Contents
 Reviews and the test process
 Types of review
 Static analysis
People techniques
 individual:
desk-checking, data-stepping, proof-reading
 group:
Reviews (informal & formal): for consensus
Walkthrough: for education
Inspection (most formal): to find faults
Static techniques do not execute code
Benefits of reviews
 Development productivity improvement
 Reduced development timescales
 Reduced testing time and cost
 Lifetime cost reductions
 Reduced fault levels
 Improved customer relations
 etc.
Reviews are cost-effective
 10 times reduction in faults reaching test, testing
cost reduced by 50% to 80%
Handbook of Walkthroughs, Inspections & Technical
Reviews - Freedman & Weinberg
 reduce faults by a factor of 10
Structured Walkthroughs - Yourdon
 25% reduction in schedules, remove 80% -
95% of faults at each stage, 28 times
reduction in maintenance cost, many others
Software Inspection - Gilb & Graham
What can be Inspected?
Anything written down
can be Inspected
 policy, strategy, business plans, marketing or
advertising material, contracts
 system requirements, feasibility studies,
acceptance test plans
 test plans, test designs, test cases, test results
 system designs, logical & physical
 software code
 user manuals, procedures, training material
What can be reviewed
?
 anything which could be Inspected
i.e. anything written down
 plans, visions, “big picture”, strategic
directions, ideas
 project progress
work completed to schedule, etc.
 “Should we develop this” marketing options
What to review / Inspect
?
Tests
Tests
Tests
Tests
Requirements
Design
Code
Functions
Integration T
Unit Test
Accept. Test
System Test
Costs of reviews
 Rough guide: 5%-15% of development effort
half day a week is 10%
 Effort required for reviews
planning (by leader / moderator)
preparation / self-study checking
meeting
fixing / editing / follow-up
recording & analysis of statistics / metrics
process improvement (should!)
Contents
Reviews and the test process
Types of review
Static analysis
Static testing
1 2
4 5
3
6
ISTQB / ISEB Foundation Exam Practice
Types of review of documents
Informal Review
undocumented
 widely viewed as useful and cheap (but no one can
prove it!) A helpful first step for chaotic
organisations.
Technical Review: (or peer review)
 includes peer and technical experts, no
management participation. Normally documented,
fault-finding. Can be rather subjective.
Decision-making Review:
 group discusses document and makes a decision about
the content, e.g. how something should be done, go or
no-go decision, or technical comments
Types of review of documents
Walkthrough
 author guides the group through a document and his or
her thought processes, so all understand the same
thing, consensus on changes to make
Inspection:
 formal individual and group checking, using sources
and standards, according to generic and specific rules
and checklists, using entry and exit criteria, Leader
must be trained & certified, metrics required
Reviews in general 1
 Objectives / goals
validation & verification against specifications &
standards
achieve consensus (excluding Inspection)
process improvement (ideal, included in
Inspection)
Reviews in general 2
 Activities
planning
overview / kick-off meeting (Inspection)
preparation / individual checking
review meeting (not always)
follow-up (for some types)
metrics recording & analysis (Inspections and
sometimes reviews)
Reviews in general 3
 Roles and responsibilities
Leader / moderator - plans the review / Inspection,
chooses participants, helps & encourages,
conducts the meeting, performs follow-up,
manages metrics
Author of the document being reviewed /
Inspected
Reviewers / Inspectors - specialised fault-finding
roles for Inspection
Managers - excluded from some types of review,
need to plan project time for review / Inspection
Others: e.g. Inspection/ review Co-ordinator
Reviews in general 4
 Deliverables
Changes (edits) in review product
Change requests for source documents (predecessor
documents to product being reviewed / Inspected)
Process improvement suggestions
 to the review / Inspection process
 to the development process which produced the product just
reviewed / Inspected
Metrics (Inspection and some types of review)
Reviews in general 5
 Pitfalls (they don’t always work!)
