooftop Solar Projects
Performance report of solar projects under NSM
Solar_companies_of_india_Copy.pptx
217332 renewable energy
Market Research India - Solar Energy Market in India 2009
History of Solar Energy
Report ntpc
Rbsa Research Report rise of solar power in India
Indian Solar Project Jan2010

Recently uploaded (20)

PDF
Consumable AI The What, Why & How for Small Teams.pdf
PDF
Zenith AI: Advanced Artificial Intelligence
PDF
A contest of sentiment analysis: k-nearest neighbor versus neural network
PPTX
Configure Apache Mutual Authentication
PDF
Enhancing plagiarism detection using data pre-processing and machine learning...
PPTX
Final SEM Unit 1 for mit wpu at pune .pptx
PDF
Architecture types and enterprise applications.pdf
PDF
Improvisation in detection of pomegranate leaf disease using transfer learni...
PDF
Developing a website for English-speaking practice to English as a foreign la...
PDF
CloudStack 4.21: First Look Webinar slides
PPTX
Microsoft Excel 365/2024 Beginner's training
PDF
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
PPTX
Benefits of Physical activity for teenagers.pptx
PDF
OpenACC and Open Hackathons Monthly Highlights July 2025
PDF
Flame analysis and combustion estimation using large language and vision assi...
PDF
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
PPTX
Training Program for knowledge in solar cell and solar industry
PDF
Getting started with AI Agents and Multi-Agent Systems
PPTX
The various Industrial Revolutions .pptx
PDF
Credit Without Borders: AI and Financial Inclusion in Bangladesh
Consumable AI The What, Why & How for Small Teams.pdf
Zenith AI: Advanced Artificial Intelligence
A contest of sentiment analysis: k-nearest neighbor versus neural network
Configure Apache Mutual Authentication
Enhancing plagiarism detection using data pre-processing and machine learning...
Final SEM Unit 1 for mit wpu at pune .pptx
Architecture types and enterprise applications.pdf
Improvisation in detection of pomegranate leaf disease using transfer learni...
Developing a website for English-speaking practice to English as a foreign la...
CloudStack 4.21: First Look Webinar slides
Microsoft Excel 365/2024 Beginner's training
How ambidextrous entrepreneurial leaders react to the artificial intelligence...
Benefits of Physical activity for teenagers.pptx
OpenACC and Open Hackathons Monthly Highlights July 2025
Flame analysis and combustion estimation using large language and vision assi...
“A New Era of 3D Sensing: Transforming Industries and Creating Opportunities,...
Training Program for knowledge in solar cell and solar industry
Getting started with AI Agents and Multi-Agent Systems
The various Industrial Revolutions .pptx
Credit Without Borders: AI and Financial Inclusion in Bangladesh

India solar power_plant_vpc

  • 1. SOLAR Power Plant  pV Module (Renewable source of  Energy)
  • 2. With  its  abundance  of  sunlight,  India  has  tremendous  potential to emerge as one of the leaders in solar power  generation.  According  to  the  Government  of  India’s  policy for the solar sector – Jawaharlal Nehru National  Solar Mission (JNNSM) – a  target  of  20  GW  of  solar  installations by 2022 has been set. 
  • 3. Global Scenario Solar  Energy  demand  globally  has  been  growing  at  about 30% per annum over the past 15 years.  In  comparison,  the  hydrocarbon  demand  growth  rate  is     0‐2% per annum. This high growth rate in solar  energy  is  due  to  many  reasons  – increasing  cost  of  petroleum  products  and  the  parallel  decreasing  cost  of  producing  power  from  solar,  and  a  concern  world  over  on  the  harmful effects of using fossil fuels 
  • 4. Solar Energy in India India  is  one  of  the  few  countries  in  the  world  that  has  a  dedicated  ministry  for  New  and  Renewable  energy  In  India, the  high  GDP  growth  rate  has  created  a  huge  demand  for  energy,  but  the  supply  is  unable  to  match  the demand. The total installed capacity of power as of  January  2012  is  187  GW.  The  per  capita  total  consumption  is  778  kWh.  The  estimated  shortage  of  power in India is about 20 GW. 
