The Court of Appeal in Mac-Attack held that the NT Act impliedly prohibits making more than one payment claim for the same contractual obligation or including in a later claim amounts from an earlier unpaid claim. This was a misinterpretation of the Act going to the adjudicator's jurisdiction, invalidating their determination. The court also held that an adjudicator's satisfaction as to criteria in section 33(1)(a), including timeliness, must be reasonable and correctly understand the law. The article analyses and critiques several aspects of the Court of Appeal's decision.