lack of training in the technique (especially
Inspection, the most formal)
lack of or quality of documentation - what is being
reviewed / Inspected
Lack of management support - “lip service” - want
them done, but don’t allow time for them to
happen in project schedules
Failure to improve processes (gets disheartening
just getting better at finding the same thing over
again)
Inspection is different
• the document to be
reviewed is given out in
advance
• typically dozens of
pages to review
• instructions are "please
review this"
• not just product,
sources
• chunk or sample
• training, roles
Inspection is different
• some people have time
to look through it and
make comments before
the meeting (which is
difficult to arrange)
• the meeting often lasts
for hours
 entry criteria to
meeting, may not be
worth holding
 2 max., often much
shorter
Inspection is different
• "I don't like this"
• much discussion, some
about technical
approaches, some about
trivia
• don't really know if it was
worthwhile, but we keep
doing it
 Rule violations, objective,
not subjective
• no discussion, highly
focused, anti-trivia
 only do it if value is
proven (continually)
Inspection is more and better
 entry criteria
 training
 optimum checking rate
 prioritising the words
 standards
 process improvement
 exit criteria
 quantified estimates of
remaining major faults
per page
typical review
early Inspection
mature Inspection
effectiveness return on investment
10 - 20% unknown
30 - 40% 6 - 8 hrs / Insp hr
80 - 95% 8 - 30 hrs / Insp hr
The Inspection Process
Software
Development
Stage
.
.
Planning
Kick
off
Ind
Chk
Meet Edit
Change
Request
Process
Improvement
Entry
Next Software
Development
Stage
Exit
At first glance
..
Here’s a document: review this (or Inspect it)
Reviews: time and size determine
rate
Time
Checking
Rate
Size
2 hrs?
100 pages?
50 pages per hour
Checking
Rate
Review “Thoroughness
?”
ordinary “review” - finds some faults, one major, fix them,
consider the document now corrected and OK
major minor
minor
Inspection: time and rate determine size
Time
Checking
Rate
Size
2 hrs?
Optimum:
1 page*
per hour
2 pages (at optimum rate)
Size
* 1 page = 300 important words
Inspection Thoroughness
Inspection can find deep-seated faults:
• all of that type can be corrected
• but needs optimum checking rate
Inspection surprises
 Fundamental importance of Rules
democratically agreed as applying
define major issues / faults
 Slow checking rates
 Strict entry & exit criteria
 Fast logging rates
 Amount of responsibility given to author
Contents
 Reviews and the test process
 Types of review
 Static analysis
What can static analysis do?
Remember: static techniques do
not execute
the code
 A form of automated testing
check for violations of standards
check for things which may be a fault
 Descended from compiler technology
a compiler statically analyses code, and “knows” a
lot about it, e.g. variable usage; finds syntax faults
static analysis tools extend this knowledge
can find unreachable code, undeclared variables,
parameter type mis-matches, uncalled functions &
procedures, array bound violations, etc.
Data flow analysis
 This is the study of program variables
variable defined* where a value is stored into it
variable used where the stored value is accessed
variable is undefined before it is defined or when it
goes out of scope
*defined should not be confused with declared
x = y + z
IF a > b THEN read(S)
x is defined, y and z are used
a and b are used, S is defined
Data flow analysis faults
n := 0
read (x)
n := 1
while x > y do
begin
read (y)
write( n*y)
x := x - n
end
Data flow anomaly: n is
re-defined without being used
Data flow fault: y is used
before it has been defined
(first time around the loop)
Control flow analysis
 Highlights:
nodes not accessible from start node
infinite loops
multiple entry to loops
whether code is well structured, i.e. reducible
whether code conforms to a flowchart grammar
any jumps to undefined labels
any labels not jumped to
cyclomatic complexity and other metrics
Unreachable code example
 Macro definitions
(different for different platforms the code runs on)
Buffsize: 1000
Mailboxmax: 1000
IF Buffsize < Mailboxmax THEN
Error-Exit
ENDIF
 Static Analysis finds the THEN clause
unreachable, so will flag a fault
Cyclomatic complexity
 cyclomatic complexity is a measure of the
complexity of a flow graph
(and therefore the code that the flow graph represents)
 the more complex the flow graph, the greater the
measure
 it can most easily be calculated as:
complexity = number of decisions + 1
Which flow graph is most complex
?
