Introduction to design of prestressed concrete structures - Part 1
1. 1
Presentation on
Prestressed Concrete
by
Prof. N. Rajagopalan
(Retd. Professor & Dean, I.I.T. Chennai)
Chief Technical Advisor – Bridges & Structures
M/s. L&T-RAMBØLL Consulting Engineers Limited,
Chennai
3. 3
Prestressing means application of a pre-
determined force on a system, for resisting
the internal stresses that may be developed
in the system, due to external loads.
4. 4
If the system is expected to have tensile
stresses due to external loads, pre-
compression can be given to the system to a
desired level even before the application of
the external loads. Then the tension
developed due to the external loads, will get
largely nullified by the initially applied
compression. This pre-compression is
called prestressing.
Generally prestressing is understood as
application of pre-compression and this
understanding will be followed hereafter
unless otherwise stated.
6. 6
Prestressing force could be applied
internally or it could also be applied by
external systems. External application of
prestressing force calls for reaction frame
and hence not preferred.
Normally, prestressing (pre-determined
force) is achieved using steel elements with
a fixed profile along the length of the
element, inside the element or outside the
element, concentric or eccentric to the axis
of the element.
7. 7
Wires (cables) are pretensioned by
stretching. Pre-compression on concrete is
achieved by:
(a) anchoring the wires (cables) to the
concrete through external anchorages.
(b) bonding the wires to concrete over a
definite length.
If there are external anchorages, there will be
an anchor plate to distribute the concentrated
force to the bigger area.
10. 10
The type of steel used for such prestressing
will be different from normal steel (mild
steel).
Such steel is called high tensile steel.
Mild steel can be stressed normally upto
140 N/mm2
with a strain of 0.00067
(Es=2.1 x 105
Mpa).
11. 11
After the force is transferred to concrete
there will be a compression (strain) in
concrete due to shrinkage and creep of
concrete, which are due to natural
phenomena and independent of pre-
compression.
This will be to an amount of 0.0006. Hence
the tensile strain in steel will get reduced by
0.0006.
12. 12
The left over tensile strain in steel will be
0.00007. This is only 10% of the applied
strain.
This would lead to only 10% of the applied
stress on steel namely 14 N/mm2
. The
corresponding stress on concrete with a vast
area will be negligible.
13. 13
The creep and shrinkage strain in concrete
(say 0.0006) is nearly constant.
To have a good residual strain/stress, the
applied stress/strain in steel should be high.
Hence the steel used should be capable of
being stressed to around 1000 N/mm2
.
This could be achieved by using high
tensile steel which will have a ultimate
strength of 1600 N/mm2
.
15. 15
Advantages of Prestressed
Concrete
When tension occurs in concrete due to
external loading, it will be nullified by the
initial compression and there will not be any
residual tension in concrete and hence there
will not be any cracking.
This would prevent atmospheric ingression
inside the concrete element and hence save
steel from corrosion and concrete from
chemical attack.
16. 16
The concrete in the tension zone (uncracked)
will also be useful in resisting external
forces.
The concrete properties of full section will
be useful. This would lead to slender
structures.
The stiffness of the structure is increased
(because of un-cracked concrete) and hence
the structure has a reduced deflection,
leading to better serviceability.
17. 17
Pre-compression introduced in concrete
increases shear capacity. This leads to
heavier load carrying capacity of the
element.
19. 19
Classification of types of
prestressing
Prestressing of concrete can be achieved in
number of ways and hence can be classified
depending on the way in which pre-
compression is transferred on concrete.
Accordingly, the classification is identified
in the following four groups:
20. 20
External or internal prestressing
Linear or circular prestressing
Pretensioning or post tensioning
Partial prestressing, limited prestressing or
full prestressing.
22. 22
Force is transferred by bond.
The length this is required to transfer is
called bond length.
The force is picked up by concrete after a
length called transmission length. Upto this
transmission length, the force will not be felt
fully.
The force is felt in the full cross-section only
after the transmission length.
Transmission length is little more than bond
length.
