“Failing to plan is planning to fail”
by J. Hinze, Construction Planning and Scheduling
• Planning:
– “what” is going to be done, “how”, “where”, by
“whom”, and “when”
– for effective monitoring and control of complex
projects
“Its about time”
by J. Hinze, Construction Planning and Scheduling
• Scheduling:
– “what” will be done, and “who” will be
working
• relative timing of tasks & time frames
– a concise description of the plan
“Once you plan your work, you must
work your plan”
by J. Hinze, Construction Planning and Scheduling
• Planning and Scheduling occurs:
– AFTER you have decided how to do the work
• “The first idea is not always the best idea.”
• Requires discipline to “work the plan”
– The act of development useful,
– But need to monitor and track
• only then, is a schedule an effective management
tool
• as-built schedules
The Work Break Down Structure
(WBS)
• An organizational tool for complex projects
– A first step in creating a schedule
– Useful for defining the Scope of Work
• After decided how to do the work
• Consists of:
– Goal statement for project
– Subdividing goal into smaller & smaller
portions
WBS
• Upper two or three levels
– require only general knowledge
– don’t get too detailed too quickly
• The deeper you go, the more knowledge
you need
• Bottom level tasks:
• simple enough to estimate durations
• can assign crews
• each task has a natural sequence relative to other
tasks
Example WBS
Warehouse WBS
Site Boundaries Elevation
Data Points
Building
Footprints
Locate
Buried Services
Survey Soils Analysis Excavate Soil Backfill & Compact
Site Preparation Foundation Structural Systems Finishing
To construct a 5-unit
warehouse for light industry
Complex
Could be used to define scope of
work for surveyor sub-contract
Order of Task Execution -
Scheduling
• Bar Charts (Gantt Charts)
– length of bar = task’s duration
– commonly used, require little training
– precedence relationships difficult to show
• precedence = the sequencing relationship between
tasks
Order of Task Execution -
Scheduling
• Network Diagrams
– Critical Path Method (CPM)
• w/in construction - most important
– Program Evaluation and Review Technique
(PERT)
• like a generalized CPM
• assumes that an activity’s duration cannot be
precisely determined
– takes most likely, optimistic, pessimistic estimates
– computes an expected duration/activity and expected
project duration
Critical Path Method (CPM)
• Identifies those chains of activities (critical
paths) that control how long a project will
take.
• Two variations:
– Activity-on-Arrow (AOA)
• activities are the arrows or lines
– Activity on Node (AON)
• also known as a Precedence Diagram
• activities are nodes connected together by lines
Some CPM Terms
• Float = the amount of time an activity can
be delayed without delaying the project
• Critical = activities with no float; these
activities can not be delayed w/o extending
project duration
• Contingency = include a time allowance to
account for time slippage & other delays
• Slippage = difference between actual and
scheduled progress
Computer Scheduling
“Projects should be scheduled one
byte at a time”
by J. Hinze, Construction Planning and Scheduling
Creating a Computerized Schedule
• Primavera P3, SureTrak, CA-SuperProject, MSProject
• Uses CPM for calculating project duration
• Offer Gantt and Precedence views
– Gantt the default
– Activities can be viewed in other forms: activity and resource
calendars, spreadsheets
• Useful for
– updating and tracking
– sorting, filtering, resource leveling
Creating a Computerized Schedule
• Specify a base calendar
– calendar days vs. working and non-working
days
– specialized activity and resource calendars
• tasks that cannot be performed on specific days
• days that resources are available
– (otherwise assumed that resources are available at all
times on every working day)
• Specify the project start or finish date
Creating a Computerized Schedule
• Input activities from the WBS
– basic info needed: name, duration,
predecessors, and successors
– if relevant: resources utilized plus associated
costs
• Collapsing the schedule
– consolidating subtasks within their summary
tasks to view main project activities w/o
cluttering the screen
Creating a Computerized Schedule
• Expanding the schedule
– showing sub tasks w/in respective summary
tasks
• Link lines
– the line that connects the bars of linked tasks on
the Gantt chart
Creating a Computerized Schedule
• Linking
– creating relationships between activities
– finish-to-start, start-to-start, finish-to-finish, or
start-to-finish
– can include lag or lead times
• Network loop
– circular logic within a set of activities
– all loops must be eliminated for computations
to be made
Creating a Computerized Schedule
• Progress bar
– graphical representation of the % completion of
an activity at a specific date
– shown adjacent to, or within, the activity bar
• Summary task
– representing a general activity of construction
– duration calculated from sub-tasks
• Create a baseline schedule
– original schedule created at the beginning
• actual progress is compared to
Getting CPM w/MSProject
• After input of schedule
– choose Gantt view
– use GanttChart Wizard to calculate CPM
• Can filter and show only CPM
– in drop-down menu:
• project  filtered for  critical
– to get back to full task list:
• project  filtered for  all
Example - Roof Structure
The following seven tasks are required for the erection of a
building roof structure. Some of the tasks can be completed
simultaneously; the overhang with sofit can be constructed
while the deck is being installed.
1 Place & secure trusses, 2 days
2 Install roof deck, 7 days
3 Apply vapor barrier, 2 days
4 Apply roof cladding, 2 days
5 Construct roof overhang, 4 days
6 Install soffits, 4 days
7 Apply flashing, 6 days