1
2 3 5
What is the cyclomatic complexity?
Example control flow graph
Result = 0
Right = 0
DO WHILE more Questions
IF Answer = Correct THEN
Right = Right + 1
ENDIF
END DO
Result = (Right / Questions)
IF Result > 60% THEN
Print "pass"
ELSE
Print "fail”
ENDIF
do
if r=r+1
end
init
if
res
pass
fail
end
Pseudo-code:
Other static metrics
 lines of code (LOC)
 operands & operators (Halstead’s metrics)
 fan-in & fan-out
 nesting levels
 function calls
 OO metrics: inheritance tree depth, number of
methods, coupling & cohesion
Limitations and advantages
 Limitations:
cannot distinguish "fail-safe" code from programming faults
or anomalies (often creates overload of spurious error
messages)
does not execute the code, so not related to operating
conditions
 Advantages:
can find faults difficult to "see"
gives objective quality assessment of code
Summary: Key Points
 Reviews help to find faults in development and
test documentation, and should be applied
early
 Types of review: informal, walkthrough,
technical / peer review, Inspection
 Static analysis can find faults and give
information about code without executing it

More Related Content

PPT
Static testing techniques
PPS
ISTQB Foundation - Chapter 3
PPT
ISTQB / ISEB Foundation Exam Practice
PPT
Iseb, ISTQB Static Testing
PPTX
CTFL Module 03
PPT
03. static techniques
PPTX
3.static techniques
PPT
ISTQB / ISEB Foundation Exam Practice - 5
Static testing techniques
ISTQB Foundation - Chapter 3
ISTQB / ISEB Foundation Exam Practice
Iseb, ISTQB Static Testing
CTFL Module 03
03. static techniques
3.static techniques
ISTQB / ISEB Foundation Exam Practice - 5

Similar to ISTQBCH3StaticxvvvbbbdghhhjvvTesting.ppt (20)

PPTX
Static Testing
PPTX
Static nopri wahyudi
PPTX
PPTX
Chapter Three Static Techniques
PPT
AiTi Education Software Testing Session 03
PPTX
Software Testing 4/5
PPT
Lecture 10 Static Testing.ppt
PDF
Testing Throughout the Software Life Cycle (2013)
PPTX
Static techniques
PPTX
Static techniques software development - Testing & Implementation
PPTX
Testing 1 static techniques
PPTX
Static Techniques (Chapter 3)
PPT
ISTQB Static Testing foundation level in QA
PPTX
Chapter 3 Static Techniques
PPTX
Static techniques
PPTX
Marjuni.
PPTX
Aim (A).pptx
PPTX
Static techniques
PPTX
Unit3 software review control software
PPT
chapter 7.ppt
Static Testing
Static nopri wahyudi
Chapter Three Static Techniques
AiTi Education Software Testing Session 03
Software Testing 4/5
Lecture 10 Static Testing.ppt
Testing Throughout the Software Life Cycle (2013)
Static techniques
Static techniques software development - Testing & Implementation
Testing 1 static techniques
Static Techniques (Chapter 3)
ISTQB Static Testing foundation level in QA
Chapter 3 Static Techniques
Static techniques
Marjuni.