  • 5. Plant Commissioned in India  Name of Plant DC Peak Power (MW) Notes Mithapur Solar Power Plant ‐ Mithapur, Gujarat (Tata Power)  25 Commissioned February 2012 WAA SOLAR POWER PLANT ‐ Surendranagar, Gujarat  10.22 Commissioned January 2012 Reliance Power Pokaran Solar PV Plant, Rajasthan  40 Commissioning in March 2012 Adani Bitta Solar Plant, Gujarat  40 Completed in January 2012 Mahindra Solar Plant, Jodhpur, Rajasthan  5 Completed in January 2012 Sivaganga Photovoltaic Plant  5 Completed December 2010 Kolar Photovoltaic Plant  3 Completed May 2010 Itnal Photovoltaic Plant, Belgaum  3 Completed April 2010 Azure Power ‐ Photovoltaic Plant  2 Completed 2009  Chesdin Power ‐ Biomass and Solar Photovoltaic Plants  4.1 Completes December 2011 Citra and Sepset Power Plants ‐ Solar Photovoltaic Plants  4 Commissioned October 2011 Jamuria Photovoltaic Plant  2 Completed 2009  NDPC Photovoltaic Plant  1 Completed 2010  Thyagaraj Stadium Plant‐Delhi  1 Completed April, 2010 Gandhinagar Solar Plant  1 Completed January 2011 Tata ‐ Mulshi, Maharashtra  3 Commissioned April 2011 Azure Power ‐ Sabarkantha, Gujarat (Khadoda village )  10 Commissioned June 2011.  Moser Baer ‐ Patan, Gujarat  30 Commissioned July 2011 B&G Solar Pvt Ltd ‐ Mayiladuthurai, Tamil Nadu  1 Commissioned June 2011 REHPL ‐ Sadeipali, (Bolangir) Orissa 1 Commissioned July 2011 Tata ‐ Patapur, Orissa 1 Commissioned August 2011 Tata ‐ Osmanabad, Maharastra 1 Commissioned 1st Aug 2011 Amruth Solar Power Plant ‐ Kadiri, Andhra Pradesh 1 Commissioned March 2012 Abengoa ‐ Gwal Pahari, Haryana  3 Commissioned September 2011 Chandraleela Power Energy ‐ Narnaul, Haryana  0.8 Commissioned December 2011 Green Infra Solar Energy Limited ‐ Rajkot, Gujarat  10 Commissioned November 2011 Total 182.1
  • 6. Why In India  India  is  in  the  sunny  regions  of  the  world  with  most  parts of the country receiving 4‐7 kwh (kilowatt‐hour)  of  solar  radiation  per  square  meter  per  day,  250‐300  sunny  days  in  a  year.  Even  though  Solar  energy  constitutes a miniscule part in India’s installed power  generation  capacity  (with  grid  connected  solar  PV  generation at a mere 6 MW as of March 2010),  in  the  medium and long run, it is expected that solar energy,  especially solar PV will form a vital component of the  country's energy mix. 
  • 9. Different suppliers of Module Manufacturer Country Model Number Watts (p) Life in years/Guarantee given Bosch Germany M 240 3 BB 240 10 years-90%, 25 years-80% Canadian solar Canada CS5A-170 170 25 years Co energy US Power Plus 215 P 215 12 years-92%, 25years-80% Del Solar Taiwan D6P_E 120 10 years-90%, 25 years-80% Evergreen solar US ES-A series 200 25 years First solar US FS Series 70 10 years-90%, Mitsubishi Japan TD/TE series 190 JA solar holdings China JAS 165 10 years-90%, 25 years-80% Q cells Germany SL 1 70 25 years PLG Solar India 10 years-90%, 25 years-80% Moser Baer India 10 years-90%, 25 years-80% Tata BP Solar India 10 years-90%, 25 years-80%
  • 11. Jawaharlal Nehru National Solar  Mission The Jawaharlal Nehru National Solar Mission (also known as the National  Solar  Mission)  is  a  major  initiative  of  the Government  of  India and  State  Governments  to  promote  ecologically  sustainable  growth  while  addressing  India’s energy security challenges. It will also constitute a major contribution  by India to the global effort to meet the challenges of climate change. Named  for Jawaharlal Nehru, the Mission is one of the several initiatives that are part  of  National  Action  Plan  on  Climate  Change. The  program  was  officially  inaugurated by Prime Minister of India, Manmohan Singh.