More Related Content

PPTX
Network scheduling
PPTX
How Project Network Diagram's Can Help You Become A Better Project Manager
PPT
Critical Path Analysis Notes
PPTX
Short Comings of Bar Chart and Remidial Measures
PPTX
Introduction to the project managment
PPT
06 pert cpm
PPTX
Network Problem CPM & PERT
PDF
05 critical path analysis
Network scheduling
How Project Network Diagram's Can Help You Become A Better Project Manager
Critical Path Analysis Notes
Short Comings of Bar Chart and Remidial Measures
Introduction to the project managment
06 pert cpm
Network Problem CPM & PERT
05 critical path analysis

What's hot (20)

PPTX
or-pert
PDF
Assignment project scheduling
PPT
Cpm n pert lecture 1
PDF
CPM AND PERT
PPTX
PPTX
Pert cpm-22-3-21
PPTX
Project management
PDF
CPM and PERT
PPTX
Critical path analysis
PDF
Management science
PDF
Network Anaysis_ critical path methods
PPTX
Project Management
PPT
Gantt chart PPT, POOJA GODIYAL
PPSX
Science behind scheduling
PPTX
Presentation7
PDF
What are the disadvantages of Gantt charts?
PPT
Ovi project
PPTX
3.1 the usage of bar chart
PPTX
Critical path analysis
PPTX
Project Management
or-pert
Assignment project scheduling
Cpm n pert lecture 1
CPM AND PERT
Pert cpm-22-3-21
Project management
CPM and PERT
Critical path analysis
Management science
Network Anaysis_ critical path methods
Project Management
Gantt chart PPT, POOJA GODIYAL
Science behind scheduling
Presentation7
What are the disadvantages of Gantt charts?
Ovi project
3.1 the usage of bar chart
Critical path analysis
Project Management
Ad

Similar to L6.2 planing&scheduling (20)

PPTX
project schdeling concepts in operating system
PPTX
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
PPT
Fundamentals of scheduling
DOCX
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
PPTX
Unit II.pptx
PDF
Advanced project management mod 4
PPTX
chapter-1.pptx scheduling for construction
PPTX
Network Analysis- CPM ppt..pptx
PDF
Project schedule- What, How, Tools & Techniques
PDF
Presentation KNJHA (1).pdf
PDF
Lecture 3 Construction Operations Management.pdf
PPTX
pm--basic.pptx
PPT
C10 project management
PPT
C10 project management
PPTX
AWIN presentation it's only logical-a scheduling overview
PPTX
PROJECT-SCHEDULING-pptx.pptx
PPT
Chapter-5-Scheduling-and-Resource-Allocation.ppt
PPT
Software engineering ppt on pert and gantt charts
DOCX
Pm chapter 5
DOCX
Pm chapter 5
project schdeling concepts in operating system
CONSTRUCTION PLANNING AND SCHEDULING-MODULE 1.pptx
Fundamentals of scheduling
Operations and Supply Chain ManagementMGMT 3306Lecture 02I.docx
Unit II.pptx
Advanced project management mod 4
chapter-1.pptx scheduling for construction
Network Analysis- CPM ppt..pptx
Project schedule- What, How, Tools & Techniques
Presentation KNJHA (1).pdf
Lecture 3 Construction Operations Management.pdf
pm--basic.pptx
C10 project management
C10 project management
AWIN presentation it's only logical-a scheduling overview
PROJECT-SCHEDULING-pptx.pptx
Chapter-5-Scheduling-and-Resource-Allocation.ppt
Software engineering ppt on pert and gantt charts
Pm chapter 5
Pm chapter 5
Ad