Aim (A).pptx
Static techniques
Unit3 software review control software
chapter 7.ppt
Ad

Recently uploaded (20)

PDF
Manager Resume for R, CL & Applying Online.pdf
PPTX
PMP (Project Management Professional) course prepares individuals
PPTX
Job-opportunities lecture about it skills
PPT
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
PPTX
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
PDF
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
PDF
esg-supply-chain-webinar-nov2018hkhkkh.pdf
PDF
Sales and Distribution Managemnjnfijient.pdf
PDF
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
PDF
Why Today’s Brands Need ORM & SEO Specialists More Than Ever.pdf
PPTX
Cerebral_Palsy_Detailed_Presentation.pptx
PPTX
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
PDF
MCQ Practice CBT OL Official Language 1.pptx.pdf
DOC
field study for teachers graduating samplr
DOCX
mcsp232projectguidelinesjan2023 (1).docx
PDF
HR Jobs in Jaipur: 2025 Trends, Banking Careers & Smart Hiring Tools
PPTX
Surgical thesis protocol formation ppt.pptx
PPTX
退学买新西兰毕业证(WelTec毕业证书)惠灵顿理工学院毕业证国外证书制作
PPTX
CORE 1 HOUSEKEEPING TOURISM SECTOR POWERPOINT
PPT
APPROACH TO DEVELOPMENTALlllllllllllllllll
Manager Resume for R, CL & Applying Online.pdf
PMP (Project Management Professional) course prepares individuals
Job-opportunities lecture about it skills
Gsisgdkddkvdgjsjdvdbdbdbdghjkhgcvvkkfcxxfg
chapter 3_bem.pptxKLJLKJLKJLKJKJKLJKJKJKHJH
Daisia Frank: Strategy-Driven Real Estate with Heart.pdf
esg-supply-chain-webinar-nov2018hkhkkh.pdf
Sales and Distribution Managemnjnfijient.pdf
Understanding the Rhetorical Situation Presentation in Blue Orange Muted Il_2...
Why Today’s Brands Need ORM & SEO Specialists More Than Ever.pdf
Cerebral_Palsy_Detailed_Presentation.pptx
PE3-WEEK-3sdsadsadasdadadwadwdsdddddd.pptx
MCQ Practice CBT OL Official Language 1.pptx.pdf
field study for teachers graduating samplr
mcsp232projectguidelinesjan2023 (1).docx
HR Jobs in Jaipur: 2025 Trends, Banking Careers & Smart Hiring Tools
Surgical thesis protocol formation ppt.pptx
退学买新西兰毕业证(WelTec毕业证书)惠灵顿理工学院毕业证国外证书制作
CORE 1 HOUSEKEEPING TOURISM SECTOR POWERPOINT
APPROACH TO DEVELOPMENTALlllllllllllllllll
Ad

ISTQBCH3StaticxvvvbbbdghhhjvvTesting.ppt

  • 1. Static Testing 1 Principles 2 Lifecycle 4 Dynamic test techniques 3 Static testing 5 Management 6 Tools Software Testing ISTQB / ISEB Foundation Exam Practice Chapter 3
  • 2. Contents  Reviews and the test process  Types of review  Static analysis
  • 3. People techniques  individual: desk-checking, data-stepping, proof-reading  group: Reviews (informal & formal): for consensus Walkthrough: for education Inspection (most formal): to find faults Static techniques do not execute code
  • 4. Benefits of reviews  Development productivity improvement  Reduced development timescales  Reduced testing time and cost  Lifetime cost reductions  Reduced fault levels  Improved customer relations  etc.
  • 5. Reviews are cost-effective  10 times reduction in faults reaching test, testing cost reduced by 50% to 80% Handbook of Walkthroughs, Inspections & Technical Reviews - Freedman & Weinberg  reduce faults by a factor of 10 Structured Walkthroughs - Yourdon
  • 6.  25% reduction in schedules, remove 80% - 95% of faults at each stage, 28 times reduction in maintenance cost, many others Software Inspection - Gilb & Graham
  • 7. What can be Inspected? Anything written down can be Inspected  policy, strategy, business plans, marketing or advertising material, contracts  system requirements, feasibility studies, acceptance test plans  test plans, test designs, test cases, test results
  • 8.  system designs, logical & physical  software code  user manuals, procedures, training material
  • 9. What can be reviewed ?  anything which could be Inspected i.e. anything written down  plans, visions, “big picture”, strategic directions, ideas  project progress work completed to schedule, etc.  “Should we develop this” marketing options
  • 10. What to review / Inspect ? Tests Tests Tests Tests Requirements Design Code Functions Integration T Unit Test Accept. Test System Test
  • 11. Costs of reviews  Rough guide: 5%-15% of development effort half day a week is 10%  Effort required for reviews planning (by leader / moderator) preparation / self-study checking meeting fixing / editing / follow-up recording & analysis of statistics / metrics process improvement (should!)