  • 12. Scheme on financing of Off‐Grid and  Decentralised Solar Applications Government  of  India,  Ministry    of  New  and  Renewable  Energy  (MNRE) has  formulated a scheme on financing of Off‐Grid and  Decentralised Solar  (Photovoltaic  and Thermal) applications as part  of  the  Jawaharlal  Nehru  National  Solar  Mission  (JNNSM).   Under  the  scheme,  banks  may  extend  subsidised  loans  to  entrepreneurs at interest rates not exceeding five per  cent  where refinance of two per cent from Government of India  is available. 
  • 13. Excise Duty Exemption on Transmission  Equipments Exemption  of  Excise  Duty  on  procurement  of  Transmission  Equipments  for  initial  setup  of  Solar  Power  Plant.  The  exemption  would  be  available  on  transmission  equipments  wherever  the  contractual  obligation  for  installing  transmission  lines/equipments up to the point of delivery is c0st on  the solar power developer. 
  • 14. Subsidy in installation of Solar  Power plant The  Ministry  of  New  and  Renewable  Energy  (MNRE)  provides 70 percent subsidy on the installation cost of  a  solar  photovoltaic  power  plant  in  North‐East  states  and  30  percentage  subsidy  on  other  regions.  The  detailed  outlay  of  the  National  Solar  Mission  highlights  various  targets  set  by  the  government  to  increase solar energy in the country's energy portfolio.
  • 15. Major other incentives In  the  budget  for  2010/11,  the  government  has  announced  an  allocation  of US  $  220  million  towards  the Jawaharlal  Nehru  National Solar Mission.  They  encouraged  private  solar  companies  by  reducing  customs  duty  on  solar  panels  by  5%  and  exempting  excise  duty on  solar  photovoltaic panels.  The  budget  also  proposed  a  coal  tax  of US$1  per  metric  ton on  domestic and imported coal used for power generation. The  government  has  initiated  a  Renewable  Energy  Certificate  (REC) scheme,  which  is  designed  to  drive  investment  in  low‐ carbon energy projects.
  • 16. Opportunities and Challenges Land is a scarce resource in India and per capita land availability is low. Dedication  of  land  area  for  exclusive  installation  of  solar  arrays  might  have  to  compete  with  other  necessities  that  require  land.  The  amount  of  land  required for  utility‐scale  solar  power  plants—currently  approximately  1 km2 for  every  20–60 megawatts  (MW) generated could  pose  a  strain  on  India's  available  land  resource.  The  architecture  more  suitable  for  most  of  India  would  be  a  highly‐distributed  set  of  individual  rooftop  power  generation  systems,  all  connected  via  a local  grid. However,  erecting  such  an  infrastructure,  which  does  not  enjoy  the  economies  of  scale  possible  in  mass,  utility‐scale,  solar  panel  deployment,  needs  the market price of solar technology deployment to substantially decline, so that it  attracts the individual and average family size household consumer. That might be  possible  in  the  future,  because  PV  is  projected  to  continue  its  current  cost  reductions for the next decades and be able to compete with fossil fuel.