Recently uploaded (20)

PDF
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
PPTX
CH1 Production IntroductoryConcepts.pptx
PPTX
Construction Project Organization Group 2.pptx
PPTX
OOP with Java - Java Introduction (Basics)
PDF
Well-logging-methods_new................
PDF
Digital Logic Computer Design lecture notes
PDF
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PDF
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PDF
PPT on Performance Review to get promotions
PPTX
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
PDF
Embodied AI: Ushering in the Next Era of Intelligent Systems
PPTX
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
PPTX
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
PPTX
bas. eng. economics group 4 presentation 1.pptx
PPT
Mechanical Engineering MATERIALS Selection
PPTX
Sustainable Sites - Green Building Construction
PPTX
UNIT 4 Total Quality Management .pptx
PDF
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
PPTX
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
PPTX
Internet of Things (IOT) - A guide to understanding
The CXO Playbook 2025 – Future-Ready Strategies for C-Suite Leaders Cerebrai...
CH1 Production IntroductoryConcepts.pptx
Construction Project Organization Group 2.pptx
OOP with Java - Java Introduction (Basics)
Well-logging-methods_new................
Digital Logic Computer Design lecture notes
SM_6th-Sem__Cse_Internet-of-Things.pdf IOT
PRIZ Academy - 9 Windows Thinking Where to Invest Today to Win Tomorrow.pdf
PPT on Performance Review to get promotions
FINAL REVIEW FOR COPD DIANOSIS FOR PULMONARY DISEASE.pptx
Embodied AI: Ushering in the Next Era of Intelligent Systems
IOT PPTs Week 10 Lecture Material.pptx of NPTEL Smart Cities contd
Engineering Ethics, Safety and Environment [Autosaved] (1).pptx
bas. eng. economics group 4 presentation 1.pptx
Mechanical Engineering MATERIALS Selection
Sustainable Sites - Green Building Construction
UNIT 4 Total Quality Management .pptx
Mitigating Risks through Effective Management for Enhancing Organizational Pe...
MET 305 2019 SCHEME MODULE 2 COMPLETE.pptx
Internet of Things (IOT) - A guide to understanding