  • 12. Contents Reviews and the test process Types of review Static analysis Static testing 1 2 4 5 3 6 ISTQB / ISEB Foundation Exam Practice
  • 13. Types of review of documents Informal Review undocumented  widely viewed as useful and cheap (but no one can prove it!) A helpful first step for chaotic organisations. Technical Review: (or peer review)  includes peer and technical experts, no management participation. Normally documented, fault-finding. Can be rather subjective.
  • 14. Decision-making Review:  group discusses document and makes a decision about the content, e.g. how something should be done, go or no-go decision, or technical comments
  • 15. Types of review of documents Walkthrough  author guides the group through a document and his or her thought processes, so all understand the same thing, consensus on changes to make Inspection:  formal individual and group checking, using sources and standards, according to generic and specific rules and checklists, using entry and exit criteria, Leader must be trained & certified, metrics required
  • 16. Reviews in general 1  Objectives / goals validation & verification against specifications & standards achieve consensus (excluding Inspection) process improvement (ideal, included in Inspection)
  • 17. Reviews in general 2  Activities planning overview / kick-off meeting (Inspection) preparation / individual checking review meeting (not always) follow-up (for some types) metrics recording & analysis (Inspections and sometimes reviews)
  • 18. Reviews in general 3  Roles and responsibilities Leader / moderator - plans the review / Inspection, chooses participants, helps & encourages, conducts the meeting, performs follow-up, manages metrics Author of the document being reviewed / Inspected
  • 19. Reviewers / Inspectors - specialised fault-finding roles for Inspection Managers - excluded from some types of review, need to plan project time for review / Inspection Others: e.g. Inspection/ review Co-ordinator
  • 20. Reviews in general 4  Deliverables Changes (edits) in review product Change requests for source documents (predecessor documents to product being reviewed / Inspected) Process improvement suggestions  to the review / Inspection process  to the development process which produced the product just reviewed / Inspected Metrics (Inspection and some types of review)
  • 21. Reviews in general 5  Pitfalls (they don’t always work!) lack of training in the technique (especially Inspection, the most formal) lack of or quality of documentation - what is being reviewed / Inspected
  • 22. Lack of management support - “lip service” - want them done, but don’t allow time for them to happen in project schedules Failure to improve processes (gets disheartening just getting better at finding the same thing over again)
  • 23. Inspection is different • the document to be reviewed is given out in advance • typically dozens of pages to review • instructions are "please review this" • not just product, sources • chunk or sample • training, roles
  • 24. Inspection is different • some people have time to look through it and make comments before the meeting (which is difficult to arrange) • the meeting often lasts for hours  entry criteria to meeting, may not be worth holding  2 max., often much shorter
  • 25. Inspection is different • "I don't like this" • much discussion, some about technical approaches, some about trivia • don't really know if it was worthwhile, but we keep doing it  Rule violations, objective, not subjective • no discussion, highly focused, anti-trivia  only do it if value is proven (continually)
  • 26. Inspection is more and better  entry criteria  training  optimum checking rate  prioritising the words  standards  process improvement  exit criteria  quantified estimates of remaining major faults per page typical review early Inspection mature Inspection effectiveness return on investment 10 - 20% unknown 30 - 40% 6 - 8 hrs / Insp hr 80 - 95% 8 - 30 hrs / Insp hr
  • 27. The Inspection Process Software Development Stage . . Planning Kick off Ind Chk Meet Edit Change Request Process Improvement Entry Next Software Development Stage Exit