  • 18. Incentives from State Government  Government of Gujarat declared comprehensive Solar  Policy 2009, wherein Govt will purchase the power at  the following minimum rates. for  first 12 years for  next 12  years from date of commissioning  Solar  PV Rs. 12/‐ kWh Rs. 3/‐ kWh  Solar Thermal Rs. 9/‐ kWh Rs. 3/‐ kWh 
  • 19. Transmission charges & transmission  losses  At  66kV  :  Transmission  charges  and  transmission  losses applicable to normal Open Access Consumer.  Below  66  kV  :  Transmission  charges,  applicable  to  normal  open  access  consumer  and  transmission  and  wheeling  losses  @  10%  of  the  energy  fed  to  the  grid,  for Solar power Plant of capacity more than 5MW.  For  Solar  power  Plants  of  capacity  less  than  5  MW,  Transmission  charges,  applicable  to  normal  open  access  consumer    and  transmission  and  wheeling  losses @ 7% of the energy fed to the grid.
  • 21. Policy related to Land Acquisition for  Solar Plant  At  66kV  :  Transmission  charges  and  transmission  losses applicable to normal Open Access Consumer.  Below  66  kV  :  Transmission  charges,  applicable  to  normal  open  access  consumer  and  transmission  and  wheeling  losses  @  10%  of  the  energy  fed  to  the  grid,  for Solar power Plant of capacity more than 5MW.  For  Solar  power  Plants  of  capacity  less  than  5  MW,  Transmission  charges,  applicable  to  normal  open  access  consumer    and  transmission  and  wheeling  losses @ 7% of the energy fed to the grid.
  • 22. Govt.’s Initiative The Government of Gujarat is promoting Solar Power Parks in the Sate.  Rolled Out  Special Policy in 2009.  Already few Plants are operational in the State.  The  development  of  solar  parks  will  streamline  the  project  development  timeline  by  letting  government  agencies  undertake  land  acquisition  and  necessary  permits,  and  provide  dedicated  common  infrastructure  for  setting  up solar power generation plants largely in the private sector.  The  State  Government  is  taking  initiative  in  providing  the  common  infrastructure/ facilities like site preparation and leveling, power evacuation,  availability  of  water,  access  roads,  security  and  services.  In  parallel  with  the  central government's initiative. .
  • 23. Contd. The  Gujarat  Electricity  Regulatory  Commission  has  announced  feed‐in‐tariff  to  mainstream  solar  power  generation  which  will  be applied for solar power generation plants in the solar park.  Gujarat  Power  Corporation  Limited  is  the  responsible  agency  for  developing  the  solar  park  of  500  megawatts  and  will  lease  the lands to the project developers to generate solar power.  Gujarat  Energy  Transmission  Corporation  Limited  will  develop the transmission evacuation from the identified interconnection  points with the solar developer. This project is being supported,  in part, by the Asian Development Bank
  • 24. Exclusive mandate for Land in  Gujarat Land area  : About 1200 acre (485 hec.) Location  : 60 km from Ahmedabad (Capital of Gujarat) 20 km from Sanand (Plant of Tata Nano Car). Expected Price  : $ 12,000/‐ per acre Primary Use  : Solar Power Plant Secondary Use  : Storage/ Warehousing 
  • 30. Expected Production  1200 acre @ 10 MW /100 acre X 0.80 = 96 MW Assuming efficiency 80% 
  • 31. Cost of the Project ($ m)  Land Cost : 1.4  Cost of Approvals/Coversion/Devlopment 0.28 (20% of land cost)  PV Power Panels @ 4m 480.00 • Thus total initial investment for 120 Mw : 48168 • Say 500.00 • Less Subsidy 30% 150.00 • Net Investment 350.00
  • 32. Expected revenue  Expected Revenue from the Selling of Electricity  @   Rs. 12/‐ per kWh for first 12 years: = 2,102,400,000/‐ or USD $ 42 mn/ year   Assuming the plant will for 5 hours a day with efficiency of 80%
  • 34. Secondary benefits  Can be used as Storage purpose if constructed as Roof  top Solar power plant,  to store the items which is not  effected by UV rays and other harmful rays.