23. 23
The disadvantages in this system are:
high tensile steel cannot be given any profile
under normal conditions.
the prestressing cannot be transferred
immediately on to cocnrete and one has to
wait till the concrete acquires sufficient
bond strength to transfer the precompression
generated by the prestressing to concrete.
24. 24
The prestressing can be done only where
there is a prestressing bed or a self straining
frame namely stress bench.
the bond properties between concrete and
steel should be good.
the prestressing force is transferred
gradually from the end and there is a
transmission distance before the prestress is
felt on the full cross-section of the structural
elements.
25. 25
Post-tensioning system
In case post tensioning, structural elements
are cast first with holes left for prestressing
elements to run through.
These holes are provided with metal
sheathing or HDPV ducts placed in proper
position and they are called cable ducts.
The prestressing cable (steel) is threaded
through these holes and tensioned.
The tensioned steel are anchored at the ends
by special type of anchoring units.
26. 26
The vacant portion of the ducts are then
grouted.
The anchorages transfer the force at the end.
The concrete and the system should be able
to take it.
The end portion called end block (anchor
zone) has to be separately designed.
28. 28
Pre-tensioning is preferred when:
the structural element to be prestressed is
small and can easily be transported.
more numbers of similar prestressed
structural elements are to be produced, such
as prestressed concrete sleepers.
labour at site is costly.
number of external anchorages and the
corresponding costs are high.
29. 29
Post tensioning is preferred when:
the structural elements to be prestressed is
very heavy.
the product is unique and not repeated many
times.
labour at site is not very costly
number of external anchorages and the
corresponding costs are not high.
30. 30
Partial prestressing, limited
prestressing or full prestressing
This type of classification was introduced in
CEB/FIP recommendations in 1970
depending on the level of prestress
introduced in the structural element to
nullify the stress that may develop during
applications of external load.
IS-1343 calls partial prestressed structures
as Type III structure.
31. 31
Type 1 refers to a fully prestressed concrete
structure and Type 2 structure with limited
prestress where tensile stresses do not exceed
the cracking stresses of concrete. Type 3
structures are those which allow tensile
stresses to occur leading to limited
crackwidths and that too under extraordinary
leading conditions which may occur rarely on
the structure.
32. 32
The cracks may get closed as soon as that
extraordinary loading moves out from the
structure. The permissible tensile stresses for
such conditions are related to permissible
crack width.
33. 33
CEB/FIP has classified them as Class I
(fully prestressed), Class II (limited
prestressed) and Class III (partially
prestressed) and Class IV (Reinforced
concrete structures).
In Class III type, the level upto which
precompression is done can be achieved:
(a) by prestressing the high tensile steel
upto desired level (much below the
permitted level of stress for prestress for
such steel) and allowing the same steel to
act of reinforcement for taking care of extra
34. 34
extra tensile force that may occur due to
occasional large loads or
(b) by prestressing the high tensile steel
near to permitted level of stressing and
providing untensioned steel to take care of
the extra tensile force that may occur due to
occasionally occurring large loads. The
first is called partially prestressed structures
and the second is called prestressed
reinforced concrete structures.
36. 36
Tendons and Cables
The prestressing steel in a prestressed
concrete element is normally referred to as
a tendon. A tendon may consist of one or
more individual wires, one or more number
of rods, number of wires 2,3 or 7 twisted
together to form an individual strand and
number of strands grouped together.
37. 37
The number of tendons grouped is called a
cable. The tendons grouped together in a
cable will be anchored with one external
anchor. The external anchorage can be
pulled with all the tendons together by a
single jack and this is called bulk pulling.
Individual tendons in the cable can also be
pulled and anchored. The tendon is
accommodated in a cable duct. The duct
has a sheathing of a minimum thickness
governed by relevant codes. The duct is
also to be tested for containing the cables
and grouting materials.
42. 42
Bruggeling has defined a full spectrum of
concrete structures as:
a) plain concrete with nominal steel to take
care of shrinkage cracks
b) reinforced concrete
c) partially prestressed (prestressed
reinforced) concrete.
d) concrete with limited prestressing
e) fully prestressed concrete
43. 43
Hence the studies are only concrete structures
with various external inputs in the form of
material or forces.
Hence Prestressed Concrete is not a
New Materials