  • 28. At first glance .. Here’s a document: review this (or Inspect it)
  • 29. Reviews: time and size determine rate Time Checking Rate Size 2 hrs? 100 pages? 50 pages per hour Checking Rate
  • 30. Review “Thoroughness ?” ordinary “review” - finds some faults, one major, fix them, consider the document now corrected and OK major minor minor
  • 31. Inspection: time and rate determine size Time Checking Rate Size 2 hrs? Optimum: 1 page* per hour 2 pages (at optimum rate) Size * 1 page = 300 important words
  • 32. Inspection Thoroughness Inspection can find deep-seated faults: • all of that type can be corrected • but needs optimum checking rate
  • 33. Inspection surprises  Fundamental importance of Rules democratically agreed as applying define major issues / faults  Slow checking rates  Strict entry & exit criteria  Fast logging rates  Amount of responsibility given to author
  • 34. Contents  Reviews and the test process  Types of review  Static analysis
  • 35. What can static analysis do? Remember: static techniques do not execute the code  A form of automated testing check for violations of standards check for things which may be a fault
  • 36.  Descended from compiler technology a compiler statically analyses code, and “knows” a lot about it, e.g. variable usage; finds syntax faults static analysis tools extend this knowledge can find unreachable code, undeclared variables, parameter type mis-matches, uncalled functions & procedures, array bound violations, etc.
  • 37. Data flow analysis  This is the study of program variables variable defined* where a value is stored into it variable used where the stored value is accessed variable is undefined before it is defined or when it goes out of scope *defined should not be confused with declared x = y + z IF a > b THEN read(S) x is defined, y and z are used a and b are used, S is defined
  • 38. Data flow analysis faults n := 0 read (x) n := 1 while x > y do begin read (y) write( n*y) x := x - n end Data flow anomaly: n is re-defined without being used Data flow fault: y is used before it has been defined (first time around the loop)
  • 39. Control flow analysis  Highlights: nodes not accessible from start node infinite loops multiple entry to loops whether code is well structured, i.e. reducible whether code conforms to a flowchart grammar any jumps to undefined labels any labels not jumped to cyclomatic complexity and other metrics
  • 40. Unreachable code example  Macro definitions (different for different platforms the code runs on) Buffsize: 1000 Mailboxmax: 1000 IF Buffsize < Mailboxmax THEN Error-Exit ENDIF
  • 41.  Static Analysis finds the THEN clause unreachable, so will flag a fault
  • 42. Cyclomatic complexity  cyclomatic complexity is a measure of the complexity of a flow graph (and therefore the code that the flow graph represents)  the more complex the flow graph, the greater the measure  it can most easily be calculated as: complexity = number of decisions + 1
  • 43. Which flow graph is most complex ? 1 2 3 5 What is the cyclomatic complexity?
  • 44. Example control flow graph Result = 0 Right = 0 DO WHILE more Questions IF Answer = Correct THEN Right = Right + 1 ENDIF END DO Result = (Right / Questions) IF Result > 60% THEN Print "pass" ELSE Print "fail” ENDIF do if r=r+1 end init if res pass fail end Pseudo-code:
  • 45. Other static metrics  lines of code (LOC)  operands & operators (Halstead’s metrics)  fan-in & fan-out  nesting levels  function calls  OO metrics: inheritance tree depth, number of methods, coupling & cohesion
  • 46. Limitations and advantages  Limitations: cannot distinguish "fail-safe" code from programming faults or anomalies (often creates overload of spurious error messages) does not execute the code, so not related to operating conditions  Advantages: can find faults difficult to "see" gives objective quality assessment of code
  • 47. Summary: Key Points  Reviews help to find faults in development and test documentation, and should be applied early  Types of review: informal, walkthrough, technical / peer review, Inspection  Static analysis can find faults and give information about code without executing it