L6.2 planing&scheduling

  • 1. EGNR 300 Project Management Planning & Scheduling -------------------------- ENGR 300 Dept. of Computer Science and Engineering University of Bridgeport, CT 06601
  • 2. “Failing to plan is planning to fail” by J. Hinze, Construction Planning and Scheduling • Planning: – “what” is going to be done, “how”, “where”, by “whom”, and “when” – for effective monitoring and control of complex projects
  • 3. “Its about time” by J. Hinze, Construction Planning and Scheduling • Scheduling: – “what” will be done, and “who” will be working • relative timing of tasks & time frames – a concise description of the plan
  • 4. “Once you plan your work, you must work your plan” by J. Hinze, Construction Planning and Scheduling • Planning and Scheduling occurs: – AFTER you have decided how to do the work • “The first idea is not always the best idea.” • Requires discipline to “work the plan” – The act of development useful, – But need to monitor and track • only then, is a schedule an effective management tool • as-built schedules
  • 5. The Work Break Down Structure (WBS) • An organizational tool for complex projects – A first step in creating a schedule – Useful for defining the Scope of Work • After decided how to do the work • Consists of: – Goal statement for project – Subdividing goal into smaller & smaller portions
  • 6. WBS • Upper two or three levels – require only general knowledge – don’t get too detailed too quickly • The deeper you go, the more knowledge you need • Bottom level tasks: • simple enough to estimate durations • can assign crews • each task has a natural sequence relative to other tasks
  • 7. Example WBS Warehouse WBS Site Boundaries Elevation Data Points Building Footprints Locate Buried Services Survey Soils Analysis Excavate Soil Backfill & Compact Site Preparation Foundation Structural Systems Finishing To construct a 5-unit warehouse for light industry Complex Could be used to define scope of work for surveyor sub-contract
  • 8. Order of Task Execution - Scheduling • Bar Charts (Gantt Charts) – length of bar = task’s duration – commonly used, require little training – precedence relationships difficult to show • precedence = the sequencing relationship between tasks
  • 9. Order of Task Execution - Scheduling • Network Diagrams – Critical Path Method (CPM) • w/in construction - most important – Program Evaluation and Review Technique (PERT) • like a generalized CPM • assumes that an activity’s duration cannot be precisely determined – takes most likely, optimistic, pessimistic estimates – computes an expected duration/activity and expected project duration
  • 10. Critical Path Method (CPM) • Identifies those chains of activities (critical paths) that control how long a project will take. • Two variations: – Activity-on-Arrow (AOA) • activities are the arrows or lines – Activity on Node (AON) • also known as a Precedence Diagram • activities are nodes connected together by lines
  • 11. Some CPM Terms • Float = the amount of time an activity can be delayed without delaying the project • Critical = activities with no float; these activities can not be delayed w/o extending project duration • Contingency = include a time allowance to account for time slippage & other delays • Slippage = difference between actual and scheduled progress
  • 12. Computer Scheduling “Projects should be scheduled one byte at a time” by J. Hinze, Construction Planning and Scheduling
  • 13. Creating a Computerized Schedule • Primavera P3, SureTrak, CA-SuperProject, MSProject • Uses CPM for calculating project duration • Offer Gantt and Precedence views – Gantt the default – Activities can be viewed in other forms: activity and resource calendars, spreadsheets • Useful for – updating and tracking – sorting, filtering, resource leveling
  • 14. Creating a Computerized Schedule • Specify a base calendar – calendar days vs. working and non-working days – specialized activity and resource calendars • tasks that cannot be performed on specific days • days that resources are available – (otherwise assumed that resources are available at all times on every working day) • Specify the project start or finish date
  • 15. Creating a Computerized Schedule • Input activities from the WBS – basic info needed: name, duration, predecessors, and successors – if relevant: resources utilized plus associated costs • Collapsing the schedule – consolidating subtasks within their summary tasks to view main project activities w/o cluttering the screen
  • 16. Creating a Computerized Schedule • Expanding the schedule – showing sub tasks w/in respective summary tasks • Link lines – the line that connects the bars of linked tasks on the Gantt chart
  • 17. Creating a Computerized Schedule • Linking – creating relationships between activities – finish-to-start, start-to-start, finish-to-finish, or start-to-finish – can include lag or lead times • Network loop – circular logic within a set of activities – all loops must be eliminated for computations to be made
  • 18. Creating a Computerized Schedule • Progress bar – graphical representation of the % completion of an activity at a specific date – shown adjacent to, or within, the activity bar • Summary task – representing a general activity of construction – duration calculated from sub-tasks • Create a baseline schedule – original schedule created at the beginning • actual progress is compared to
  • 19. Getting CPM w/MSProject • After input of schedule – choose Gantt view – use GanttChart Wizard to calculate CPM • Can filter and show only CPM – in drop-down menu: • project  filtered for  critical – to get back to full task list: • project  filtered for  all
  • 20. Example - Roof Structure The following seven tasks are required for the erection of a building roof structure. Some of the tasks can be completed simultaneously; the overhang with sofit can be constructed while the deck is being installed. 1 Place & secure trusses, 2 days 2 Install roof deck, 7 days 3 Apply vapor barrier, 2 days 4 Apply roof cladding, 2 days 5 Construct roof overhang, 4 days 6 Install soffits, 4 days 7 Apply flashing, 6 days